MS - For Installation of Structured Cabling System

Uploaded by

Adnan Abdul
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 12

Project Title:

DELTA MIXED-USE DEVELOPMENT


Doc. Title: Doc. Ref. ALF-MST-EL-004-R0
No.
Method Statement for Installation of Date: 03 FEB 2024

Structured Cabling System. -- 1 of 12


Page

DELTA MIXED-USE DEVELOPMENT

Method Statement for Installation of Structured Cabling System

This cover page is a record of all revisions of the standard/procedure identified above by number and title. All
previous cover pages are hereby superseded and are to be destroyed.

Prepared by
Reviewed By Checked By Approved By
QA/QC
Safety Engineer. Project Engineer. Project Manager
Status Mr. Adnan
Index Date Mr. Fasil Mustafa Mr. Muzammil Mr. Misbah Ahmed
Modifications Abdul Mateen
Signature Signature Signature Signature

Submission
Rev :0 02.0.24
for approval
Project Title:

DELTA MIXED-USE DEVELOPMENT


Doc. Title: Doc. Ref. ALF-MST-EL-004-R0
No.
Method Statement for Installation of Date: 03 FEB 2024

Structured Cabling System. -- 2 of 12


Page

INDEX

CONTENTS

1. PURPOSE

2. SCOPE

3. ABBREVIATION

4. REFERENCES & RELATED DOCUMENTS

5. RESPONSIBILITIES

6. MATERIALS:

7. WORK METHODOLOGY

8. EQUIPMENT REQUIRED

9. HEALTH AND SAFETY CONTROL MEASURES

10. QA/ QC DOCUMENTS

11. ATTACHMENT

 Comply statement of project specification


 Installation Check list.
 Risk assessment.
 ITP.
Project Title:

DELTA MIXED-USE DEVELOPMENT


Doc. Title: Doc. Ref. ALF-MST-EL-004-R0
No.
Method Statement for Installation of Date: 03 FEB 2024

Structured Cabling System. -- 3 of 12


Page

1 PURPOSE
This Method Statement provides the control sequence of construction and
methodology that will be used for the Installation of the Structured Cabling system.
2 SCOPE
This method statement is applicable to the installation of a structured cabling
system. Ensure that the work is installed and conforms to the requirements of
contract documents & engineering specifications and IFC drawings.

3 ABBREVIATION
HSE : Health, Safety & Environment
ITP : Inspection Test Plan
MS : Method Statement
MSDS : Material Safety Data Sheet
PPE : Personal Protective Equipment
QA/QC : Quality Assurance /Quality Control
Cat 3 : Category 3 cable
Cat 6A : Category 6A cable
ANSI : American National Standards Institute
TIA : Telecommunications Industry Association
RJ45 : Registered Jack # 45. (Registered Jack specifications are
related to the wiring patterns of the jacks)
UTP : Unshielded twisted pair
F/UTP : Foiled with unshielded twisted pairs.
SECNET : security network
ACN : Access control network

4 REFERENCES & RELATED DOCUMENTS

 Project Specification Ref. (Section – 27 & 28)


 ANSI/TIA-568 standards.
 SBC 401
 Approved Shop Drawing.
 Approved Material Submittal Ref. ALF-MAR-EL-031-R0,
 Project Quality plan
 ITP
Project Title:

DELTA MIXED-USE DEVELOPMENT


Doc. Title: Doc. Ref. ALF-MST-EL-004-R0
No.
Method Statement for Installation of Date: 03 FEB 2024

Structured Cabling System. -- 4 of 12


Page

5 RESPONSIBILITIES
Project Manager:
Shall be responsible for the proper execution of this procedure and to ensure that works are
undertaken in a safe manner as described herein, to the requisite quality in accordance with
relevant quality procedures, and to the agreed timescale.

Project Engineer:
Shall be responsible for the site implementation of these procedures and to provide all the
resources from competent and trained manpower, tools, equipment, and approved materials. He
shall coordinate with Quality.
Control Inspector for inspections and issuance of Request for Inspections (RFI). He shall be
responsible for the safety of all personnel working on these activities.

Safety Engineer:
Shall be responsible for the implementation of safety procedures on site and to ensure that the
Risk Assessment within this method statement is followed.
He shall assign a competent Safety Officer to enforce these procedures and to provide guidance
to the operations where applicable.

QA / QC ENG:
Shall be responsible for the proper implementation of these procedures and ensure that
inspections and tests are carried out according to the relevant approved Inspection Test Plan. He
shall assign a competent Quality Control Inspector to perform inspections.

Safety Officers:
Shall be responsible for the implementation of all safety requirements and to ensure that the
works are undertaken in a safe and proper manner, all in accordance with the approved
Construction Phase HSE Plan, the approved method statement, and the approved Job Safety
Analysis.
Site Supervisors and Site Foremen:
The project team consisting of experienced supervisors and foremen must ensure the quality of the
installation work performed and must also ensure that it complies with the latest approved shop
drawing issued for the facility and the instructions received from the site engineer.
The site supervisor will provide his subordinates (charge hand) with adequate information to carry
out their duties.

To ensure that he has adequate resources of machinery, labor, and materials to carry out all the
activities efficiently and to discuss with the Site Engineer.
Project Title:

DELTA MIXED-USE DEVELOPMENT


Doc. Title: Doc. Ref. ALF-MST-EL-004-R0
No.
Method Statement for Installation of Date: 03 FEB 2024

Structured Cabling System. -- 5 of 12


Page

6 MATERIALS:

6.1 Material Receipt:

a) Prior to delivery of materials, material receipt information will be conveyed to the site
engineer and storekeeper to arrange sufficient and safer storage area for the materials
and the arrangement of all lifting arrangements.

b) Upon receipt of materials at site stores, all delivered materials will be checked for
manufacturer details as per delivery notes and approved material submittal to ensure
that the delivery is correct.
c) All cable drums will be inspected for their nameplate details available with the cable
drums and the ends of cables are protected with end caps.

d) Check that the weight of the cable drum is indicated on the nameplate to ensure the
proper capacity of lifting equipment and no damage to the cable drum during shipment.

e) Ensure IT equipment, patch panels, and racks are delivered with standard
manufacturer’s packing.
f) Any damage or discrepancies with the delivered materials will be immediately notified
to the concerned parties for their further action.
g) Verify the type, quantity, and model of the delivered equipment as per the approved
material submittal and relevant documents.
h) Material receipt details will be conveyed to the site engineer, QA/QC engineer, and
HSE engineer for their necessary action.
i) Material inspection will be raised to the main contractor and the material will be
inspected by the engineer. Approved material inspection will be recorded for future
records and requirements.

6.2 Material Handling:

a. Use hand gloves while shifting / Unloading / Loading and Handling of delivered
materials.
b. Ensure all lifting equipment like crane, forklifts, chain blocks, and nylon sling belts
are with their necessary test certificates and with proper lifting capacity prior to
unloading.
c. Cable drums will be lifted with adequate mechanical arrangements to prevent damage
to the cable drums.
Project Title:

DELTA MIXED-USE DEVELOPMENT


Doc. Title: Doc. Ref. ALF-MST-EL-004-R0
No.
Method Statement for Installation of Date: 03 FEB 2024

Structured Cabling System. -- 6 of 12


Page

d. All material handling, transportation, and equipment movement will be coordinated


with concerned parties.
e. Only trained personnel will be utilized for loading / Unloading and lifting procedures
and appropriate safety measures will be followed.

6.3 Material Storage:

a) Ensure the storage area is cool and fully covered from external weather conditions,
clean, tidy, and with no ingress of water.
b) Ensure all equipment is stacked properly as per the manufacturer’s
recommendations.
c) Cover all the materials with thick polythene sheets to prevent scratches and
accumulation of dirt.
d) Ensure necessary warning signs and protection barriers are provided to prevent
unauthorized entry and misuse.

7 WORK METHODOLOGY

The Structured cabling is based on six components that, together, provide a convenient,
repeatable, and easily implemented framework for installing telecommunications cabling.
The six components of structured cabling are the following:

1. Entrance Facilities

2. Equipment Room

3. Backbone Cabling

4. Telecommunications Room

5. Horizontal Cabling

6. Work Area
Project Title:

DELTA MIXED-USE DEVELOPMENT


Doc. Title: Doc. Ref. ALF-MST-EL-004-R0
No.
Method Statement for Installation of Date: 03 FEB 2024

Structured Cabling System. -- 7 of 12


Page

A. Interconnection Requirements for Structured Cabling Network

(1) Provide complete earthing and containment for its cable and provide pin down and
earthing arrangement with switch.
(2) Ensure that all enclosures conform with IEC 297-4 and will be provided at the
following locations:

I. Main Communication Room


II. Telecom Intake Position
Project Title:

DELTA MIXED-USE DEVELOPMENT


Doc. Title: Doc. Ref. ALF-MST-EL-004-R0
No.
Method Statement for Installation of Date: 03 FEB 2024

Structured Cabling System. -- 8 of 12


Page

III. ELV risers within the Car park at each level for each riser.
IV. ELV riser within retail at each floor riser within BOH areas.
V. Ensure that the backbone connections provide fiber patch panels for multicore
connections to remote panels and to local equipment panels.
VI. Provide Cat 6A RJ45 patch panels for backup connections to remote panels, and
for local connections within the equipment room.
VII. Ensure that the backbone structured network shall serve the following
equipment as listed:

 Information points in the circulation of public areas.


 Internet access terminal.
 Telephone and Data outlets within the Fire Control Center.
 Wireless LAN, DECT & GPS distribution points.
 Access control system.
 CCTV Systems
 Interface to building systems, including but not limited to; GRMS; Lighting
Control; Emergency Lighting Systems, etc.

All cables will be pulled in accordance with the manufacturer’s recommendations, the
approved shop drawings, and project specifications.
Installation will be in accordance with SBC-401 building wiring requirements of the
structured cabling system and as per project specifications.
All outlets will be installed in the approved manner and to the mounting height and
positions as mentioned in the approved shop drawings and related documents.
All cabling will be installed in the appropriate containment taking into account the
spacing factor of space capacity required as per project specification.

UTP Cables will be pulled from each ACN/LAN & IT outlet inside the rooms to the IT
patch panel as per project specification and approved shop drawings. \
The approved IDF and IT cabinet racks will be installed in the data rooms as per the
approved shop drawing.
Fiber Optic and CAT 6A cables from IT racks, patch panels, and outlets shall be laid as
per approved shop drawings and related standards and specifications.
UTP cables will be terminated using class B (ANSI/TIA/EIA-568B) the termination will
be using the punching tools to join the 8 cores.
Pulling the unshielded twisted pair category 6A will be in cable Trunking, EMT
Conduits and GI boxes, the copper cable will be well addressed and tied to the
horizontal and vertical Trunking.
Project Title:

DELTA MIXED-USE DEVELOPMENT


Doc. Title: Doc. Ref. ALF-MST-EL-004-R0
No.
Method Statement for Installation of Date: 03 FEB 2024

Structured Cabling System. -- 9 of 12


Page

According to the Recommendations, the UTP cables will be terminated using class B
(ANSI/TIA/EIA-568B), the termination would be using the punching tools to join the 8
cores (4 Pairs-color & Strip) to the RJ 45 Module female as following arrangement.

PIN1: WHITE/ORANGE CORE


PIN2: ORANGE CORE
PIN3: WHITE/GREEN CORE
PIN4: BLUE CORE
PIN5: WHITE/BLUE CORE
PIN6: GREEN CORE
PIN7: WHITE/BROWN CORE
PIN8: BROWN CORE

The termination standard will be applied in both parts, the user side and covered by the
face plates and data frame side and ACN, SECNET in the patch panels.
All cabling will originate from rack mounted RJ45 patch panels and terminate upon
single/dual faceplates at the required user locations. The IT Cabinets in the Data Room
will contain a Patch Panel, Patch cords, and cable manager along with the patch panels to
organize the cords patched to Network Active components.
To ensure the transmission performance requirements of a category 6A system are
maintained, the amount of untwisting in a cable pair shall be no greater than ISO
specification. In addition, the stripping back of the outer sheath shall also be limited to
the minimum amount required to achieve a successful termination.
Each category of cable must consist of four twisted pairs with stranded conductors sized
23 AWG with thermoplastic insulation and an overall thermoplastic jacket with a
diameter less than or equal to 9.0mm. This section also states that the cables must meet
the mechanical performance requirements, testing, and test methods defined below:

 Category 6A — ANSI/CEA S–102–732–2009

All tools and equipment shall be approved type and as per the recommendation of the
manufacturer.
All installations will be inspected and certified by the specialist supplier and necessary
certifications and test reports will be forwarded to the consultant for their review and
approval. (a separated method statement will be submitted for testing & commissioning)
An inspection will be offered to the consultant for their approval.
Project Title:

DELTA MIXED-USE DEVELOPMENT


Doc. Title: Doc. Ref. ALF-MST-EL-004-R0
No.
Method Statement for Installation of Date: 03 FEB 2024

Structured Cabling System. -- 10 of 12


Page

8 EQUIPMENT REQUIRED

General electrical wiring and cable installation small tools


7.1. Drilling machines
7.2. Electrical extension cords
7.3. Rigging cables, slings, and related equipment
7.4. Tools (cutting. machine, spanners)
7.5. Splicing Tools / Hacksaw
7.6. Measuring Tape
7.7. Scaffolding & Ladders

9 SAFETY

 Note: All activities will be executed in accordance with OCC WEAVERS safety guidelines and
Alfaneyah safety plan.

8.1 Dangers & Hazards

81.1. Operating grinders and drilling machines.


81.2. Operating lifting equipment.
81.3. Working with corrosive and hazardous material –cleaning and protective Chemicals.
8.2 Safety Equipment and PPE Requirements

8.2.1. Safety Helmet


8.2.2. Safety foot ware
8.2.3. Goggles and helmets
8.2.4. Gloves were necessary for handling the materials/tool.
8.2.5. Safety goggles for drilling and use of grinders
8.2.6. All operatives will be made aware of first aid and emergency procedures as well as
the site rules at the site induction on their first arrival to site. This will be provided
by the Main contractor.

8.3. Key Personnel to Be Informed in Case Of Emergency

• The Table listed below is Alfaneyah Co. Emergency Response Team and their
contact numbers. In case of emergency, they need to be notified.
Project Title:

DELTA MIXED-USE DEVELOPMENT


Doc. Title: Doc. Ref. ALF-MST-EL-004-R0
No.
Method Statement for Installation of Date: 03 FEB 2024

Structured Cabling System. -- 11 of 12


Page

S NAME DESIGNATION CELL.


/ NO.
N
Project Engineer/ERT
1 Mr. Raja Muhammad 054 9760410
Member
2 Engr. Muzammil Hussain Project Engineer 054 3227649

3 Mr. Faisal Mustafa Project HSE Responsible 058 3398529

4 Mr. Azher Uddin Safety Officer 057 8631289

8.4 Distance to nearest hospitals from site location

Hospitals Distance Drive Service Contact


Dr. Suliman fakeeh medical
center
Basateen Dist. Jeddah 23717
3 Km 6 Min 24 hours 920012777

My clinic Parking
Al Mohammadiyyah Dist. 23617
5.5 Km 8 Min 24 hours 920022811
Dr. Abdul rahman clinics
Prince sultan road 6 Km 10 Min 24 hours 054 5901392
Muhammadiyah

8.5 Nearest Ambulance / Civil Defense

997 24 hours 3 3.1 KM AL Muhammadiyah 23617

8.6 Emergency Evacuation Procedure:

It is the responsibility of all Management and Supervisors to familiarize themselves with


Emergency Procedures, which apply to all areas he is working in, and to instruct their crew
members accordingly. Details of the Procedure can be obtained from the Project Engineer,
Construction Manager and Alfaneyah Safety Manager / Responsible.

Alfaneyah Company is responsible for reporting all the incidents / accidents to OCC / Kling
consultant as required.

Emergency situations shall also be reported by dialing general emergency telephone


numbers.

Proponent Safety representative shall be immediately informed about the emergency (i.e.,
personnel injury, fire, and property damage, etc.) and the exact location, name and badge
number of the person reporting shall also be identified.
Project Title:

DELTA MIXED-USE DEVELOPMENT


Doc. Title: Doc. Ref. ALF-MST-EL-004-R0
No.
Method Statement for Installation of Date: 03 FEB 2024

Structured Cabling System. -- 12 of 12


Page

10 QA/QC DOCUMENTS

9.1 Installation checklist


9.2 Approved Shop drawing.
9.3 Inspection Test Plan
9.4 Risk Assessment

11 ATTACHMENT

10.1. Installation checklist


10.2. Inspection Test Plan
10.3. Risk Assessment
10.4. Comply statement.