Week3 Moodle
Week3 Moodle
2
Application time!
Please apply what you learned each week to your project report.
3
Important notes
4
1.
RISK
MANAGEMENT
PROCESSES 2.
(ISO31000)
3.
4.
5.
5
Risk scenario is an event with undesirable impact on
project's objectives.
6
7
(critical activities)
(normal activities)
8
normal Critical activities
9
Visualisation – Different methods
10
Visualisation – Best Practice
11
12
13
CPM-
14
CPM-
15
=> Top row of activity blocks
16
17
(when populating the top
row of activity blocks)
Given
Given
18
(project completion time can be found
but not critical activities yet)
19
Practice
Practice: Calculate the project completion time
CPM- (project finish time can
be found but not critical
activities yet)
21
=> bottom row of activity blocks
22
23
CPM- Step three: backward pass
(when populating bottom
row of activity blocks)
Given
Given
24
(in critical activities, early times and late times are
the same = no buffer)
25
Quiz question 1 What is the latest finish time for activity “C”? And what
activities are on the critical path?
27
(early times and late times are
the same for critical activities,
i.e. there is no time buffer)
28
Quiz question 2
For the below project, the contractor will receive a $500 bonus for completing the project
within 15 working days. The contract also contains a penalty clause in which the contractor will
lose $100 for each day the project takes longer than 15 working days. How much
bonus/penalty is expected to be paid? And What is the latest finish time for activity “E”?
29
Lag (time buffer)
30
13
31
Practice:
Find the latest start and finish times for project activities
32
33
What is the latest finish time for activity “C”? And what
Quiz question 3
activities are on the critical path?
3.
4.
5.
35
Thank you