Mechanical Integrity Exchanger Tube Bundle

Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

Your Company Here Sample from IndustryDocs MNT-FIXED-001 Rev.

0
Anytown, USA https://www.industrydocs.org/maintprocs.html Maintenance Procedure

Remove, Clean, and Re-Install Bundle from an Exchanger

APPROVED:_________________________ DATE APPROVED:__________ DATE EFFECTIVE:__________


Maintenance Manager

PURPOSE This Procedure describes the steps required to remove the tube bundle from an
exchanger. This procedure applies to all Maintenance personnel that perform
or assist in this work.

REFERENCES • MATERIAL SAFETY DATA SHEETS


• Hazardous Energy Control Procedure
• Safe Work Permit Procedure
• Lock Out/ Tag Out Procedure
• Lifting Procedure
• Safe Work Program for Handling Inorganic Metals in Process Scales
• Welding on Towers/Vessels or Exchangers Procedure

SPECIAL Refer to proper MATERIAL SAFETY DATA SHEETS


EQUIPMENT

PREREQUISITE This procedure requires qualified craftsmen.

1. REVIEW this procedure with the Operations and Maintenance crews to


ENSURE all steps and cautions are clear and all hazards have been
DEFINED. Match the proper MATERIAL SAFETY DATA SHEETS with the
equipment service.

2. Use special precautions defined on MATERIAL SAFETY DATA SHEETS


and verify operation of all safety showers and eyewashes near the work
area to ENSURE they are in good working order.

3. Field VERIFY with Operations that the equipment has been BLOCKED IN,
DE PRESSURIZED, and BLED DOWN. VERIFY that block valves are
HOLDING satisfactorily.

4. INSTALL locks and tags where required per the Lock Out/ Tag Out
Procedure.

5. Maintenance personnel shall VERIFY with the unit operator that all
applicable equipment is LOCKED and TAGGED OUT and is NON-
OPERABLE (Lock, Tag, Test, Try).

6. REVIEW and OBTAIN Work Permit at this time.

PROCEDURE REMOVE, CLEAN, AND RE-INSTALL TUBE BUNDLE FROM AN


EXCHANGER IN THE VACUUM-I UNIT.

Printed: 1/6/2019 CONTROL COPY Page 1 of 9


Your Company Here Sample from IndustryDocs MNT-FIXED-001 Rev. 0
Anytown, USA https://www.industrydocs.org/maintprocs.html Maintenance Procedure

CAUTION
"First Flange Break" - Personnel must stand upwind of flange being broken
to lessen exposure to hazard. Personnel shall loosen and remove bolts
on far side of flange first to lessen chances of exposure.
CAUTION

1. INSTALL blinds on the shell side inlet and outlet nozzles if required.

2. REMOVE channel cover and channel head.

3. INSTALL blind flanges on the tube side inlet and outlet piping if required.

4. PULL bundle.

5. Hydro-blasters to CLEAN tubes, bundle and heads if required.

6. Inspection Department to INSPECT all parts.

7. REPAIR as needed per Inspection Memo.

8. RE-ASSEMBLE exchanger, except for channel cover.

9. OBTAIN test pressures from Operations.

10. HYDROTEST shell side and complete hydrotest forms. Cold gas oil must
be used to test.

11. RE-INSTALL channel cover, Hydrotest tubes, complete Hydrotest forms.


Cold gas oil must be used to test.

CAUTION
"First Flange Break" - Personnel must stand upwind of flange being broken
to lessen exposure to hazard. Personnel shall loosen and remove bolts
on far side of flange first to lessen chances of exposure.
CAUTION

12. REMOVE all blinds.

13. NOTIFY Operations that work is complete.

14. REMOVE all locks and tags.

15. After system is back in service, Operations will SIGN OFF the Work
Order/Work Permit as completed.
* Note: During turnaround or complete unit shutdown with all isolation blinds in
place, water may be used to Hydrotest exchangers if there is sufficient
steam in the unit to effectively steam out exchangers after testing.
END OF PROCEDURE

Printed: 1/6/2019 CONTROL COPY Page 2 of 9


Your Company Here Sample from IndustryDocs MNT-FIXED-001 Rev. 0
Anytown, USA https://www.industrydocs.website/maintprocs.html Maintenance Procedure

APPROVED: ________________ DATE APPROVED: _________ DATE EFFECTIVE: _________

Technical Writer: Content Expert:


_______________________________________________________________________________

Purpose Establish inspection guidelines to ensure mechanical integrity and continued


reliable operation of shell and tube heat exchangers. This procedure applies to
the pressure containing parts of the exchanger alone with supporting structures.

References Material Safety Data Sheets (MSDS) are electronically stored and can be
referred to in the MSDS program by equipment number, MSDS can also be
found by searching by manufacturer, product name, or chemical. The
procedure user is responsible for referring to the appropriate MSDS.

Corporate Safety Procedures shall be referred to for all safety related issues.
They are accessible electronically plant wide by going to the Health and Safety
Services tab on the Intranet. Personnel are responsible for referring lo the
appropriate safety procedures.

National Board Inspection Code ANSI-NB-23, Latest Edition

APl-510 Pressure Vessel Inspection Code: Maintenance Inspection, Rating,


Repair, and Alteration; Latest Edition

American Society of Mechanical Engineers (ASME), Section VIII, Division 1

American Society of Mechanical Engineers (ASME), Section IX, Latest Edition

Applicable Local, Stale and Federal Regulations

Applicable Engineering Standards and Practices API

RP571 Conditions Causing Deterioration and Failure

API RP572 Inspection of Pressure Vessels

API RP750 Management of Process Hazards

Applicable Maintenance Inspection Procedures

Vendor Drawing for the vessel being inspected.

Printed: 1/6/2019 CONTROL COPY Page 3 of 9


Your Company Here Sample from IndustryDocs MNT-FIXED-001 Rev. 0
Anytown, USA https://www.industrydocs.website/maintprocs.html Maintenance Procedure

Precautions The Authorized Inspector should assure that all work permits, isolation and
entry procedures/permits are current.

Prerequisites Prior to any inspection, a review should be done through Reliability


Equipment Files and facility databases:

• Inspection history

• Current mechanical design requirements

• Previous repair history

• Re-rating history material degradation

• Corrosion rates

The Authorized inspector should take into consideration operating conditions


and the process chemistry the equipment is subjected to and determine
potential degradation mechanisms.

Procedure External Inspection

• External inspection of an air cooled exchanger is part of the


determination of mechanical integrity.

• Then Authorized Inspector should examine platforms, ladders,


stairways, and their supports (including fireproofing), to assure their
serviceability.

• The concrete pedestals, foundations and steels structures should be


examined for cracks, chips, spalling, or deterioration. Grounding
connections should be inspected to insure that they are attached

• The Authorized Inspector should ensure that the exchanger is properly


stamped or identified.

• Nozzles should be examined for distortions, cracks, corrosion and other


degradation.

• Examinations should be made to determine the header boxes wall


thicknesses using Ultrasonic testing. Applicable thickness data should
be entered into the facility database.

• If access is provided, examine fan blades and hubs for cracking.

• Examine hold down bolting arrangement-slots should be free of material


that would restrict thermal growth.

Printed: 1/6/2019 CONTROL COPY Page 4 of 9


Your Company Here Sample from IndustryDocs MNT-FIXED-001 Rev. 0
Anytown, USA https://www.industrydocs.website/maintprocs.html Maintenance Procedure

Procedure Inspection Intervals

Inspection intervals for Shell and Tube exchangers will be in accordance with
pressure vessels as defined in API 510 Vessel Inspection Code, Generally, this
means inspection at vessel half remaining life, up to a maximum of ten years.
Same Code also provides for extensions based on historical findings.

External Inspection intervals for Shell and Tube Exchangers will be in


accordance with pressure vessels as defined in API 510 Vessel Inspection
Code. Generally, this interval is 5 years.

Internal Inspection

NOTE: The below scopes for Internal and external Inspection should not be
considered the limits of inspection. Inspector is responsible for
inspecting in accordance with and on the basis of referenced Code
Documents.

Internal Inspections should be performed by or under the directions of an


Authorized Inspector as defined by Code. An External Inspection should be
performed in conjunction with each Internal Inspection.

• The Inspector should examine the internal walls of the shell, channel
and nozzles for cracking, pitting, general corrosion and erosion.
Indications should be quantified through use of pit depth gages, or
ultrasonics (straight or angle beam). Locations and depths should be
plotted on an equipment drawing

• Scale buildup or sludge deposits should be noted along with their


location on the shell or nozzle.

• All gasket surfaces should be examined for any signs of damage.

• Examine condition of pass partition plate and weldments (typically for


cracking) and gasket surfaces for metal loss.

• When the tube bundle is removed from the shell, a visual examination
should be done before cleaning noting the amount of scale, sludge and
general fouling products. Also, if variations of deposits exist, note
locations.

• Baffles and tie-rods should be examined for loose nuts as well as metal
loss. Also check for tube OD wear where the pass through baffles.

• Verify proper location of impingement plate and for tube OD erosion in


the vicinity of inlet nozzles.

Printed: 1/6/2019 CONTROL COPY Page 5 of 9


Your Company Here Sample from IndustryDocs MNT-FIXED-001 Rev. 0
Anytown, USA https://www.industrydocs.website/maintprocs.html Maintenance Procedure

• After the bundle is cleaned, a thorough examination should be


performed on tubes, tube ends and tube sheets for pitting, thinning and
general corrosion. A representative portion of the above should be
measured using appropriate instruments. Data should include ID and
OD tube measurements, and pit depths. Findings should be noted on
equipment drawing.

Internal Lining Inspection

• Metallic and nonmetallic linings (e.g. strip and plate linings, overlays,
internal coatings, refractory) shall be examined during internal
inspections of pressure vessels.

• The inspection scope and methods recommended in API RP 572 for


metallic and nonmetallic linings should be followed to assess the
condition of the lining and the vessel surface beneath.

• A visual inspection of the accessible internal lining should take place at


each internal inspection interval. The lining should be inspected for
damage such as separation, bulging, spalling, holes, blisters, cracks,
chipping, and erosion.

• If lining damage is detected, representative portions of the internal liner


should be removed to assess the condition/effectiveness of the liner and
the metal beneath the lining. Alternatively, ultrasonic scanning from the
external surface may be used to asses the damage beneath the lining,

• Thermography (IR) is an accepted on-stream inspection method to


detect refractory damage. Reference Maintenance Procedure; MNT-
INSP-029. Infrared.

External Inspection

The following items should be included among those Items checked during
external Inspections:

NOTE: It is preferred that an External Inspection Checklist is utilized for


recording the results.

• Platforms, ladders, stairways, and their supports, to assure their


serviceability.

• Concrete pedestals, foundations, skirt fire proofing should be examined


for cracks, chips, spalling, or deterioration. Grounding connections
should be inspected to insure that they are attached.

• Paint coating should be examined for blister and chipping that would
expose the vessel to corrosive elements Insulation and metal jacketing

Printed: 1/6/2019 CONTROL COPY Page 6 of 9


Your Company Here Sample from IndustryDocs MNT-FIXED-001 Rev. 0
Anytown, USA https://www.industrydocs.website/maintprocs.html Maintenance Procedure

should be examined for integrity of sealing and for indications of


corrosion under insulation.

• Condition of Data Plates and ID Markings.

• Nozzles should be examined for distortions, cracks, corrosion, and other


degradation. Reinforcements should be examined for evidence of
leakage. Weep holes should be open.

• Any ancillary equipment such as level bridles, temperature or pressure


gauge connections, should be inspected for external corrosion, signs of
leakage, and condition of support

• The Inspector should examine the surfaces of the shells, channel


covers, and heads for possible cracks, bulges, and other evidence of
deterioration. Attention should be given to support saddles and other
external supports.

• Follow-up examinations should be made to determine the shell and


channel wall thickness (using Ultrasonic testing) in significant wall toss
is observed.

Repairs and Alterations

• All repairs end alterations performed on shells, channels and heads will
be done in accordance with Maintenance Procedure; MNT-INSP-015,
Vessel Repair/Alteration Procedure, and in accordance to applicable
Codes.

• Repairs to bundles (tube pluggings) or bundle replacements are lo be


documented by the Inspector in the equipment file. Location of plugged
tubes should be mapped on equipment tubesheet drawing along with
date plugged.

• All repairs, whether to shell or bundle, are to be approved by the


Reliability Authorized Inspector Maintenance Engineer should be
consulted with for repairs not of a routine nature.

• Repair, alteration and bundle replacement documentation is to be kept


in the Reliability Equipment Files or Plant Condition Monitoring System
(PCMS).

Nonconformities

• Definition - Any change in the condition of an item described on the


original Manufacturer's Data Report (U-1A), NBIC-R1 or API 510
Repair/Alterations Reports that affects the pressure containing capability
of the pressure vessel.

Printed: 1/6/2019 CONTROL COPY Page 7 of 9


Your Company Here Sample from IndustryDocs MNT-FIXED-001 Rev. 0
Anytown, USA https://www.industrydocs.website/maintprocs.html Maintenance Procedure

• Non-conformance conditions will be reviewed by a designated Technical


Team (typically Area Inspector and Area Maintenance Engineer) who
will make repair or alteration recommendations in accordance with
Maintenance Procedure; MNT-INSP-027, Inspection Recommendation
Process, to assure continued integrity and Code compliance.

• Non-conformance issues should be forwarded to Refinery Management


if proper resolution is not reached in a timely manner.

Reports

At a minimum, condition of the following should be indicated on Inspection


Report:

1. Recommendations and Repairs Completed during current Maintenance


Event.

2. Condition of the following:

a. Bundle

i. Tubes (ID and OD)

ii. Tubesheet (face a, baffle and gasket surfaces)

iii. Floating Head (ID and OD, pass partitions, gasket


surfaces)

iv. Spacers, baffles, impingement plates

b. Shell

i. Shell Can Section and Body Flanges

ii. Nozzle Necks and gasket surfaces

iii. Shell Cover and gasket surfaces

iv. Small bore Taps

c. Channel

i. Dollar Plate (Channel Cover) and gasket surfaces

ii. Pass Partition and gaskets surfaces

iii. Nozzle Necks and gasket surfaces

NOTE: External Checklist should be used for External Inspection Topics

Printed: 1/6/2019 CONTROL COPY Page 8 of 9


Your Company Here Sample from IndustryDocs MNT-FIXED-001 Rev. 0
Anytown, USA https://www.industrydocs.website/maintprocs.html Maintenance Procedure

Documentation

Inspection Reports should become a part of the Equipment Items


Progressive Inspection Records.

Documentation and results on inspections should be kept in Reliability


Equipment Files and/or in Plant Condition Monitoring System Data
Base.

END OF PROCEDURE

Printed: 1/6/2019 CONTROL COPY Page 9 of 9

You might also like