Ui Roofing and Guttering Standard V 002
Ui Roofing and Guttering Standard V 002
Ui Roofing and Guttering Standard V 002
Standard
Design, Engineering, Planning &
Sustainability
University Infrastructure
Document Edit Control
Document Name: Roofing and Guttering Standard
Where any ambiguity exists between this standard and the aforementioned mandatory
requirements then:
a. The highest performance requirements must apply.
b. Applicable requirements must follow this order of precedence:
1. Workplace Health and Safety legislation.
2. Safety in Design Legislation.
3. Disability Discrimination legislation.
4. State Environmental Planning and Assessment legislation.
5. All other Commonwealth and State legislation.
6. NCC, BCA and PCA.
7. AS/NZS.
8. This standard and other University of Sydney standards.
2 Scope
This standard describes minimum requirements for design, purchase, construction, and operation
and maintenance of fire services plant, equipment and infrastructure for buildings and spaces
owned, operated, maintained and/or managed by the University of Sydney. It applies to:
The standards apply to all planners, project managers, consultants, contractors, sub-contractors,
tenants, managing agents and University staff involved in the design, construction and
maintenance of existing, new and proposed University buildings and facilities.
All Roofing and Guttering systems products and services provided or specified by designers,
consultants, staff and contractors must conform to this standard.
Where specific applications are not explicitly covered, or ambiguity exists, the intent of the
design standard must be satisfied. In such cases a return design brief must be provided for
review and approval by the issuer of this standard or their appointed delegate who must have
relevant technical competence in the subject matter. Additional more stringent requirements
may apply on a project-specific basis dependent upon risk management and insurance
requirements.
3 Glossary of Terms
Flashing Components used to weatherproof or seal the roof perimeters,
penetrations, walls and other places where the roof covering is
interrupted or terminated
Anchor Point Any single or multiple fixed anchor point or static line support
point, whether part of a work positioning, abseiling or fall arrest
system.
Dry Joints A joint between any two sections of material. A dry joint does not
rely upon sealants such as silicone, solder or electric welding to
seal the joint.
Wet Joints A joint between any two sections of material. A wet joint includes a
substance such as silicone, solder or the use of electric welding to
seal the joint.
Surface Mounted Any anchor that is fastened (by means of friction, mechanically or
“clipped”) to a roof sheet, eave or batten.
5 Existing Buildings
The design for projects within existing buildings must be assessed on a case by case basis and
developed in conjunction with this standard. The project scope will drive the design
requirements.
Any items not included in the scope must not be priced into the overall project to achieve the
following aim; To reduce the need to value engineer any services.
New projects within existing buildings must assess what the expectation of the refurbishment
will be. This will enable the right outcome for the given project.
These specific requirements must be included in the scope of works specification for design and
construction of the roofing and guttering in a building:
Obtain the Gate Paper from the Project Manager and understand the scope of works in
relation to the space and fit out requirements. Understand the expectation from the end user.
Equipment must be suitable for the intended new purpose and life expectancy of the works,
comply with current codes and achieve energy targets.
Equipment must be cleaned, have consumables replaced, tested, relabeled and re-
commissioned.
Remove redundant pipework, equipment and wiring, including inaccessible ceiling spaces, and
make good exposed surfaces before commencing the installation of new services.
6 Technical Requirements
6.1 Introduction
The buildings within the University’s campuses range from mid 19th century constructions to
modern contemporary design. Each building shows significant design details of that period.
Due to this, careful planning and consideration is needed when designing or repairing these
assets.
This document is intended to inform designers and installers of the need to properly plan future
works. All the items included in this design standard have been identified as best practice by
the University of Sydney.
Sustainability is a key factor when designing new infrastructure. Recycled materials and
usability will be highly regarded when evaluating the design.
It is the designers and the installing contractor’s obligation to document and install systems,
equipment and materials that are “fit for purpose” from both a WH&S and operational
perspective. Any disputes in regard to the interpretation of this clause shall be referred to
NSW Fair Trading and/or the UI Project Manager for a final determination.
a. Building Physics - provide advice to the project team, including other design team members
that would improve the inherent building performance, which may lead to reductions in both
capital and energy costs. This may initially take the form of simple advice relating to
existing infrastructure capacity and location, which may affect the siting of the building,
and subsequently backed up by modelling or similar methods. The process may take a
number of iterative steps. The consultant or designer is expected to advice, contribute and
if necessary lead such processes.
b. Planning and Architecture – provide advice on the appropriate location of plant rooms and
reticulation strategy to assist in both the planning of the building and the facilitation of
As part of the design development, the University expects consultants and designers to select
proven and reliable roofing and guttering systems.
Products which are of closed systems and proprietary in nature, thus locking the University into
exclusive dependence of one manufacturer must be avoided and only used if there are no
other options.
In the sizing of equipment, the University expects consultants, designers and installers to follow
good industry practice. Sizing of all roofing components are to equal or preferably exceed
the relevant Australian Standards. This is especially important for the sizing of downpipes and
stormwater infrastructure.
The provision of spare capacities for roof platforms and access to cater for future services and
equipment upgrades, must be considered for all projects. In making such considerations, careful
analysis of spare capacity against all applications must be considered. The practicality of
proposed future equipment sizing, and selection must be submitted by the consultant and
contractor to UI for approval.
The contractor shall be fully responsible for the complete design of the roofing and guttering
installations, including the selection, sizes and quantity of materials and equipment, and shall
provide calculations and drawings and other documentation as necessary to demonstrate
conformance with the design parameters, industry practice, UI requirements, codes, regulations
and standards. This includes all calculations required to confirm that existing infrastructure is
sufficient to supply the proposed systems installed under the project.
The contractor shall allow to fully co-ordinate the documentation with the Architect, Structural
Engineer and all other services consultants / contractors.
Each building must be equipped with the appropriate roofing and guttering as a full system,
all designed and installed in accordance with the requirements of the NCC.
6.3.3 Refurbishments
The requirements for the refurbishment of existing roofing and guttering within existing
buildings will often be the same as for new buildings.
Whilst every endeavor is made to comply with current NCC regulations during refurbishments
and upgrades, it is unlikely that the full extent of the building regulations can always be met.
Within any building proposed for refurbishment, the Standard of Performance for all existing
systems must be reviewed by the consultant/contractor for compliance with the current NCC
and Australian Standard requirements. The details of this review together with a proposed
roofing and guttering upgrade strategy must be submitted to UI for approval during the initial
design development.
6.3.4 Calculations
As part of the contractor’s design, it is expected that the following design calculations as a
minimum are produced for review by UI for approval prior to finalising design:
For each service, present on the schematic layout for that service, a “Basis of Design” summary.
The summary shall identify how the system works, basis of design, any departures form
Australian or UI standards and all substantial information are required to review the adequacy
of the design intent. The basis of design is to include pressure and flow information from the
Sydney Water Pressure inquiry or the on-site fire flow test results.
It shall be maintained up to date using Revision Numbering throughout the checking and review
process.
The contractor is responsible for producing all design and as-built documentation, including, but
not limited to:
a. Concept Design documentation (as required).
b. Detailed Design documentation, including:
i. Layout drawings.
ii. Details.
iii. Schematics, including a Basis of Design Statement for each service.
iv. Design certification.
v. Equipment details.
vi. Testing / commissioning procedures.
vii. Workshop drawings, including:
viii. Drawings for the purpose of system manufacture.
ix. As Built drawings, including:
x. Detailed drawings demonstrating the as installed system.
xi. Operations and Maintenance manuals.
xii. Training manuals.
6.4.2 Safety
Roof safety is an integral part of all work performed on all the university roofs.
Roof safety is to be achieved through the provision of permanent edge protection such as
handrails, balustrades or parapets.
Persons wanting to use a roof safety system for access must be suitably qualified and have
approved Permit and Safe Work Method Statements (SWMS).
Must be applied through the University’s Roof Permit Process – located on the Design
standards page - link
All safety systems installed must be of the “Work Positioning” type. This allows workers to
access the edge of the roof or structure eliminating the chance of a fall.
Safety harnesses are to be tied off onto either a certified anchor point, static line or to a
suitably engineered structure.
All anchor points installed must be accompanied by a structural engineer’s certification. The
certification must identify the roof structure the anchor point is connected to. The certification
must confirm the structure can sustain the loads that could be applied to it in the event of a fall.
Roof anchors being attached to a timber framed roof requires structural certification of the
roof frame. A report detailing the species and condition of timber is also required for
attachment of anchors.
At no time must “surface mounted” anchor points be installed on any University owned roof.
All anchors must be mechanically, chemically, clamped or braced to the roof structure.
All safety systems must be installed complete with data plates and appropriate signage. Data
plates and signage are to be installed in accordance with the relevant Australian Standards.
An access hatch must have a stair or step built underneath for ease of access. A platform or
level area must be provided outside the hatch to provide safe access onto the roof.
The access hatch must also incorporate a chain or metal strap fixed to the lid to securely prop
the lid open. All access hatches are to be secured by means of a hasp staple and padlock. This
padlock is to be keyed to the University Roofing Barrel.
Roof penetrations need considerable planning and design before installation. Penetrations
must be in areas of the roof that will require the minimum flashing detail. The sole purpose of a
flashing is to weatherproof the penetration. The flashing is not to be used to support equipment
or structures.
Flashing details are to be made of the same if not similar material to what it is being attached
to.
All tile or slate flashings must extend up the roof and under the next full tile or slate.
Flashings will need to be designed so as they facilitate the southern weather pattern that is
regular in the Sydney area.
Roof penetration and flashing details are attached in the appendix in the rear of this
standard. Where a detail is not covered by this standard, a detailed design of the proposed
penetration must be submitted to UI for approval.
The pan flashing is to cover at least one ridge either side of the penetration. The pan flashing
must extend up to the ridge.
Multiple pipes are not be flashed by one flashing component. Each service or piece of
equipment will be dedicated its own silicone flashing.
6.4.7 Movement
Roofs and roofing components are invariably constructed from a number of materials which
may adjoin or overlay one another. Each material has its own physical properties, including the
degree the material will move with changes in temperature and moisture. Wherever two
different materials meet or overlap they must be detailed in such a way as to allow the
primary function of the roof to perform, which is to exclude rainwater.
The co-efficiency of each roofing material will need to be considered in the design. Each
material has a different rate of expansion and contraction. Expansion joints or overlapping of
materials needs to be taken into consideration when planning long runs of materials. All
expansion joints and roof overlap details must be submitted to UI for approval.
Where contact between dissimilar metals cannot be avoided, suitable galvanic separation
materials must be placed between those metals to eliminate direct contact. Separation
materials must be weather resistant, UV stable, durable and chemically inert.
6.4.9 Jointing
Only soft soldered, welded, brazed or lapped joints will be approved for use. If proven that
a silicone joint is the only possible solution, full details of the joint must be submitted for
approval by UI.
Dry Joints
Dry joints are the pinnacle of all flashing detail. This jointing detail allows movement between
a number of materials. Dry joints do not depend on silicone or any other sealant as the
waterproofing component. Dry joints can be adapted to any surface, component or structure.
Wet Joints
Wet joints are approved to be used within the University. The wet joint must be used with a
means of mechanical fixing. For mechanical fixings, a staggered pattern of the fixings must be
adopted across the joint. The mechanical fixings are to be installed then the jointing compound
is to be sweated in and around the rivets.
Silicone joints
Silicone must only be used when sandwiched between two surfaces by means of mechanical
fixings. The mechanical fixings must be installed in a staggered pattern. Silicone is not to be
used as a gap filler. Silicone is designed to be sandwiched between two surfaces.
6.4.10 Gutters
Gutters are one of the major causes of leaks into the University’s buildings. Gutters are
susceptible to blocking, overflowing and causing damage to the buildings external and internal
fabric. Fail-safe designs are to be achieved to alleviate any possible malfunction of the gutter.
Box gutters must not be installed without specific approval from UI. Listed are minimum
requirements in order of preference for guttering within the University.
6.4.10.1 Eaves Gutters
a. The face of eaves gutters must not finish higher than the back of the gutter.
b. Eaves gutters to have an aluminium silicone coated leaf guard installed.
c. All gutter guards are to be easily removable.
d. All leaf guards must be submitted for approval by UI.
6.4.10.2 Valley Gutters
a. Valley gutters must be adequately supported by valley boards running the entire length
of the gutter.
A slotted overflow no less than three quarters of the length of the rain head must be included
in the design. The overflow must be installed no less than 100mm from the end of any
ancillary product supplying the rain head. The capacity of the overflow is to be no less than 1
½ times the size of the gutters/downpipes supplying the rain head.
For further information regarding roof plumbing please refer to the UI Hydraulic Services
Standard.
6.4.15 Insulation
All new roofs must achieve a system thermal resistance of R-value 2.5 or greater. Insulation
fixed at the rafters is recommended over ceiling batts. Thermal requirements must meet or
exceed those outlined in Section J of the National Construction Code, and the Building and
Architecture Standard.
6.4.16 Plant
All plant and equipment must be installed in a plant room fit for purpose. This creates fewer
penetrations through the roof surface.
Where unachievable, approval must be sought from UI to install a platform to house the plant.
The platform must be constructed of Aluminium and is to be a prefabricated system. The
platform will be constructed in such a way that the roof surface and plant equipment are
easily accessible.
A minimum distance of 600mm must be provided between the roof surface and the platform.
This distance also relates to the lowest point of any equipment installed on or below the
platform. This clearance may be reduced for items which are liftable without mechanical
assistance such as condenser units.
Platforms are to be designed so that the sections of the platform can be disassembled to allow
access for roof maintenance. This also reduces cutting of the material and hot works when
installing.
All platforms are to comply with the current version of AS/NZS 1657.
6.4.18 Materials
Different roof types require different levels of skill and design. All materials must be of high
quality with no blemishes or damage. Existing Materials that are found to be of inferior
quality will be removed at the contractor’s expense. Heritage roof alterations must be
approved by the University’s Heritage Architect and installed by a competent contractor with
demonstrated experience on Heritage roofing systems. Below are the approved materials and
their design requirements:
6.4.18.1 Steel and Aluminium
a. Roofing – Minimum 0.48mm BMT
b. Flashings/Guttering – Minimum 0.60mm BMT
The selected profile of the roof must be fit for purpose. Where practicable the roof sheet
profile must be of the “KLIP LOK” or other internal fastening type. Aspects such as building
location (coastal, inland, near chemical fall out or industrial areas), climate and classification of
All tiles selected for use on the university’s roofs are to be of the “glazed” type. All tiles must
match existing colour of building and/or match existing roof. Pitch and rafter length will
dictate tile selection. Every tiled roof must include an anti-ponding board that runs down from
the first batten to the top plate. Appropriate moisture resistant sarking is to be included in the
construction of the roof.
6.4.18.3 Membrane
a. Roofing – Minimum 3-layer Polyester Bitumen Sheet
b. Flashings/Guttering – Minimum 3-layer Polyester Bitumen Sheet
All membrane roofs are to be of the polyester bitumen base sheet system. This system provides
excellent flexibility for building movement. This membrane system also provides for quick and
straightforward repairs and alterations. The bottom sheets must be a vented sheet if there is a
likely hood of residual moister in the substrate. The top sheet must include a mineral layer. The
membrane is to be provided with means of venting moisture either at the perimeter of the roof
or with the use of vent cowls spaced across the roof area.
6.4.18.4 Copper
a. Roofing - 0.7mm soft drawn
b. Flashings/guttering - 0.7mm half hard
Joints in copper roofing, guttering and downpipes are to be seamed or welded together
rather than screwed or rivet fixed. Dry joints in copper must have a minimum of a 75mm
overlap. Wet joints to have a minimum of 35mm.Copper roof sheet must be separated from its
supporting deck with a layer of polyester reinforced bitumen sheet for cushioning effect.
6.4.18.5 Lead
a. Roofing – Minimum 25kg/m2
b. Flashings/Guttering – Minimum 30kg/m2
Sections of ridges and valleys to have a maximum length of 1500mm. Dry joints 75mm, wet
joint 35mm overlap. All lead roofing, flashing or capping must have patination oil applied
upon completion of the works.
6.4.18.6 Slate
a. Roofing – Welsh or Canadian
b. Flashings/Guttering - Nil
Slate tiles are to be pre-drilled not punched and must be fixed with copper clouts that fit
snugly into the hole. Copper straps 0.55mm and 20mm wide are to be used to secure the last
few slates when finishing off. Slate hooks are not to be used.
A project specific commissioning plan is to be developed and provided to the University for
review and approval.
Detailed testing and commissioning records must be provided for each system and each
component as appropriate. All such records must be witnessed and verified by the project
consultant/head contractor prior to witness commissioning by UI Engineers and COS
representatives.
Project handover plan must be developed by the consultant/designer to allow the system to be
handed over to The University. A 12-month building tuning process will commence at Project
handover with systems monitored monthly, reported and assessed quarterly, and include
assessment of feedback from the occupants.
All roof components must be subjected to testing before Practical Completion is awarded.
Photo evidence and a site visit from the UI Engineer must be organised during the testing.
Detailed testing and commissioning records must be provided for each system and each
component as appropriate. All such records must be witnessed and verified by the project
consultant/designer.
Below are the minimum standards required for the following components;
a. Membrane roofs - these roofs must be flood tested so as all of the roof area will be
covered with at least 10mm of water. All membrane roofs are to be tested after the first
and last layer of membrane is applied. Bungs used to block the sumps/outlets are to be of
the manufactured type or rags bundled with electrical tape. All bungs are to have rope or
wire attached so it cannot be lost down the outlet. The wire or rope must be securely
fastened to a nearby structure. Testing must take place for at least 24hrs.
b. Box gutters-. these gutters must be flood tested so the highest point of the box gutter has
at least 10mm coverage of water. Bungs used to block the sumps/outlets are to be of the
manufactured type or rags bundled with electrical tape. All bungs need to have rope or
wire attached so it cannot be lost down the outlet. The wire or rope must be securely
fastened to a nearby structure. All testing must take place for at least 24hrs.
c. Roof plumbing- the entire above ground stormwater system must be placed under a
hydrostatic test. All rain heads and sumps must undergo hydrostatic testing. All testing must
take place for at least 24hrs.
d. Penetrations – all penetrations will be subject to a half hour water test. This water test will
consist of a constant spray from a hose mimicking a rain event.
e. Mechanically Fastened Safety Systems – This type of safety system includes steel or
concrete as the base material. Load testing must be conducted to confirm the safety system
supports the designed load. Documents confirming the test results must be signed by the
consultant/contractor. A structural engineer’s certification for all anchor points and the
entire safety system, must included in the Operational and Maintenance manuals.
f. Clamped/Braced Safety Systems – This type of system includes timber as the base
material. Load testing must be conducted to confirm the safety system supports the
designed load. Documents confirming the test results must be signed by the
consultant/contractor. A structural engineer’s certification for all anchor points and the
entire safety system, must be included in the Operational and Maintenance manuals.
Design risks must be considered for the asset lifecycle covering construction, operational and
maintenance, refurbishments and decommissioning.
This may be provided as a design risk register where appropriate and must include results of
any calculations, testing and analysis etc.
This documentation must be provided by the consultant/contractor in both electronic and hard
copy formats and approved by the University.
This documentation must be provided by the contractor in both electronic and hard copy
formats and approved by the University prior to Practical Completion being granted.
Each asset required to be collected can be found in the Form COS-ASSET-F001, each asset
required to be coded will be identified by a unique equipment code.
Asset lists are to be submitted prior to practical completion of the project for review and
approval by COS.
Equipment Warranties are to be provided for a minimum of 12 months from the date of
practical completion. Warranties are to be provided as certificates as part of the O&M from
the supplier of the equipment. It is the responsibility of the installation contractor to ensure all
maintenance/ servicing required to the equipment is provided to ensure warranties are valid
at the end of the project DLP period.
11 Operations
Access to all roofs within the University is controlled by a University of Sydney roof access
permit. This permit must be submitted at least 3 business days before the start of works.
This permit provides the University with vital information about the applicant. Permits are to be
submitted to the University delegate. The University delegate will review risk assessments and
SWMS before access is granted.
Access to roofs must be through a plant room, stairwell or roof space. Access must not be
situated in an area freely accessible to the public. Roof spaces used to access roofs are to be
fitted out with walkways and lighting.
If you require University Security patrol to give you access to a roof area, you must submit a
Service Request in Campus Assist Online (ask your UI/ COS representative if you don't have
access to Campus Assist Online) on the preceding business day and at least 24 hours before
the requested time. You must attach the authorised Permit to Work to the Service Request.
Any details which will affect the future performance of the new or upgraded equipment must
be supplied by the installation contractor at Practical Completion.
Prior to completion of the DLP, a final inspection of the installed systems will be carried out by
the: installation contractor, appropriate UI and COS staff, and University services maintenance
contractor, in order to reconcile the performance of the equipment during DLP to produce a
final list of project defects. All project defects identified must be rectified by the installation
contractor prior to finalisation of the DLP.
Discuss with UI to understand what format to submit the O&M Manuals. Typical submissions
come via soft copy (editable) and used via a system like Aconex.
Contractors must submit the university designed Asset Management Master Asset Data Capture
Spreadsheet (COS-ASSET-F001) designed for recording operational and maintenance
activities including materials used, test results, comments for future maintenance actions and
notes covering asset condition. Completed logbook pages recording the operational and
maintenance activities undertaken for Practical Completion and during the Defects Liability
Period must also be provided.
Facilities Maintenance must establish, document and implement procedures for operation and
maintenance of fire services, plant and equipment to ensure fire services are fit-for-purpose,
provide secure, efficient, safe and reliable electrical power, and comply with requirements of
this standard.
14 Authorisation of Variations
Project managers, consultants, contractors, commissioning agents and facilities maintenance
personnel must ensure compliance with these requirements is achieved.
Consultants and contractors must identify and justify requirements of the standard that do not
apply to the project or which need to be varied and these which must be approved by the
issuer of this standard. Formal requests for all variations to this Standard must be submitted
using the UI Request for Dispensation Form (UI-ENG-F001). The issuer of this standard or their
delegated authority must review and consider requirements of stakeholders from clients,
projects and facilities management before deciding whether to approve variations. Their
formal sign-off is required for acceptance of any non-compliances and departures from this
standard’s requirements.
15 Quality Control
15.1 Design Standard Compliance
Compliance with requirements of this standard must be checked throughout the design,
construction and commissioning phases of projects by UI’ services consultant. Any issues or
deviations from this standard must be reviewed and approved in writing by the issuer of this
standard.
Competent UI consultants and representatives must check compliance with this standard during
design reviews and formal site inspections. Any non-conformances with requirements of this
standard must be documented and provided to the UI Project Manager for issue to contractors
and their consultants.
Project Managers must maintain a formal register of non-conformances and manage close out
of outstanding non-conformances. Contractors and their consultants issued with non-
conformances must take appropriate corrective actions. The UI Project Manager must ensure:
a. Proposed corrective actions are implemented.
b. Close out of non-conformances in relation to this standard is formally approved and signed
off by the author of the standard or their delegate.
Notwithstanding UI’s internal quality control processes, contractors and their consultants must
implement their own robust quality assurance and control procedures to ensure compliance with
requirements of this standard.
15.4 Acceptance
The University will only accept projects as complete when all of the above have been carried
out, submitted and verified.
The above standards are not an exhaustive list of the relevant requirements. The
consultant/contractor must incorporate all relevant standards and Authorities requirements into
project specific design, documentation and installation.
16 References
Design and documentation utilising these standards is to incorporate the requirements of the
following current standards and requirements as a minimum:
a. AS/NZS 3500 Plumbing and Drainage
b. HB39-1997 Installation code for metal roof and wall cladding
c. National Construction Code
d. AS/NZS 1891-2001 Height safety and Re-Certification
e. AS/NZS 4488 Industrial Rope Access Systems
f. A3 4349 1998 Building Inspections
g. Australian Bureau of Meteorology
h. Traditional Copper Roofing (Author: H. Glover and D.E. Toner)
i. Code of Practice Safe Work on Roofs 1993 (Work Cover)
j. AS 2050 Installation of Roof Tiles
k. The above standards are not an exhaustive list of the relevant requirements. The
consultant/contractor must incorporate all relevant standards into project specific design
and documentation.
18 Attachments
Attachment 1 – Standard Roof and Wall Services Penetration Details
INDEX
Sheet Detail
Number Number Item Description Current Revision
- - Short Form Specification of Minimum Standards for Materials and C
Details
1 1 Wall flashing folded sheet metal over membrane roof – cut in type A
_________________________________________________________________________________________________
Revision C: 05.03.04 Page 1 of 2
UNIVERSITY OF SYDNEY
INDEX
Sheet Detail
Number Number Item Description Current Revision
20 26 Small diameter penetration spigots, lead, for slate/ tile roofs A
(section)
21 27 & 28 Concrete pad and unistrut bracket mounting for hydraulic, electrical and A
refrigeration lines transversing membrane on concrete roof.
22 29 uPVC fume cupboard exhaust through membrane on concrete B
roof (section)
23 30 Wall flashing, lead, over membrane/ concrete roof – no cavity A
Colorbond roofs - 8, 9, 10, 19, 20, 21, 22, 23, 34, 35, 38, 39, 42, 45
Membrane roofs - 1, 2, 5, 6, 7, 11, 12, 13, 14, 27, 28, 29, 30, 31, 32, 33, 36, 37, 40
Slate/ tile roofs - 15, 16, 17, 18, 24, 25, 26, 41, 44
Copper roofs - 3, 4, 23
_________________________________________________________________________________________________
Revision C: 05.03.04 Page 2 of 2
sealant to be polyurethane compatible with
adjacent materials
35
sawcut 10 x 35 mm slot in wall, apply continuous
bedding layer of sealant, insert flashing, point up with
sealant out to face of wall
remove redundant flashing (where applicable) &
100
1 VERTICAL SECTION
1:5 CUT-IN FLASHING TO WALL
2 VERTICAL SECTION
1:5 PRESSURE SEAL FLASHING TO WALL
UNIVERSITY OF SYDNEY - FACILITIES MANAGEMENT OFFICE DETAILS
STANDARD ROOFING AND WATERPROOFING DETAILS
SCALE: 1:5 DATE: 07.05.02 REV No: A SHEET No: 01
1
Prepared by DTB Architects Pty Ltd 2
face sandstone wall
see Detail A below
polyurethane sealant
in purpose cut rebate
150 min.
concealed copper
fixing clips at 600 cts
3 VERTICAL SECTION
1:5 COPPER CUT-IN FLASHING TO STONE WALL
35
30
polyurethane sealant
folded copper
overflashing
welted joint
clip fixing
upstand edge of
copper roof sheet
4 VERTICAL SECTION
1:2 DETAIL A
60 min.
120
open
450
open
DETAIL 6
120
fold out bottom edge to form fix to roof with brass screws into
fixing flange plastic masonry plugs
5 PLAN
1:5 BOXING FOR MAJOR ROOF PENETRATIONS
CONCRETE ROOF
UNIVERSITY OF SYDNEY - FACILITIES MANAGEMENT OFFICE DETAIL
STANDARD ROOFING AND WATERPROOFING DETAILS
SCALE: 1:5 DATE: 07.05.02 REV No: A SHEET No: 03 5
Prepared by DTB Architects Pty Ltd
NOTE: box construction to be same material throughout u.n.o.
ie. all colorbond, or
all gal., or
all copper etc.
cap/ plug
100
30 x 30 x 1 copper angle
welded to inside copper box
topping
150
200
eq.
eq.
6 VERTICAL SECTION
1:5 BOXING FOR MAJOR ROOF PENETRATIONS
CONCRETE ROOF WITH MEMBRANE AND TOPPING SLAB
UNIVERSITY OF SYDNEY - FACILITIES MANAGEMENT OFFICE DETAIL
STANDARD ROOFING AND WATERPROOFING DETAILS
SCALE: 1:5 DATE: 07.05.02 REV No: A SHEET No: 04 6
Prepared by DTB Architects Pty Ltd
NOTE: box construction to be same material throughout u.n.o.
ie. all colorbond, or
all gal., or
all copper etc.
100 copper sliding lid
30 x 30 x 1 copper angle
450
topping
150
site measure
eq.
eq.
7 VERTICAL SECTION
1:5 BOXING FOR MAJOR ROOF PENETRATIONS
CONCRETE ROOF WITH MEMBRANE AND TOPPING SLAB
UNIVERSITY OF SYDNEY - FACILITIES MANAGEMENT OFFICE DETAIL
STANDARD ROOFING AND WATERPROOFING DETAILS
SCALE: 1:5 DATE: 07.05.02 REV No: A SHEET No: 05
7
Prepared by DTB Architects Pty Ltd
200 400 200
FALL
see upstream
flashing detail no. 23
coach screws
open
DETAIL 9
FALL FALL
open
fold up (bottom
200
sheet)
8 PLAN
1:5 BOXING FOR MAJOR ROOF PENETRATIONS
METAL DECK ROOF ON TIMBER FRAME
UNIVERSITY OF SYDNEY - FACILITIES MANAGEMENT OFFICE DETAIL
STANDARD ROOFING AND WATERPROOFING DETAILS
SCALE: 1:5 DATE: 07.05.02 REV No: A SHEET No: 06
8
Prepared by DTB Architects Pty Ltd
NOTE: box construction to be same material throughout u.n.o.
ie. all colorbond, or
all gal., or
all copper etc.
Ø 40 Ø 40
Dektite collar flashing
to penetrations
site measure
timber
trimmer
eq.
battens
silicone seal
lapped sheets
eq.
9 VERTICAL SECTION
1:5 BOXING FOR MAJOR ROOF PENETRATIONS
METAL DECK ROOF ON TIMBER FRAME
UNIVERSITY OF SYDNEY - FACILITIES MANAGEMENT OFFICE DETAIL
STANDARD ROOFING AND WATERPROOFING DETAILS
SCALE: 1:5 DATE: 07.05.02 REV No: A SHEET No: 07
9
Prepared by DTB Architects Pty Ltd
NOTE: box construction to be same material throughout u.n.o.
ie. all colorbond, or
all gal., or
all copper etc.
Ø 40 Ø 40
Dektite collar flashing
to penetrations
extend
cover to
ridge
50
site measure
eq. eq.
new timber
P1001 Unistrut welded to 200 x 50 x 5 MS trimmers
plate hot dip galvanised end plates and
bolted through to purlins/ rafters existing rafter
framing (VOS)
10 VERTICAL SECTION
1:5 BOXING FOR MAJOR ROOF PENETRATIONS
METAL DECK ROOF ON TIMBER FRAME
UNIVERSITY OF SYDNEY - FACILITIES MANAGEMENT OFFICE DETAIL
STANDARD ROOFING AND WATERPROOFING DETAILS
SCALE: 1:5 DATE: 07.05.02 REV No: A SHEET No: 08
10
Prepared by DTB Architects Pty Ltd
230 120 200 120
60 min.
120
open
DETAIL 14
120
DETAIL 13
11 PLAN
1:5 BOXING FOR MINOR ROOF PENETRATIONS
12 ELEVATION
1:5 BOXING FOR MINOR ROOF PENETRATIONS
TOP PORTIONS - CONCRETE ROOFS
UNIVERSITY OF SYDNEY - FACILITIES MANAGEMENT OFFICE DETAILS
STANDARD ROOFING AND WATERPROOFING DETAILS
SCALE: 1:5 DATE: 07.05.02 REV No: A SHEET No: 09 11
Prepared by DTB Architects Pty Ltd 12
copper sliding lid
safe edge
topping
waterproof membrane
layed over cement cove or
hardwood fillet (50mm
min. radius)
13 VERTICAL SECTION
1:5 BOXING FOR MINOR ROOF PENETRATIONS
CONCRETE ROOF WITH MEMBRANE & TOPPING SLAB
UNIVERSITY OF SYDNEY - FACILITIES MANAGEMENT OFFICE DETAIL
STANDARD ROOFING AND WATERPROOFING DETAILS
SCALE: 1:5 DATE: 07.05.02 REV No: A SHEET No: 10 13
Prepared by DTB Architects Pty Ltd
copper sliding lid
safe edge
5°
200
waterproof membrane
layed over cement cove or
hardwood fillet (50mm
min. radius)
14 VERTICAL SECTION
1:5 BOXING FOR MINOR ROOF PENETRATIONS
CONCRETE ROOF WITH MEMBRANE & TOPPING SLAB
UNIVERSITY OF SYDNEY - FACILITIES MANAGEMENT OFFICE DETAIL
STANDARD ROOFING AND WATERPROOFING DETAILS
SCALE: 1:5 DATE: 07.05.02 REV No: A SHEET No: 11 14
Prepared by DTB Architects Pty Ltd
230 120 200 120
60 min.
120
open
DETAIL 18
120
DETAIL 17
15 PLAN
1:5 BOXING FOR MINOR ROOF PENETRATIONS
16 ELEVATION
1:5 BOXING FOR MINOR ROOF PENETRATIONS
TOP PORTION - TILE AND SLATE ROOFS
UNIVERSITY OF SYDNEY - FACILITIES MANAGEMENT OFFICE DETAILS
STANDARD ROOFING AND WATERPROOFING DETAILS
SCALE: 1:5 DATE: 07.05.02 REV No: A SHEET No: 12 15
Prepared by DTB Architects Pty Ltd 16
copper sliding lid
safe edge
200 MIN.
new timber packers lead flashing
17 VERTICAL SECTION
1:5 BOXING FOR MINOR ROOF PENETRATIONS
TILE & SLATE ROOFS
UNIVERSITY OF SYDNEY - FACILITIES MANAGEMENT OFFICE DETAIL
STANDARD ROOFING AND WATERPROOFING DETAILS
SCALE: 1:5 DATE: 07.05.02 REV No: A SHEET No: 13 17
Prepared by DTB Architects Pty Ltd
copper sliding lid
5° safe edge
200
cap/ plug end
see also detail 24
450 top
copper rebate
10mm (welded)
200
150
lead flashing
slates
18 VERTICAL SECTION
1:5 BOXING FOR MINOR ROOF PENETRATIONS
SLATE & TILE ROOFS
UNIVERSITY OF SYDNEY - FACILITIES MANAGEMENT OFFICE DETAIL
STANDARD ROOFING AND WATERPROOFING DETAILS
SCALE: 1:5 DATE: 07.05.02 REV No: A SHEET No: 14 18
Prepared by DTB Architects Pty Ltd
230 120 200 120
60 min.
120
open
DETAIL 22
120
DETAIL 21
19 PLAN
1:5 BOXING FOR MINOR ROOF PENETRATIONS
20 ELEVATION
1:5 BOXING FOR MINOR ROOF PENETRATIONS
TOP PORTION - METAL DECK ROOFS
UNIVERSITY OF SYDNEY - FACILITIES MANAGEMENT OFFICE DETAILS
STANDARD ROOFING AND WATERPROOFING DETAILS
SCALE: 1:5 DATE: 07.05.02 REV No: A SHEET No: 15 19
Prepared by DTB Architects Pty Ltd 20
colorbond steel sliding lid
safe edge
colorbond flashing
timber
silicone seal trimmer
new timber packers lapped sheets battens
21 VERTICAL SECTION
1:5 BOXING FOR MINOR ROOF PENETRATIONS
METAL DECK ROOFS ON TIMBER FRAMES
UNIVERSITY OF SYDNEY - FACILITIES MANAGEMENT OFFICE DETAIL
STANDARD ROOFING AND WATERPROOFING DETAILS
SCALE: 1:5 DATE: 07.05.02 REV No: A SHEET No: 16 21
Prepared by DTB Architects Pty Ltd
colorbond steel sliding lid
5° safe edge
200
cap/ plug end
450 top
of box
silicone seal
50
lapped sheets
22 VERTICAL SECTION
1:5 BOXING FOR MINOR ROOF PENETRATIONS
METAL DECK ROOFS ON TIMBER FRAMES
UNIVERSITY OF SYDNEY - FACILITIES MANAGEMENT OFFICE DETAIL
STANDARD ROOFING AND WATERPROOFING DETAILS
SCALE: 1:5 DATE: 07.05.02 REV No: A SHEET No: 17 22
Prepared by DTB Architects Pty Ltd
ridge (or wall/ parapet etc.)
SIDE
23 ISOMETRIC - EXPLODED
1:5 FLASHING FOR MAJOR ROOF PENETRATIONS
METAL DECK ROOFS
UNIVERSITY OF SYDNEY - FACILITIES MANAGEMENT OFFICE DETAIL
STANDARD ROOFING AND WATERPROOFING DETAILS
SCALE: 1:5 DATE: 07.05.02 REV No: A SHEET No: 18 23
Prepared by DTB Architects Pty Ltd
fold back top edge
of lead flashing
slate
lead
sheet
flashing
e
ec
on underside
pi
vertical spigot seamed
e
gl
sin
on down hill side
t-
ee
sh
ad
le
of
nt
slates
te
ex
box gutter
24 VERTICAL SECTION
1:5 LEAD FLASHING FOR PIPE OR CONDUIT PENETRATION -
SLATE AND TILE ROOFS
UNIVERSITY OF SYDNEY - FACILITIES MANAGEMENT OFFICE DETAIL
STANDARD ROOFING AND WATERPROOFING DETAILS
lead flashing
sheet
25 ISO VIEWS
1:5 LEAD FLASHING FOR SERVICES
PENETRATION - SLATE OT TILE ROOF
service pipe
vertical spigot
lead spigot - angle down lead flashing sheet
approx. 5 degrees lead flashing sheet
services
100
min.
26 VERTICAL SECTIONS
1:5 LEAD FLASHING FOR PIPE OR CONDUIT PENETRATION -
SLATE AND TILE ROOFS
UNIVERSITY OF SYDNEY - FACILITIES MANAGEMENT OFFICE DETAILS
STANDARD ROOFING AND WATERPROOFING DETAILS
SCALE: 1:5 DATE: 07.05.02 REV No: A SHEET No: 20 25
Prepared by DTB Architects Pty Ltd 26
300
100
PLAN
450 - 600 mm
25 MPa concrete
180 nom.
300
40
100
pvc or stainless
turn membrane up behind steel cover flange
pvc cover - provide cement with stiffening
fillet to support membrane gussets (4 no.)
101 min.
paving slab
existing built up roof topping slab or insulation
roof structure
(as applicable)
29 SECTION
1:5 FLUE PENETRATION
CONCRETE ROOF WITH MEMBRANE AND TOPPING
UNIVERSITY OF SYDNEY - FACILITIES MANAGEMENT OFFICE DETAIL
STANDARD ROOFING AND WATERPROOFING DETAILS
SCALE: 1:5 DATE: 05.03.04 REV No: B SHEET No: 22 29
Prepared by DTB Architects Pty Ltd
DETAIL - LONGITUDINAL DETAIL
JOINT 1:2
1:2
sealant between top of
lead lapped
concrete wall flashing and concrete
and folded
brick wall
lead flashing screw or clout
50 NOM. fixed to concrete wall then
turned over at top to
protect fixing
150
not bond or fix membrane to flashing - (remove existing roof membranes)
allow differential movement
structur
topping slab
e
(where
applicable)
30 SECTION
1:1 FLASHING AT BRICK/CONCRETE WALL - NO
0
CAVITY
install new flashing over existing in same form new weep holes or clean
material - new flashing to extend out from out existing weep holes
wall face and dress down over new
membrane
32 PLAN
1:5 AT VENT PIPE
33 SECTION
1:5 AT VENT PIPE
CONCRETE ROOF WITH MEMBRANE
UNIVERSITY OF SYDNEY - FACILITIES MANAGEMENT OFFICE DETAILS
STANDARD ROOFING AND WATERPROOFING DETAILS
SCALE: 1:5 DATE: 07.05.02 REV No: A SHEET No: 24 32
Prepared by DTB Architects Pty Ltd 33
metal decking
34 PLAN
1:5 AT VENT PIPE
cover flashing
(see also detail 45)
roof sheet
new packers
turn up cut ends
35 SECTION
1:5 AT VENT PIPE
METAL DECK ROOF ON TIMBER FRAME
UNIVERSITY OF SYDNEY - FACILITIES MANAGEMENT OFFICE DETAILS
STANDARD ROOFING AND WATERPROOFING DETAILS
SCALE: 1:5 DATE: 20.11.03 REV No: B SHEET No: 25 34
Prepared by DTB Architects Pty Ltd 35
cement fillets by
membrane applicator
36 PLAN
1:5 AT STEEL POST BASE
cement fillets by
membrane applicator
locally chop out and steel base plate & bolt connection to
main slab
replace topping slab structural engineers details
37 SECTION
1:5 AT STEEL POST BASE
CONCRETE ROOF WITH MEMBRANE AND TOPPING
UNIVERSITY OF SYDNEY - FACILITIES MANAGEMENT OFFICE DETAILS
STANDARD ROOFING AND WATERPROOFING DETAILS
SCALE: 1:5 DATE: 21.05.02 REV No: A SHEET No: 26 36
Prepared by DTB Architects Pty Ltd 37
Dektight collar flashing (mechanically
fixed at ridges only)
38 PLAN
1:5 AT STEEL POST BASE
600 MM CLEARANCE
steel apron welded to pipe 600 mm CLEARANCE
5mm x 25mm (for maintenance
access.)
stainless steel ring clamp
cover flashing
'Dektite' (or equal)
typical metal pan
collar flashing
roof sheeting
sealant
cover flashing
(see also detail 45)
typical roof pan
39 SECTION
1:5 AT STEEL POST BASE
METAL DECK ROOF ON STEEL FRAME
UNIVERSITY OF SYDNEY - FACILITIES MANAGEMENT OFFICE DETAILS
STANDARD ROOFING AND WATERPROOFING DETAILS
SCALE: 1:5 DATE: 20.11.03 REV No: B SHEET No: 27 38
Prepared by DTB Architects Pty Ltd 39
max.
30 13 24
furring channel
150 MIN.
50 min.
190 (min)
150 (max)
40 SECTION
1:5 MEMBRANE FLASHING AT WALL
WITH OVERCLADDING & DISH DRAIN
UNIVERSITY OF SYDNEY - FACILITIES MANAGEMENT OFFICE DETAIL
STANDARD ROOFING AND WATERPROOFING DETAILS
SCALE: 1:5 DATE: 21.05.02 REV No: A SHEET No: 28 40
Prepared by DTB Architects Pty Ltd
See also detail 24
PVC or stainless
steel duct
PVC or stainless
steel weld
PVC or stainless
steel skirt
150 min.
Lead flashing
fla in.
g
steel joint (skirt)
in
le 0 0 m
sh
2
ad
Locally remove tiles,
sarking and battens
41 SECTION
1:5 PVC DUCT PENETRATION
SLATE AND TILE ROOFS
UNIVERSITY OF SYDNEY - FACILITIES MANAGEMENT OFFICE DETAIL
STANDARD ROOFING AND WATERPROOFING DETAILS
SCALE: 1:5 DATE: 05.03.04 REV No: B SHEET No: 29 41
Prepared by DTB Architects Pty Ltd
PVC or stainless
steel duct
PVC or stainless
steel weld
PVC or stainless
steel skirt PVC or stainless steel cover
150 min.
welded pvc or
50
Locally remove
sheeting, sarking
and battens/ purlins
Trim penetration
with new battens/
purling
42 SECTION
1:5 PVC DUCT PENETRATION
METAL DECK ROOF ON TIMBER FRAME
UNIVERSITY OF SYDNEY - FACILITIES MANAGEMENT OFFICE DETAIL
STANDARD ROOFING AND WATERPROOFING DETAILS
SCALE: 1:5 DATE: 05.03.04 REV No: B SHEET No: 30 42
Prepared by DTB Architects Pty Ltd
NOTE: Preferred material of construction is copper.
Where copper is not possible (eg. Due to presence
of other less noble metals) use colorbond steel.
50
60
INSIDE
40
OUTSIDE
solid back
3
35 150
(VARY TO SUIT PIPE)
30°
copper hood
(removable)
pipe
safe edge
corner cleats
fla in.
g
in
le 0 0 m
sh
2
ad
lead flashing
slates
44 SECTION
1:5 AT VENT PIPE
SLATE AND TILE ROOFS
UNIVERSITY OF SYDNEY - FACILITIES MANAGEMENT OFFICE DETAIL
STANDARD ROOFING AND WATERPROOFING DETAILS
SCALE: 1:5 DATE: 07.05.02 REV No: A SHEET No: 32 44
Prepared by DTB Architects Pty Ltd
ridge (or wall/ parapet etc.)
pipe, vent or
platform leg
N.
MI
0
20
45 ISOMETRIC
1:5 COVER FLASHING FOR PENETRATIONS IN
CONJUNCTION WITH PROPRIETRY PIPE/CONDUIT
FLASHINGS - METAL DECK ROOFS
UNIVERSITY OF SYDNEY - FACILITIES MANAGEMENT OFFICE DETAIL
STANDARD ROOFING AND WATERPROOFING DETAILS
SCALE: 1:5 DATE: 20.11.03 REV No: A SHEET No: 33 45
Prepared by DTB Architects Pty Ltd