Unit5 Chapter 9 Monitoring and Control
Unit5 Chapter 9 Monitoring and Control
1
Why?? … Monitoring and
control
Once work schedules have been published and the project is
is progressing. These raw details could be quite numerous and complex on a large
project
Data processing – we process the progress data and convert it into ‘information’
which makes it easier for the project managers and others to understand the
with that planned, the plans are modified. This may require the modelling of the
6
Overall responsibility
Responsibilities
for ensuring
satisfactory progress
Day-to-day progress
responsibility
7
Categories of Reporting
9
Taking snapshots
– Degree of risk
10
9.3 Collecting the data
Need to collect data about:
• Achievements
• Costs
11
Partial completion reporting
– Schedule of activity
12
13
Red/amber/green (RAG) reporting
• Avoid asking for estimated completion dates instead ask of
the likelihood of meting the planned target date.
• of partial completion: traffic-light method
• Identify key tasks
• Break down into sub-tasks
• Assess subtasks as:
Green – ‘on target’
Amber – ‘not on target but recoverable’
Red – ‘not on target and recoverable only with difficulty’
• Status of ‘critical’ tasks is particularly important 14
15
• Gantt charts
• The Slip Chart
• The Timeline
16
Gantt charts
17
The Slip Chart
18
The Timeline
19
9.5 Cost monitoring
• A project could be late because the staff originally committed
have not been deployed
• In this case the project will be behind time but under budget
20
Project is delayed 21
22
9.6 Earned value analysis
• Planned value (PV) or Budgeted cost of work
scheduled (BCWS) – original estimate of the
effort/cost to complete a task
– Percentage Completed:
24
Monitoring earned values
• Schedule variance(SV)
– SV= EV-PV
– Negative SV means project is behind the schedule
SV=35k-40k= (-5k)
• Cost variance
= EV – AC
27
Earned value – an example
• Tasks
28
Earned value – an example
• Tasks
• In previous example, if
30
Earned value analysis – actual cost
• In previous example, if
32
Time variance
52
Typical change control process
1. One or more users might perceive the need for a change
54
The role of configuration librarian: