Cost of Production Report
Cost of Production Report
City of Naga
PROCESS COSTING
Companies track costs flows by departmental production report that describe the materials, labor and overhead by
each processing department during a given accounting period. The initial department is the department that
begins producing a product. A subsequent department is a processing department that continue the further
processing to produce the desired finished product. Cost flow refers to the physical flow of the cost of the product
as it moves from the initial department to subsequent department. The flow of the unit and costs of the product
under the process is captured in the Cost of Production Report which is prepared by each processing department
on a monthly basis.
Although shortcuts are sometimes taken, the methodical procession through each of the five steps minimizes error.
The first two steps concentrate on what’s occulting in physical or engineering terms. The peso impact of the
production process is measured in the final three steps.
Illustrative Problem:
The following data were taken from the Production Report of Department A for the month of April and May:
Costs:
Work in Process, beginning 0 Php 4,500.00
Costs added during the month:
Material Php 12,750.00 Php 24,000.00
Labor 7,650.00 14,400.00
Overhead 5,100.00 9,600.00
Total Php 25,500.00 Php 48,000.00
Required: Prepare a Cost of Production Report for the month of April and May.
Solution:
Department A
Cost of Production Report
Month Ended April 30, 20xx
Quantity Schedule:
Actual Work Done Equivalent
Production
Units for be Accounted For:
Started in Process 10,000
Department A
Cost of Production Report
Month Ended April 30, 20xx
Quantity Schedule:
Actual Work Done Equivalent
Production
Units for be Accounted For:
Units in process, beginning 3,000
Started in process 15,000
Total Units to be Accounted For 18,000
When there are units in process at the beginning of the costing period, the cost of these units upon
completion is computed as follows:
Cost of the previous month plus the cost needed to complete them this month.
Cost last month simply means the accumulated co9st when it was processed partially last month. On the other
hand, the cost added this month, pertains to the additional cost incurred during the current month to bring it to its
completion.
Illustrative Problem:
The following production data were taken from the books of Greyhound Manufacturing Co. which manufactures its
product in three (3) successive departments namely, Cutting, Assembly and Finishing:
Cutting Assembly Finishing
Units:
Work in Process, July 1 2,000 5,000 7,000
Stage of completion ¼ 2/5 1/7
Finished and transferred to the next Department 15,000 15,000 20,000
Work in Process, July 31 5,00 5,000 2,000
Stage of completion ½ 2/5 ½
Costs:
Work in process, July 1 Php 5,000.00 Php 67,500.00 Php 118,500.00
Costs incurred in July:
Materials 85,000.00 7,500 40,000.00
Labor 51,000.00 45,000.00 60,000.00
Overhead 34,000.00 22,500.0 20,000.00
Required: Cost of Production Report for Cutting, Assembly and Finishing Departments.
Solution:
Cutting Department
Cost of Production Report
Month Ending July 31, 20xx
Quantity Schedule:
Actual Work Done Equivalent Production
Cost Analysis:
Work in Process, Beg + Units Started = Units Completed + Work in Process, End
Quantity Schedule:
Actual Work Done Equivalent Production
Cost Analysis:
Finishing Department
Cost of Production Report
Month Ending July 31, 20xx
Quantity Schedule:
Actual Work Done Equivalent Production
Cost Analysis:
Illustrative Problem:
Diamond Manufacturing Co. manufactures a product in one department; all materials added at the beginning of
the process. Labor and overhead are applied uniformly about the process. Production data for the month of
August follows:
Units:
In process, August 1, 3/5 complete 1,000
Started in process 11,000
In process, August 31, 3/10 complete 2,000
Costs:
Work in process, August 1 Php 7,000.00
Costs incurred in July:
Materials 55,000.00
Labor 15,000.00
Overhead 10,000.00
Solution:
Quantity Schedule:
Materials Conversion Costs
Actual Work Done EUP Work Done EUP
Cost Analysis:
Illustrative Problem:
Finishing – This department adds all materials at the end of the process while conversion costs are applied
uniformly throughout the process
Mixing Finishing
Units:
Units in process, September 1 10,000 8,000
Stage of completion ¾ 4/5
Finished and transferred to the next Department 42,000 44,000
In Process, September 30 8,000 6,000
Stage of completion 2/5 2/3
Costs:
Work in Process, September 1 Php 18,800.0 Php 55,600.00
Cost added this September:
Materials 81,600.00 44,000.00
Conversion 113,100.00 124.800.00
Solution:
Mixing Department
Cost of Production Report
Month Ending September 30, 20xx
Quantity Schedule:
Materials Conversion Costs
Actual Work Done EUP Work Done EUP
Cost Analysis:
;
Finishing Department
Cost of Production Report
Month Ending September 30, 20xx
Quantity Schedule:
Materials Conversion Costs
Actual Work Done EUP Work Done EUP
Cost Analysis: