Introduction To Construction Productivity
Introduction To Construction Productivity
Construction
Productivity
by Dr. Ayman Gouda
Contents:
Significance of Construction Productivity
Construction Process
Construction Process Outputs
Construction Process Inputs
Totally consumed resources and
Partially consumed resources
Basics and Terms related to productivity
Product
Production
Production rate
Usage rate
Significance of Productivity:
• To realize Construction project objectives, planned levels of
productivity must be achieved.
• Productivity and quality are the two major driving forces behind the
Construction Engineering discipline.
• Productivity is one of the ,most essential KPIs for any organization
e.g.. Project, Company, Industry or nation).
Significance of Productivity:
• Improving Productivity at the national level will lead to
The survival and growth of any organization, industry, or nation.
Paving the way for firms to pay higher wages.
Making more people buy goods and services because they get
better value for money. So, increasing the country’s ability to
improve the quality of life over time.
Reducing waste and seeing resources used more efficiently.
Solving many economic problems such as inflation,
unemployment, and unstable currency.
Construction Process
Construction processes require INPUTS. The inputs are used in the
PROCESS of producing the construction OUTPUTS/PRODUCTS.
𝒐𝒖𝒕𝒑𝒖𝒕
𝑷𝒓𝒐𝒅𝒖𝒄𝒕𝒊𝒗𝒊𝒕𝒚 =
𝑰𝒏𝒕𝒑𝒕
Rule 2:
To improve productivity, we must produce More Achievement per same or
fewer Resources
To remain competitive, we have to produce more for each pound spent on
construction. And every worker, every level, and every process in the
organization and at a job site can contribute to improved productivity.
“Productivity is about ‘working smarter’, rather than ‘working harder’: it reflects our ability to
produce more output by better combining inputs, thanks to new ideas, technological
innovations and new business models.”
Example: Difference between Production rate and Productivity
• Case 1:
Suppose that at construction site installed10,000m2 of
block woks by employing 50 workers at 8 hours/day for
25 days/month. What are the production, production rate,
and (labor) productivity?
Example: Difference between Production rate and Productivity
• Case 1:
Suppose that at construction site installed10,000m2 of
block woks by employing 50 workers at 8 hours/day for
25 days/month. What are the production, production rate,
and (labor) productivity?
Solution:
Then, in this case:
Production = 10,000 m2
Production rate = 10,000 m2 / month
Labor productivity = total output / labor input
= 10,000 / (50 * 25 * 8)
= 1 m2 / 1 man-hr
Example: Difference between Production rate and Productivity
• Case 1:
Suppose this construction site increased its production to 12,000 m2 by
hiring 10 additional workers at 8 hours/day for 25 days. What are the
production, production rate, and (labor) productivity?
Example: Difference between Production rate and Productivity
• Case 2:
Suppose this construction site increased its production to 12,000 m2 by hiring
10 additional workers at 8 hours/day for 25 days. What are the production,
production rate, and (labor) productivity?
Solution:
Then, in this case:
Production = 12,000 m2
Production rate = 12,000 m2 / month
Labor productivity = total output / labor input
= 12,000 / (60 * 25 * 8)
= 1 m2 / 1 man-hr.
Clearly, the production rate of block works has gone up by 20% (from 10,000 to
12,000 m2 / month), but the labor productivity has not gone up at all.
Example: Difference between Production rate and Productivity
• Case 3:
Suppose this construction site increased its production to 15,000 m2 by
hiring 30 additional workers at 8 hours/day for 25 days. What are the
production, production rate, and (labor) productivity?
Example: Difference between Production rate and Productivity
• Case 3:
Suppose this construction site increased its production to 15,000 m2 by hiring
30 additional workers at 8 hours/day for 25 days. What are the production,
production rate, and (labor) productivity?
Solution:
Then, in this case:
Production = 15,000 m2
Production rate = 15,000 m2 / month
Labor productivity = total output / labor input
= 15,000 / (90 * 25 * 8)
= 0.83 m2 / 1 man-hr.
Clearly, the production rate of block works has gone up by 50% (from 10,000 to
15,000 m2 / month), but the labor productivity has down by 20%.
Example: Difference between Production rate and Productivity
• Case 3:
Suppose this construction site increased its production to 15,000 m2 by hiring
30 additional workers at 8 hours/day for 25 days. What are the production,
production rate, and (labor) productivity?
Solution:
Then, in this case:
Production = 15,000 m2
Production rate = 15,000 m2 / month
Labor productivity = total output / labor input
= 15,000 / (90 * 25 * 8)
= 0.83 m2 / 1 man-hr.
Clearly, the production rate of block works has gone up by 50% (from 10,000 to
15,000 m2 / month), but the labor productivity has down by 20%.
Example 1 (Tutorial)
By reviewing the performance of a construction site, it as fond that a painting
team of three workers had produced 40 m2 of painting work. Owing to
increased demand, it was found necessary to increase output. The team
was increased to four men who produced 50 m2 per day. The operation was
studied, and by using an improved method, the four workers can now
produce 70 m2 per day. Calculate the operation’s output rate and labor
productivity in the three cases.
Example 1 (Tutorial)
Case (1)
Operation’s output rate = 40 m2 / day
Labor productivity = 40 m2 / (3 * 8) = 1.67 m2 /man-hr
Case (2)
Operation’s output rate = 50 m2 / day
Labor productivity = 50 m2 / (4 * 8) = 1.56 m2 /man-hr.
Case (3)
Operation’s output rate = 70 m2 / day
Labor productivity = 70 m2 / (4 * 8) = 2.19 m2 /man-hr.
In case (2), the production rate has risen, but labor productivity has fallen.
In case (3), the production rate and labor productivity have increased.
Example 2 (Tutorial)
In the first four days of erecting interior walls of a school building, a masonry
team of three workers produced 100 m2 of brick work. Owing to owner's
need to shorten activity duration, the contractor decided to increase output.
One mason was hired and added to the team. The team (four workers)
produced 40 m2 in the fifth day. The site engineer studied the operation and
by using an improved method, the four workers produced 90 m2 in the last
two days (sixth and seventh) of the operation.
a) For the above-mentioned three cases, determine the hourly
production rate.
b) For the above-mentioned three cases, determine the unit rate.
c) For the above-mentioned three cases, calculate the labor productivity.
Improving Productivity
Rule 1:
“An increased production (rate) does not necessarily mean increased
productivity.”
Rule 2:
To improve productivity, we must produce More Achievement per same or
fewer Resources
To remain competitive, we have to produce more for each pound spent on
construction. And every worker, every level, and every process in the
organization and at a job site can contribute to improved productivity.
“Productivity is about ‘working smarter’, rather than ‘working harder’: it reflects our ability to
produce more output by better combining inputs, thanks to new ideas, technological
innovations and new business models.”
Improving Productivity
Productivity improvements will occur if any of the following conditions
are made to exist:
𝒐𝒖𝒕𝒑𝒖𝒕
𝑷𝒓𝒐𝒅𝒖𝒄𝒕𝒊𝒗𝒊𝒕𝒚 =
𝑰𝒏𝒕𝒑𝒕
3. Relationship between the result achieved and the resources used (ISO 9000/2015).
According to this definition efficiency ≈ productivity
4. The ratio of actual output attained to expected or standard output.
Example: The output of an operator is 120 pieces per hour while the standard rate is 180
pieces per hour:
Operator efficiency = 120/180 = 66.7%
Effectiveness Definition
1. The degree to which planned objectives are achieved.
𝑨𝒄𝒕𝒖𝒂𝒍 𝑹𝒆𝒔𝒖𝒍𝒕𝒔 𝑨𝒄𝒕𝒖𝒂𝒍 𝑶𝒖𝒕𝒑𝒖𝒕𝒔
𝑬𝒇𝒇𝒆𝒄𝒕𝒊𝒗𝒆𝒏𝒆𝒔𝒔 = =
𝑷𝒍𝒂𝒏𝒏𝒆𝒅 𝑹𝒆𝒔𝒖𝒍𝒕𝒔𝒔 𝑷𝒍𝒂𝒏𝒏𝒆𝒅 𝑶𝒖𝒕𝒑𝒖𝒕𝒔
𝑷𝒍𝒂𝒏𝒏𝒆𝒅 𝑹𝒆𝒔𝒐𝒖𝒓𝒄𝒆𝒔
𝑪𝒐𝒔𝒕𝑬𝒇𝒇𝒆𝒄𝒕𝒊𝒗𝒆𝒏𝒆𝒔𝒔 =
𝑨𝒄𝒕𝒖𝒂𝒍 𝑪𝒐𝒏𝒔𝒎𝒆𝒅 𝑹𝒆𝒔𝒐𝒖𝒓𝒄𝒆𝒔