Adidas - Line Balancing 1
Adidas - Line Balancing 1
LINE
BALANCING
INTRODUCTION : WHAT IS LINE BALANCING?
Variation is ‘smoothed’
No one waiting
Everyone working together in a BALANCED
fashion
LINE BALANCING
- Way of adjusting each operation’s loading to make each operation’s time value almost the same
- key driver for a good production efficiency
- based on workers cycle time / the average GSD SMV for the style
Your production line have 3 operations, below are details, how to calculate the line
balancing rate?
A 2 1
B 5 2
C 2 1
BOTTLENECK / CONSTRAINT
Why balancing is important in setting up the line:
To eliminate excessive work in progress (WIP) or bottlenecks
What is Bottleneck?
- operators completing sewing operations of higher SMV’s, compared to all other
operators
- holds up the work for operators further down the line causing production stoppages
BOTTLENECK / CONSTRAINT
How to determine bottleneck operation?
- through WIP (Work In Progress)
- cycle time check
What does WIP do?
• Hides the problem
• Disable quality control
• Limits labor utilization
5 FOCUSING STEPS
7
HOW TO ANALYZE THE LINE BALANCE
• Production output?
• SMV?
• Stop watch to check cycle time
8
LINE BALANCING
Improve the
operations
which are far
from takt time
or shows to
create potential
bottleneck
9
LINE BALANCING PROCESS
TIME
CYCLETIME
CYCLE
Share Method
Rearrange bottleneck operation
OPERATOR 1 2 3 4 5
OPERATOR 1 2 3 4 5
CYCLE
OPERATOR
OPERATOR TIME
CYCLETIME 11 22 33 44 55
10
LINE BALANCING PROCESS
Optr 4
TIME
CYCLETIME
CYCLE
Optr 3
Reduce cycle time by
additional/shared operator
OPERATOR
OPERATOR 1
1 2
2 3&
34 5
4 6
5
TIME
CYCLETIME
CYCLE
OPERATOR
OPERATOR 11 22 23 34 45
11
LINE BALANCING EXAMPLE
12
LINE BALANCING PROCESS
Build Sewer Database:
Sewer Database
- After finished sewing of the 1st style, IE updates highest potential efficiency of
the sewer on the Sewer Database.