Post Pour Concrete Slab
Post Pour Concrete Slab
Post Pour Concrete Slab
Contents
Inspection details 3
Accessibility 6
Summary 7
Significant items 8
Additional comments 19
Conclusion 31
If you have any queries with this report or require further information, please do not hesitate to contact
the person who carried out the inspection.
Inspection details Page 3
Inspection details
Property Address: Rockbank Area - Melbourne
Client
Name:
Email Address:
Phone Number:
Consultant
Site drainage: The site is inadequately drained, however at this stage of the build
Accessibility
Areas Inspected
The inspection covered the Readily Accessible Areas of the property. Please note obstructions and limitations to
accessible areas for inspection are to be expected in any inspection.
- The site
- Slab
The inspection does not include areas which are inaccessible due to obstructions, or where access cannot be
gained due to unsafe conditions.
- Vapour barrier
- Soil Abutting The Slab
Obstructions increase the risk of undetected defects, please see the overall risk rating for undetected defects.
Summary Page 7
Summary
SUMMARY INFORMATION: The summary below is used to give a brief overview of observations made in each
inspection area. The items listed in the summary are noted in detail under the applicable sub headings within the
body of the report. The summary is NEVER to be relied upon as a comprehensive report and the client MUST read
the entire report and not rely solely on this summary. If there is a discrepancy between the information provided in
this summary and that contained within the body of the Report, the information in the body of the Report shall
override this summary. (See definitions & information below the summary to help understand the report)
Not Applicable
Significant items Page 8
Significant items
Safety Hazard
Non Compliant
Significant items Page 9
-/ The contract that states that the builder will build to all regulations.
Looking at the side of the slab, it appears evident that the slab has not been vibrated to all
parts. The honeycomb effect that is made up of hundreds of air pockets is what should not
be
present.
Had this slab been vibrated to all parts, then this honeycomb effect would not be present
and the concrete would have a smooth like finish.
The defect is that if it has not been done to the outer skin of the exposed areas, then the
likely
hood is that the internal of the slab has the same honeycomb effects as well and if this is the
case then the density of the concrete will be compromised.
————————————————————————————————————————
——————
All AREAS to the ENTIRE slab should be checked CAREFULLY to identify any further defects
that are the same as this defect.
Significant items Page 10
Significant items Page 11
The builder must use all endeavours to ensure that the site is safe and left clean whilst in
construction and a clean, builders waste free site prior to final handover as per the building
act and contractual agreements.
————————————————————————————————————————
——————
All AREAS to the ENTIRE slab should be checked CAREFULLY to identify any further defects
that are the same as this defect.
Significant items Page 12
It is important as well prior to just cutting the excess concrete off, that the bottom
procedures take place :
It was noted at the time of inspection that a vapour barrier had not be installed in accordance
with AS2870 and BCA Part 3.2.2.6.
All of the vapour barrier system has NOT been done correctly and ALL areas of non
compliance is required to be repaired.
The polyethylene vapour barrier from beneath the concrete floor slab must be turned up the
external side faces of its edge beams. Failing to install the vapour barrier correctly will allow
moisture ingress via slab edge dampness into the internal timber wall skins and/or the floor
coverings if not done.
The polyethylene vapour barrier must properly extended up the external side faces of the
edge beams to at least 600mm above the height of the slab for now and then at future
finished ground level of the solid, concrete , etc.
Without a vapour barrier installed, these areas are non-compliant with Australian Standards
and are susceptible to excessive moisture, which may create major secondary defects as the
building ages. Rectification works are necessary as soon as possible to ensure all standards
are met.
————————————————————————————————————————
——————
All AREAS to the ENTIRE slab should be checked CAREFULLY to identify any further defects
that are the same as this defect.
Significant items Page 16
Significant items Page 17
As per the Domestic Building Contracts Act 1995, each state based legislation contains
implied warranties concerning all domestic building work.
These include, but are not limited to, that the builder warrants that the work will be carried
out in a proper and workmanlike manner and in accordance with the plans and specifications
set out in the contract.
It is obvious that that the brick rebate has had concrete added at a later stage when the
original concrete was drying and/or dry as there is a cold joint between the two surface
areas.
Cold Pour Joints in concrete foundations which leave visible lines in the concrete foundation
wall are not usually a structural problem but may in some cases form a dry joint which
permits water leakage through the foundation wall.
Cold pour joints occur because of the time delay between subsequent "pours" into the
foundation forms.
An astute inspector, by noting the position, pattern, and slope of the cold pour joint, can
probably determine the position from which the concrete was poured into the forms (the high
end of the sloping lines) and the extent of delay between pours (evidence of water leaks
through the joints indicates that enough time passed for the lower pour to solidify).
This remedial works requires a structural engineer to determine the repair method prior to
any further works advancing over the rebate.
————————————————————————————————————————
——————
All AREAS to the ENTIRE slab should be checked CAREFULLY to identify any further defects
that are the same as this defect.
Significant items Page 18
Substandard Workmanship
Incomplete
Additional comments
There are no additional comments
Noted Items
NOTE :
THE PHOTOS WITH THE BLUE ARROWS INDICATE THE REFERENCE POINTS, WHICH
DETERMINES IN MILLIMETRES IF THE OTHER LOCATIONS ARE HIGHER OR LOWER
THEN THE REFERANCE POINTS WITH THE BLUE ARROWS.
THIS PROPERTY INDICATES THAT THE FLOORING IS WITHIN TOLERANCES & IS WITHIN
THE ACCEPTABLE AUSTRALIAN STANDARDS .
————————————————————————————————————————
——————————————
The photos will demonstrate that the floor levels are within Guide To Standards And
Tolerances 2015, Footings, Slabs And Setting Out, 2.08 and Australian Standards ( AS
1684 )
The overall deviation of floor level ( concrete slab ) to the entire building footprint shall not
exceed 20 mm, as per the `Guide to Standards and Tolerances` Section 2.08 and AS 1684.
1. Purpose
The purpose of our inspection is to identify any defects in the finishes and the quality of those
finishes presented by the builder at the stage of works nominated on the front of this report.
This report contains a schedule of building defects that in the writer’s judgement do not
reach an acceptable standard of quality, level of building practice, or have not been built in a
proper workmanlike manner relative to the Building Code of Australia, the relevant Australian
Standards or the acceptable standards and tolerances as set down by the Building Control
Commission.
2. Scope
Our engagement is confined to that of a Building Consultant and not that of a Building
Surveyor as defined in the Building Act, of 1993. We therefore have not checked and make
no comment on the structural integrity of the building, nor have we checked the title
boundaries, location of any easements, boundary setbacks, room dimensions, height
limitations and or datum’s, glazing, alpine and bush-fire code compliance, or any other
requirements that is the responsibility of the Relevant Building Surveyor, unless otherwise
specifically noted within this report.
Observations Page 29
This report contains a list of a number of defects that in our judgement require rectification.
Conclusion
Building consultant's summary
IMPORTANT NOTE:
I have ONLY taken LIMITED photos of the defects and attached are LIMITED photos of the defects in SOME
AREAS ONLY.
All AREAS to the entire property should be checked CAREFULLY to identify any further defects that are the
same.
————————————————————————————————————————-
We highly recommend that a Re-Inspection to inspect the rectified defects is performed prior to further
works commencing.
Definitions Page 32