Line Break, Equip Opening Permit

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

National Refinery Limited NRL-FAF-FPR-001 (A)

Permit No.__________
EQUIPMENT OPENING/LINE BREAK PERMIT Rev. # 00 Date: 23-08-2022

Section 1 – Work Description


A. Identify Plant Facility area:

B. Exact work location:

C. Work to be done

d. Equipment to be used at the site

STOP WORK if job site does not meet work permit conditions and any applicable National Refinery Limited safety and health requirements at any time.

Section 2 – Hazards identification & Control: (Tick mark the Relevant)


A. Identify and attach any supplementary forms required to perform/control the work:
Job Safety Analysis Gas test records Isolation plan Blind list Critical Lift Plan
Excavation Checklist Hydrotest procedure(s) Other ________________________________ Other: _______________________________
B. Energy Types:
Hydrocarbon/gas/steam/chemicals Mechanical Electrical Hydraulic/pneumatic
Potential energy (spring loaded, gravity) Automated extinguishing system Other _________________________________________________
C. Isolation Method(s):
Locked switch/breaker Mechanical block Block valve Single block & bleed
Double block & bleed Blinding Disconnect Others
D. Potential Exposures:
High noise level Hydrogen Sulfide (H2S) Flammable liquids/gases Hazardous/toxic materials High Pressure
Radioactive materials High Temperature Pyrophoric Material Other: _______________________________
E. Protective Equipment:
Personal H2S monitor Gas Masks Goggles/face shield Chemical Suit.coveralls Fall protection
Barricades/warning signs Respiratory protection Additional Safety Precautions
F. Fire Protection Methods:
Fire Extinguisher Fire monitor/hose Area wetted Fire barriers/shields
G. Remove all Ignition sources within 15 m (35 ft) of equipment opening/line break
H. Inform downwind activities (or operations) of equipment opening/line break
I. Fire Watch required J. List any Additional Safety Precautions: ____________________________________________________________
_________________________________________________________________________________________________________________________________
IN AN EMERGENCY: Call at 2329 /2330. In case of Fire Emergency call at 2333.
Section 3 – Gas Testing/Monitoring
Periodic monitoring required: Yes No if yes. Gas testing frequency: ________________________________________________
ONLY CERTIFIED GAS TESTERS PERFORM GAS TESTS
Other gases
LEL (%) H2S (ppm) O2 (%) Date NRL No. Signature
(name/value)
Before break

After break

Section 4 – Permit Authorization & Closure

Issuing Authority Receiving Authority


Duration: From: _________ hrs. To: _______ hrs.
NRL No.
NRL No. Countersignature(s) if applicable: (Manager / Sr. Engineer / Engineer)
Signature
Signature Issuing Authority Receiving Authority
Date:
Date:
________________
This permit is Date: ___________________ Issuing Authority Receiving Authority
renewed / Extended
From: _______ hrs. To: _______ hrs. Sign:_______________ NRL No.:________ Sign:_______________ NRL No.:_______
I HAVE INSPECTED THE WORK SITE AND CONFIRM THAT IT HAS BEEN RETURNED TO A SAFE CONDITION

Issuing Receiving
Permit Closeout: Authority: ________ NRL No. _________ Authority: ________ NRL No. ______

Date: ___________ Time: __________ Date: _________ Time: __________

You might also like