Final Project GC2015 4BE
Final Project GC2015 4BE
IRRIGATION PROJECT
Advisor: Endalkachew
DECLARATION
Approval of the adviser Mr. Endalkachew
I approve that this project has been done by the students whose name is mentioned below and all
of the sources and materials used for the report have been acknowledged.
ACKNOWLEDGMENT
We would like to express our gratitude to all those who help us for the success and
accomplishment of the final project, whose support was either direct or indirect during our
project progress. Especially we are deeply indebted to express our thanks to our advisor
Endalkachew, who gave us comments and suggestion how to proceed the project.
We would to like thank our parents for their tremendous contributions and support both morally
and financially towards the completion of this project.
Finally, Our thanks and appreciations go to our friends in developing the project and people who
have willingly helped us with their abilities and valuable discussions during the progress work of
the Project.
FINAL YEAR PROJECT REPORT AGZI-3 DIVERTION WEIR HWRE Page iii
BIT FCWRE 2007
I =intensity of rainfall
Contents
DECLARATION ............................................................................................................................................... ii
ACKNOWLEDGMENT .................................................................................................................................... iii
Acronym and Abbreviation .......................................................................................................................... iv
1. INTRODUCTION ..................................................................................................................................... 1
1.1. Background ................................................................................................................................... 1
1.2. Description of the Project Area..................................................................................................... 1
1.2.2. Accessibility ........................................................................................................................... 2
1.3. Objectives of the Study ................................................................................................................. 3
1.3.1. Major Objective .................................................................................................................... 3
1.3.2. Specific Objectives ................................................................................................................ 3
1.3.3. Scope of the Study ................................................................................................................ 4
1.4. Methodology................................................................................................................................. 5
2. HYDROLOGY .......................................................................................................................................... 6
2.1. . HYDROLOGY ANALYSES ............................................................................................................... 6
2.1.1. DATA AVAILABILITY ............................................................................................................... 6
2.1.2. Outlier test ............................................................................................................................ 6
2.1.3. Check for variance................................................................................................................. 8
2.1.4. D-Index test ........................................................................................................................... 8
2.1.5. Design Flood Analysis .......................................................................................................... 10
2.1.6. Design Storm Analysis ......................................................................................................... 10
2.2. Peak Discharge Determination ................................................................................................... 11
2.2.1. General ................................................................................................................................ 11
2.2.2. Time of concentration (Tc) .................................................................................................. 11
2.2.3. Run off synthesis ................................................................................................................. 12
2.2.4. Peak flood analysis by SCS unit hydrograph method.......................................................... 13
2.3. Tail water depth computation .................................................................................................... 16
3. HEADWORK ......................................................................................................................................... 20
3.1. Headwork Site Selection ............................................................................................................. 20
3.2. River Geomorphology ................................................................................................................. 20
3.2.1. River Bed condition ............................................................................................................. 21
3.2.2. River Bank condition ........................................................................................................... 21
4.3.3. Slope.................................................................................................................................... 51
4.3.4. Side slope for unlined canal ................................................................................................ 52
4.3.5. Longitudinal slope ............................................................................................................... 53
4.3.6. Permissible velocity............................................................................................................. 53
4.3.7. Roughness Coefficient (n) ................................................................................................... 54
4.3.8. Design discharge ................................................................................................................. 54
4.4. Main canal design ....................................................................................................................... 55
6 CONCLUSION AND RECOMMENDATION ............................................................................................ 58
7 The following recommendations are drown: ..................................................................................... 59
8 REFERENCE .......................................................................................................................................... 60
9. APENDIX .............................................................................................................................................. 61
9.1 Annex 1: Percent Rainfall Profile Chart for 24 hr Storm ................................................................. 61
9.2 Annex 2: Creep coefficient for different soil type....................................................................... 61
9.3 Annex 3: For outlier test Kn values ............................................................................................. 62
9.4 Annex 4: KT VALUES for Pearson Type III distribution (positive skew) ....................................... 63
FINAL YEAR PROJECT REPORT AGZI-3 DIVERTION WEIR HWRE Page vii
BIT FCWRE 2007
FINAL YEAR PROJECT REPORT AGZI-3 DIVERTION WEIR HWRE Page viii
BIT FCWRE 2007
1. INTRODUCTION
1.1. Background
In Ethiopia, under the prevalent rain-fed agricultural production system, the progressive
degradation of the natural resource base, especially in highly vulnerable areas of the highlands
coupled with climate variability have aggravated the incidence of poverty and food insecurity.
The major source of growth for Ethiopia is still conceived to be the agriculture sector. Hence,
this sector has to be insulated from drought shocks through enhanced utilization of the water
resource potential of the country, (through development of small-scale irrigation, water
harvesting, and on-farm diversification) coupled with strengthened linkages between agriculture
and industry (agro-industry), thereby creating a demand for agricultural output. In line with the
above, efforts have been made by the government to improve the situation in the country in areas
of domestic water supply provision, irrigation, watershed management, etc.
1.2.2. Accessibility
The project area is accessed through Gravel Surfaced road 20Km from adis kidam to washa
amba Kebele, and the rest 9km is accessed road 6km and 3km on foot, along flat and gentle slope
ground surface to the site.
practices (if any) are under taken by individual farmers that use the river flow to the extreme left
side is with hardship. So, the farmers in the project area are very much interested to upgrading
the traditional scheme to modern scheme.
To make sustainable the rain-fed crop production and make extra production in the dry
season possible for 50 ha of land through irrigation.
There is a general consensus that irrigation investments will achieve broader food
security and poverty reduction impacts and if efforts are also geared towards up-grading
existing traditional farming practices with support to enhance access to input supply,
output marketing and extension to facilitate access to information and innovations.
This objective is to be realized by constructing diversion structures across the AGZI
Rationale for the intensification and modernization of small-holder agriculture and rural
lifestyles.
The engineering study and design enables the realization of the project by the provision of
engineering structures that will allow the appropriate abstraction of the river water for delivery in
to the identified irrigation fields of the study area. Hence, this engineering design is specifically
targeted to:
Analyze hydrologic requirements of the project and engineering structures;
The formulation of sound and stable structure, with necessary provisions that allow safe,
easy and low-maintenance operation in the service life of the project;
Develop working drawings;
Estimation of construction costs.
Determination and estimation of water application conveyance and other losses and irrigation
efficiencies and consideration of those parameters in design steps.
Check and test hydraulic and structural designs of main canal considering total demand and
the required capacity and the base flow availability,
Prepare general plans and drawings for all irrigation infrastructure and irrigation systems
designs,
1.4. Methodology
In the designing of this final year project on diversion weir we will use the following procedures:
Gathering rainfall data from our project advisor that he got from responsible body and
making its analysis. such as:
Hydrological analysis
Consistency test
Computation of flood discharge.
Estimation of peak discharge from the given rainfall data
Tail water depth computation
Selection of site and weir type
Designing of the selected head work structures
Weir designing
Design of divide wall, under sluice, head regulator and stilling basin
Design retaining wall with its stability analysis
Description of the Study Area
Compiling of report and preparation of document.
Computing the specification & bill of quantity for head work structures
2. HYDROLOGY
2.1. . HYDROLOGY ANALYSES
2.1.1. DATA AVAILABILITY
Small scale irrigation project designers and planners are faced with lack of good data on the
hydrology of the stream/river system that will be their water source and on local weather and
climate conditions. Stream gauging stations are virtually non-existent in remote rural areas of
Ethiopia; meteorological stations are almost rare. Likewise, at washa amba Kebele (Project area
location) and in the catchment area of this project, there is no meteorological station of any level.
Moreover, there are no flow data for the river near the project. Therefore, data for the hydro-
meteorological analysis is taken from the nearby station and similar areas. Rainfall &
temperature data are considered from Injibara Meteorological station. In fact, this station is very
close to the project area.
As per the data of the station, March – April are identified as high temperature periods whereas
December–January are low temperature periods. The mean annual rainfall amount is more than
1200mm (1991 - 2010 data) and most of it occurs from June to August.
Descending Logarithmic
Year Max. RF Order(X) Rank Value/Z/
1991 68.6 99.4 1 1.9974
1992 79.6 90.4 2 1.9562
1993 67.2 89.2 3 1.9504
1994 89.2 87 4 1.9395
1995 55.3 79.6 5 1.9009
1996 51.6 79.4 6 1.8998
1997 87 73.6 7 1.8669
1998 53.6 72.1 8 1.8579
1999 68.73 70.3 9 1.8470
2001 90.4 68.73 10 1.8371
2002 64.1 68.6 11 1.8363
2003 51.4 67.2 12 1.8274
2004 73.6 64.1 13 1.8069
2005 58.4 59.5 14 1.7745
2006 70.3 58.4 15 1.7664
2007 72.1 55.3 16 1.7427
2008 79.4 53.6 17 1.7292
2009 99.4 51.6 18 1.7126
2010 59.5 51.4 19 1.7110
SUM 1339.43 34.9601
MEAN 70.50 1.8400
STANDARD DEVATION 14.13 0.0864
SKEWNESS COEFICIENT 0.421 0.1008
( )
√
Mean = 70.50
= Standard error
( ) Acceptable
Relative standard error which is calculated above is less than 10%. Hence, the data series could
be regarded as reliable and adequate.
Where Xi and Xi‟ are the ith highest observed and computed values for the distribution
respectively.
All the candidate distributions give almost identical correlation coefficients. However, the
standard errors are significantly lower for the Log Pearson Type III Method which is 0.241. but,
the design rain for this distribution has been selected as the Gumbel method. Because it gives
high values which make safe design.
The design rainfall using Gumbel Method is given as
R f Rmean . n1 * K
T
Yt ln ln( ) , T= Return period = 50 years
T 1
50
Yt ln ln( ) 3.9
50 1
Yn, Sn = constant found from Gumbel‟s extreme value distribution table for N= 19 Years
Yn = 0.52 and Sn = 1.07
3.9 0.52
K ( ) 3.17
1.07
R f 70.5 14.13 * 3.17 115.30mm
Maximum probable flood is a hypothetical flood at a selected location, whose magnitude is such
that there is no chance to exceed. It is estimated by combining the most hydrological and
meteorological conditions considered reasonably possible at the particular location under
consideration.
As we have described earlier 19 years daily heaviest Rainfall data obtained from the nearby
station to injibara Meteorological station is used for determination of maximum probable flood.
Based on the available data, the following methods are used to estimate the design
= 1-0.044*(40.47)^0.275
= 0.878
=0.878*115.3
=101.3mm
elevation
length Tc=0.948*(L^3/H)
Class min Max differences
km ^0.385 hr
meter
So, the time required from the most remote point to the outlet is 3.3 hours. This time is the Time
of Concentration (Tc).
∑ {( ) ( ) ( ) }
Tim Desig Rainf Rainf Area to Area Increme Desce Asce Rearr Rearrange
e(hr) n all all point rain ntal nding nding anged d
point Profil Profil rain fall fall, Rainfall order Order order Rainfall(m
Rainf e (%) e ratio % (mm) (mm) m)
all (mm) Increment Accu
(mm) al mulat
ive
0-1 115.3 45 51.89 73.67 38.22 38.22 38.22 1 6 4.80 4.80
1-2 115.3 57 65.72 79.52 52.26 14.04 14.04 2 4 7.41 12.22
2-3 115.3 66 76.10 83.14 63.27 11.01 11.01 3 3 11.01 23.22
3-4 115.3 72 83.02 85.14 70.68 7.41 7.41 4 1 38.22 61.45
4-5 115.3 76 87.63 86.14 75.49 4.80 4.11 5 2 14.04 75.49
5-6 115.3 79 91.09 87.38 79.59 4.11 4.80 6 5 4.11 79.59
( )
Qp for
Incremental
incremental
runoff Incremental Hydrograph
runoff
Time
(mm) (m3/s)
Begin peak end
1 2
time time(Tp) time(Tb)
0-1 0.02 0.000 0 2.48 6.62
1.0-2.0 2.18 7.475 1 3.48 7.62
2.0-3.0 6.81 23.327 2 4.48 8.62
3.0-4.0 32.81 112.426 3 5.48 9.62
4.0-5.0 13.17 45.147 4 6.48 10.62
5.0-6.0 3.90 13.378 5 7.48 11.62
The peak runoff rate derived from triangular hydrograph is expressed as,
qp:
q p:=0.21* =3.43m3/s/mm
Qp for
Incremental
incremental
runoff Incremental Hydrograph
runoff
Time
(mm) (m3/s)
end
1 2 Begin time peak time(Tp)
time(Tb)
0-1 0.02 0.000 0 2.48 6.62 H1
1.0-2.0 2.18 7.475 1 3.48 7.62 H2
2.0-3.0 6.81 23.327 2 4.48 8.62 H3
3.0-4.0 32.81 112.426 3 5.48 9.62 H4
4.0-5.0 13.17 45.147 4 6.48 10.62 H5
5.0-6.0 3.90 13.378 5 7.48 11.62 H6
Hydrograph computation is the next step to compute the peak discharge. Its computation is done
by triangular hydrograph considering two slopes are opposite and join at a coordinate of peak
time and peak discharge.
Table 7: - Hydrograph coordinates
Time H1 H2 H3 H4 H5 H6 SUM Remark
0.00 0.00 0
1.00 0.00 0.00 0
2.00 0.00 3.01 0.00 3
2.48 0.00 4.46 4.51 9
3.00 0.00 6.03 9.41 0.00 15
3.48 0.00 7.48 13.92 21.76 43
4.00 0.00 6.54 18.81 45.33 0.00 71
4.48 0.00 5.67 23.33 67.09 8.74 105
5.00 0.00 4.73 20.40 90.67 18.20 0.00 134
5.48 0.00 3.87 17.69 112.43 26.94 2.59 164 Peak discharge
6.48 0.00 2.06 12.06 85.28 45.15 7.98 153
6.62 0.00 1.81 11.27 81.48 43.62 8.74 147
The peak discharge is determined as the maximum of horizontal sum of each incremental runoff
hydrograph which is equals to 164 m3/s
180.00
160.00
140.00
Series1
120.00 Series2
Series3
100.00
Series4
80.00 Series5
Discharge (m^3/s)
Series6
60.00
Series7
40.00 Series8
Series9
20.00
0.00
0.00 2.00 4.00 6.00 8.00 10.00 12.00 14.00
-20.00 Time (hr)
From the analysis, the 50 year return period design run off is 164 m 3/s.
The distance of the river cross-section is determined by the given data, which is east and north
coordinates. Distance of river cross-section is the sum of the square of differences in northing
and easting, then square root them. The cumulative of this distance is river cross section distance.
The water level of the river is taken at different points along the river channel around the head
work site. Surveying work done for 79.6m length. And then, average water surface slope is
considered as the river bed slope.
River profile
2177.4
2177.2
2177
River profile
2176.8
Elevation
2176.6
2176.4
2176.2 y = -0.0159x + 2177.2
2176 R² = 0.9422
2175.8 Linear (River profile)
2175.6
0 20 40 60 80 100
Chainage
Sr.No Elevation H A P R V Q
1 2175.57 0 0 0 0 0 0.000
2 2176.1 0.5 2.055 6.7617 0.30392 1.5818 3.251
3 2176.6 1 6.5619 14.3295 0.45793 2.0789 13.642
4 2177.1 1.5 12.6972 13.7991 0.92015 3.3104 42.033
5 2177.6 2 19.8581 16.0968 1.23367 4.0251 79.931
6 2178.1 2.5 28.0446 18.3945 1.52462 4.6354 129.997
7 2178.6 3 37.2568 20.6922 1.80052 5.179 192.952
The maximum flood calculated is164m3/s. By interpolation, the elevation of the maximum
probable flood becomes 2178.34masl. That means, that HFL before construction is 2178.34masl.
Again by interpolation, the corresponding velocity is 4.929m/s and its velocity head is 2.77m.
So, D/S TEL=2178.34+2.77=2181.11masl. So, the height of D/S guide bank can be fixed at
2181.11masl.
Finally, stage discharge curve is drawn, which is elevation in a vertical axis and discharge in a
horizontal axis.
2
Stage discharge curve
1 Linear (Stage discharge curve)
0
0.000 50.000 100.000 150.000 200.000 250.000
discharge
3. HEADWORK
3.1. Headwork Site Selection
The site selection for the diversion headwork is based on Engineering principles (hydraulics,
structure etc) and other socio-economic bases, which prove the design to be preceded. From
hydrology report, the maximum probable flood occur in 50 years is 164m3/s. As the head work
topographic map shows, the average river width (i.e. the perpendicular distance measured
between the left and the right banks of the river) at the selected weir axis cross-section is about
23m.
The location of the weir and the actual site is selected with the following considerations.
i) A narrow well defined channel with banks is the best.
ii) The canal alignment should enable suitable command without excessive digging.
iii) Availability of materials of construction like sand and gravel.
iv) Accessibility of the site by rail and road.
v) Arrangement of diversion of the river during construction
unit horizons (top low plastic clay and lower boulder deposit and massive basalt) are found up to
kms. These overburden soil materials have been affected by erosion/ flood under cutting which is
widening the bank by forming nearly vertical slope. Such vertical slope configuration observed
at upstream and downstream bank part forms instability or collapse. Here, it is important to
design the bank slope to stable configuration, just by providing retaining wall.
3.2.6. Water
Water for construction purposes can be found from the project stream, Agzi, itself. The stream is
perennial throughout the year that there is some amount of flow along its course. During this
field time the stream flow was more than 140l/second.
Total loss=head loss across head regulator + loss in the canal + head loss at the turn out + head
loss at the field = 0.06+0.05+0.05+0.00= 0.16m
= 2177.76 - 2175.57
= 2.19m
Length of the weir depends on the stability of the riverbanks near the weir site and taking into
Account the area of submergence on upstream side of the weir axis.
But, the actual width of the river cross section along the weir axis is 23m. So, the actual length is
Used for design of the structure.
According to the Beligh‟s formula, top and bottom width of the weir body is determined as
follows
Input Data:
P: Height of weir (m) = 2.2
He: specific energy head (over flow depth + approaching velocity head (m))
: Specific weight of weir body (2.3 for cyclopean concrete)
He
Top width, B 1.81m
1
He P
Bottom width, B' 3.73m
1
Provide 1m and 3m top and bottom width respectively, which will be tested for adequacy during
stability analysis.
From the stage –discharge curve prepared the high flood level before construction (i.e. D/s HFL)
corresponding to the design flood is 2178.340amsl.
Q=Cd*Le*He3/2
The shape of crest profile depends upon or affected by the shape of the weir; because of the
coefficient of discharge, Cd varies with the type of weir and shape. Since the type of weir
selected for AGZI-3 project is broad crest and the coefficient of discharge Cd was assumed to be
1.7.
The usual broad crest weir formula is used for the evaluation of the discharge that could pass
over 100% of the weir and it is expressed by the above formula. Hd is the depth of water over the
weir crest. This is calculated by assuming broad crested weir formula.
Design head over the weir, Hd is the difference between head over the weir and approach
velocity head. To calculate the velocity head, the approach velocity is computed by the formula
found below and the result is calculated by trial and error.
The velocity head, ha is computed from the approach velocity as shown below
2
va
ha
2g
Q
Va
Lxh d
2 2
Q 164
L * hd ( 23) * hd 2.59
ha H e hd 2
(2 g ) ( 2 * 9.81) hd
U/s HFL =U/s TEL –velocity head = 2180.36 m a.m.s.l – 0.12m = 2180.240m a.m.s.l
3.4. Afflux
Afflux is the rise in maximum flood level of the river upstream of the weir after construction of
the structure. The amount of afflux will determine the top level of the guide bank and merge
bank. The limit of the afflux to a safe value of 1.0 to 1.2 meters, however, in steep reaches with
rocky bed; a higher value of afflux may be permitted.
U/S HFL=2180.36
D/S HFL=2178.34
⇒ Afflux = U/s HFL- D/s HFL = 2180.24 a.m.s.l – 2178.340 a.m.s.l = 1.90m.
From the flood level analysis, it is seen that the flood overtops the banks of the river u/s of the
structure. The calculated afflux, 1.90 is greater than the allowable afflux 1, but the river banks
are low Plastic Clay soil. In addition to this, protection walls are provided. Therefore, the
calculated afflux could be adopted.
Needs some treatment measures to protect the overtopping of the water over the river bank due
to the construction of the weir. Therefore it is important to know where the effects of the back
water curve will case.
Approximate method:-
Y=((XS-2 0)2)/4 0
= rise water above the normal water depth at the weir site
(x=0)
Y=((xs-2 0)2)/4 0
0=((xs-2 0)2)/4 1
((xs-2 0)=0
0=(Hw+Hd)-TWD = 1.9
X = 253.3m
So that the effect of construction of the weir on the water profile during peak flood at around
253.3m back from the axis. But the topography of u/s of the river both right and left side almost
slant (sloppy) and the back water have not effect.
Hydraulic jump is a jump of water that takes place when a super critical flow changes into a sub
critical flow. It is formed on a place when large velocity and lower depth flow contact with lower
velocity and higher depth flow. This phenomenon is called hydraulic jump. The computation of
hydraulic jump is done in momentum equation.
As discussed in the geologic report, the river bed is boulder deposit and slightly massive basalt
rock and hence stilling basin for energy dissipation is not required. But 3m apron proved in D/S,
b/c river bed material 0.2-0.3m boulder and underlain basalt rock. Both left and right side banks
are low Plastic Clay soil, a wing walls are required at u/s and D/s sides, so as to protect the
scouring of the bank due to the wing walls, and not to flow the river out of river bank in high
flood cases.
The length of wing walls is determined based on the length of Jump, and it is calculated as
shown below.
Neglecting the loss between upstream of the weir and at the toe of the weir considering the same
datum point, energy equation should be applied. Therefore, the energy in both locations became
equal. E0=E1
2.2m + 2.6m=y1+0.363/y12
4.8 = y1+0.363/y12
The value of initial depth, y1 from the above equation is computed by trial and error. The value
of y1 =0.81m. The corresponding velocity is calculated by:-
V1=q/y1=7.13/0.81=8.8m/s
(√ ) (√ )
Hydraulic jump length (L) for Fr=3.12 from the graph L=5*y2=5*3.2=17m or L=5(y2-y1) =12m
adopt 10m, b/c boulder and Rock River bed.
II. Basins for Froude numbers between 1.7and 2.5:- pre-jump stage, Basins for Froude numbers
between 2.5and 4.5(type I) transition flow stage
III. Basins for Froude numbers greater than 4.5 and velocity less than 15m/s (type II) provide
basin with chute blocks, baffle blocks and end sills.
IV. Basins for Froude numbers greater than 4.5 and velocity greater than 15m/s (type III) in this
case baffle block is not provided.
Therefore, in our case the Froude value between 2.5and 4.5(type I) transition flow stage.
Oscillating Jump (Fr=2.5 to 4.5):‐ there is oscillating jet entering the jump bottom to surface and
back again without any periodicity. The energy dissipation is between 20 to 40%.
Case 4: TWRC lower than JHC at low discharges, but higher at high discharges
Case‐5: TWRC higher than JHC at low discharges, but lower at high discharge
water Eo =
depth Q q=Q/L Hw He Z+He Y1 eqn eqn-1 Fr1 Y2
0 0 0 2.19 0 2.19 2.18 2.18 0.01 0 0
0.5 3.251 0.14 2.19 0.190 2.38 0.06 0.343 2.038 3.070 0.232
1 13.642 0.59 2.19 0.496 2.69 0.08 2.882 0.196 8.369 0.908
1.5 42.033 1.83 2.19 1.049 3.24 0.24 3.195 0.044 4.963 1.569
2 79.931 3.48 2.19 1.611 3.80 0.44 3.620 0.181 3.802 2.156
2.5 129.997 5.65 1.24 2.228 3.47 0.66 4.398 0.932 3.366 2.829
3 192.952 8.39 2.19 2.899 5.09 0.93 5.077 0.011 2.986 3.490
3.5
3
water depth,m
2.5
2
jump height curve
1.5
Tail water curve
1
0.5
0
0 50 100 150 200 250
discharge,m3/s
The horizontal apron may be depressed by excavating the river bed downstream of the toe of the
spillway to increase the tail water depth. The depth of depression may be equal to the difference
b/n the tail water depth and post jump depth.
Sloping apron is constructed above the river bed level extending from the spillway surface to the
toe. The sloping apron raises the level of the point where the hydraulic jump is formed. The river
be may be excavated to provide a drop in the river bed to lower the tail water depth.
H1=Hd+Hv = 2.6
H2=Y2- Hw = 1.01
Since H2/H1 = 0.19 i.e. less than 0.75 the flow is free (modular)
The stability analysis was done for the worst and static (normal) case for expected sever different
load combinations. The safety of the weir against sliding, overturning, compressive, tensile and
shear stress is calculated as follows:
Fo >=1.5
In the computation process the structure considering monolithic section & a unit length of the
weir& earth quake force is assumed to be negligible
For the ease of calculating moment arm for each section of the curved profile of the weir, the
curved surface was assumed to be linear from the weir height to the toe. Therefore, the weir will
be divided in to two sections.
These are the forces acting on the weir due to the reservoir created upstream of the overflow
section. This includes hydrostatic and uplift pressure.
Ph= ( )( )
C) Silt pressure
The gradual accumulation of significant deposit of fine sediments especially silt, against the face
of the weir generates a result of horizontal pressure Ps on the upstream section of the weir. Its
magnitude is a function of the sediment depth at worst condition with a height equals to silt
height (hs) assume that silt will be deposit up to weir height.
The silt pressure is computed using the widely used Rankin‟s formula
Ps= 1.17334KN/m
Equilibrium seepage patterns will develop under a weir section due to pores or discontinuous. It
is given by
U1 =Yw*h1*B
The stability analysis is done for expected sever different load combinations. This is the
condition when the weir body is subjected to design floodwater and pond levels with all intakes
and sluice gates are closed, tail water depth at the downstream level and silt pressure equivalent
to the silt height is acting on the upstream face of the overflow section.
125.92
W1 1.000 2.190 50.370 0.000 2.500 5 0.000
193.08
Sum 23.1261 8.76 112.502 31.496 5.293 5 31.579
Fo
( M ) 193.085 6.11 >1.5 Safe!
( M ) 31.579
ii) Factor of safety against sliding (FS)
Fs
V ,
H
112.502
Fs * 0.7 2.50 >1.5 Safe!
31.496
iii) Check for tension (i.e. whether the resultant lies within the middle third)
X
M ( ) M ( ) 193.085 31.579 1.44m
V 112.502
3
The eccentricity (e) should be less than B/6 = 0.5 , Hence the obtained e = 0.06m < 0.5m.
6
Conclusion: From stability analysis, the designed weir section is over safe. To be economical,
Provide 1m top width and 3m bottom width.
Divide wall is designed in order to create separation between outlet canal and natural river
course. The divide wall allows safe and stable base flow to the canal outlet. Flow turbidity
created by current flow impact over the weir body is reduced.
Hence the level of divide wall and weir body foundation should be the same and is
2175.570ma.m.s.l.
Provide 5 m wall height and the top level of the divide wall =2175.570+5m =2180.570a.m.s.l
Considering the construction case, take the thickness of the divide wall = 1m
Factor of safety
$ Against sliding, Fs
V =
H
Against sliding = 2.16>1.5 Ok!
$Against overturning =
Fo
( M ) 971.667 5.41
( M ) 179.667
Against overturning = 5.41>1.5 Ok!
Xavg
M ( ) M ( ) 971.667 179.667 2.4m
V 330
Xavg = 2.40
e = 0.4
To enables the canal to flow silt free water from surface as much as possible
To remove the silt that is deposited in front of the canal off take (regulator) by scouring
it.
To preserve a clear and defined river channel approaching the regulator.
In addition to the supply of water to the intake and the removal of silt, this acts to remove the
Under sluice provided to control water during irrigation period and to rush out silt and water
during summer season. The sill level of this under sluice is fixed to be 0.7 m higher than the
minimum bed level.
Hence, the sill level of the under sluice=river bed level + 0.7 =2175.57 + 0 .7=2176.26
The design of under sluice is done to ensure a well defined river channel near to the out let, scour
away the silt deposited in front of the out let, to pass safely the base flow of the river during
construction & maintenance times and to pass small amount of the flood to the d/s direction.
The sluice way gate should have a capacity of passing about five times dry weather base flow
Assume the dimension of under sluice is 1m *1m with allowable thickness of 6mm and area of
the under sluice is, A= 1m^2.
The discharge that passes through under sluice for orifice flow is
Qd = 2.19 m3/s which is greater than the above assumed under sluice discharge, 0.70 m3/s
therefore , the assumed dimension can pass more than five times dry weather base flow softly
The minimum command area is determined by the minimum flow of the river. But the canal
capacity should be determined for maximum command area and the corresponding discharge. In
this case the outlet capacity is fixed considering maximum duty and command area and 1
correction factors are considered to account the variation of duty.
The sluice way gate should have a capacity of passing about one point five times base flow
Q = CLHe3/2
Q 0.08
L 3/ 2
0.3m
CHe 1.7 x0.33 / 2
Where:-
For the first iteration of the intake structure, the area of the sluice gate is taken to be 0.5m*0.5m
So using the above formula for Qd, by changing the values of depth and width, we can find the exact
Since this value, 0.144m3/s is greater than the amount of discharge that want to pass through the
under sluice gate, 0.074m3/s. So, the under sluice gate dimension is enough to pass the
discharge.
The height of Maximum design flood and the flood jump height govern the height of the
retaining wall with some free board provided. Since for the case of this project the jump depth is
higher than the tail water depth the downstream retaining wall is based on the level of the jump
depth and free board (0.3m). However the upstream retaining wall design is based on the high
flood level on the upstream and free board. The length of U/S and D/S retaining wall is
determined with afflux and jump length.
Table 15:- Determination height of the U/S and D/S retaining wall
Description Result
U/S HFL 2180.24
U/S RBL 2175.57
Unit wt masonry 22.5
Unit wt saturated 19
Free board(assume) 0.3
Retaining wall height 5
H FB HT B1 B2 B
Load Moment
Code Vertica Lever Arm, R
Horizontal Positive Negative
l
W1 67.5 0.3 20.3
W2 174.4 1.6 284.8
W Soil 147.3 2.7 392.7
Pw 108.4 1.7 180.6
P Soil 69.3 1.7 115.4
SUM 389.1 177.6 878.3 115.4
Table 18:- Stability analysis
H FB HT B1 B2 B
3.2 0.30 3.5 0.6 1.8 2.4
Load Moment
Vertica
Code l Horizontal Lever Arm, R Positive Negative
W1 47.3 0.3 14.2
W2 70.9 1.2 85.1
W Soil 59.9 1.8 107.7
Pw 50.2 1.2 58.6
P Soil 32.1 1.2 37.5
SUM 178.0 82.3 265.6 37.5
As per the hydrological analysis and on the basis of the traditional Ethiopian Agro-Ecological
Zones (MOA, 2001), the UGDWIP area is basically classified as moist Woina Dega (cold) agro-
ecological zone, indicating better moisture condition in the area in wet seasons.
Most of the study area soils are categorized as deep soil (1-1.5 meter depth). Soils of the
command area are suitable for most of the selected crops to be grown.
The calculation of crop water requirement is a very important aspect for planning of any
irrigation project. Several methods and procedures are available for this. The Food and
Agriculture Organization (FAO) of the United Nations has also made available several
publications on this subject and other issues related with this. The computer program available in
FAO Irrigation and Drainage Paper No. 56 “CROPWAT” has been used for the calculation of
Crop Water requirement. This program is based on Penman-Monteith approach and procedures
for calculation of crop water requirements and irrigation requirements are mainly based on
methodologies presented in FAO Irrigation and Drainage Paper No. 24 “Crop Water
Requirements” and No. 33 “Yield Response to Water”.
The corresponding values of the crop water requirements of the proposed crops of the project are
presented in the Agronomy Study of the same project.
The gross requirement of water for irrigation system is very much dependent on the overall
efficiency of the irrigation system, which in turn is dependent on several factors:
Method of irrigation
type of canal (Lined and/or Unlined)
method of operations (simultaneously and continuous or Rotational water supply), and
Availability of structures (for controlling and distribution and measuring and
monitoring).
On the basis of these factors, the project has planned to impose surface irrigation method (using
furrows). The canal system is unlined other than main canal.
Hence, the conveyance efficiency has been estimated to be 90%, distribution efficiency 85%, and
field application efficiency 64%. As a result of these the overall irrigation efficiency has been
estimated to be 49%. According to soil Lab result, soils of the command area are predominantly
characterized as heaver clayey soils.
For this project, among the various irrigation methods, surface irrigation method has been
selected. Of the surface irrigation methods furrow, border and basin irrigation methods can be
used to supply irrigation water to the plants/crops. However, each method has its own advantages
and disadvantages. Care should be taken when choosing the method which is best suited to the
local circumstances, i.e.
Based on the above factors surface irrigation method has been proposed for the proposed crops
in this project. The method allows applying light irrigation and can be laid out in sloping fields
along the contour. Furrow irrigation method is best suited for most of the proposed and row
planted crops. In general, furrow irrigation method is simple, manageable and widely practiced
irrigation method. This method is suitable for row crops that cannot stand in water for long
periods. The only thing required to use this method is row planting of crops. Besides, basin and
border irrigation method would be used for the non-row planted crops. Rotational flow water
distribution is also recommended for the project area.
The proposed cropping pattern of Agize diversion irrigation project has showed a maximum net
irrigation water requirement (NIWR) in the month of March with the amount of 4.69mm/day for
18 working hours for specific proposed crop (cabbage). However, for the designing of the
irrigation water application and the flows in the entire canal systems, from the overall proposed
crops the one that has maximum NIWR was used for irrigation duty calculation
For Agize River/Stream Diversion Irrigation Project, it decided to adopt 64% field application
efficiency, 85% distribution efficiency, and 90% conveyance efficiency as the soil is heaver clay
textured and the canal systems are estimated to be unlined except main canal. Hence, the
overall/project efficiency for the selected surface irrigation method has been estimated to be
48.96% (64/100*90/100*85/100) which is rounded to 49%.
The GIWR, 9.57 mm/day, represents the daily quantity of water that is required to be applied.
This water quantity is also used for the determination of the canal discharge in consideration of
the time of flow and is defined as the duty, expressed as l/s/ha.
The duty for the GIWR of 9.57 mm/day and 18 hours of daily irrigation time (t = 18), is
supported to be used with furrow irrigation method. Hence, Duty for 18 working hours, as the
site is nearer to farmers‟ village and local farmers have experiences in irrigation, is computed as
follows:
4.3.3. Slope
Slope is fixed by the design discharge and silt factor or velocity. A steeper slope with maximum
permissible velocity will be more economical, but the FSL will be lower. Additionally the design
slop is flatter than the natural available slope. Fall is provided to adjust the slope, but the number
of falls must be of minimum.
In our project work the Side slope for unlined canal is taken as trapezoidal section so that the
recommended Side slope is 1V: 1H value. So it is Tertiary canals.
Cutting Embankment
However in our project work the Side slope for lined canal is taken as rectangular section so that
Side slope is zero value.
Take longitudinal slope from below table between the ranges. But for lined main canal 1/800 to
1/1000. S=0.0035 for unlined canal and 0.00125 for lined canal.
Material Coefficient(n)
Wood 0.013-0.165
Steel 0.0125-0.018
Concrete 0.013-0.018
Masonry 0.02-0.036
Earth 0.0225-0.035
Minimum base flow of the river is 140 l/s and allows 42.8% to downstream =140*42.8
=60 l/s so, we can divert140 l/s - 60 l/s ≈80 l/s amount of water.
The main canal is designed for a discharge of 80l/s and depending on the site specific condition,
appropriate slope is provided and it contain reach-1 and reach-2.
Hydraulic parameters of the main canal Reach-1, 0+1+000 are shown below.
D=0.414m
A=2D2 = 2*0.3142 =0.19m2
P=4D =4*0.314 =1.26m
R= A/P = 0.19/1.26 = 0.16m
= 0.42m/s<2.7m/s OK
A= BD+MD2
0.19=B*0.57+0*0.57^2
B=0.433m
D=0.363m
A=2D2=2*0.363=0.132m2
P=4D=4*0.363=1.089m
R=A/P=0.121m
V=Q/A=0.608m/s , B=0.4m
2. Farmers training, how to operate and maintain the project structures as a whole and
available and water resources has a paramount important.
3. The irrigation hours per day and per week should be flexible based on base flow
amount of each week or month.
4. Close supervision of the construction should be made to modify (if need be) each
Components of irrigation system based on specific site conditions.
5. The local peoples should be considered and include in the project construction
working activities
8 REFERENCE
1. FAO (1977) guidelines for predicting crop water requirements. No 24
2. Design of small Canal structures , USBR
3. Applied hydrology ,Vent Chow Edition 1988
4. Engineering Hydrology K Subramanya, third edition Tata McGrawl, 2008
5. Irrigation Engineering and Hydraulic Structure, by Santosh Kumar Garg, fourteen edition,
august 1999.
6. Drainage design manual chapter 5 hydrology part, by Ethiopia road authority 2002.
9. APENDIX
9.4 Annex 4: KT VALUES for Pearson Type III distribution (positive skew)