Reza 2012
Reza 2012
Abstract—The main purpose of this paper is to serve as a containing the cause of the fault.
guideline for assessing the impact of distributed generation (DG) The presented method can be simply extended to the case
on the protection coordination of the distribution network. In of multiple DG by considering the most updated coordination
particular, the paper details and presents a generalized charts, short circuit levels, and protection settings imposed by
assessment procedure for determining the impact of the the presence of initial DG installations. Then, the assessment
integration of DG on the protection practices of distribution method can be applied to determine the protection-based
systems.To ensure the relevancy and the compatibility with the penetration limit for additional DG on a given feeder. Due to
existing utility practices, demonstrations are carried out using the diversity of possible scenarios, a detailed study for a given
ETAP, which are the commonly used software for distribution
system should be carried using the presented guideline.
system protection planning.
Figure 4. Coordination chart for the path from the utility to bus 4 with a 2
MVA DG installed in the suburban system.
Figure 2. Suburban benchmark system with the DG installation candidate
points.
2) A generalized method to assess the loss of coordination
penetration limits
The goal of this section is to develop a generalized
procedure that determines the penetration limit of DG, in terms
of size, location, and technology, from the point of view of loss
of coordination. The general procedure can be summarized in
the following steps:
1. In a given system, define different coordination paths. A
coordination path can be defined as a set of protective devices
located along a circuit path starting from the main feeder
breaker to the most down stream protective device. The fact
that most of the lateral (or sub-laterals) fuses are selected to be
similar (to ease the maintenance), leads to a limited number of
different coordination paths. A single coordination path might
represent many laterals utilizing the same types of fuses.
2. Perform the coordination study and construction the
coordination charts for different protection paths for the system
under study.
3. Observe the minimum short circuit current at which the
loss of coordination may occur among all protection
coordination paths. This current may be the intersection
Figure 3. Coordination chart for the path from the utility to bus 4 without between the coordination curves of two successive protection
DG in the suburban system. devices. It should be noted this minimum current might not
exist in the case where there is no intersection between the
coordination curves. In such a case, there will be no limit for
the installed DG to violate the system coordination.
4. Define the candidate points at which the DG may be
installed. The penetration limit will be calculated for these
specific points. These candidate points may be obtained from a
planning study to determine the optimum location of DG to Start
minimize system losses and improve the voltage profile, or it
might be dictated by the customer.
Define the protection paths in
5. Simulate the installation the DG at the first candidate the distribution system under study
point, then increase the DG size and its interfacing transformer
step by step until reaching the minimum short circuit current
for the loss of coordination, then record the DG size. It should Perform the coordination study
be noted that increasing the size of the DG and its interfacing and construct the coordination
charts of the protection paths
transformer inherently increases the short circuit MVA for the existing system
capacity of the combined DG/transformer set. The DG
impedance estimation function in ETAP provides a useful tool Outcome of
to determine the DG impedance based on its rating. The Define candidate points for DG planning study
installation
impedance estimation tool is based on the IEEE Violet Book or customer
requirements
guidelines [6].
Using the coordination charts,
In addition, the interfacing transformer impedance can be determine the minimum short
estimated based on its rating parameters. This function is circuit current that yields loss
of coordination
available in ETAP as well.
6. Repeat step 5 for other candidate points.
7. Tabulate the results. Does the minimum No limit for the
short circuit current
8. Change the DG technology by considering the cases of that yields loss of
loss of
coordination
synchronous, inverter or induction-based generators, and then coordination exists?
IV. CONCLUSION
Upgrading some components can mitigate the loss of
coordination. A new coordination study with the DG installed Increase the DG size step by step and
can be conducted to determine the appropriate sizing and perform the short circuit study until the
occurrence of the loss of coordination
upgrades of protection devices; most probably fuses. The new
protection coordination study will ensure no loss of
coordination even with the increase of the short circuit current Record the DG size
by moving the intersection point of the primary and backup
protection coordination curves to the right hand side on the
time-current coordination curve. Install the DG a t
Last candidate point
the next
reached?
candidate point and
REFERENCES conduct
short circuit studies