Detailed Unit Price Analysis (DUPA) - Residential 1
Detailed Unit Price Analysis (DUPA) - Residential 1
Detailed Unit Price Analysis (DUPA) - Residential 1
MARK-UPS
OCM 5%
PROFIT 10%
VALUE ADDED TAX (VAT) 0%
INPUT ONLY ON GRAY CELLS
DIRECT COST
Remarks
Manpower Equipment/
/Labor Tools Materials
ARCHITECTURAL / CIVIL WORKS
Area of the project for clearing 600.00 21,555.20 -
Total concrete volume of Footing & Slab on grade 13,025.21 7,276.75 55,942.60
Determine and input the total area of flush type door 3,543.75 354.38 11,550.00
Determine the total area of Wooden Panel Door 1,604.17 160.42 6,600.00
Manpower / Equipment/
Labor Tools Materials
BUILDING
INDIRECT COST
- - - - #DIV/0!
899.88 1,799.75 - 20,697.17 103.49
- - - - #DIV/0!
- - - - #DIV/0!
- - - - -
- - - - -
- - - -
71,513.05 143,026.11 - 1,644,800.25
Prepared by:
MARK-UPS
TOTAL MARK-UP
ITEM ESTIMATED IN PERCENT TOTAL UNIT
DESCRIPTION QUANTITY UNIT VAT TOTAL COST
NO. DIRECT COST INDIRECT COST COST
OCM PROFIT % VALUE
(9) (10) (11) (12) (13)
-1 (2) (3) (4) (5) (6) (7) (8)
(5)X(8) (5)+(9)) (9)+(10) (5)+(11) (12)/(3)
ARCHITECTURAL / CIVIL WORKS
800(1) CLEARING AND GRUBBING 200.00 SQ.M. 22,155.20 5% 10% 15% 3,323.28 0.00 3,323.28 25,478.48 127.39
800(3)a INDIVIDUAL REMOVAL OF TREES (UPTO 2.00 EACH 4,458.94 5% 10% 15% 668.84 0.00 668.84 5,127.78 2,563.89
803(1)a 300MM DIAMETER)
STRUCTURE EXCAVATION (COMMON SOIL) 23.00 CU.M. 5,193.40 5% 10% 15% 779.01 0.00 779.01 5,972.41 259.67
803(1)a STRUCTURE EXCAVATION (SOFT ROCK) 0.00 CU.M. 0.00 5% 10% 15% 0.00 0.00 0.00 0.00 #DIV/0!
804(4) GRAVEL BEDDING 3.00 CU.M. 5,502.50 5% 10% 15% 825.38 0.00 825.38 6,327.88 2,109.29
902(1) REINFORCING STEEL OF REINFORCED 1,200.00 KGS. 107,711.97 5% 10% 15% 16,156.80 0.00 16,156.80 123,868.77 103.22
CONCRETE STRUCTURES FOR ONE-
STOREY, GRADE 40/60
902(1) REINFORCING STEEL OF REINFORCED 50.00 KGS. 4,513.10 5% 10% 15% 676.97 0.00 676.97 5,190.07 103.80
CONCRETE STRUCTURES FOR TWO UPTO
FIVE STOREY
900(1)c2 STRUCTURAL CONCRETE FOR FOOTING 12.40 CU.M. 76,244.56 5% 10% 15% 11,436.68 0.00 11,436.68 87,681.24 7,071.07
AND SLAB ON FILL (CLASS A, 28 DAYS)
900(1) STRUCTURAL CONCRETE FOR FOOTING 23.60 CU.M. 150,481.03 5% 10% 15% 22,572.15 0.00 22,572.15 173,053.18 7,332.76
903(2) TIE BEAM, COLUMN,
FORMWORKS SUSPENDED SLAB,
AND FALSEWORKS (FOR 49.00 SQ.M. 39,861.41 5% 10% 15% 5,979.21 0.00 5,979.21 45,840.62 935.52
1046 GIRDER/BEAM
100MM CHB NON LOADA,BEARING/LOAD
ONE-STOREY (CLASS
BUILDING) 28 DAYS) 189.00 SQ.M. 150,751.13 5% 10% 15% 22,612.67 0.00 22,612.67 173,363.80 917.27
BEARING (INCLUDING REINFORCING STEEL)
1046 150mm. CHB NON LOAD BEARING (including 36.00 SQ.M. 40,588.30 5% 10% 15% 6,088.25 0.00 6,088.25 46,676.55 1,296.57
Reinforcing Steel)
Page 11 of 61
1027(1) CEMENT PLASTER FINISH WITH 19MM 420.00 SQ.M. 86,319.95 5% 10% 15% 12,947.99 0.00 12,947.99 99,267.94 236.35
THICK & 1:3 MORTAR MIXTURE
1047(2)b STRUCTURAL STEEL ROOF TRUSS 0.00 KGS. 0.00 5% 10% 15% 0.00 0.00 0.00 0.00 #DIV/0!
1047(2)c STRUCTURAL STEEL PURLINS 200.00 KGS. 17,997.54 5% 10% 15% 2,699.63 0.00 2,699.63 20,697.17 103.49
1013(1) CORRUGATED METAL ROOFING 0.00 SQ.M. 0.00 5% 10% 15% 0.00 0.00 0.00 0.00 #DIV/0!
1013(2) FABRICATED METAL ROOFING ACCESSORY 38.00 M. 9,107.71 5% 10% 15% 1,366.16 0.00 1,366.16 10,473.87 275.63
(RIDGE/HIP ROLLS/FLASHING/COUNTER
FLASHING/ VALLEY ROLL)
1013(2) FABRICATED METAL ROOFING ACCESSORY 13.00 M. 3,214.01 5% 10% 15% 482.10 0.00 482.10 3,696.11 284.32
(GUTTER)
1014 PREPAINTED METAL SHEETS 0.00 SQ.M. 0.00 5% 10% 15% 0.00 0.00 0.00 0.00 #DIV/0!
(CORRUGATE, SHORT SPAN/LONG SPAN)
1014 PREPAINTED METAL SHEETS (RIB TYPE 0.4- 140.00 SQ.M. 68,648.33 5% 10% 15% 10,297.25 0.00 10,297.25 78,945.58 563.90
0.5MM THICK)
1016(1)a WATERPROOFING CEMENT BASE 66.00 SQ.M. 12,211.47 5% 10% 15% 1,831.72 0.00 1,831.72 14,043.19 212.78
1018 UNGLAZED TILES/ GRANITE TILES/ 80.00 SQ.M. 103,219.95 5% 10% 15% 15,482.99 0.00 15,482.99 118,702.94 1,483.79
SYNTHETIC GRANITE TILES
1003(1) FIBER CEMENT BOARD/MARINE 130.00 SQ.M. 157,424.74 5% 10% 15% 23,613.71 0.00 23,613.71 181,038.45 1,392.60
PLYWOOD/ORDINARY PLYWOOD ON METAL
FRAME CEILING
1010(2)a HOLLOW CORE FLUSH DOOR 5.04 SQ.M. 15,448.13 5% 10% 15% 2,317.22 0.00 2,317.22 17,765.35 3,524.87
1010(2) WOODEN PANEL DOOR WITH HEAVY DUTY 2.10 SQ.M. 8,364.59 5% 10% 15% 1,254.69 0.00 1,254.69 9,619.28 4,580.61
DOOR KNOB
1043(1) PVC DOORS AND FRAMES W/ HEAVY DUTY 1.26 SQ.M. 3,615.00 5% 10% 15% 542.25 0.00 542.25 4,157.25 3,299.40
DOOR KNOB
1032(1)a PAINTING WORKS (MASONRY PAINTING) 540.00 SQ.M. 155,302.96 5% 10% 15% 23,295.44 0.00 23,295.44 178,598.40 330.74
1032(1)c PAINTING WORKS (METAL PAINTING) 45.00 SQ.M. 29,161.13 5% 10% 15% 4,374.17 0.00 4,374.17 33,535.30 745.23
SPL - ? SUPPLY AND INSTALLATION OF ANALOK 11.34 SQ.M. 45,360.00 5% 10% 15% 6,804.00 0.00 6,804.00 52,164.00 4,600.00
TYPE SLIDING WINDOW
SPL - ? (INPUT ITEM DESCRIPTION) 1.00 L.S. 0.00 5% 10% 15% 0.00 0.00 0.00 0.00 0.00
PLUMBING WORKS
1001(1)a 50MM DIA - 100MM DIA SANITARY PVC PIPE, 12.00 M. 3,190.00 5% 10% 15% 478.50 0.00 478.50 3,668.50 305.71
SERIES 600/1000
1002(6) WATERLINE PIPES & FITTINGS 1.00 L.S. 5,200.00 5% 10% 15% 780.00 0.00 780.00 5,980.00 5,980.00
Page 12 of 61
1002(5) WATER CLOSET/ URINAL W/ COMPLETE 1.00 SET 7,095.00 5% 10% 15% 1,064.25 0.00 1,064.25 8,159.25 8,159.25
1002(5) ACCESSORIES
KITCHEN SINK/ SCRUB/ SLOP SINK W/ 1.00 SET 5,445.00 5% 10% 15% 816.75 0.00 816.75 6,261.75 6,261.75
COMPLETE ACCESSORIES
1002(5) WALL HANG/COUNTERTOP/ UNDER 1.00 SET 4,345.00 5% 10% 15% 651.75 0.00 651.75 4,996.75 4,996.75
COUNTER LAVATORY W/ COMPLETE
ACCESSORIES
1002(5) FLOOR DRAIN PLATES (ANY SIZE) 2.00 SET 968.00 5% 10% 15% 145.20 0.00 145.20 1,113.20 556.60
1002(5) SOAP HOLDER /TOILET SOAP/LIQUID 1.00 SET 570.63 5% 10% 15% 85.59 0.00 85.59 656.22 656.22
1002(5)p SOAP/TISSUE HOLDER
FACIAL MIRROR 0.50 SQ.M. 804.38 5% 10% 15% 120.66 0.00 120.66 925.03 1,850.06
SPL- ? (INPUT OTHER PLUMBING WORK ITEM 1.00 L.S. 0.00 5% 10% 15% 0.00 0.00 0.00 0.00 0.00
THAT IS NOT FOUND IN THIS
SPREADSHEET)
ELECTRICAL WORKS
1002(5) 15MM-25MM DIA. FLEXIBLE CONDUIT 200.00 M. 17,306.80 5% 10% 15% 2,596.02 0.00 2,596.02 19,902.81 99.51
1100 JUNCTION UTILITY/PULL / SQUARE BOX 33.00 PC. 4,900.50 5% 10% 15% 735.08 0.00 735.08 5,635.58 170.78
1101(2) 1.6MM2 - 5.5MM2 ELECTRIC WIRE 600.00 M. 25,080.00 5% 10% 15% 3,762.00 0.00 3,762.00 28,842.00 48.07
(TW/THHN/TWHN2)
1101 SINGLE CONVINENCE OUTLET/ 13.00 SET 3,305.25 5% 10% 15% 495.79 0.00 495.79 3,801.04 292.39
RECEPTACLE, GROUNDING TYPE/HEAVY
DUTY CONVENIENCE OUTLET
1101 DUPLEX CONVINENCE OUTLET/ 10.00 SET 3,205.00 5% 10% 15% 480.75 0.00 480.75 3,685.75 368.58
RECEPTACLE, GROUNDING TYPE/HEAVY
DUTY CONVENIENCE OUTLET
1102 PANEL BOARD WITH MAIN 1.00 SET 8,168.50 5% 10% 15% 1,225.28 0.00 1,225.28 9,393.78 9,393.78
BREAKER/BRANCHES, 3 WIRES, 1 NEUTRAL,
1103(2) 50AMP-200AMP
FLOURESCENT LIGHTING FIXTURE WITH 40.00 SET 17,820.00 5% 10% 15% 2,673.00 0.00 2,673.00 20,493.00 512.33
BALLAST/ LIGHT EMITTING DIODE (LED)
BULB, 1 BULB
SPL- ? (INPUT OTHER ELECTRICAL WORK ITEM 1.00 L.S. 0.00 5% 10% 15% 0.00 0.00 0.00 0.00 0.00
THAT IS NOT FOUND IN THIS
SPREADSHEET)
Php 1,644,800.25
Prepared by:
Page 13 of 61
DETAILED UNIT PRICE ANALYSIS
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
Sub-Total for E P
F. Direct Cost (C+E) 22,155.20
G. Overhead, Contingencies & Miscellaneous 5% 1,107.76
H. Contractor's Profit (CP) 10% 2,215.52
I. Value Added Tax (VAT) 0% 0.00
J. Total Cost 25,478.48
k. Total Unit Cost 127.39
DETAILED UNIT PRICE ANALYSIS
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
Sub-Total for E P
F. Direct Cost (C+E) 4,458.94
G. Overhead, Contingencies & Miscellaneous 5% 222.95
H. Contractor's Profit (CP) 10% 445.89
I. Value Added Tax (VAT) 0% 0.00
J. Total Cost 5,127.78
k. Total Unit Cost 2,563.89
DETAILED UNIT PRICE ANALYSIS
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
A. Labor
a. Construction Foreman/Engineering Assistant 1 0.14 800.00 115.00
b. Laborer 3 0.14 400.00 172.50
Sub-Total for E P
F. Direct Cost (C+E) 5,193.40
G. Overhead, Contingencies & Miscellaneous 5% 259.67
H. Contractor's Profit (CP) 10% 519.34
I. Value Added Tax (VAT) 0% 0.00
J. Total Cost 5,972.41
k. Total Unit Cost 259.67
DETAILED UNIT PRICE ANALYSIS
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
A. Labor
a. Construction Foreman/Engineering Assistant 1 0.00 800.00 0.00
b. Laborer 3 0.00 400.00 0.00
Sub-Total for E P
F. Direct Cost (C+E) 0.00
G. Overhead, Contingencies & Miscellaneous 5% 0.00
H. Contractor's Profit (CP) 10% 0.00
I. Value Added Tax (VAT) 0% 0.00
J. Total Cost 0.00
k. Total Unit Cost #DIV/0!
DETAILED UNIT PRICE ANALYSIS
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
A. Labor
a. Construction Foreman/Engineering Assistant 1 0.31 800.00 250.00
b. Laborer 3 0.31 400.00 375.00
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
Item No./Description: 902(1) REINFORCING STEEL OF REINFORCED CONCRETE STRUCTURES FOR ONE-STOREY, GRADE
Unit of Measurement: KGS. 40/60
Output per day: 1,147.50 KGS./DAY
Quantity: 1,200.00 KGS.
56.43
DETAILED UNIT PRICE ANALYSIS
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
Item No./Description: 902(1) REINFORCING STEEL OF REINFORCED CONCRETE STRUCTURES FOR TWO UPTO FIVE
Unit of Measurement: KGS. STOREY
Output per day: 1,032.75 KGS./DAY
Quantity: 50.00 KGS.
56.43
DETAILED UNIT PRICE ANALYSIS
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
Item No./Description: 900(1)c2 STRUCTURAL CONCRETE FOR FOOTING AND SLAB ON FILL (CLASS A, 28 DAYS)
Unit of Measurement: CU.M.
Output per day: 2.86 CU.M./DAY
Quantity: 12.40 CU.M.
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
Item No./Description: STRUCTURAL CONCRETE FOR FOOTING TIE BEAM, COLUMN, SUSPENDED SLAB,
GIRDER/BEAM (CLASS A, 28 DAYS)
900(1)
Unit of Measurement: CU.M.
Output per day: 2.16 CU.M./DAY
Quantity: 23.60 CU.M.
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
Stripping:
a. Construction Foreman/Engineering Assistant 1 0.775 800.00 620.06
b. Laborer 6 0.775 400.00 1,860.19
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
Item No./Description: 1046 100MM CHB NON LOAD BEARING/LOAD BEARING (INCLUDING REINFORCING STEEL)
Unit of Measurement: SQ.M.
Output per day: 30.60 SQ.M./DAY
Quantity: 189.00 SQ.M.
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
Item No./Description: 1046 150mm. CHB NON LOAD BEARING (including Reinforcing Steel)
Unit of Measurement: SQ.M.
Output per day: 25.44 SQ.M./DAY
Quantity: 36.00 SQ.M.
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
Item No./Description: 1027(1) CEMENT PLASTER FINISH WITH 19MM THICK & 1:3 MORTAR MIXTURE
Unit of Measurement: SQ.M.
Output per day: 57.000 SQ.M./DAY
Quantity: 420.00 SQ.M.
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
Erection:
a. Skilled Laborer 3 0.00 600.00 0.00
b. Laborer 3 0.00 400.00 0.00
The estimate need to count and specify the stee materials and
compute for its weight in kilograms
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
The estimate need to count and specify the stee materials and
compute for its weight in kilograms
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
Item No./Description: 1014 PREPAINTED METAL SHEETS (CORRUGATE, SHORT SPAN/LONG SPAN)
Unit of Measurement: SQ.M.
Output per day: 16.608 SQ.M./DAY
Quantity: 0.00 SQ.M.
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
Item No./Description: 1014 PREPAINTED METAL SHEETS (RIB TYPE 0.4-0.5MM THICK)
Unit of Measurement: SQ.M.
Output per day: 22.152 SQ.M./DAY
Quantity: 140.00 SQ.M.
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
Item No./Description: 1018 UNGLAZED TILES/ GRANITE TILES/ SYNTHETIC GRANITE TILES
Unit of Measurement: SQ.M.
Output per day: 15.60 SQ.M./DAY
Quantity: 80.00 SQ.M.
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
Item No./Description: 1003(1) FIBER CEMENT BOARD/MARINE PLYWOOD/ORDINARY PLYWOOD ON METAL FRAME CEILING
Unit of Measurement: SQ.M.
Output per day: 9.94 SQ.M./DAY
Quantity: 130.00 SQ.M.
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
Item No./Description: 1010(2) WOODEN PANEL DOOR WITH HEAVY DUTY DOOR KNOB
Unit of Measurement: SQ.M.
Output per day: 2.88 SQ.M./DAY
Quantity: 2.10 SQ.M.
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
Item No./Description: 1043(1) PVC DOORS AND FRAMES W/ HEAVY DUTY DOOR KNOB
Unit of Measurement: SQ.M.
Output per day: 2.52 SQ.M./DAY
Quantity: 1.26 SQ.M.
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
Sub-Total for B P
C. Total (A+B) 77,142.86
D. Output per day =
Name and Specifications Quantity Unit Unit Cost Amount
E. Materials
a. Concrete Penetrating Sealer 16.88 gals. 590.00 9,956.25
b. Solvent Base Acrylic Primer 24.55 gals. 950.00 23,318.18
c. Patching Compound 54.00 kgs. 70.00 3,780.00
d. Semi Gloss Solvent Base Paint (Top Coat) 27.00 gals. 910.00 24,570.00
e. Baby Roller 16.20 pcs. 76.00 1,231.20
f. 2" Paint Brush 16.20 pcs. 65.00 1,053.00
g. 4" Paint Brush 16.20 pcs. 80.00 1,296.00
h. Body Filler 9.00 gal. 650.00 5,850.00
i Other Consumables 7,105.46
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
Sub-Total for B P
C. Total (A+B) 6,750.00
D. Output per day =
Name and Specifications Quantity Unit Unit Cost Amount
E. Materials
a. Red Oxide Metal Primer 1.80 gals. 550.00 990.00
b. Quick Dry Enamel Paint 4.50 gals. 670.00 3,015.00
c. Paint Thinner 33.75 gal. 469.00 15,828.75
d. Tinting Color 4.50 pints. 120.00 540.00
e. Consumables (5% of Material Cost) 2,037.38
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
Item No./Description: SPL - ? SUPPLY AND INSTALLATION OF ANALOK TYPE SLIDING WINDOW
Unit of Measurement: SQ.M.
Output per day: 12.00 SQ.M./DAY
Quantity: 11.34 SQ.M.
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
Item No./Description: 1001(1)a 50MM DIA - 100MM DIA SANITARY PVC PIPE, SERIES 600/1000
Unit of Measurement: M.
Output per day: 24.00 M./DAY
Quantity: 12.00 M.
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
NOTE:
The estimator shall determine the needed materials and determine
the duration to complete this item.
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
Item No./Description: 1002(5) KITCHEN SINK/ SCRUB/ SLOP SINK W/ COMPLETE ACCESSORIES
Unit of Measurement: SET
Output per day: 4.00 SET/DAY
Quantity: 1.00 SET
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
Item No./Description: 1002(5) WALL HANG/COUNTERTOP/ UNDER COUNTER LAVATORY W/ COMPLETE ACCESSORIES
Unit of Measurement: SET
Output per day: 4.00 SET/DAY
Quantity: 1.00 SET
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
Sub-Total for B P
C. Total (A+B) 225.00
D. Output per day =
Name and Specifications Quantity Unit Unit Cost Amount
E. Materials
a. Shower Head & Valve 1.00 set 2,600.00 2,600.00
b. Consumables (5% of Material Cost) 260.00
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
Item No./Description: SPL- ? (INPUT OTHER PLUMBING WORK ITEM THAT IS NOT FOUND IN THIS SPREADSHEET)
Unit of Measurement: L.S.
Output per day:
Quantity: 1.00 L.S.
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
Item No./Description: 1101 SINGLE CONVINENCE OUTLET/ RECEPTACLE, GROUNDING TYPE/HEAVY DUTY
Unit of Measurement: SET CONVENIENCE OUTLET
Output per day: 32.00 SET/DAY
Quantity: 13.00 SET
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
Item No./Description: 1101 DUPLEX CONVINENCE OUTLET/ RECEPTACLE, GROUNDING TYPE/HEAVY DUTY
Unit of Measurement: SET CONVENIENCE OUTLET
Output per day: 26.67 SET/DAY
Quantity: 10.00 SET
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
Item No./Description: 1102 PANEL BOARD WITH MAIN BREAKER/BRANCHES, 3 WIRES, 1 NEUTRAL, 50AMP-200AMP
Unit of Measurement: SET
Output per day: 1.45 SET/DAY
Quantity: 1.00 SET
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
Item No./Description: 1103(2) FLOURESCENT LIGHTING FIXTURE WITH BALLAST/ LIGHT EMITTING DIODE (LED) BULB, 1
Unit of Measurement: SET BULB
Output per day: 8.00 SET/DAY
Quantity: 40.00 SET
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
Item No./Description: SPL- ? (INPUT OTHER ELECTRICAL WORK ITEM THAT IS NOT FOUND IN THIS SPREADSHEET)
Unit of Measurement: L.S.
Output per day:
Quantity: 1.00 L.S.