STP Report 2019 20
STP Report 2019 20
STP Report 2019 20
A Report
On Industrial Visit of
8 MLD STP at
BrahmpuriJaipur
Session 2019-2020
Department of Civil Engineering
February 2020
JAIPUR ENGINEERING COLLEGE AND RESEARCH CENTRE
Aim: -
The objective of the Industrial visit was to acknowledge the student about
Sewage treatment plant and to give them practical knowledge about how the
sewage water is being treated These days and is being used in agriculture. By
this, they will be able to solve the common engineering problem related to
treatment of water occur in an Engineer’s life. Industrial Visit is considered as
one of the tactical methods of teaching interaction, working methods and
employment practices, Moreover, it gives exposure from academic point of
view. Main aim of industrial visit is to provide an exposure to students about
practical working environment. They also provide students a good opportunity
to gain full awareness about engineering practices. Through these visits the
students get awareness about new technologies. By these practices they can
share their knowledge with their colleagues.
JAIPUR ENGINEERING COLLEGE AND RESEARCH CENTRE
Overview:-
Department of Civil Engineering of Jaipur Engineering College and Research
Centre Organised this visit to the Sewage treatment Plant on the 6th February
2020, at Brahmpuri Jaipur for the third-year students of Civil Engineering Batch
A.
The Sewage treatment Plant named as 8 Million Liters per day Sequential Batch
Reactor Sewage treatment Plant Brahmpuri is was established in 2019 with an
objective of treating water By PHED Rajasthan.
About:-
The Sewage treatment Plant is the plant constructed to dispose the municipal
and industrial waste water for its reuse and to reduce the consumption of the
pure water than usual which helps to save the environment. The 8MLD STP
was a small plant with the limit of treating 8 million liters of waster water per
day which connects its lines with the Jaisinghpura STP and takes the 8 Million
liters of inlet from it and let the rest of 60 million waster water lead to the
Jaisingpura STP It works on Solar energy as there are lot of Solar panel are
installed. Like every other STP it has two equipment for each process.
Methodology: -
Folllowing Methods were carried on the plant
Screeing
In Coarse screeing the size of the screen was 20 mm wide. Weather In fine
screening the size of the screen was 10mm.
Conclusion:-
By this visit students learnt methods to clean water by SBR technology
and they learnt various methods at different stages of cleaning and how
we can use the waste water as a Recycling material.