QUESTION NO 2:
Consider a sample software project having two main phases.
Each phase consists of three main tasks:
Requirements, design, and development.
These steps must be performed sequentially. Requirements for phase two can begin immediately
on the completion of the requirements task for phase one, but the design for phase two must
await satisfactory development of the phase one design task. Requirements task is expected to
take 4 weeks for phase one, and 2 weeks for phase two, while the design is expected to take 3
weeks for phase one and 2 weeks for phase two. Development is expected to take 2 weeks for
both phases.
Your task is to develop a Gantt Chart based on the above-mentioned scenario. After Developing
it, you have to submit a screenshot of the drawn Gantt chart. The screenshot must include the
current date and time.
The recommended link for creating the required Gantt chart is given below you need to open the
given link in any browser on your PC. After logging in you can create it freely without any
cost/charges.