3 Develop and write report on Business Model Lump Sum 1 250,000.00 25000 50,000.00 325,000.00
for Micro-Utility Owner/Operators
13 Netwire Fencing of Land Area to protect sqm 2,500 5,000.00 550.00 750.00 15,750,000.00
the power house and the solar array etc
14 Other civil works ( Provision of Sqm 2,500 3,000.00 330.00 600.00 9,825,000.00
gravelling, trench and landscaping)
15 8.5m (28')Concrete poles No 160 240,000.00 26,400.00 36,000.00 48,384,000.00
16 Route survey and pegging km 8 150,000.00 16,500.00 22,500.00 1,512,000.00
17 100mm AAC Conductor km 25.3 43,000.00 4,730.00 8,600.00 1,425,149.00
18 Channel iron 3x 2x 21 (11kV) No 0 12,000.00 1,320.00 1,800.00 0.00
19 MV Stay insulator No 53 750.00 82.50 112.50 50,085.00
20 5/8" Stay Wire (mv/11KV) m 320 350.00 38.50 52.50 141,120.00
21 6' stay Rod (MV/11KV) m 53 9,000.00 990.00 1,350.00 601,020.00
22 Double Groove Shacle insulator complete No 640 1,300.00 143.00 195.00 1,048,320.00
with D-iron & pins
23 Sign Board with FMoP logo No 2 56,000.00 6,160.00 8,400.00 141,120.00
24 Earthing Rod No 122 5,000.00 550.00 750.00 768,600.00
25 Earthing Wire ( Copper ) m 30 4,000.00 440.00 600.00 151,200.00
26 Earthing Mat (1m x 1.5m) No 1.00 6,000.00 660.00 900.00 7,560.00
27 16 x 51 Bolts, Nuts & Washers No - - 0.00
28 16 x 152 Bolts, Nuts & Washers No 352 300.00 33.00 45.00 133,056.00
29 16 x 200 Bolts Nuts & Washers No 176 550.00 60.50 82.50 121,968.00
30 16 x 254 Bolts, Nuts & Washers No - - 0.00
31 16 x 280/305 Bolts Nuts & Washers No 160 800.00 88.00 120.00 161,280.00
32 Flat Washer for 22mm Dia No 704 500.00 55.00 75.00 443,520.00
33 Flat Washer for 18mm Dia No 880 430.00 47.30 64.50 476,784.00
34 M20 x 2282 Bolts Nuts & Washers No 1,760 550.00 60.50 82.50 1,219,680.00
35 Phase Colour Disc No 6 22,000.00 2,420.00 3,300.00 166,320.00
36 Pole identification No 160 5,000.00 550.00 750.00 1,008,000.00
37 Barbed Wire (6m/HV Pole) Set - - 0.00
38 Danger Plate No 160 2,200.00 242.00 330.00 443,520.00
39 NEMSA Certification Lot 1 250,000.00 250,000.00
40 PC System + As-Built Drawings No 3 450,000.00 49,500.00 67,500.00 1,701,000.00
41 Services Connection (House) No 120 90,000.00 9,900.00 13,500.00 13,608,000.00
42 Stay Block No 53 3,500.00 385.00 525.00 233,730.00
43 Minimum of 7days on site training on Lump Sum 1 300,000.00 300,000.00
operation of Distribution Networks for the
Owner/Operator and two engineers from
the Ministry
Supply and Installation of Solar Minigrid/Lighting to bring Power Supply to Rural Homes
and Villages at Various Location (Provision of Three - in –One Monocrystalline high
PROJECT TITLE: quality Solar Street Lights compliant with site location climatic conditions and STATE: EBONYI
applicable IEC Industry standards in Ekwetekwe Ogbuinyagu In Ezza North LGA, Ebonyi
State)
BEME (RATE)
Sn COMPONENTS SPECIFICATION DESCRIPTION QTY MATERIAL TRANSP ERECTION
TOTAL COST =N=
SEE ATTACHED
RECOMMENDED
SPECIFICATION OUTLINE
3 FMP Inscription FMP should be written on each of the poles using Green
indelible ink
260 5,000.00 500.00 1,000.00 1,690,000.00
5 Civil Work Refer to the attached concrete mix order (Grade 20 Concrete
with Reinforcement, bolts and nuts) 260 25,000.00 2,500.00 5,000.00 8,450,000.00
7
1 70000.00 7,000.00 14,000.00 91,000.00
Sign Post Dimension attached
SUB - TOTAL
96,083,000.00
8 Allow 5% for feasibility study, design, projects supervision and management.
4,804,150.00
VAT (7.5%) 7,206,225.00
9
GRAND TOTAL
108,093,375.00
10
FINAL SUM
281,098,744.10
AMOUNT IN FIGURE: 281,098,744.10
AMOUNT IN WORDS: Two Hundred and Eighty One million, Ninety eight thousand, Seventy five naira only
AUTHORIZED SIGNATURE:
DATE: 8/11/2021