Volume I
Volume I
Volume I
Volume I
GENERAL INDEX
Installation Section 2
Commissioning Section 3
INDEX
Contents Page
1. INTRODUCTION
The gas turbine package consists of a two sections, housing the auxiliaries and
the gas turbine.
Both gas turbine and auxiliaries are mounted on a common integral base plate.
On this one is mounted an acoustical enclosure that hold gas turbine and
auxiliaries.
The accessory side of the compartment contains the mechanical auxiliaries, both
mechanically (via accessory gear) and electrically driven, the lube oil system, the
fuel systems and the gas turbine starting means.
The turbine side is separated from the accessory compartment by the combustion
air inlet plenum.
The enclosure is equipped with access doors for inspection and maintenance.
The following code numbers refer to gas turbine model MS5001PA “Turbogroup
General Arrangement”, SOM 5086226/3.
When the starting system is actuated and the clutch is engaged, ambient air is
drawn through the air inlet plenum assembly, filtered and compressed in the
axial-flow compressor.
For pulsation protection during start-up, the air flow coming from the 10th stage
extraction valve is conveyed to the atmosphere through the exhaust duct/stack.
When the starting system has accelerated the rotor to ignition speed, the two
spark plugs are energized and fuel is turned on. The resulting fuel/air mixture is
injected, by means of 10 burners, in the relevant combustion chambers and
ignited by the spark plugs. When the chambers are lit, as indicated by the flame
detectors, the start-up sequence continues.
When the rotor speed relay actuates at 95% speed, the antisurge valves
downstream the 10th stage extraction are closed. The air extracted from the 10th
stage will be used as cooling and sealing air in the wheel spaces and in the
bearings.
Air from the compressor flows into the annular spaces between the outer
combustion casings and the combustion liners, and enters the combustion zone
through the combustion liner.
The hot gases from the combustion chambers flow through the transition pieces.
The gases then enter the 1st stage fixed nozzles and the 1st stage turbine wheel
buckets and subsequently the 2nd stage nozzles and 2nd stage wheel buckets. In the
nozzle rows, the energy of the jet is increased, with an associated pressure drop
and is absorbed as useful power on the turbine rotor.
After passing through the 2nd stage buckets, the gases are directed into the exhaust
hood and diffuser, which contains a series of turning vanes to turn the gases from
an axial direction to a radial direction, to minimize exhaust hood loses.
The gases then pass into the exhaust plenum and are introduced to atmosphere
through the exhaust stack. Resultant shaft rotation is used to produce electric
power turning the driven Generator.
Filter House
Turbine combustion air is sucked by the turbine through the air filter system. This
air filter is then cleaned to give the air filter greater cleaning efficiency and
greater life.
The system is designed as a two stages barrier type air filter and are composed
mainly by a prefilter barrier to separate the roughly parts contained in the air and
finally by the high efficiency barrier to separate the small foreign parts of the air.
Upstream and downstream the two barrier there are two marine vane separators.
Upstream the first barrier are installed two screens to avoid the insertion of birds
and insects in the air suction section that can cause damages to the engine.
Between the two stages there is inserted a duct blowing the air to the ventilation
system of the enclosure..
Downstream the high efficiency filters is installed a silencing system composed
by several silencer panels installed inside the air inlet duct.
Contained within the gear casing are the gear trains, which provide the proper
gear reductions to drive the accessory devices at the required speed, with the
correct torque values. The starting clutch assembly is mounted forward on the
horizontal joint of the main gear shaft and is used to connect the starting device to
the gas turbine.
Accessories driven by the gear include: the main lube oil pump and the main
hydraulic supply pump.
The gear box transmits a torque from the starting means to the gas turbine during
start up.
Lube oil main shaft driven pump, or stand-by and emergency pumps, when
running take their suction from the lube oil tank and discharge into a common
bearing header at a pressure of 172 kPa. The lube oil pumped from the lube oil
reservoir to the bearing header flows through an heat exchanger to remove excess
heat and then through the cartridge type filter providing 12 micron filtration.
After lubricating the bearings the oil flows back through various drain lines to the
reservoir. Minimum start up oil temperature is 20°C.
The lube oil filtration system is made out of two parallel filters and one transfer
valve directing the lube oil flow to one or to the other. This allows the
replacement of one filter without stopping the unit. Filter elements should be
changed when the differential pressure transmitter (96QQ-1) gives a differential
pressure of 1,7 kPa.
The preferred oil for the Nuovo Pignone’s gas turbine is the Light Grade oil
having a viscosity of 140 to 170 SUS (Saybolt Universal Seconds) at a
temperature of 38°C (100°F) (Lube oil type ISO VG 32).
The properties of three light grade oils are listed in Table 1 and the lubricated
equipment in Table 2.
Table 1
Viscosity at 100°F
(37,8°C) SUS
(min.) 140 140 140
(max.) 170 170 170
Viscosity at 210°F
(99°C.) SUS
(min.) 43 43 43
Table 2
CONSUMPTION
(LITERS/DAY)
FREQUENCY
LUBRICANT
OF CHANGE
Q.TY OF 1ST
EXPECTED
(LITERS)
SAMPLE
FILLING
LUBRICATED OIL MAKER
TYPE
PART
SHELL
Any
LUBE OIL-ISO VG 32 GT
Gas fuel is first cleaned by passing through a strainer, metered and controlled by
the gas valve (Gas Stop/Speed Ratio and Gas Control Valve) to supply the
required flow to the gas turbine combustion system through 10 combustors (one
for each combustion chamber).
The fuel gas speed ratio and control valve consists of two independent valves (a
speed ratio and control valve) combined into one housing assembly. Both the gas
speed ratio valve and gas control valve are single action, electro-hydraulically
operated.
The fuel gas control valve is activated by a Speedtronic control signal to admit
the proper amount of fuel required by the turbine for a given load or speed. The
fuel gas stop ratio valve is used also as shutoff gas control valve.
Associated with this gas valve are the vent valve, control servo valves, pressure
gauges, as above mentioned, and the distribution piping to the combustion fuel
nozzles.
This cooling and sealing air provides airflow to certain internal and external
turbine parts to prevent excessive temperature build-up in these parts during
normal operation and for sealing the turbine bearings. The parts of the turbine
section which are cooled by air consist of: the first and second stage turbine
wheel forward and afterward faces, the turbine shell and the bearings.
The combustion chambers liners, transition pieces, and the combustion casing,
are designed to utilize compressor discharge air for effective cooling of these
parts.
2.13 Bearings
The gas turbine unit MS5001PA has two journal bearings to support the rotor,
and one thrust bearing for axial thrust.
The bearing # 1 is located in the compressor inlet casing and the bearing # 2 is
located outside after the discharge casing; the thrust bearing, positioned in the
bearing # 1 casing, is composed by two parts: one positioned in the active side of
the rotor collar to support the active thrust and the other positioned in inactive
side to support the transient thrust.
The bearing assembly consists of oil seal system, an oil ring and the surrounding
housing.
The turbine bearings are pressure-lubricated by the lube oil supplied from the
lube oil header. The drain oil returns through passages in the bearing housing,
then into the drain line to the oil tank. The oil seals control the oil flow along the
shaft. The seals consist of labyrinth packing of teeth assembled at the extremities
of the bearing assemblies.
3. GENERATOR DESCRIPTION
The Electric Power Generator (brushless type) (see Fig. 1.2) consists of a three
phases alternating current generator and is composed by a static part as stator
(called Armature: the assembly of conductors in which the voltage is inducted)
and a rotor (called Field: consisting of a source of magnetic lines of flux) and the
rotating exciter connected and driven by the rotor, installed in the N.D.E. side of
generator, necessary to produce and supply the power to the rotating field
winding.
The Generator is installed on a baseplate common with the load Gear Box that
reduce the rotating speed from Turbine speed to the Generator speed (rpm 1500).
3.1 Stator
The stator consists of the frame, the core with its thousands of lamination and the
stator winding (armature). The stator winding is provided with the phase
connection rings and bushings, transmitting the electrical power generated.
3.2 Rotor
The rotor is made up of a forging shaft which contains the rotor winding (know as
field). It is also composed by wedges and retaining rings necessary to contain the
rotor winding against the very high centrifugal forces developed during its
rotation. It is supported at the ends by two journal bearings continuously oil
lubricated.
The possible transient axial thrust is supported by the Gear Box thrust bearing.
Being the low shaft of the Gear Box, driving the Generator, rigidly connected to
the Generator.
At the end of the rotor (N.D.E. side) is keyed the exciter current generator
(brushless type with rotating diodes ) to excite the Generator field.
3.3 Bearings
The two Journal bearings, sleeve type, are lubricated by the oil coming from the
turbine bearings header to which the Generator bearings header is connected.
The bearings are grounding insulated to avoid the induction currents through the
shaft and the bearings.
4. DESIGN BASE
5. AUXILIARY - FACILITIES
INDEX
Contents Page
Contents Page
1. FOREWORD
The present section describes the main erection activities to be carried out in a
Power Generation Station.
Every work shall be carried out according to the Contractor and/or to the Owner
standards and specifications either for the general prescription or for specific
manufacturing standards, norms, special norms of pre-commissioning, execution,
checking, etc..
These instructions, that do not purport to cover all details not to provide for every
possible contingency, are intended to supplement the experience and ability of
qualified personnel who is assumed to be familiar with the installation of turbo-
generator, in general and with the use of tools and commonly used elements,
materials and methods.
Good judgment and proper safe practices to avoid personal injury and property
damage shall be exercised by the personnel who shall not consider the instructions
as relieving him from the responsibility of ensuring a competent care of the
equipment.
! WARNING
The standard and special tools listed hereinafter permit to carry out the installation
operations of all component parts of the Turbine.
Before carrying out any operation demanding the use of the following tools, it is
necessary that the installation-men perfectly know how to use the machine, fol-
lowing the instructions supplied by the manufacturer and the indications reported
on the machine itself.
Moreover, the installation-men must be well trained to do their job and to use the
special tools.
! DANGER
BEFORE LIFTING THE DEVICES, VERIFY THEIR POSITION AND THE LIFT-
ING POINT CAPACITIES IN THE LIFTING DRAWINGS.
THEN, CHECK THE SPECIAL TOOLS FOR CORRECT POSITIONING AND
CLAMPING.
DO NOT USE SPECIAL TOOLS FOR OPERATIONS OTHER THAN THOSE
FOR WHICH THEY HAVE BEEN BUILT.
ONLY SPECIALLY TRAINED PERSONNEL MUST CARRY OUT ALL LIFTING
AND HANDLING OPERATIONS.
For details, please refer to “Reference Drawings and Special Tools” Volume of
the Job.
For Electric Generator tools see the relevant “Brush” Generator Manual.
4. STANDARD PRACTISES
! WARNING
4.1 Turbogenerator
The heavy equipments (as Turbine, Generator), installed directly in the final
location, will be protected by the adverse conditions using suitable coverings.
If the storage time is short it is advisable to keep the equipments temporary
protected by the shipping packing until the beginning of erection activities.
Particularly for the turbine package, the internal parts are already protected in
factory, before shipping. In the mentioned way the turbine is protected for a term
of six months, if the time of storage will be longer is necessary to provide again to
a further protection after an inspection of Nuovo Pignone personnel.
EXPIRY TERM
Storage place Class ITN 54701.00 (months)
with barrier bag
Indoors, in air-conditioned
A 12
shed
4.1.7 Miscellaneous
A wooden protection must be installed to protect the equipment against possible
damages due to the lifting device slings. For the transoceanic transportation and
once the unit is loaded and firmly secured on the ship, the lifting device shall be
sea fastened to avoid any wear against the unit due to ship motions.
All the instruments which could be damaged during transportation due to the
vibration must be properly supported and / or fixed. All instrumentation with glass
part has to be protected by rigid covers and nylon wrapped-up with plugs and
silicagel bags installed.
All equipment that is supported on antivibration supports shall be blocked to take
the weight off the supports and also secured (air cooler, if applicable, etc.)
The pipework that is supported on spring type supports or resting on guides or
with directional anchors shall be locked in position and secured.
Equipments shall be secured inside panel racks.
The cabinets shall be secured by temporary bracings. They shall be wrapped with
waterproof material.
Vessel internal (KO Pot) shall be checked for rigidity and where necessary
blocked and secured to prevent movements. In this case a notice has to be placed
externally.
All parts of flanges, valves and other parts not coated will be greased, wrapped
with waterproof barrier material and sealed.
Special care will be taken to unloading, handling and storing of all construction
material, arriving in site.
Check carefully the condition and quantity of arriving material, as per packing
list. Notify immediately to the Responsible for everything not conforming to the
packing list or for some damaged material. Take a picture of everything damaged.
File a report with the Shipper for damaged material.
Put the damaged material in a separate place from the right one.
On site must be available the lifting and transport means (cranes, tractors, tracks,
etc.) of adequate characteristic and quantities necessary to unload the arriving
materials and to move the same inside the site and bring them from the storage
area to the erection place.
Ensure all equipment is stored so as to prevent damage from the weather. Place all
ship loose items and control system parts in an area suitable for such equipment.
Electronic components and other sensitive parts should be kept under cover and in
a dry area.
Leave additional supports, bracing, covers etc. installed for shipping, until the
installation.
Reinstall all inspection covers that have been removed for inspection.
Turbine skid and Generator/Load Gear Box skid normally are discharged from the
transport means and immediately installed on proper foundations completed with
the required shim packs.
5.2 Storage
All material arriving at site will be stored in right condition and in appropriate and
codified place.
The heavy equipments installed directly in the final location will be protected by
the adverse conditions using suitable coverings.
If the storage time is short it is advisable to keep the equipments temporary
protected by the shipping packing until the beginning of erection activities.
Particularly for the turbine packages, the internal parts are already protected in
factory, before shipping. In the mentioned way the turbine is protected for a term
of six months, if the time of storage will be longer is necessary to provide again to
a further protection after an inspection of Nuovo Pignone personnel.
For turbine packaged with the enclosure installed on the base in enough to
maintain the doors closed installing inside some heater to avoid the condensation
formation.
For turbine oil reservoir and internal pipes the protection is performed by oil with
an additive anti rust. Before shipping the reservoir will be filled by an adequate
quantity of oil + additive.
For Generator/Gear Box skid the preservation will be carried out following the
Supplier’s instructions (see the relevant service manual).
The control and electrical boards will be stored in a clean, close and, if possible,
air conditioned ambient, to prevent condensation that may damage the electronic
components and circuits. If not possible the boards will be protected by a
breathable covers.
Piping may be stored externally without specific protection for a period of six
months. If the storage time will be longer is necessary to store them under a shed.
The piping will be normally shipped with the external surface painted and
plugged at the extremities.
! WARNING
Environmental Impact
During operation, the turbine produces a series of exhaust gases due to combus-
tion, approximately: 15% O2, 6% H2O, 2.5% CO2, N2 for the rest; also, minimal
quantities of polluting substances are present due to the type of fuel employed.
When the fuel employed is a natural gas, the main polluting substances are nitric
oxides (NO) and carbon monoxide (CO).
The turbine combustion chambers have been designed to reduce to a minimum the
presence of such oxides by acting on the mixing of fuel and air and by means of
low flame temperatures combustion (weak combustion).
Generally, nitric oxides tend to increase (also in percentage) with the turbine
power, while carbon monoxide (CO) acts in the opposite way. Carbon monoxide,
in fact, is less significant than NO but increases remarkably in low load conditions
(inferior to 30%) and, for this reason, it is necessary, if possible, to avoid running
in such conditions.
Sulphur oxides (SO) derive from the sulphur present in fuel and generally gas oil
contains more sulphur than other fuels.
Besides exhaust gas, other emissions are oil vapours due to the lubricating liquids
employed.
Once the plant is operational and during its whole life, it is the duty of the user to
keep emissions within the levels indicated by the relevant regulations in force and
to follow the instructions below:
- Perform all maintenance operations listed in this manual, according to the
schedule suggested;
- Do not modify the adjustments made by the Manufacturer upon installation;
- Remove any malfunctioning - as soon as possible -, which might cause an
increase in the emission rate (if necessary, refer to GE OIL & GAS Nuovo
Pignone Assistance Service).
Waste, derived from maintenance operations, must be stocked and treated accord-
ing to the local law in force and by referring, if necessary, to the safety data sheet
of the product itself (as concerns lube oils in particular) and the related filters in
order to prevent any risks for people and the environment.
Decommissioning
According to the principles of the EN ISO 14000 standard and the ISO EN 14040,
in particular, about Life Cycle Assessment, GE Oil & Gas Nuovo Pignone, in the
planning stage, has perfected a series of devices to facilitate the reutilization and
recycling of the materials and components of the turbine and its auxiliary systems,
and to reduce the environmental impact of the product in each one of its life cy-
cles.
In case of turbine decommissioning, perform the following operations:
Reduce to the minimum the materials to be dumped by their reutilization and re-
cycling (according to the related local law in force). GE Oil & Gas Nuovo Pig-
none is specialized in the recovery, reconditioning and reutilization of machines.
Contact GE Nuovo Pignone qualified technical personnel for turbine disassembly
procedures.
- Recover oils and other liquids from the related tanks and dispose of them
according to the local laws in force.
Fig. 2.1
Fig. 2.2
The Fig. 2.3 shows the final position of the foundation bolts, tightened and locked
as required. The lifting screw, before tightening the anchor bolts, will be
unscrewed leaving some gap between it and the lifting plate.
Fig. 2.3
Fig. 2.5 - Devices for horizontal positioning and locking of GT baseplate (typical)
1. Ruler with scraped control plans, length: 5000 mm, thickness admissible
tolerance: ± 0.05 mm.
2. Square level gauge, sensitivity: 0.03 mm per meter; length of sides: 200 ÷
250 mm
3. Template or Harmonic steel wire; length: 3000 x 0.5 mm
4. Outside micrometer 0 to 25 mm
5. Steel metric measuring tape; tape length: 20m
7. PRE-ALIGNMENT
7.1 General
On site alignment for turbo groups generally is divided in two phases: pre-
alignment and final alignment. Both alignments use the same philosophy and
same values, however:
Pre-Alignment:
Pre-alignment will permit the start of interconnecting piping and ducts assembly
and installation.
Final Alignment:
This alignment phase is carried out when all major mechanical components have
been installed: ducts, structures, interconnecting piping, gear box, generator, etc.
Temperature has a great impact on alignment readings: see alignment specifica-
tion for temperature impact and/or reference temperature.
7.2 Preparation
Before starting pre-alignment it is necessary to remove transportation devices
from the turbine and generator; these items are located on shaft end for locking.
Remove the turbine from the transportation third point using proper jacking
devices and refer to the turbine documentation.
Then proceed as follows:
• Prepare the shims pack for turbine and generator taken care to clean and
lubricate every single sheet. Prepare the necessary equipment for unit skid
lifting in case jacking bolts are not used. Be sure that no items interfere with
alignment activity in the alignment tools working area.
• Set in axial middle position the drive and the driven shafts and verify their
“face to face” distance respect the alignment specification requirements.
• Install the necessary alignment tool and the proper dial gauges as per the
Fig. 2.6
The vertical value (pos. 3) provides the misalignment value multiplied for two.
Example: if the specification set the vertical value to –2.00 mm and the reading
shows – 3.00 mm, the driven machine (the machine were has been taken the read-
ing) must drop 0.5 mm (3,00 – 2,00)/2.
Attention: when comparing the reading values with the spec values, remember to
subtract the set value. If in pos. 1 the gauge has been set at 2.00 mm, this quantity
is added to every position.
As explained above for the vertical reading, as soon as a reading turn is finish, the
sum of the horizontal values (pos. 2.& pos. 4) must be equal the vertical value
(pos. 3).
The following instruction describes how to record the readings using two gauges
for the axial readings and a third gauge for the radial readings; the alignment tools
are usually provided for this kind of alignment.
The readings will be done on four position: at 12:00 hours, 03:00 hours, 06:00
hours, 09:00 hours starting from the top and following the shafts operational rota-
tion sense; the top will be the position 1 and following the rotation sense, position
2,3,4 every 90°.
The alignment tool is fixed on drive shaft and the readings are taken on driven
shaft (in not differently specified on the alignment specification). Sign with a
marker the four reading positions on the reading disc; don’t scratch the surfaces
and don’t use paint that can create a relief, or the reading will be altered by its
thickness. Don’t use solvent-based paint if the reading surface is the hub surface.
Set the gauges on the starting position: radial gauge in position 1, axial gauge A in
position 1 and axial gauge B in position 3. Set a positive reference values to all
the gauges (same value for all of them): If the gauges are set to zero values or to
other values close to the gauge stroke end, in case of excessive negative values,
the gauge will be not in condition to get the reading.
Start to keep alignment readings moving the shaft in the correct rotation sense
every 90°; move both the shafts in position 2 and next to the other positions.
Attention: When the gauges can back in the starting position (pos. 1) they must
show the same values set prior start the readings! Only axial gauges can show an
apparently different values: An axial movement of the shaft due to the rotation ef-
fect can add or remove a value to the original set, but it is the same value for both
the gauges.
Example: axial gauges A and B are set at 2 mm in starting position (see Fig. 3).
After a complete turn, they can back showing a reading of 2,2 mm. This is not an
error because both of them reporting plus 0,2 so the shaft axial movement oc-
curred. The reading errors is a reading shoving different addition values: axial
gauge A 2,2 mm, axial gauge B 2,4 mm. To understand if errors are happening
during the reading on position 2, 3 and 4 , see the alignment methodology expla-
nation in next paragraph.
The reasons whose determinate wrong readings can be several, but the principal
causes are the following:
• The gauges are not properly fixed on alignment tool.
• The alignment tool is not properly fixed on shaft.
• The reading disc shaft has not be stopped in a different position
• Operator did wrong gauges reading.
• A load has been accidentally applied on alignment tool during the readings
recording.
Compare the recorded reading with alignment specification values and correct the
differences using the skid lateral jacking bolts and the jacking devices to add or
remove shims.
Be sure to use shim pack supplied only. Other shims type with different characteris-
tics and/or different materials can not be used if not authorized by Nuovo Pignone.
Be sure to tight the skid anchor bolts prior to execute a reading.
8.1 Enclosure
8.1.1 Installation
The main activities to be carried out are as follow:
• Sole plates level checking, before installing the structures.
• Support structures installation, levelling and alignment ready for grouting
• Foundation bolts tightening after grouting as per required torque.
• Erection of enclosure walls and roof panels.
• Erection of gangways, ladders, gratings, etc., inside and outside the
enclosure.
• Installation of doors, windows, gutter pipes, plugging, finishing touches and
accessories.
• Erection of cranes, rail ways and relevant accessories included the ladders,
gratings, protections, etc. for access way;
• Erection of ventilation system as below described.
• Enclosure inside and outside lighting system (AC and DC), construction and
installation.
• Drilling of walls and roof where necessary, in order to install pipes and
electrical cables and conduits or cable trays and relevant restoration.
• Construction and installation of fire fighting and gas and fire detection
systems.
8.2.1 Checks
8.2.1 Installation
Erection of ventilation system including the relevant structures, fans, ducts, filters,
dampers, gangways, ladders, gratings and all accessories, as follows:
• After Structural Platform has been erected, proceed with installation of all
ductwork;
• Install centrifugal ventilation fans [88BA-1 & 88BA-2]. Carry out the air
extraction fans skids positioning and levelling on dedicated supporting
structure as per drawings;
• Check the alignment of electric motors with relevant fans. If not differently
specified by the vendor, the alignment is referred to “0”. In this phase, verify
also the cleanliness of shims used;
• Tightening the motors & fan anchoring bolts as soon as the alignment has
been completed;
• Check the preservation condition and the correct opening/closing of the
gravity dampers at fans air outlet;
• Verify if transmission belt tension is correct;
• Verify all rotating parts;
• Verify if air extraction group bearings are correctly lubricated;
• Verify if air diffuser is correctly installed and centred;
• Align the fan suction with the relative duct on Air inlet system;
• Install the air ducting starting from the air inlet system side. Verify, during
the installation, the cleanliness of the connecting flange and the correct
application of the gaskets;
• Install the expansion joints avoiding tension and stress on elastic surface and
excessive compression;
• Check the right connection and operation of the inlet and outlet air dampers
operated by the fire fighting system extinguishing gas, on accessory
compartment and turbine compartment.
• Tighten all duct connecting bolts starting from the flange centre.
• Verify if deflectors of ventilation ducting inside the turbogenerator enclosure
are correctly oriented.
• Complete the painting on ventilation system components if/where required.
• Assemble the necessary pneumatic connections to actuate the ventilation
dampers. Install the actuators and the pneumatic tubing line as per
schematics.
• Installation and connection of the instruments for temperature and explosive
gas detection, position limit switches and differential pressure switch to start
the stand-by ventilation fan.
• Install the cable trays/conduits for the ventilation system instrumentation and
motors.
• Execute the limit switches wiring as per schematics and wiring diagrams.
• Execute the fan electric motor wiring as per schematics and wiring diagrams
• Install the grounding system where required.
• Remove anti-rotation sea fastening on all impellers.
controlling the valve arrives by means of a capillary tube coming from the oil
supply to the auxiliary gear box.
Correct installation and connection of instruments.
9.2.1 General
This paragraph defines the methods to be used to remove all foreign bodies and
ensuring through cleaning of all piping, filter bodies, coolers and other
components which will come in contact with lube oil.
Flushing shall be carried out when all the oil system components have been
completely installed.
After flushing must be certificate the right re-installation of piping and devices as
per relevant drawings.
For more information see the following Oil Flushing description.
SUPPLEMENTARY CRITERIA
1. For a more efficient flushing, oil shall be warmed. If the oil heaters of
machine are not enough for this purpose, will be prepared the adequate
means. During flushing oil temperature will be kept in a range within 60 ÷
80°C.
2. Use [PL-2] (auxiliary pump) to carry out the flushing activities.
MEASUREMENTS
1. Current absorbed by the pump motors should be checked frequently and shall
never exceed the rated values.
2. Oil temperature, during the flushing, shall be kept lower than 80 °C:
3. Flushing oil must not enter in contact with hot parts to not exceed the flame
point (approx. 150°C.).
) NOTE
) NOTE
Table 1
Solide contaminant code - Tabular presentation
) NOTE
THE ABOVE TABLE COVERS THE MOST USUAL SERIES OF CODES BETWEEN
RANGES 8 AND 20. OTHER CODES WHICH ARE NOT SHOWN CAN BE
CONSTRUCTED FROM ANNEX “A”.
Table 2
Comparison list - International standards
ISO 4406 of IMPURITY NAS 1638 SAE ACFTD MIL STD
3 (1964) contents 1246 A
CETOP RP 70 H cm - 10 µ (1963) 3
mg/dm (1967)
26/23 140000 1000
25/23 85000 1000
23/20 14000 100 700
21/18 4500 12
20/18 2400 500
20/17 2300 11
20/16 1400 10
19/16 1200 10
18/15 580 9 6
17/14 280 8 5 300
16/13 140 7 4 1
15/12 70 6 3
14/12 40 200
14/11 35 5 2
13/10 14 4 1 0,1
12/9 9 3 0
18/8 5 2
10/8 3 100
10/7 2,3 1
10/6 1,4 0,01
9/6 1,2 0
8/5 0,6 00
7/5 0,3 50
6/3 0,14 0,001
5/2 0,04 25
2/8 0,01 10
A. Activity
1. Check the correct installation of the oil tank level indicator;
2. Drain the tank protection oil;
3. Clean carefully the oil tank, inside;
4. Check the conditions of the oil tank internal parts;
5. Check the correct installation of the tank oil drain valves;
6. Remove the orifices (in case of regulating orifices, open completely) from the
oil supply pipes to the bearings;
7. Disconnect the oil supply piping to the bearings and install the temporary
piping returning to the oil tank, by-passing the bearings;
8. Fill the tank with flushing oil (see oil specification, normally OTE 32 type);
9. Install a local temporary switch to operate the auxiliary oil pump [88QA-PH-
2];
10. Verify the electrical supply on the MCC (check that the pump & heaters
breakers be extracted);
11. Verify the piping connections of the lines submitted to flushing operation;
12. Check that all interception valves on the local instrument panel be closed;
13. Insert the breakers of the pump & heaters on the MCC;
14. Start up the aux. oil pump [88QA] operating by the local temporary switch;
15. Stop the pump after 30 seconds and verify the oil leakage from the flanged
couplings;
16. Start up again the aux. oil pump;
17. Put in “ON” position the heaters switches;
18. During the oil flushing operations, keep the temperature within 60° and 80°C;
19. Check the piping oil leakage with the oil at rated temperature;
20. Hammering the discharge pipes with warmed oil, every 30 minutes;
21. The oil flushing activity will be carried out continuously for 48 hours or
alternatively for four days if it will be stopped during the night;
After the mentioned time of oil flushing, will be draw a sample of oil for analysis,
comparing the results to the acceptance criteria mentioned in the table 1.
9.4.2 Piping
− Connection of the turbine fuel gas line on base with Purchaser’s gas supply
line (TP100) from gas scrubber.
− Correct installation and connection of the vent lines with the terminal points
(TP101) and (TP102).
− Carry out the piping blowing (where required).
To perform the interconnecting piping blowing see the relevant procedure.
Blowing operation must involve all piping upstream of the turbine skid
connection limit. Piping installed inside the skid is generally clean and sealed; if
in doubt, contact NP supervisor. Be sure no foreign bodies are left inside the lines.
Restore the Fuel gas system after blowing. If necessary remove all parts, and
equipment used and clean the area. A blowing execution certificate must be
issued.
At the end of cleaning procedures restore the pipe lines ready for pressurisation
with gas and install the instruments and control and safety valves (already
calibrated in the instrument calibration room) on the pipes.
Carry out the bandaging of the gas pipe flanges ready for pressurisation test, to be
executed in the following phase of commissioning.
Each pipe and relevant connection, before connecting to the gas system on
turbine, will be carefully checked for cleanliness and sound conditions.
9.4.3 Checks
As soon mechanical installation is complete a system check it is useful to assure
installation of all the parts and their correct assembly.
− Check the Fuel Gas lines supporting system.
− Verify (with schematic diagram) the piping already installed on the package,
in order to determine missing or damaged items or other non-conformity.
− Execute a visual inspection of the Fuel gas valves installed, looking for
damage, loose connections, and openings and missing connections (tubing &
cables).
− Verify if all internal valves/device vent lines are all connected to the vent
header.
− Verify if the fuel lines already installed are connected in the proper ports on
the instrument console. Use schematic (P&ID) and piping route drawing for
verification.
− Execute a fuel line system check to the instrument console; verify if all
instruments and manifolds are correctly installed.
− Check the system for foreign blind flange/disc or inspection screens left
installed.
− Verify and/or complete the wiring and cabling of all instrumentation and
devices on the fuel gas system.
− Verify that the instruments and devices are provided with identification tags
according to instrument list.
− Verify the whole fuel system is installed according to schematic diagram and
drawing.
− Verify the correct installation of the measuring flow system and the valves
and instruments loosed shipped by Nuovo Pignone.
− Install or complete the earthing system.
9.5.1 General
The Air Inlet Duct is composed by (starting from the turbine inlet plenum):
expansion joint, an empty vertical duct, an elbow, a horizontal section duct
containing silencing panels, another horizontal section empty duct and finally an
expansion joint connecting the inlet duct to the filter house.
The cleanliness of Air duct components must be guaranteed.
Part of the Air duct assembly is a silencer. The silencing ducts must have their
silencing panels inserted prior to connect them with the other ducts.
Weld structure support plates only after confirmation of alignment; inlet duct with
the Turbogroup skid.
9.5.2 Checks
− Check the foundations for correct structure locations and potential
interference with other structures and/or equipment.
− Check the diagonal distance between all supporting plate position points.
Subplates are connected to the structure columns.
− Check the anchor bolt holes on the support structure plates to see if they are
compatible with the provided anchor bolts size.
) NOTE
9.5.3 Installation
All bolts used inside the Air system must be provided with anti-loosening guards
(system) or be welded.
The threaded bars used to support the expansion joint during transportation and
erection, must be taken out before putting unit into operation.
The ventilation system is connected to the inlet duct. Be sure to close and seal all
the openings until ventilation ducts are installed.
The inlet duct is provided with one or more inspection doors; Verify if inspection
doors are free from obstruction (structures, piping etc.) and if they are installed
with correct gasket and correct bolts.
Then:
− Ensure the air inlet steelwork is correctly erected.
− Lift each section of air inlet ductwork and install them as follows:
a. First expansion joint on the inlet plenum. The expansion joint will be
delivered ‘locked’.
b. Vertical transition duct section on the expansion joint.
c. The elbow connecting the vertical section to the horizontal sections of duct.
a. A section containing Silencers. If not already fitted, insert acoustic panels
into silencer sections in correct position referred to the air flow
d. The horizontal straight transition empty duct.
e. The expansion joint connecting the duct with the filter house.
− Check elevations and level using the adjustable bolts (if any).
− Unlock the expansion joint from they threaded bars after completing the
installation.
− Check the presence of all required gaskets and tighten all bolts on duct’s
connecting flanges.
− Proceed with grounding system installation.
9.6.1 Checks
Check the foundations for correct structure location and potential interference
with other structures and/or equipment.
Check the diagonal distance between all supporting plate position points. Sub
plates are connected to the structure columns.
Check anchor bolt holes on support structure plates to see if they are compatible
with the provided anchor bolts size. (Where applicable)
) NOTE
9.6.2 Installation
Tight the baseplate anchor bolts as soon as the alignment of exhaust duct with the
Turbogroup skid is confirmed.
Assemble the exhaust ducts according to assembly drawing and tighten
connecting bolts as per torque value required. Use anti-size compound on exhaust
duct bolts and begin tightening from the flange centre and proceeding
alternatively from the left side to the right side for a better flange distension.
Ensure the exhaust system supports are correctly erected, then lift each section of
exhaust duct / stack and install it as follows:
a. Assembly of the exhaust plenum lateral extension covers.
located at list 10 meters from the exhaust centreline and if these connections
are provided with sealing plugs/blind flanges.
− Verify if inside the exhaust duct, there are no flammable materials.
− Install the cable trays/conduits for the exhaust duct instrumentation.
− Execute the thermocouple wiring as per schematics and wiring diagrams.
− Connect the grounding system.
9.7.1 Checks
Upon receipt, the generator package installed on the skid with a reduction Gear
Box; loose parts have to be checked for damage or loss. A careful visual
inspection will reveal any damage, while missing of any parts can be found by
comparing the received goods with the relative packing list. When any damage is
found, reported immediately to NP representative.
9.7.2 Installation
Maintain cleanliness in all parts of the machine and working area during the
installation activities.
1. During the installation, all openings should be covered as much as possible,
in order to prevent water, dust, dirt or other foreign objects from entering the
machine.
2. It is advisable to connect and switch on the heaters inside the generator as
soon as possible after placing on the machine, to prevent the windings of the
generator becoming damp.
3. Install the air winding cooling system on the generator (water coolers) as per
relevant drawings.
4. Connect the oil piping to the turbine bearing headers (inlet & outlet). Remove
the transportation sealing flanges on the battery limit only during the starting
of interconnecting piping assembly. In case of removal for checks, be sure to
restore the sealing flanges after the inspection.
) NOTE
BE SURE NO FOREIGN BODIES ARE LEFT INSIDE THE LINES OR FOREIGN BLIND
FLANGE/DISC ACCIDENTALLY LEFT INSTALLED IN THE SYSTEM.
5. Verify if all the devices and instrumentals are installed according to the
relevant schematic and drawing.
6. Install the line & neutral cubicles with the relevant instrument / devices, sent
loose.
7. Install (or verify the installation of) the instruments and devices identification
labels.
8. Proceed with cables wiring according to schematic and wiring diagram.
9. Install or complete the ground system.
9.8.1 Checks
Upon arrives the load gear box, installed on common base with the Generator,
loose parts have to be checked for damage or loss. A careful visual inspection will
reveal any damage, while missing of any parts can be found by comparing the
received goods with the relative packing list. When any damage is found, reported
immediately to NP representative. Then proceed as follows:
9.8.2 Installation
Keep the cleanliness on all parts of the gear box and working area during the
installation activities.
a. Verify the alignment with the Gas Turbine and with the Generator.
b. Carry out the bolts tightening as per required torque after alignment
completion.
c. Connection of lube oil piping inlet and outlet to the lube oil headers of the
turbine.
d. Open the visit door and check the contact between the teeth.
e. Install and connect the vent.
f. Verify the correct installation of the instruments and install the instruments
loose shipped, if any.
9.9.1 Checks
Check the foundations for correct structure locations and potential interference
with other structures and/or equipment.
Check the position of structure journal sub-plates.
It is suggested to check the diagonal distance between plates, in order to discover
eventually rhomboidal errors in previous anchor bolts/subplates positioning
Weld structure foundation pockets after confirmation of the alignment of inlet
duct with the Turbine skid.
9.9.2 Installation
• As soon as the foundations have been verified, the structure installation can
start. Verify the correct structure elevation and the centring with the Air inlet
duct. In the same time can start the assembly of parts of filter house that can
be installed on the ground, as internal walkway, hand rails and ladders.
• Pay attention if during the modules assembly the connection flanges and the
internal surfaces are clean: Also if a final cleaning will be perform prior crank
operations, some internal areas can results impossible to be inspected and
cleaned after the assembly completion. This will elevate the risks of
damaging for the machine.
• Prior the assembly, verified inside the Filter house the components assembled
with bolts. All bolts used inside the Filter House must be provide of anti-
loosening guards (system) or welded.
• After the structure completion, proceed with the filter house connection with
the Air inlet duct, taking care of gasket between flanged connections and their
cleanliness.
• Tight flanged connection bolts as per required torque values and begin the
bolts tightening starting from the flange centre proceeding alternatively from
the left side to the right side for a better flange distension.
• For the expansion joint installed between Filter House and Inlet Duct take in
consideration that the threaded bars used to support it must be taken out
before placing unit into operation. They must be re-installed again for
eventual further disassembly and assembly activities. In a correct installation,
in the expansion joint there will be not any tension and there will be not any
presence of torsion on its surface.
• As soon as the journal structure is installed and the filter house positioned on,
it can be installed the provided walkway and ladders; these items can be
previously installed if they don’t obstruct the Filter House positioning.
• Filter House is provided of inspection doors; Verified if inspection doors are
free from obstruction (structures, piping etc.), and if the opening /closing it’s
free from interference. Verify if gaskets are correctly applied.
• Proceed with the installation of rain hoods, inlet protection net, drain piping
and air cooler device as for example piping or ducts.
• Installation of the instruments installed on filter house near the maintenance
door.
Prior start up, the Filter House and all the Air inlet system must be inspect, and
eventually cleaned; an acceptance certification must be issued
For more information’s regarding the installation procedure see the relevant
Manual from filter house Supplier.
9.12.1 Checks
As soon as the skid has been delivered, check to verify any non-conformity or
damage.
Verify if the hydraulic piping already installed on turbine skid is in accordance
with the drawing and schematics.
Special attention must be given to the connecting union for the flexible piping.
These items must be delivered protected and sealed. Any scratch on the union
contact surface can result in non-repairable leakage.
The interconnection piping/hoses are as follows:
- Installation of the interconnecting piping among the skid and the washing
solenoid valves on turbine baseplate terminal point ((TP438; TP438A;
TP438B) connections.
- Connection with water supply (TP435).
- Connection with chemical additive supply (TP436).
- Connection of the drain valves to the drains system (MP443).
- Connection of the drain valves from inlet plenum (TP448); from the turbine
case (TP449); from the exhaust plenum (TP450).
Make the electrical/instruments connection of the Local control Panel and
motor/pump on the skid, checking the correct voltage before feeding the
instruments and electrical equipments.
It is suggested a spray manifold check from solenoid valves to avoid risk of
nozzle non-conformity or dirty presence inside the lines with possible
consequence of potential machine damage.
9.12.2 Piping
Water wash piping construction: If some interconnecting piping has to be
assembled on site, take the following steps during the assembly:
• Start fabrication & welding according to welding procedures piping sketches
and line specification requirements.
• Proceed with X-rays & Hydraulic test execution, as per line specification.
• Build (or adjust) piping support.
• Proceed with pipe painting, cleaning and/or piping identification colour/tag
application
9.13.1 General
Fire fighting skid (CO2 bottles) arrives on site already assembled except for the
bottles that will be supplied later and assembled on site; it is necessary to install
the skid positioning and levelling it as required by drawing.
As soon as the skid has been delivered, check to verify any non-conformity or
damage.
When handling the skid, be careful not to cause collisions and ensure that the
console doors are well locked because they may open during the handling
operations.
Interconnecting piping and material for CO2 fire fighting system is supplied in
commercial lengths and loose fittings and will be fabricated on site.
9.13.2 Installation
Expansion bolts must be used for Skid anchoring on foundations (see the relevant
drawing).
Install and connect (as required by the Schematic Piping) the CO2 bottles (bank
“A” and bank “B”) inside the skid.
Restoration of the internal parts of bottles rack to make the system able to operate.
The voltage must be checked before feeding the instruments.
Make the electrical connection to the solenoid valves and the fire fighting system
state signals as: lights, horns and limit switches.
9.13.3 Piping
Piping installation, after initial checks and positioning, will consider on site
construction and assembly of:
- Construction and connection of piping from limit of the CO2 line of the
bottles skid headers to the Gas Turbine fire fighting system quick and slow
discharge lines, and with the ventilation dampers supply tubing.
- Build and install piping support.
- Proceed with pipe painting, cleaning and/or piping identification colour/tag
application
9.14.1 Installation
The Cabin will be positioned, levelled and bolted where required by drawing on
relevant concrete base and then electrically connected with the Turbogenerator
and its auxiliaries.
Install and connect, as required by the relevant drawings, the inside devices and
equipment separately shipped. (batteries on relevant room with ventilation system,
main & emergency lighting systems, etc.)
Install the ladders and walkways externally to the cabin.
Install and connect the HVAC systems.
Restoration of the internal parts to make the system able to operate.
The voltage must be checked before feeding the electrical equipments.
10.2 Couplings
For positioning, the panels shall be lifted through hoist or crane by eyebolts that
shall be tightened in the upper part of the frame. In case this operation is not
possible, the panels have to be shifted by rollers, taking all the precautions to
prevent deformation of the metallic structure and consequent damage of internal
components.
Precautions need to be taken in order to prevent damage to the floor in the control
rooms where the panels has already been installed.
− Make sure that each power connection corresponds to the right power supply;
− Make sure that input leads comply with contractual standards;
− Make sure that terminals are tightly clamped to their terminal boxes;
− Make sure that lead protection sheaths are not damaged; if necessary replace
the leads;
− Check the insulation of power leads;
− Check the interconnection cables with other systems (correct tampering and
numeration).
− Check the licences of the software installed in the interface.
For electrical and pneumatic connection see Electrical and Pneumatic hook up.
11.5 Miscellaneous
INDEX
Contents Page
1. COMMISSIONING OF TURBOGENERATOR
The gas turbine MS5001 is provided with automatic sequence for “start-up” and
“shutdown” by means of SPEEDTRONICTM Mark VI.
The instructions given hereby are indicative and are referred to the instructions
manual of the gas turbine with the essential reference to the driven machines.
The indicative sequence of the main operation have the same order shown in the
index.
The main reference documents for start-up, operating and shut-down of gas tur-
bine are the following:
• Schematic Piping & Instrument Diagram
) NOTE
) NOTE
Following are illustrated the operation to be carried out on gas turbine & Generator
skids and on related systems for their commissioning, after completing the installa-
tion on site.
When the mentioned operation are completed, it is possible to proceed with the
starting up of the lube oil system, as follows:
a. Turn the emergency lube oil pump driver [88QE] control switch in “manual”
position and start the emergency lube oil pump [PL-3] checking for direction
of rotation and unusual noise on the motor/pump. Stop the emergency pump.
b. Turn the auxiliary lube oil pump driver [88QA] control switch in “manual”
position and start the auxiliary lube oil pump [PL-2] checking for direction of
rotation and unusual noise on the motor/pump.
c. Turn the auxiliary lube oil pump driver [88QA] control switch in “manual”
position and turn the emergency lube oil pump driver [88QE] control switch
in “auto” position.
d. Put in auto position the electric oil heaters switches [49QT-1÷4], regulating
the oil temperature inside the oil tank by means of the temperature transmitter
[LTOT-1].
e. Check that the main lube oil filter [FL-1A] is full with oil looking at the
overflow of oil through the sight glass devices.
f. Open the filling valve of the stand-by lube oil filter [FL-1B] and check when
the filter is full with oil, looking at the overflow of oil through the sigh glass.
g. Leave open the stand-by lube oil filter filling valve.
h. Move the lube oil filters transfer valve and leave it in the position of main
filters [FL-1A] in service.
i. Open the drain valve of the oil lines of the lube oil filter differential pressure
gauge and lube oil filter pressure transmitter, then open first the isolating
valve on the upstream line, and subsequently the isolating valve on the
downstream line.
j. Close finally the drain valve.
k. Check the oil flow from accessory gear, journal and thrust bearings of gas
turbine, by means of the flow sight glass.
l. Check the lube oil pressure in the lube oil header and make sure that it is
according to [VPR-2] pressure control valve setting (172 kPa G).
m. Check the lube oil pressure in the lube oil header and make sure that it is
according to [VR-1] pressure control valve setting (650 kPa G).
n. Then, stop manually the auxiliary lube oil pump and the emergency lube oil
pump and check the pressure point at which the gas turbine trips because of
lube oil pressure transmitters [96QT-2A÷C] installed on the Generator lube
oil bearing header
o. Turn the driver's control switches of the auxiliary lube oil pump and the
emergency lube oil pump in automatic position. The emergency lube oil
pump will stop because of the action of the lube oil pressure transmitter
[96QT-2A÷C].
p. Verify on the display of the Speedtronic Mark VI that the alarms of the lube
oil system are off, except: auxiliary lube oil pump running.
q. Stop manually the auxiliary lube oil pump leaving the emergency lube oil
pump in automatic position. The emergency lube oil pump will start because
of the action of the lube oil pressure transmitter [96QT-2A÷C].
The emergency pump starting comes after the turbine stopping.
r. During the normal operation the lube oil flow will be supplied by means of
the lube oil main pump, driven by the accessory gear and the auxiliary lube
oil pump will manually stopped, it will be automatically restart when the oil
pressure decrease under the values provided for restart the auxiliary pump by
acting of pressure transmitter [96QT-2A÷C].
! WARNING
a. Check the “Y” strainer on the gas supply line to the turbine, correct
installation and cleanness condition;
b. Check that isolating valves of pressure transmitter and gauge [96FG-1] and
[PI-8] respectively, are open.
c. Check that the pressure transmitters [96FG-2A/2B/2C] and pressure
indicators [PI-9], isolating valves are open.
d. Check that the vent valves of pressure gauges and pressure transmitters, are
closed.
e. With the fuel gas feeding line empty (fuel gas supply line closed) check
operating of fuel gas trip valve [SRV-1], with lube oil system and hydraulic
oil supply system started, by opening of solenoid valve [20FG-1] and
operating the control valve [90SR].
f. With the fuel gas feeding line closed, check operating of fuel gas control
valve [GCV-1] with the hydraulic oil supply system started, by operating the
control valve [65GC].
g. Calibrate the signal coming from LVDT’s transmitters [96SR-1/2] and
[96GC-1/2] on Control Panel during the valve stroke.
h. Check the correct operation of the intervalves vent valve [20VG-1].
i. Check the correct operation of the solenoid valve in fuel gas warm up line
valve actuator [20VG-2]
! WARNING
Electrical:
f. Power cables and bus bars testing (insulation and conductivity).
g. Unit ground connection verification.
h. Excitation system calibration and setting.
i. Protections relays calibration and setting on the relevant protection Panel.
j. Generator neutral point and line star point connection with the power
distribution system completion verification.
On turbine:
a. Checking the calibration of the turbine wheel space temperature 1st stage
forward by reading in the MARK VI display the temperature indicated from
[TT-WS1FI-1, TT-WS1FI-2] double thermocouples.
b. Checking the calibration of the turbine wheel space temperature 1st stage
afterward (by reading in the MARK VI display the temperature indicated
from [TT-WS1AI-1, TT-WS1AI-2] double thermocouples.
c. Checking the calibration of the turbine wheel space temperature 2nd stage
forward (by reading in the MARK VI display the temperature indicated from
[TT-WS2FI-1, TT-WS2FI-2] double thermocouples).
Checking the calibration of the turbine wheel space temperature 2nd stage
afterward (by reading in the MARK VI display the temperature indicated
from [TT-WS2AI-1, TT-WS2AI-2] double thermocouples.
The setting values of all wheel space thermocouples are: Alarm: 427°C;
Trip:457°C.
d. Exhaust thermocouples [TT-XD-1 ÷ TT-XD-13] calibration and testing as per
instrument list. Set: Alarm: 574°C; Trip: 582°C..
Check the readings before, at steady state of the turbogenerator.
e. Calibration and testing of the differential pressure transmitters [96EA-1A ÷
1C] between the exhaust duct and atmosphere. Set: Alarm: 5,0 KPa d ;
Trip: 6,0 kPa d.
Flame control
a. Flame detectors [28FD-2, 28FD-3, 28FD-7, 28FD-8] testing, exciting them
with a small flame.
b. Transformers [95TR-1, 95TR-10] powering and spark plugs [95SP-1, 95SP-
10] testing, after dismounting them from the combustion chambers.
Reinstalling the sparkplugs on the combustion chambers after completing the
test.
! WARNING
1.10 Miscellaneous
Axial compressor air flow control
Check the operating condition of the antisurge valves [VA2-1, VA2-2] with the
relevant intervention of the limit switches [33CB-1, 33CB-2] inhibiting the
Turbogenerator starting-up when the valves are fully open. Check the correct
operation to the servovalve [20CB-1]
Verify the operation of the IGV control system operating by the servovalve
[90TV-1] and the flow control valve [VC-1]; then living it in correct position to
enable the Turbogenerator start-up.
Check also the correct calibration of the LVDT [96TV-1, 96-TV-2] for IGV
position control.
Grounding system
Grounding system of each component of Turbogenerator correct connection and
conductivity checking (Turbine, Gear Box, Generator, Enclosure, etc.).
2.1 Foreword
! WARNING
These instructions describe a detailed procedure for the operation of the machine.
Since the instructions do not provide for every possible contingency to be met in
connection with operation, slight different procedures can be used.
Regardless of the procedure used, only qualified and experienced personnel shall
be entrusted with this task.
! WARNING
2.2 General
Here below are described the commissioning activities to be carried out on the
auxiliary equipment of Turbogenerator train positioned outside the main
baseplates. The commissioning activities referred to the Turbogenerator auxiliary
installed on the Turbogenerator base are mentioned on Turbogenerator
commissioning section.
The main reference documents for start-up and operating of gas turbine are the
following:
• Schematic Piping Diagram
• Field Instrument List SOM 6617991/3
• Control System Functional Description SOM 6672827/4
! WARNING
b. Check calibration and setting of the safety valves installed on the water outlet
lines from the coolers set at 883 kPa G.
d. Check electric motor [88QV-1; 88QV-2] with relevant space heaters [23 QV-
1 & 23QV-2] absorption values and fan correct operation
e. Check oil tank differential pressure values during machine running with
differential pressure indicators [PDG-7184 & PDG-7185].
b. Calibration and setting of the level control valves of the pressurized drains
[LCV-7107 and LCV-7108];
c. Check calibration and setting of the safety valves installed on the vessels
[VR104-A and VR104-B].
b CO2 bottles restored on the relative racks with relevant piping connected and
tighten.
j Fire fighting system and relative piping checked. No loose components, un-
ions or flanged connections have been detected after commissioning comple-
tion.
d Check the correct readings of the differential pressure gauges [PDI-20 &
PDI-21].
g Duct final internal cleanness condition checking before starting the turbine.
INDEX
Contents Page
1. GENERAL................................................................................................................ 4-1
1.1 General indication............................................................................................. 4-1
1.2 Foreword........................................................................................................... 4-2
1. GENERAL
When the services before mentioned are available and the commissioning
activities referred to all systems involved in Turbogenerator operation are
completed, the Operators may proceed with the initial start activities.
1.2 Foreword
! WARNING
These instructions describe a detailed procedure for the operation of the machine.
Since the instructions do not provide for every possible contingency to be met in
connection with operation, slight different procedures can be used.
Regardless of the procedure used, only qualified and experienced personnel shall
be entrusted with this task.
! WARNING
2.1 General
The gas turbine MS5001PA is provided with automatic sequence for “start-up” and
“shutdown” by means of SPEEDTRONICTM Mark VI.
The instructions given hereby are indicative and are referred to the instructions ma-
nual of the gas turbine with the essential reference to the driven machines.
The indicative sequence of the main operation have the same order shown in the
index.
The main reference documents for start-up, operating and shut-down of gas turbine
are the following:
Schematic Piping Diagram
Field Instrument List SOM 6617991/3
Control System Functional Description SOM 6672827/4
! WARNING
) NOTE
2.3 Introduction
The scope of the preparatory works to get the Turbogenerator plant started is:
1) Commissioning and put in service Turbogenerator Fire & Gas detection and
protection System.
2) Commissioning and put in service Fire & Gas Detection System for Control
Cabin (at least) , if any.
3) Commissioning and energize the MCC and all utilities needed for a normal
operation of Turbogenerator plant, such as:
• AC & DC distribution system (MCC, UPS, etc.)
4) Commissioning and starting all the utilities for a gas turbine normal operation
(oil systems, fuel gas, ventilation systems, oil cooling system, GTG fire fight-
ing system, etc.)
Valves position (opened/closed) for initial start-up and normal operation of lube
oil system is indicated in Schematic Piping Diagram.
The unit is equipped with one mechanical shaft-driven pump [PL-1], an AC auxil-
iary pump [PL- 2] and a DC emergency pump [PL- 3]. Their purpose is, to lubri-
cate and cooling the GT, as well as the gear box and generator, bearings during
the unit operation.
The lube oil pumps are designed for continuous operation but are not operated af-
ter the gas turbine package is shut down and the cooldown timer has elapsed.
To operate the mineral lube oil pumps, the oil tank level and temperature shall be
between the operation limits; if the level (300÷400 mm. from tank top cover) or
temperature (20°C÷79°C) is not OK before starting, starting will be inhibited and
an alarm will occur. If one of the parameters will be not OK during operation of
the unit an alarm and subsequently a shut down will occur.
Valves position (opened/closed) for initial start-up and normal operation of lube
oil system is indicated in Schematic Piping Diagram.
Prior to start the gas turbine, the operator selects: ”Auto” control in MCC for
[23QT-1÷4] lube oil heaters and [88QA] auxiliary lube oil pump, and in DCP for
[88QE] emergency lube oil pump.
When unit start is selected the lube oil system starts automatically.
When the right pressure is restored permission to continue with starting sequence
is given.
When the gas turbine reaches the ”OPERATING SPEED”, at 95% of the rated
speed, the AC auxiliary lube oil pump will be manually stopped and the accessory
gear driven main lube oil pump guarantees the oil flow amount.
As long as the gas turbine is above the ”OPERATING SPEED”, if the conditions
”LUBE OIL HEADER PRESSURE LOW” (MK VI command name 4QA) will
be detected, the AC auxiliary oil pump will be automatically started. If normal
conditions are restored, the stand by pump can be stopped manually from the HMI
or from the MCC according to the duty/standby philosophy.
The lube oil header pressure low-level threshold [63QT-2A ÷ 63QT-2C], installed
on the Generator lube oil header, causes the DC emergency lube oil pump to start
if lube oil header pressure is lower than the shutdown level.
With such threshold, when the emergency pump comes in operation, the unit is in
shutdown condition.
Once the pump is started, it runs continuously for 15 minutes and then 30 seconds
on, 3 minutes off cycle is started for power supply batteries safeguarding until the
end of cooldown. The DC emergency lube oil pump will be stopped as soon as the
condition ”LUBE OIL HEADER PRESSURE NORMAL” is detected [96QT-2A
÷2C].
Valves position (opened/closed) for initial start-up and normal operation of the
hydraulic system is indicated in Schematic Piping Diagram.
The Gas Turbine is equipped with one mechanical shaft-driven pump installed on
the Accessory gear box. Its purpose is to operate the axial compressor IGV noz-
zles and the GT gas valves .[SRV-1 and VCG-1].
The H.P oil pump is designed for continuous operation but is not operated after
the gas turbine package is shut down.
To operate the Hydraulic oil pump, the oil pressure shall be inside the operation
limit; if the pressure value is not OK (6500 kPaG min.) an alarm will occur. The
maximal pressure admitted for the hydraulic mechanical driven pump delivery is
9000 kPaG regulated by a overpressure valve [VR-21]; and is also protected from
overpressure by a pressure regulating valve [VPR3-1] inside the pump body that
will be regulated at 8000 kPaG.
If the pressure decrease under the minimal pressure (6500 kPaG) during the Unit
operation an alarm is generated by a pressure switch [96HQ-1]
When the hydraulic oil pump driven by accessory gear box reaches the 1500
RPM it guarantees the oil pressure and flow amount during gas turbine operation.
Valves position (opened/closed) for initial start-up and normal operation of oil
vapor separator is indicated in Schematic Piping Diagram.
Prior to starting the GT operator selects ”Auto” control in MCC for [88QV-1]
lube oil vapor separator.
One of the two lube oil vapor separator fans [88QV-1 and 88QV-2] (the selected
one as main) will be started at turbine start-up and will continue to operate up to
the end of cooldown sequence. The stand-by one will be started, by intervention
of differential pressure transmitters [96QV-1A ÷1C], in case of oil tank pressure
increasing over the rated limit. Set: Alarm 20 mm.H2O; Trip 50 mm.H2O.
The fan will be started also in case of pressure detected in the lube oil tank after
cooldown end.
Prior to first gas-in, fuel gas system will be leak tested at normal operating pres-
sure afterwards followed by fuel gas system inerting using nitrogen (filling and
purging until oxygen content at point of supply to stop / ratio valve drops below
2%).
A ”Fuel gas pressure low” alarm is given in the Mark VI software by the [96FG-
1] pressure transmitter, when gas pressure drops to 1400 kPaG.
Required fuel gas temperature for normal running at point of supply to Turbogen-
erator will be 28°C above dew point and in any case between 45°C and 60°C.
Valves position (opened/closed) for initial start-up and normal operation of pack-
age fuel gas system is indicated in Schematic Piping Diagram.
The antisurge valves will be checked and will be open to be enable to start the
Unit, the control of opening of the valves will be verified by the signal transmitted
by the positioning micro-switches [33CB-1 and 33CB-2] sending a signal to the
Control Panel.
Check the correct operation of the antisurge valves, before starting the turbine, us-
ing an external source of air, to be able to open them by acting the relevant ser-
vovalve [20CB-1].
Before proceeding to first start up of ventilation system operator ensures that all
fire dampers for ventilation air inlet and outlet are opened. Operation with fire
dampers closed is not allowed.
The GT compartment ventilation fans are designed for continuous operation but
are not operated after the gas turbine package is shut down and cooldown timer
has elapsed.
Prior to start the gas turbine, the operator selects: ”Main/Duty” for [88BA-1] tur-
bine enclosure ventilation fan and ”Standby” for [88BA-2] turbine enclosure ven-
tilation fan, in Mark VI software, and ”Auto” control in MCC for [88BA-1 and
88BA-2] and for [23BA-1; 23BA-2] of motors space heaters.
Fans inhibition for fire dampers closed is not latched and once the dampers are
open again the fans are no more prevented to run.
During normal GT operation, the operator is never allowed to manually stop the
duty fan.
The operator is normally allowed to manually start and stop the standby fan,
unless it is prevented to run or required on by the control logic.
The operator is allowed to initiate any time a duty/standby changeover: the selec-
tion is performed by means of the MK VI <HMI> operator interface software
pushbutton.
Valves position (opened/closed) and instruments condition for initial start-up and
normal operation of ventilation system is indicated in Schematic Piping Diagram .
Valves position (opened/closed) and instruments condition for initial start-up and
normal operation of starting system is indicated in Schematic Piping Diagram.
Prior to starting the gas turbine, the operator will close the switch of [88CR-1]
starting motor in MCC.
After this condition the DCS send a consent to Starting Motor Sequence
(3CZ).putting it in starting condition.
Before starting will be selected the mode of Turbogenerator operation putting the
Main Selector in required condition (CRANK, FIRE, MANUAL, AUTO, RE-
MOTE).
Will be checked the correct operation of the [33CS-1] (starting clutch limit
switch).
Valves position (opened/closed) and instruments condition for initial start-up and
normal operation of fire fighting system is indicated in Schematic Piping Dia-
gram.
The two banks of CO2 bottles (main and spare) are operated by the Turbine Con-
trol System.
The condition “ready to start” will be given by the limit switches [33CP-1/2A,
33CP-1/2B] positioned on the quick and slow discharge valves installed on the
CO2 line to the turbine enclosure.
There are in the system two discharge solenoid valves operating the different
groups of CO2 bottles (for quick discharge and for slow discharge). When the fire
is detected the valves [45CR-1/2] in bank “A” (main bank) or [45CR-3/4] in bank
“B” (spare bank), are energized opening the quick discharge group and conse-
quently also the slow discharge flow.
When is detected the fire signal are activated two alarms signal on the acoustic
enclosure, through the horns [XA-1÷2] as acoustic signal and through the flashing
lights [XL-1÷2] as a visual signal.
The UCP fire fighting system is provided with two “Fire fighting auto-inhibit
switch” [33CP-1A and 33CP-1B] to inhibit the discharge phase of CO2 and two
[33CP-2A and 33CP-2B] for permission to start-up. Every inhibit signals from the
fire fighting system send an alarm to the UCP inhibiting the turbine start-up.
The start-up of the turbine will be also inhibited when the signal “System fault”
(66XX-A/B) send an alarm to the UCP.
2.12 Generator
Valves position (opened/closed) for initial start-up and normal operation of lube
oil system of Generator is indicated in Schematic Piping Diagram.
Prior to starting the gas turbine, the operator shall check the correct oil supply
pressure to the generator bearings by the pressure indicators on the oil header, on
the bearings inlet piping DE and NDE side respectively. Will be checked also the
oil flowing through the discharge oil piping flow gauges (FG-7103, FG-7104).
The operator will check on the vibration monitor, Generator section, the correct
readings of vibration sensors, the key-phasor values and the bearings temperature
elements, to verify the correct operation.
Will be checked also the stator winding cooling thermoelements readings for cor-
rect operation.
Valves position (opened/closed) for initial start-up and normal operation of lube
oil system of Gear Box is indicated in Schematic Piping Diagram.
Prior to starting the Turbogenerator group, the operator shall check the correct oil
supply pressure to the Gear Box bearings by the pressure indicator on the oil hea-
der and the oil flowing through the bearings discharge oil piping flow gauge (FG-
7188).
Furthermore will be checked on the vibration monitor, gear box section, the cor-
rect axial positioning of the shaft and the readings of vibration sensors and the
bearings temperature elements, to verify the correct operation.
3. PROCEDURE OF START-UP
1) With turbine oil pumps running check the oil flushing through the generator
bearings and the load gear box.
The following checks must be done on a Turbogenerator, these checks should in-
clude: leakage test, vibration unusual noise, overheating, and lubrication.
3.2.2 Crank
1. Listen for rubbing noises in the turbine compartment, load gear and genera-
tor.
2. A sound scope or some other listening type device is suggested. Shutdown
and investigate if unusual noise occurs.
3. Check for unusual vibration
4. Inspect for oil leakage.
3.2.3 Fire
1. Check entire fuel system and the area immediately around the fuel nozzle for
leaks. In particular check for leaks at the following points:
a. Fuel oil piping/tubing to fuel nozzle
b. Fuel gas valves
c. Gas piping to the burner.
2. Monitor the turbine control panel readings for unusual exhaust thermocouple
temperature, wheel-space temperature, lube oil drain temperature, highest to
lowest exhaust temperature spreads and ”hot spots”, combustion chamber
burning hotter than all others.
3. Listen for unusual noises and rubbing.
4. Monitor for excessive vibration.
3.3.1 Introduction
This manual provides information needed by an operator to start and operate the
power generation units. This document describes the mode of operation, which
are defined to be:
• OFF
• CRANK
• FIRE
• MANUAL
• AUTO
• REMOTE
3.3.2 References
Reference shall be made to the:
Schematic Piping Diagram
Instrument List SOM 6617991/3
Control System Functional Description SOM 6672827/4
3.3.3 General
The GT Unit Control Panel is equipped with two HMI: one (local) in the Unit
Control Building, for controlling purposes, and the other (remote) in the Main
Control Room for monitoring purposes, as normal options.
Once the main HMI fails, the controlling functionality of the second HMI is en-
abled and the operator can continue to control the unit.
modes OFF, CRANK, FIRE, MANUAL, AUTO and REMOTE are below de-
scribed.
Mode selection can be used to bring in some hold points in the start sequence and
to monitor the process at these stages.
a) Off Mode
When the OFF Mode is selected, the UCP does not accept the START command,
and is thus not possible to start-up the machine. All other functions remain active.
Auxiliaries’ manual control is possible, if the relevant safeties are satisfied.
It shall not be possible to select and initiate the OFF Mode when the Turbogenera-
tor train is running or the COOLDOWN sequence is still in progress.
OFF Mode may be selected and initiated at any other time.
b) Crank Mode
CRANK sequence may only be selected after the gas turbine has stopped rotating.
Starting the turbine with this selection is possible if the unit start permissive is sat-
isfied.
Starting the turbine with this selection will bring the shaft up to crank/purge speed
value of 20% (14HM).
Sequence will precede changing Master Selector position to FIRE, MANUAL,
AUTO, or REMOTE position. The shaft will continue to rotate at 20% of speed
value until the operator initiates a normal STOP, changes the Master Selector po-
sition or a shutdown occurs. Gas turbine shaft can remain at his speed indefinitely
if the operator will not select another command.
For OFF-LINE WATER WASH the selection of CRANK mode is mandatory, and
as long as the wash cycle is enabled the CRANK mode will be locked.
c) Fire Mode
This mode of operation shall primarily be used to verify that the GT start se-
quence functions properly.
Once the start permissive listed in § 3.5 item “a” are valid/healthy, the operator
may initiate start.
Sequence steps § 3.5 “b” to§ 3.5 ”p” are executed, and the turbine will continue
to run at warm-up speed, unless the operator selects another operation mode or
initiates a normal stop or shutdown.
By subsequently selecting MANUAL, AUTO or REMOTE Mode, sequence step
§ 3.5. “q” to 3.5 “t” is executed to accelerate the shaft of the turbine to the prese-
lected speed.
d) Manual Mode
In the MANUAL Mode a start signal will result in an automatic start-up and load-
ing to the minimum operating speed, then the shaft speed is controlled by raise
and lower commands on HMI.
e) Auto Mode
In the AUTO Mode a start signal will result in an automatic start-up and loading
to the selected value, an external signal from DCS is taken as shaft speed set
point.
f) Remote Mode
In REMOTE Mode position, the set point of load may be varied from outside
through the commands from DCS. The increase and decrease variation speed of
the turbine shaft depends on the value imposed by the automatic ramp and can be
modified through the Operator Interface.
n) Allow a maximum of 1 minute for light off; activate ”fail to ignite alarm” if
flame is not detected within 2 minutes and continue to rotate at crank speed.
o) The fuel amount is reduced and the warm-up timer is started.
p) At the end of warm-up period (1 minute), the torque converter raises output
torque unless ”Fire mode” is selected; in this case the turbine shaft will con-
tinue to rotate at warm-up, more than 20% speed.
q) The torque converter is accelerated and fuel is increased to reach the mini-
mum operating speed; during the acceleration sequence, when the turbine
shaft reaches the 60% speed (14HC), the clutch will automatically discon-
nected. The starting system decelerating up to minimum speed, the starting
system is stopped five minutes later (cooling time).
r) At 90% speed of the shaft (14HSX), minimum operative speed, the lube oil
auxiliary pump [88QA-1] – (4QA) will receive a command to stop. The gen-
erator excitation is enabled.
s) When the turbine shaft reaches 95% of speed (14HS-1) will be closed the ax-
ial compressor bleed valve and the complete sequence flag will be set.
t) After completing the Start up sequence, are enabled the speed set-point varia-
tion and the turbine is ready to synchronize.
a) Off mode
Disable all the Mark VI synchronizing functions.
b) Manual mode
The synchronization will be made in manual mode. The panel will send the
raise/lower commands signals to excitation panel for the voltage regulation. When
the unit is synchronized, the operator will close the breaker from the HMI.
c) Auto mode
The Mark VI will adjust the speed the speed and voltage, and will issue the com-
mand for breaker closure when unit is synchronized.
Droop mode
When the Turbogenerator unit is connected in parallel to the main grid, the system
frequency is determinated by the grid itself and is maintained constant. The excess
of fuel flow does not result in speed variation, but in augmentation of power ex-
ported to the grid.
The operator can enter a certain MW value as a load control constant. When pre-
selected load is selected the unit will automatically load or unload till the required
value.
The selected mode of control (spinning reserve, preselected) will be reset to man-
ual control when the operator uses the raise/lower commands on HMI or when the
governor control is transferred from droop to isochronous.
The VAR control is based upon the use of voltage raise and lower signals to ECP.
Isochronous
The unit is controlled to maintain a constant speed, regardless of the grid load re-
quest and regardless of the supplier power. When the unit is in this mode, it is not
possible to set a supplied power set point.
4. TYPICAL READINGS
4.2.2 Generator
• Generator bearing metal temperature: max value H: # °C
Journal bearing DE side # °C
Journal bearing NDE side # °C
• Generator bearing oil inlet flow: 38 l/m
operating pressure/temperature: 172 kPaG / 55°C
• Generator vibration probe (no contact):
Journal bearing DE & NDE sides: max value: H: # m
HH: # m
• Winding generator phase U-V-W temperature: H: # °C
HH: # °C
Generator cold air inlet temperature: H: # C
HH: # °C
Generator warm air outlet temperature: H: # C
HH: # °C
(*) All the values flagged ”#” will be supplied after the first Gas Turbine tests.
INDEX
Contents Page
ITN 02175.00
ITN 02175.04
ITN 02175.07
PROTECTION & PRESERVATION SPECIFICATION 4
ITN 02175.08
ITN 02175.12
ITN 02175.21
5. GE REFERENCE DOCUMENTS