QC Plan
QC Plan
Project Lead
Project Engineer
Revision Philosophy
Revisions for review will be issued at R01, with subsequent R02, R03, etc. as required.
All revisions approved for issue or design will be issued at A01, with subsequent A02, A03, etc as required.
Documents approved for Construction will be issued at C01, C02, C03, etc as required
Documents or drawings revised as “As built” will be issued as Z01, Z02 Z03 etc as required
Narrative sections revised from previous approved issues are to be noted in the table below and/or
highlighted in the RH margin (using the appropriate revision status) thus: A02
Previous revision highlighting to be removed at subsequent issues.
Drawings/diagrams revised from previous approved issues are highlighted by 'clouding' the affected areas and
by the use of a triangle containing the revision status.
If a document is cancelled the document will be issued at the next sequential number and suffixed with a X.
For example, if 02R is the current revision then 03X will be the Cancelled revision
All revisions to this document must be approved by the relevant technical authority
Revision History
TABLE OF CONTENT
1.0 Introduction ……………………………………………………………………………….………………. 5 - 6
2.0 Quality Objectives ………………………………………………………………………………………. 6
3.0 Responsibilities ………………………………………………………………………………………..… 6 - 8
4.0 Documentation/Project Codes and Standards ……….………………………………….. 8
5.0 Purchasing …………………………………………………………………………………………………. 8
6.0 Product Handling ……..………………………………………………………………………..……… 8
7.0 Storage/Traceability ……………………………………………………………………………….... 9
8.0 Resources …………………………………………………………………………………………………. 9
9.0 Design Development ………………………………………………………………………………… 10
10.0 Project Inputs …………………………………………………………………………………………… 10
11.0 Customer Communications ……………………………………………………………………… 10
12.0 Management Review ………………………………………………………………………………. 10 - 11
13.0 Change Control Management …………………………………………………………….…... 11
14.0 Special Processes ………………………………………………………………………………….… 11
15.0 Installation ……………………………………………………………………………………………... 11 - 12
16.0 Inspection and Testing ………………………………………………………………………….… 12
17.0 Configuration Management ……………………………………………………………………. 12
18.0 Commissioning …………………………………………………………………………………....…. 12
19.0 Passivation ……………………………………………………………………………………………… 13
20.0 Non-Conformances …………………………………………………………………………………. 13
21.0 Monitoring And Measurement ……………………………………………………………..… 13
22.0 Training and Competency ……………………………….………………………………………. 13
23.0 Internal Audit Schedule …………………………………………………………………………... 13 - 14
24.0 Material Reconciliation …………………………………………………………………………... 14
25.0 Project Organization Chart ………………………………………………………………….….. 15
ATTACHMENT: QUALITY CONTROL CHART …………………………………………….. 17
1.0 INTRODUCTION
The purpose of the document is to clearly outline the Project Quality System that is applicable to BOGT
Produce Water Inline Meter Installation (SPDC- Bonny Oil & Gas Terminal). It is expected that Step II
International Nigeria Limited with the aim of observing and achieving the highest quality standard for
the work to be comparable with any such job anywhere in the world. To achieve this aim, Step II
International Nigeria Limited will, in line with standard quality reference codes and specifications design,
propose and specify the quality procedures to be applied in all the phases of the job, for approval by the
client (SPDC). In order to constantly apply the procedures without deviation, SPDC will through its
representatives constantly monitor the job execution for strict adherence. This Project Quality Plan is
therefore specifically made for the project under reference as the underlying document.
In summary, it:
(i) Provides the PE's quality index for the execution of the Project and to be used by all his
representatives.
(ii) Provides guide for us as a Company to work towards the quality requirement of the project.
(iii) Puts together necessary quality aspects that are very important for the delivery of the project.
(iv) Provides, together with the welding procedure specifications and other quality codes, guidance
for achieving sound welds productions.
For the smooth execution of the project, all personnel on site shall use English language as the official
means of communication. Pictorial representations, in the form of pictures, shall also be posted on
notice boards to aid communications and emphases important points.
2.0 QUALITY OBJECTIVES
Step II International Nigeria Limited shall ensure that the BOGT Produce Water Inline Meter Installation
(SPDC- Bonny Oil & Gas Terminal) will comply with all relevant statutory requirements, national,
international and SPDC accepted standards and specifications. The project quality shall be good enough
to meet the design requirement in terms of cost and durability. It shall also meet and comply with all
levels of HSE for the installation and satisfy the needs and requirements of stakeholders return on
investment. It will ensure continuous performance improvement, through early identification of quality
assurance matters and feedback. It will also see to the timely execution of projects at the lowest
possible cost, and without loss to lives and assets.
3.0 RESPONSIBILITIES
The responsibility of successful completion of the job falls on the entire project construction team under
the supervision of the project engineer. They will ensure that the project construction and delivery
comply with SPDC Spec and other standard specified internationally and as required by Step II
International Nigeria Limited through the designs.
This means that:
(i) The design, as shown on the construction drawings and other Approved for Constructions (AFC),
is met.
(ii) Construction is done within the SPDC facilities.
(iii) Only qualified procedures and personnel are used on the job.
(iv) Step II International Nigeria Limited QA/QC personnel, in conjunction with SPDC Inspectors, will
work together to ensure good quality job.
(v) All activities and processes of the job are properly documented and recorded through daily
reports for reference purposes.
(vi) Any deviation or nonconformance noticed by Step II International Nigeria Limited QA/QC shall be
corrected and recorded and SPDC representatives duly informed.
2. Project Manager (PM) The PM is saddled with the daily site administration of the job
and represents the company on all matters concerning the
execution of the project.
3. QA/QC Manager Represents the company on all quality related matters; Verify
implementation and adherence with QC procedures and/or
work instruction; Provides training/instruction, as may be
required, for QC personnel; Preparation of new procedures
and/or work instructions; Report items of non-conformance
to the Operations Manager; Report on the corrective
action/resolution on non-conforming items; Assure the
permanent QC records for materials and test are maintained.
4. QA/QC Engineer Prepares the quality plan and ITPs; supervises workshop pre-
fabrication process; prepares blasting, painting and
hydrostatic tests procedures; conducts welder’s & WPS
qualification tests, coordinates NDT activities, etc.
5. Site Engineers Represents the PM on different sites like the manifold, the
wellhead and workshop during fabrication/installations.
10. Fitters Fit the pipe for the welders as prescribed in the WPS.
STEP II INTERNATIONAL NIGERIA LIMITED TECHNICAL SERVICES LTD shall, at the completion of the
project, handover complete project dossier, which shall be maintained during the life of the project.
5.0 PURCHASING
All required materials for the project shall be procured by Step II International Nigeria Limited upon
issuance of order for the purchase and transferred to her storage area or warehouse for safe keeping.
Pipes and other structural materials stored in the storage area shall be properly stacked on a properly
prepared supports such that there will be no bending or deflection.
In addition, all consumables like grinding stones, power brush, electrodes, cutting gases, diesel and any
other materials, together with equipment needed for the job, shall be provided and stored by Step II
International Nigeria Limited for the efficient execution of the project. All such purchases shall be
inspected and approved by SPDC before and after purchase.
7.0 STORAGE/TRACEABILITY
All the materials for the project shall be properly identified, labeled and stored in their separate
positions to avoid mistaken identity and usage.
8.0 RESOURCES
The resources for this project are human and material. The human resources include all the personnel.
All personnel on board must possess valid SPDC swimming pass or SAS/HUET, valid medical and other
relevant certificates and must be qualified for the aspect of work they are engaged to perform.
!
PERSONNEL
1. Site Engineer
2. QA/QC Engineer
3. HSE Officer
4. Site Supervisor
5. Welders
6. Fitters
7. Fitter’s/Welder’s Mates
8. Operators/Drivers
9. Scaffolders
10. NDT technicians
11. Site Nurse, etc.
EQUIPMENT
1. Welding Machines
2. Generator
3. Crane
4. Air Compressor
5. Gas testing equipment,
6. Grinding machines etc.
NB: They will be duly pre-mobbed by necessary SPDC department before taken to site with valid
premob certificate.
All necessary resources required for the timely execution of this project on the part of SPDC shall be
provided to Step II International Nigeria Limited as contained in the contract.
The AFC will be interpreted with a view to capturing the material requirements for the project so that
early requisition/procurement will be carried out prior to mobilization.
MD XXXXXXXXXXX
PM XXXXXXXXXXX
HSE MANAGER XXXXXXXXXXX
If as a result of the review, any of the above items should require clarification or amplification, the
project manager shall inform the client accordingly and maintain all queries pending when it is closed
out.
Following the review of the management requirements and prior to the start of the project activities, all
assigned lead personnel shall prepare a design criteria summary for each discipline. Each summary shall
contain details of the work scope and lists the applicable client specifications and philosophies,
regulatory requirements and laws, and in-house national and international standards. It shall be the
responsibility of the respective project managers to ensure that all reference documents are updated
and are accessible to all parties concerned.
13.0 CHANGE CONTROL MANAGEMENT
In situations where there are changes to the original design, appropriate measures shall be taken to
ensure that the quality of the work processes conforms to specified requirements. Such changes at the
job sites will be managed in accordance with the Step II International Nigeria Limited Change Control
Procedure, which outlines that any change in design must be discussed with the client and agreed upon
before effecting change.
15.0 INSTALLATION
The fabricated spools shall be installed on SPDC existing facilities. The following sequence of operation
shall be undertaken:
Mechanical isolation. I
Welding.
18.0 COMMISSIONING
The commissioning of the project shall take place after the mechanical completion and pre-
commissioning is completed. Step II International Nigeria Limited Quality Assurance Engineer shall
ensure that non-conformance items that were identified during the mechanical completion and pre-
commissioning are properly close-out and also ensure proper audit of project as regards quality test
records. Once it is ascertained that the project execution meets SPDC specification, the project will be
handed over to SPDC.
19.0 PAINTING
Only prescribed leak proof paints without contamination shall be used. All surfaces to be painted must
be cleaned properly before applying the primer and other coats. The primer shall be zinc rich silicate.
The DFT of each coat shall be measured and recorded accordingly.
20.0 NONCONFORMANCES
All processes, materials, equipment must conform to applicable standard in the industry. Any material
or equipment that does not conform shall be identified and rejected on grounds of non-conformance.
Such processes shall only be allowed after they have been corrected and/or replaced. Step II
International Nigeria Limited QA/QC engineer shall separately or jointly inspect all processes, equipment
and materials with the client representative. Report made on nonconformance must be closed out and
signed by the client representative before proceeding to the next stage.
MD