PETROCHEMICAL AND LUBE INTEGRATION PROJECT “LuPech” (J-18)”

AT IOCL
GUJARAT REFINERY, VADODARA, GUJARAT,INDIA
EPCC-5 PACKAGE (MS BLOCK AND OCTAMAX UNIT)

PURCHASE ORDER NO.: SBU - O & G (OIL, GAS & HYDROCARBONS)/LUPECH J18 -IOCL-MS BLOCK/500054/20537

VENDOR NAME: ARTSON ENGINEERING LIMITED

PMC DOCUMENT NO.: 077154C-27794927-0000-AEL03-QCA-B1203-005

CONTRACTOR DOC NO.: 500054-TPL-20537-F999-00005

DOCUMENT TITLE: TDC FOR FASTENERS

CHARGE HEATER CONDENSATE DRUM(1835-V-009) &


ITEM DESCRIPTION
STABILIZER REBOILER CONDENSATE DRUM(835-V-011)

TAG NO: (1835-V-009) & (835-V-011)

REVISION NO: 0 REV. DATE 05.02.2024

DOCUMENT CATEGORY A REV. OBJECT IFA

Technip Energies Review Stamp

Additional information which Contractor wants to mention

0 05.02.2024 ISSUE FOR APPROVAL Amit Saroj Samir Ipar Samir Ipar

PURPOSE/ DESCRIPTION OF
REV. DATE Written by Checked by Approved by
REVISION
Artson Engineering Limited
D-5, MIDC, Ambad, Nashik-422010

Document no: - 077154C-27794927-0000-AEL03-QCA-B1203-005, R.0 Date: - 05.02.2024

Technical Delivery Condition of Fasteners for Vessels.

1) Material: - Fastener SA 193 GR B16 & SA 194 GR 4

2) Governing Code: - ASME Sec.II, Part-A, Edition-2021.

3) Specification & Grade: - As per above material specification.

4) Chemical Analysis: - As per above material Specification.

5) Mechanical Properties: - As per above material specification.

6) Heat Treatment: - As per above material specification.

7) Manufacturer’s Test Certificate: - Required (MTC shall be to EN10204 Type 3.1.

8) Visual Inspection: - All Fasteners shall have workman like finish and shall be free from
injurious defects.

Hardness of Nuts shall be approx 15 BHN less than associated hardness of studs.

Prepared by Checked by Approved By