EVM Practice Exercises-3
EVM Practice Exercises-3
BAC (Budget at Completion): How much you are expected to spend on the project
BAC: 50×100=5000
PV (Planned value): BAC x Approved value of work to be completed in a given time (what you should
have delivered so far/what you were supposed to spend)
PV: 5000×25÷100=1250 QR
AC: 1140
EV (Earned Value): BAC x Actual value of work you have earned (How much work the team has finished)
EV: 22×50=1100
SV (Schedule Variance): EV – PV
BAC (Budget at Completion): How much you are expected to spend on the project
BAC:
PV (Planned value): BAC x Approved value of work to be completed in a given time (what you should
have delivered so far/what you were supposed to spend)
PV:
PV:
AC (Actual Cost): What the team has actually spent.
AC:
EV (Earned Value): BAC x Actual value of work you have earned (How much work the team has finished)
EV:
EV:
SV (Schedule Variance): EV – PV
SV:
SV:
CV (Cost Variance): EV-AC
CV:
CV:
SPI (Schedule Performance Index): EV/PV
SPI:
SPI:
CPI (Cost Performance Index): EV/AC
CPI:
CPI:
TCPI (To Complete Performance Index): BAC-EV/BAC-AC
TCPI:
TCPI:
TCPI:
EAC (Estimated Actual Cost): BAC/CPI
EAC:
EAC:
BAC (Budget at Completion): How much you are expected to spend on the project
BAC:
PV (Planned value): BAC x Approved value of work to be completed in a given time (what you should
have delivered so far/what you were supposed to spend)
PV:
PV:
AC (Actual Cost): What the team has actually spent.
AC:
EV (Earned Value): BAC x Actual value of work you have earned (How much work the team has finished)
EV:
EV:
SV (Schedule Variance): EV – PV
SV:
SV:
CV (Cost Variance): EV-AC
CV:
CV:
SPI (Schedule Performance Index): EV/PV
SPI:
SPI:
CPI (Cost Performance Index): EV/AC
CPI:
CPI:
TCPI (To Complete Performance Index): BAC-EV/BAC-AC
TCPI:
TCPI:
TCPI:
EAC (Estimated Actual Cost): BAC/CPI
EAC:
EAC:
BAC (Budget at Completion): How much you are expected to spend on the project
BAC:
PV (Planned value): BAC x Approved value of work to be completed in a given time (what you should
have delivered so far/what you were supposed to spend)
PV:
PV:
AC (Actual Cost): What the team has actually spent.
AC:
EV (Earned Value): BAC x Actual value of work you have earned (How much work the team has finished)
EV:
EV:
SV (Schedule Variance): EV – PV
SV:
SV:
CV (Cost Variance): EV-AC
CV:
CV:
SPI (Schedule Performance Index): EV/PV
SPI:
SPI:
CPI (Cost Performance Index): EV/AC
CPI:
CPI:
TCPI (To Complete Performance Index): BAC-EV/BAC-AC
TCPI:
TCPI:
TCPI:
EAC (Estimated Actual Cost): BAC/CPI
EAC:
EAC: