08-16G WireCable&Terminations
08-16G WireCable&Terminations
Facilities Services
Design Guide Wire, Cable and Terminations
Basis of Design
This section applies to the design and installation relating to wire and cable systems and terminations.
Design Criteria
Medium Voltage
• Review and modify the attached guide specification as required to meet the project
requirements.
• Cable and wire procurement, especially for short lengths of interlock armored cable, can take
additional time. The consultant shall include fair warning to the Contractor in the
specifications.
• Cables are subject to ambient temperatures of –20º to +40º C (0 to 105º F).
• Connection points shall be provided in all electrical vaults and manholes to allow future
facilities and other services to be connected to the primary distribution system.
• The following are typical medium voltage connections:
Design Evaluation
• Construction Document Phase: Complete one-line diagram showing conductor and cable
sizing. Complete plans showing distribution routing and cable schedules. Final details on
location of connections and types of termination to the primary distribution system. Complete
detail drawings showing connection hardware information, protection methods and grounding
information. Complete specifications.
Submittals
• For medium voltage systems, refer to attached guide specification, MV.Wire, Cable and
Terminations.
• For low voltage systems, submit standard industry requirements.
Medium Voltage
• Power conductors shall be stranded copper, 98% conductivity. Number 12 AWG is the
minimum conductor size. #12 and #10 shall be solid conductor for lighting and receptacle
branch circuits, and stranded for motor and equipment circuits and wherever vibration is a
consideration.
• Insulation THWN or XHHW (Also THHN when 1/O or smaller)
• Conductor color code per requirements in Electrical – Identification section
• 600 volt control wiring cable shall be in accordance with power conductors above, except #14
AWG shall be permitted and all control wiring shall be stranded.
• "Low voltage" and special cables shall be as specified in subsequent functional sections (e.g.
communications, fire alarm, computerized system, television, etc.)
• 600 volt splices shall be:
1) Solderless type only
2) Preinsulated "twist-on" type permitted on solid conductor size # 10 and smaller
3) Hydraulic compression long barrel type with application preformed insulated cover,
heat shrinkable tubing or plastic insulated tape for all stranded conductors
4) For stranded conductors provide terminations designed for use with stranded
conductors.
• 600V terminations:
Medium Voltage
• Provide cable ties (limit torque on ties) in panelboards, cabinets, and other unconfined
spaces. Group and lace wiring neatly, and do not tie to factory-installed wiring in equipment.
Bundle and tag multi-pole circuits in laboratory surface metal raceway.
• Branch circuits: Homeruns greater than 75 feet to first outlet shall be # 10 minimum.
• Do not use mechanical means for pulling wires. Uselubricants that do not clog conduits after
use. Splices are not allowed in Homeruns.
• Terminate conductors so that conductor information is easily visible on at least one
termination per feeder or within panel or switchboard pulling space.
• Observe cable bend radius limitations and follow lug manufacturer's installation procedure.
• Provide all control wire terminations with approved wire markers which mark the conductor
with the terminal number for the wire.
• Do not score the conductor when stripping insulation, and always pare or pencil when using
a blade. Use of a stripping tool is preferable.
GUIDE SPECIFICATION
The following specification is intended as a guide only. The Consultant shall write the specifications to
meet the project requirements in consultation with the Owner.
PART 1 - GENERAL
1.01 DESCRIPTION
A. Purpose
1. This section covers medium voltage cable and terminations for use in the University's primary
and secondary power distribution systems.
1.02 QUALIFICATIONS
A. Approved manufacturers
1. Medium voltage 5 and 15kV wire and cables
a. 5 and 15kV single conductor: Pirelli, Aetna, and Okonite
b. 5 and 15kV armored cable: Pirelli, Aetna, and Okonite
(1) Service Wire for short lengths of interlock armored cable (< 500 feet)
c. All other manufacturers shall be approved during the design prior to bidding.
A. The work under this section is subject to requirements of the Contract Documents, including the
General Conditions, Supplemental Conditions, and sections under Division 1 General Requirements.
B. Electrical Identification
1.04 REFERENCES
1.05 COORDINATION
1.06 SUBMITTALS
A. General
1. Submittals shall be in accordance with Conditions of the Contract and Division 01
Specification Sections.
2. Submit detailed maintenance manuals and drawings, which include catalog information
indicating the complete electrical and mechanical characteristics.
3. Submit current manufacturer’s AEIC pre-qualification data.
4. Submit dimensioned cross-sectional drawings (manufacturer’s data sheets are acceptable).
5. Submit finished cable tests – Manufacturer’s Certified Test Reports showing compliance with
ICEA S-68-516, Part 3, and UL 1072 for physical requirements of the armor and all AEIC final
tests, including x-y plots of corona discharge for the actual cable furnished.
6. Submit pulling calculations and plan for each medium voltage cable length.
7. Submit data sheet on crimping tools to be used.
8. Submit for approval the résumés of the medium voltage cable splicers. Qualifications should
include certification, recent work history on similar splice type and knowledge of the “Safety
Standards for Electrical Workers” (WAC 296-45).
A. Operations and Maintenance Manuals shall be in accordance with Conditions of the Contract and
Division 01 Specification Sections.
B. Operations and Maintenance Manuals shall include but not be limited to pull calculations and catalog
information indicating complete electrical and mechanical characteristics.
1.08 MEETINGS
A. Pre-installation conference
1. The Contractor shall request a pre-installation conference with the University’s Campus
Engineering and University’s Physical Plant High Voltage Shop for projects with medium and
high voltage work.
B. Attend meetings with the Owner and/or Owner’s Representative as required to resolve any
installation or functional problems.
C. Within 1 month after “Notice to Proceed,” schedule a meeting with UW Representatives to review
electrical identification requirements.
PART 2 – PRODUCTS
2.01 GENERAL
A. These cable and terminations specifications are in accord with the University's policy to construct
permanent installations with long life, coupled with maximum reliability and safety. It is intended that
the best available materials be used and new and better materials adopted as they become available
and are approved by the University.
A. The following shall apply to both 5kV and 15kV medium voltage power conductors used as single
conductors or assembled into 3/c armored cable:
1. Single conductors
a. Conductors: Class B stranded, concentric, soft or annealed copper per Part 2 of ICEA S-
68-516
b. Strand screen: Extruded semi-conducting thermosetting compound applied over the
conductor. The material shall be compatible with the conductor metal, shall be uniformly
and firmly bonded to the overlying insulation, and be free of stripping from the conductor.
c. Insulation: High quality heat, moisture, ozone and corona resistant Ethylene Propylene
Rubber (EPR) compound
(1) The insulation shall contrast in color with the strand screen and insulation shield per
AEIC CS 6.
(2) Insulation level shall be 133% (115 mils for 5KV, 220 mils for 15KV).
(3) The minimum thickness of the insulation at any point shall not be less than 90% of
the specified nominal thickness.
(4) The insulation shall contain no more than 2% polyethylene.
d. Insulation shield: Extruded semi-conducting thermosetting compound applied directly
over the insulation. The material shall be compatible with the insulation and overlying
metallic shield. The insulation shield shall be clean and free of stripping from the
insulation and comply with Paragraph D.1 of AEIC CS 6.
e. Manufacturing process: The strand screen, insulation, and insulation shield shall be
applied with a triple-tandem process providing a virtual corona-free core. The EPR
insulation system shall not be exposed to the atmosphere during manufacture.
f. Metallic shield and individual jacket: .005 inch thickness of copper tape helically applied
over the insulation shield material with a 20% overlap, covered with an extruded PVC
outer jacket meeting the requirements of ICEA S-68-516 Paragraph 4.4.10.
g. Identification: The following information shall be surface-printed on the overall jacket:
Manufacturer’s name, cable size, cable type, year of manufacture and voltage rating.
2. Armored cable
a. Single conductors: Per the section above. (Note: Individual PVC jacket shall be
required for each single conductor).
b. Grounding conductors: Bare copper, stranded in accordance with ICEA S-68-516, Part 2.
Minimum size shall be in accordance with UL 1072, Table 11A. (Note to designer:
Provide a larger size, if required, to handle calculated fault current.)
c. Filler material: Non-hygroscopic material, fine fiber, completely filling center and
peripheral interstices
d. Binder tape: Applied over assembly to provide a solid core
e. Armor: Galvanized steel or aluminum, interlocked armor in accordance with ICEA S-68-
516, Part 4 and UL 1072, Part 25.11
f. Overall jacket: Polyvinyl Chloride (PVC) in accordance with ICEA S-68-516 paragraph
4.4.10. Industry standard color by voltage class (15kV cable – red; 5kV cable – yellow).
g. Identification: The following information shall be surface printed on the overall jacket:
Manufacturer’s name, cable size, cable type, year of manufacture and voltage rating.
h. Listings: Finished cable shall be UL listed as Type MC, MV-90 and "For CT USE."
i. Color for outer jacket shall be consistent with industry standards.
3. Cable rejection
a. Cable shall be subject to inspection by the University at delivery and installation and
subject to rejection for shipping and/or installation damage including, but not limited to,
jacket penetration, armor denting, or other indications that cable integrity has been
compromised.
b. Hi-pot and Megger testing will not be the sole determining factor in the Owner accepting or
rejecting damaged cable.
A. Medium voltage
1. Medium voltage connections and terminations (armored cable and single conductor) - Long
barrel, 2-hole hydraulic crimp lugs, with Raychem "HVT" or 3M "Quick Term" series 5600
termination kits
2. Medium voltage connections and terminations (armored cable and single conductor) - Long
barrel, 2-hole hydraulic crimp lugs, with Raychem "HVT" or 3M "Quick Term" series 5600
termination kits.
3. Splices other than cold shrink are to be housed in a listed enclosure: OZ Gedney Series
SPKJR, G&W #E74 or Adalet 3AS manufactured by PLM, with fittings to suit cable.
4. Method of crimp termination for #8 awg and larger shall be performed with correctly sized
hexacentric die only.
a. Approved manufacturers: 3M, Elastimold; all other manufacturers shall be approved prior
to bidding.
PART 3 – EXECUTION
3.01 REQUIREMENTS
A. General installation
1. Identification
a. Reference section Electrical - Wire, Cable and Terminations
2. Installation
a. Only personnel qualified and experienced in this type of work shall make connections.
b. The installation of cables shall be done with care to avoid damage.
(1) Cables showing damage after installation shall be replaced.
(2) Rollers and spools shall be used in adequate numbers for pulling in cables.
(3) The tension limitations, side wall pressure, and minimum bending radius as given by
the cable manufacturer shall be observed.
c. Cable pulling
(1) In no case will strands be removed to attach pulling eyes.
(2) Tension is limited to 1000 lbs. using basket grips.
(3) Lubrication shall be as approved for the insulation and raceway material.
(4) Prior to pulling, calculations of pulling tension and side wall pressure shall be
submitted.
(5) A dynamometer shall be used and tension recorded for all MV pulls.
(6) Use no mechanical means for pulling #8 and smaller AWG conductors.
d. Cable pulling setups and operations shall be witnessed by the University Physical Plant
High Voltage Shop and Campus Engineering.
e. Interlocked armor cable shall be pulled only when both the armor and conductors are
gripped. Remove cable similarly.
f. All cable that leaves a tray shall be taped/wrapped with Scotch 77, MAC AP30, or Quelcor
“Quelpyre” fireproofing tape.
10. Do not score the conductor when stripping insulation and always pare or pencil when using a
blade. Use of a stripping tool is preferable.
11. All terminations shall be secure and tightened in accordance with the manufacturer's
recommendations.
D. Training
1. Provide operation and maintenance training for two 2-hour sessions of on-site training for a
total of 6 maintenance personnel.
2. Include troubleshooting, repair and maintenance manuals for each participant.
E. Testing
1. Provide factory field startup and testing services to assist the ETC (Electrical Testing
Contractor) per Section Electrical - Inspection, Calibration and Testing.