Om - Section 4 Part C - Student
Om - Section 4 Part C - Student
Learning Objectives
Understanding the key decisions for project
management
Applying the techniques (Gantt chart, CPM, PERT) for
project management
Drawing diagram network
Determining critical part
Calculating ES, LS, S, EF, LF
Introduction
Projects are unique, one-time operations designed to
accomplish a specific set of objectives in a limited time
frame
How to draw?
Identify the major activities required.
Estimate time for each activity.
Determine the sequence of activity.
Disadvantages:
- Can’t maximize the benefit of resources (materials,
time...)
GANTT CHART - Example
A set of activities needed for making a new product
+ A – working hours: 4h
+ B – 3h
+ C – 5h
+ D – 6h
+ E – 4h
Requirement: B and D start after A completes; C after
B; E after D.
Draw Gantt Charts to present these activities and
determine the total working hours.
Critical Path Method (CPM)
For planning and coordinating large projects
b 3 d
Critical Path Method (CPM)
A critical path
The longest path which determines expected project
duration.
Critical activities are ones on the critical path, which
have to be completed immediately . If delayed, it will
affect the completion time of project.
Note: no slack time for critical activities
Critical Path Method (CPM)
Earliest Finish (EF) Latest Finish (LF)
For the first activity of a For the last activity of a
project: project: LF = EF
EF1 = t1 n n
ES = EF - t
LS = LF - t
CPM - Example
Activities Preceding Completion time (days)
Activity
A - 20
B A 10
C B 8
D A 11
E C,D 7
F E 6
G D 12
H E 13
I G, H 5
CPM - Example
Requirements:
Draw a network diagram
Determine a critical path
Calculate EF, LF, S, ES, LS of each
activity
Exercise 1
Activities Preceding Completion
Activity time (days) Draw a
A - 12 diagram
B A 6 Determine the
C A 9 critical path
D B 14 Calculate ES,
E C 5 LS, EF, LF, S
F C 5
G D 8
H E 13
I G 7
J H, F, I 14
Exercise 2
Activities Preceding Completion
Activity time (days) Draw a
A - 6 diagram
B A 3 Determine the
C A 7 critical path
D C 2 Calculate ES,
E B, D 4 LS, EF, LF, S
F D 3
G E, F 7
Example 3
Activity Immediate Duration (Days)
Predecessor
A - 2
B - 3
C A 2
D B 3
E B 2
F C,D 3
G F,E 7
H C,D 3
I G,H 6
J C,D 2
K F,E 5 25