Module 1 - Projects - Edited
Module 1 - Projects - Edited
PROJECT FORMULATION
Project
Guide to Project Management Body of Knowledge
(PMBOK) by Project Management Institute (PMI)
defines Project as follows:
A temporary endeavour undertaken to provide a
unique product or service
Implementation Phase
Basic Design Detailed Tendering Execution Closure
Phase Design Phase Phase Phase
Phase
Post-Implementation Phase
Utilization Phase Close-down Phase
Case Study Example – Construction Project
(Bubshait and Al-Musaid 1992)
Tasks related to Pre-Implementation Phase
1. Assigning a task force to conduct preliminary studies for the
proposed project
2. Studying the users’ requirements
3. Defining the technical specifications and conditions that determine
the quality of the required work
4. Studying how to secure funds to finance the project
5. Estimation of the project cost and duration
6. Approval of the project cost
7. Studying and determining the technical specifications of the
materials
8. Studying the impact of the project on the safety and health of the
community and environment
9. Establishing criteria for the selection of project location
Tasks related to Pre-Implementation Phase
10. Advising members of the task force (consultant, engineering, etc.)
on the approved funds
for the project
11. Establishment of milestones for the project for review and
approval
12. Describing the responsibilities and authority of project parties
13. Pre-establishing a system to prepare for ‘change order’ procedures
14. Establishment of design criteria for structural specifications
15. Conducting a feasibility study of the proposed project
Tasks related to Implementation Phase
Design-related tasks (Bubshait and Al-Musaid 1992)
1. Arranging the documents of the construction contract
2. Qualifying of design professionals
3. Performing technical and financial analysis of offers from competing
contractors
4. Selecting the design team
5. Negotiating with the qualified design professionals
6. Providing the qualified design professionals with the needed
information
7. Monitoring the design progress of the proposed project
8. Evaluating the design and making the necessary decisions
9. Updating design documents
10. Reviewing design documents
11. Conducting design peer review
Tasks related to Implementation Phase
12. Monitoring design quality
13. Updating drawings and specifications to reflect the requirements
of location or environment
14. Using technical standards (e.g., Indian standard, American
standard, British standard, etc.)
to describe materials quality and construction methods
Tasks related to Implementation Phase
Tendering- and construction-related tasks (Bubshait and Al-Musaid
1992)
1. Pre-qualifying contractors
2. Holding a pre-bid conference and providing the necessary
information
3. Negotiating contract price with qualified contractor
4. Reviewing at frequent intervals documents submitted by the
contractor (e.g., work schedules, manpower qualifications,
equipment)
5. Interpreting and clarifying ambiguities in the contract documents
6. Taking necessary precautions to prevent the loss of project data
7. Making necessary decisions against contractor claims during project
implementation
8. Monitoring and controlling implementation methods, cost, schedule
and contractor productivity
Tasks related to Implementation Phase
Tendering- and construction-related tasks (Bubshait and Al-Musaid
1992)
1. Pre-qualifying contractors
2. Holding a pre-bid conference and providing the necessary
information
3. Negotiating contract price with qualified contractor
4. Reviewing at frequent intervals documents submitted by the
contractor (e.g., work schedules, manpower qualifications,
equipment)
5. Interpreting and clarifying ambiguities in the contract documents
6. Taking necessary precautions to prevent the loss of project data
7. Making necessary decisions against contractor claims during project
implementation
8. Monitoring and controlling implementation methods, cost, schedule
and contractor productivity
Phases in a Project Life Cycle (in detail)
(based on investment)
Characteristics of a project life cycle
• Measurement problems
• Uncertainty
• Temporal spread
Types of Capital Investments
Planning
Controlling Executing
Generic rules for managing projects
1. Define clear objectives
2. Develop a detailed plan
3. Allocate resources wisely
4. Communicate effectively
5. Manage risks proactively
6. Monitor progress regularly
7. Adapt to change
8. Empower the team
9. Manage stakeholder expectation
10. Document everything
11. Evaluate & learn
Generic rules for managing projects
• Set a clear project goal
• Determine the project objectives
• Establish checkpoints, activities,
relationships and time estimates
• Draw a picture of the project schedule
• Direct people individually and as a project
team
• Reinforce the commitment and excitement
of the project team
• Keep everyone connected with the project
informed
• Build agreements that vitalize team
members
• Empower yourself and others on the
project team
• Encourage risk taking and creativity
Types of plans made in a project
Integrated Approach to Project
Management (Ref: PMBOK)
Factors to be considered for quick and
economical implementation of projects
(Ref: Projects, Prasanna Chandra)
Project identification
Purpose and Need for Project Identification
• Resources are limited
• Investment decisions have to be made wisely
• All aspects have to be looked into
Consider
OBJECTIVES
STRENGTH WEAKNESS
OPPORTUNITY THREAT
ALTERNATE PROJECT
POSSIBILITIES
Generation of ideas
Types of Objectives
• Productivity improvement
• Cost reduction
• Capacity utilization
• Expansion into promising fields
• Philanthropic nature
• National/global objectives
Generation of ideas
SWOT Applied…
Generation of ideas
Project chosen
time
Identifying Investment Opportunities
(For Reading – Ref: Chapter 3, Projects, Prasanna Chandra)
• Generation of ideas
• Monitoring the environment
• Corporate Appraisal
• Tools for identifying investment opportunities
• Scouting for project ideas
• Preliminary screening
• Project Rating Index
• Sources of positive net present value
Failure of Projects
Some of the main causes of failure of projects are:
• Inadequate project formulation: Poor filed investigation,
inadequate project information, unrealistic cost estimates, lack
of experience, inadequate project analyses, poor investment
decisions.
• Poor planning for project implementation: Inadequate time plan,
inadequate resource plan, inadequate equipment supply plan,
unanticipated interlinking, poor cost planning and poor
organizational structure.
• Lack of proper contract planning and management: Improper
pre-contract actions, poor post award contract management.
• Lack of project management execution: Inefficient and
ineffective working, delays, changes in the scope of the work,
difficult location, unforeseen calamities, deliberate attempts by
undesirable elements.
Common problems of management failure
• Planning failure: Unclear objectives and targets, unworkable plans, top
management’s failure to back-up plans, failure to identify critical items, lack
of understanding of operating procedures and policy directions, reluctance
to take timely decisions, ignorance of appropriate planning tools and
techniques.
• Organizational failure: Due to incorrect organizational structures resulting in
conflicts, ambiguity on responsibility, inadequate delegation of authority,
higher management interference etc.
• Resource failure: Inadequate/inefficient staff and other resources.
• Directional failure: Lack of team spirit, internal conflicts, poor human
resource management and labour strikes.
• Controlling failure: Unclear targets, inadequate information flow,
incompetency in adopting appropriate monitoring techniques and an
absence to timely corrective measures.
• Coordination failure: Lack of communication, lack of day to day decisions to
fill procedural gaps, absence of cooperation and team spirit.
• Other failures: Faulty procurement of machinery and materials, bad
workmanship, poor performance of subcontractors, accidents, unforeseen
bad weather and a failure to adopt to the local conditions.