KT-DR 2023-046 DailyReport-2023.11.23

Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

菲律宾凯萨卡供水隧洞设计建造项目

DESIGN AND BUILD OF THE KAYSAKAT RAW WATER TRANSMISSION LINE


- TUNNEL WORKS
Address: Sitio Apia, Brgy. Calawis, Antipolo City, Rizal Province Email: [email protected]

Reference No.: CWE/KT/DR 2023-046


Date: 23 November 2023

Daily Report
1. Progress of Completion
Completion progress of Total Completion
No. Description
the Day Percentage
1 Design Work
Topographic map review by
1.1 Topographic survey (Tunnel inlet & outlet) third-party measurement 100%
company
Topographic map review by
1.2 Topographic survey (Tunnel alignment) third-party measurement 98.5%
company
1.3 Geotechnical Investigation (Tunnel inlet & outlet) Lab testing of rock samples 95%
No progress due to the
1.4 Geotechnical Investigation (Tunnel alignment) 46.7%
landlord’s obstruction.
Designs for the tunnel
entrance, including the
1.5 Design of tunnel portal including launching cradle launch pad, have been 100%
submitted and are awaiting
approval.
1.6 TBM Design and approval Mechanical Design 80.9%

2 Planning & Management


2.1 Material sampling test and mix ratio design Shotcrete test is ongoing. 26%
Revision of risk management plan (RMP) and
2.2 Revision completed. 100%
mobilization & demobilization plan (MDP)
Construction methodologies (draft) and Construction methodologies
2.3 are being revised.
94%
Construction management plan.
Progress report, site inspection and acceptance
Discussing the site
2.4 process discussion and format/templates inspection format
62%
confirmation
EDMS, Measurement and payment (Project Preparing the project billing
2.5 No.1
88%
Billing) process format/templates confirmation
3 Mobilization
3.1 Major Personnel & Equipment mobilization No progress 50%
Preparation of the site for contractor’s The installation of container
3.2 rooms is in progress
73%
accommodation and office
2. Manpower
POSITION No. of Personnel In Work
I. CHINESE
1 Project Director/ Assistant Project Director 2 2
2 Project Manager/ Deputy Project Manager 2 2
3 Assistant Project Manager & Project Controller 1 1
4 Quality Manager 1 1
5 Procurement Manager 1 1
6 Design Manager 1 1
7 Commissioning Manager 1 1
8 Planner/Scheduler 1 1
9 Tunnel Superintendent 1 1
10 Engineer/Technician/ Mechanic/ Electrician 21 21
11 Surveyor 3 3
Sub-total 35 35
II. LOCAL
ADMINISTRATIVE:
1 Admin. Officer 1 1
2 HR Officer 1 1
3 Secretary
4 Driver 7 7
5 Housemaid 3 3
OFFICE ENGINEERING:
1 Civil Engineer 1 1
2 Mechanical Engineer 1 1
3 External Affairs Senior Officer 1 1
HEALTH, SAFETY & ENVIRONMENT
1 Safety Manager 1 1
2 Safety Officer 1 1
3 Security guard 6 6
SURVEY:
1 Surveyor
CONSTRUCTION/STRUCTURAL:
1 Foreman
2 Carpenter
3 Plumber 1 1
4 Mason
5 Welder
6 Steelman
7 Labor 13 4
EQUIPMENT:
1 Electrician 1 1
2 Mechanic
POSITION No. of Personnel In Work
3 Operator 2 2
Sub-total 40 31
Total 75 66

3. Equipment
Quantity
No. Equipment
Working Idle Total
1 Excavator 1 1 2
2 Bulldozer 0 1 1
3 Wheel loader 0 2 2
4 Dump truck 0 5 5
5 Generator 1 2 3
6 Hydraulic breaker 0 1 1
7 Tractor 0 1 1
8 Concrete mixer 0 1 1
9 Welding Machine 0 3 3
10 Cutting Machine 0 2 2
11 Service vehicle 5 0 5
12 Digital acoustic instrument 0 1 1
Multi-electrode electrical measurement
13 0 1 1
system
14 Drilling machine 2 0 2
15 GPS 0 5 5
16 Level 1 0 1
Total 10 26 36

4. Materials & Tools


Description Unit Quantity Remark
No.
1 Container facilities 3*6m set 51
2 Container 20ft pcs 2
3 Air pump pcs 1
4 Equipment accessory batch 1
5 Tools batch 1

5. Activities
5.1 Equipment mobilization
No equipment is delivered for mobilization today.
5.2 TBM design and manufacture
TBM master drive drawing has been confirmed and sent to the structure workshop.

5.3 Campsite Facilities Construction


1) The concrete casting for foundations is processing.
2) The rooms interior decoration is in progress.
3) Constructing flower beds.

Figure 5.3 Campsite Facilities Construction

5.4 Topographic Survey and Geological Investigation


ZK10 was not drilled today due to the landlord’s obstruction and the negotiations with the landlord is in
progress.
Lab testing of rock sample is in progress.
The topographic map review is being carried out by third-party measurement company.

Figure 5.4 Negotiation with the landlord

5.5 Planning & Management


The Construction Methodologies is under review.

6. Design progress
1) Modify the preliminary 3D model of segment according to the TBM design.
2) Prepare the design of glide groove.

7. Issues Encountered
The drilling of ZK10 is suspended by the landowner. Before we started the drilling, our GI engineer tried
to coordinate with the landowner, but couldn’t find him/her. The chieftain of Barangay San Jose said the
landowner lives in Manila so we could't find her here. The chieftain allowed us to start the drilling and
should have already coordinated with the landowner. However, when we were performing the drilling,
the landowner sent one of her relatives to stop our work and ask for money. She is asking for P150,000
today rather than P100,000 yesterday. We are now negotiating with the landowner together with the help
of Bgy. Official.
A report is prepared to be submitted to KAKSAAN NE DUMAGUIT as instructed and a meeting will
be held tomorrow to address this issue.

Prepared by: Noted by:

Wang Dongheng Byong-Hun Min


Deputy Project Manager Project Manager
China International Water & Electric DOHWA Engineering Co., Ltd.
Corp.

You might also like