Andragogy Form 7 TM 1 CBLM Writing Guide

This document provides competency-based learning materials for the unit of competency 'Fabricate, Install and Remove Wooden Formworks' for carpentry. It includes an introduction to the module, lists the learning outcomes, assessment criteria, and module content which outlines preparing materials and tools, laying out and cutting form sheating and stiffeners, assembling and erecting form panels and components, erecting wooden scaffolds, stripping form panels and dismantling scaffolds, and cleaning and storing reusable materials. The document provides information and instructions to develop practical skills for this competency.

Uploaded by

Rayza Austria
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
32 views15 pages

Andragogy Form 7 TM 1 CBLM Writing Guide

This document provides competency-based learning materials for the unit of competency 'Fabricate, Install and Remove Wooden Formworks' for carpentry. It includes an introduction to the module, lists the learning outcomes, assessment criteria, and module content which outlines preparing materials and tools, laying out and cutting form sheating and stiffeners, assembling and erecting form panels and components, erecting wooden scaffolds, stripping form panels and dismantling scaffolds, and cleaning and storing reusable materials. The document provides information and instructions to develop practical skills for this competency.

Uploaded by

Rayza Austria
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 15

COMPETENCY-BASED LEARNING MATERIAL

Sector : CONSTRUCTION SECTOR

Qualification Title: CARPENTRY NC II

Unit of Competency: Fabricate, Install and Remove Wooden


Formworks

Module Title: Fabricate, Install and Remove Wooden


Formworks

Valenzuela City Technological College


Kamagong St., Fortune VI, Parada, Valenzuela City

CARPENTRY MODULE Date Developed:


Core Competency Module 2 May 2024 Page 1
of 15
Fabricate, Install and Developed by:
Remove Wooden Formworks Argie L. Lacasandile
TABLE OF CONTENTS

How to use this Competency Based Learning Materials………….. 3


List of Competency…………………………………………………………... 4
Module Content .....………………………………………………………….. 5
Learning Outcome Summary………………………………………………. 7
Learning Experiences………………………………………………………... 9
Information Sheet No. 2.1-3……………………………………………….. 10
Job Sheet 2.1-3………………..……………………………………... 11
Performance Criteria Checklist 2.1-3 …………………………… 13
Definition of Terms ………………………………………..……………….. 14
References …………………………………………………………………….. 15

CARPENTRY MODULE Date Developed:


Core Competency Module 2 May 2024 Page 2
of 15
Fabricate, Install and Developed by:
Remove Wooden Formworks Argie L. Lacasandile
HOW TO USE THIS COMPETENCY- BASED LEARNING MATERIAL

Welcome! to the module Carpentry. This module contains training


materials and activities for you to complete.
The unit of competency "Fabricate, Install and Remove Wooden
Formworks" contains knowledge, skills, and attitudes required for
Carpentry NC II.
You must go through a series of learning activities to complete each
learning outcome of the module. In each learning outcome are Information
Sheets, Self-Checks, Task Sheets, Operation Sheets, and Job Sheets.
Follow these activities on your own. If you have questions, don't hesitate to
ask your facilitator for assistance.
The goal of this program is the development of practical skills. To gain
these skills, you must learn basic concepts and terminologies. For the most
part, you'll get this information from the Information Sheets.
This module is prepared to help you achieve the required competency
in "Fabricate, Install and Remove Wooden Formworks."
It will be the source of information for you to acquire knowledge and
skills in this particular competency independently and at your own pace,
with minimum supervision or help from your learning facilitator.

Remember to:
 Work through all the information and complete the activities in each
section.
 Read information sheets and complete the self-check. These competency-
based learning materials include suggested references to supplement the
materials provided in this module.
 Most probably, your learning facilitator will also be your supervisor or
manager. He/she is there to support you and show you the correct way
to do things.
 You will have plenty of opportunities to ask questions and practice on the
job. Make sure you practice your new skills during regular work shifts.
This way, you will improve both your speed and memory and also your
confidence.
 Use the Self-checks, Operation Sheets, or Job Sheets to test your
progress at the end of each section.
 When you feel confident that you have had sufficient practice, ask your
learning facilitator to evaluate you. Check the Progress Chart and
Accomplishment Chart from time to time for the status of your training.

CARPENTRY MODULE Date Developed:


Core Competency Module 2 May 2024 Page 3
of 15
Fabricate, Install and Developed by:
Remove Wooden Formworks Argie L. Lacasandile
COMPETENCY BASED LEARNING MATERIALS

CARPENTRY NC II

LIST OF CORE COMPETENCIES

No Unit of Competency Module Title Code

1 Layout reference lines Laying reference lines CON711301

Fabricate, install and Fabricating, installing


2 remove wooden and removing wooden CON711302
formworks formworks
Install wooden door Installing wooden door
3 jamb, window frame and jamb, window frame CON711303
panels and panels
Install ceiling and wall Installing ceiling and
4 CON711304
frames and panels wall frames and panels
Fabricate and install Fabricating and
5 CON711305
wooden stairs installing wooden stairs
Install wooden floor Installing wooden floor
6 CON711306
supports and panels supports and panels
Fabricating and
Fabricate and install
7 installing roofing CON711307
roofing system
system
Fabricating and
Fabricate and install
8 installing wooden CON711308
wooden cabinet
cabinet

CARPENTRY MODULE Date Developed:


Core Competency Module 2 May 2024 Page 4
of 15
Fabricate, Install and Developed by:
Remove Wooden Formworks Argie L. Lacasandile
MODULE CONTENT

QUALIFICATION TITLE: CARPENTRY NC II

UNIT OF COMPETENCY: FABRICATE, INSTALL AND REMOVE


WOODEN FORMWORKS
MODULE TITLE: FABRICATING, INSTALLING AND
REMOVING WOODEN FORMWORKS
INTRODUCTION: This unit covers the knowledge, skills, and
attitudes to fabricate, install and remove
wooden formworks.

LEARNING OUTCOMES

LO1. Prepare Materials, Tools and Equipment


LO2. Lay-Out and Cut Dimension of Form Sheating and Stiffeners
LO3. Assemble and Erect Form Panels and Components
LO4. Erect Wooden Scaffolds
LO5. Strip Form Panels and Dismantle Scaffold
LO6. Clean and Store Reusable Form Panels and Components
ASSESSMENT CRITERIA

1. Personal protective equipment (PPE) is used in accordance with Rule


1080 of Occupational Safety and Health Standards.
2. List of materials, hand tools and equipment are secured and followed
according to job requirements.
3. Materials, tools and equipment are selected, inspected and prepared
consistent with job requirements.
4. Work area is cleaned according to safety and environmental
regulations (e.g. PD1152 Section 6, 8 & 42).
5. Required output is completed as specified by the immediate
supervisor based on work schedule.
6. Personal protective equipment (PPE) is used in accordance with Rule
1080 of Occupational Safety and Health Standards.
7. Form sheating and stiffeners are measured and marked according to
job specifications.
8. Form sheating and stiffeners are laid out and cut according to
required dimensions.
9. Work area is cleaned according to safety and environmental
regulations.
10. Required output is completed as specified by the immediate
supervisor based on work schedule.
11. Personal protective equipment (PPE) is used in accordance with Rule
CARPENTRY MODULE Date Developed:
Core Competency Module 2 May 2024 Page 5
of 15
Fabricate, Install and Developed by:
Remove Wooden Formworks Argie L. Lacasandile
1080 of Occupational Safety and Health Standards.
12. Sheatings are positioned and fixed to stiffeners.
13. Assembled form panels are checked for squareness, levelness,
plumbness and alignment.
14. Primary and secondary supports are positioned and fixed to hold
assembled form panels as per drawings.
15. Assembled form panels are checked for compliance with job
requirements.
16. Work area is cleaned according to safety and environmental
regulations.
17. Required output is completed as specified by the immediate
supervisor based on work schedule.
18. Personal protective equipment (PPE) is used in accordance with Rule
1080 of Occupational Safety and Health Standards.
19. Soleplates/ timber planks are prepared, placed and spaced
accordingly considering ground surface conditions based on design
requirements.
20. Wooden scaffold components are erected, plumbed and leveled based
on design requirements.
21. Wooden scaffolds systems are checked based on design requirements.
22. Lifeline for fall protection devices (harness) are installed in accordance
with job specification and OSHS requirements.
23. Work area is cleaned according to safety and environmental
regulations.
24. Personal protective equipment (PPE) is used in accordance with Rule
1080 of Occupational Safety and Health Standards.
25. Tools, equipment and staging area are prepared.
26. Bracing, supports and form panels are removed as scheduled
accordingly.
27. Shores and scaffolds are removed according to schedule.
28. Panels and other components are sorted, clean and stored for the next
reuse.
29. Work area is cleaned according to safety and environmental
regulations (e.g. PD1152 Section 6, 8 & 42).
30. Personal protective equipment (PPE) is used in accordance with Rule
1080 of Occupational Safety and Health Standards.
31. Materials such as scaffolding and formworks are recovered and
stockpiled according to company rules and procedures.
32. Work area is cleaned according to safety and environmental
regulations (e.g. PD 1152 Section 6, 8 & 42).
33. Tools, equipment and other materials are cleaned after use.
34. Required output is completed as specified by the immediate
supervisor based on work schedule.

CARPENTRY MODULE Date Developed:


Core Competency Module 2 May 2024 Page 6
of 15
Fabricate, Install and Developed by:
Remove Wooden Formworks Argie L. Lacasandile
LEARNING OUTCOME NO. 3 Assemble and Erect Form Panels
and Components
Contents:

1. Assembling form panels and stiffeners.


Assessment Criteria

1. Personal protective equipment (PPE) is used in accordance with Rule


1080 of Occupational Safety and Health Standards.
2. Sheating are positioned and fixed to stiffeners.
3. Assembled form panels are checked for squareness, levelness,
plumbness and alignment.
4. Primary and secondary supports are positioned and fixed to hold
assembled form panels as per drawings.
5. Assembled form panels are checked for compliance with job
requirements.
6. Work area is cleaned according to safety and environmental
regulations.
7. Required output is completed as specified by the immediate
supervisor based on work schedule.

Condition:

The learners must be provided, or with access, with the following:


1. WORKPLACE LOCATION
2. TOOLS AND EQUIPMENT
 Claw Hammer
 Pencil/Marking Pen
 Pull-Push Rule
 Nylon String
 Steel Square
 Try-Square
 Hand Saw
 Chalk Line
3. TOOLS AND EQUIPMENT
Learning Packages
Bond paper
Ball pens
 Personal Protective Equipment (PPE)
 Portable Circular Saw
 Plan and working drawings
 Lumber
 Nails
 Plywood
CARPENTRY MODULE Date Developed:
Core Competency Module 2 May 2024 Page 7
of 15
Fabricate, Install and Developed by:
Remove Wooden Formworks Argie L. Lacasandile
Manuals
Related References
Assessment Method:

1. Demonstration

CARPENTRY MODULE Date Developed:


Core Competency Module 2 May 2024 Page 8
of 15
Fabricate, Install and Developed by:
Remove Wooden Formworks Argie L. Lacasandile
LEARNING EXPERIENCES

Learning Outcome 3: PREPARE MATERIALS, TOOLS AND EQUIPMENT

LEARNING ACTIVITIES SPECIAL INSTRUCTIONS

1. In this learning outcome, you’ll be able


to learn how to assembling form panels and
stiffeners.
Read Information Sheet 2.1-
3 on Assembling form panels
2. Watch the video presentation so that
and stiffeners
you’ll know the steps and procedures in
how to assembling form panels and
Answer Self-Check 2.1-3
stiffeners.
Compare answers to Answer
3. Go through the Information Sheet and
Key 2.1-3
answer Self-check to ensure that knowledge
of the standards on assembling form panels
Perform Task Sheet 2.1-3
and stiffeners.
Evaluate output using
4. Perform all the task in Job Sheet for
Performance Criteria
practical hands-on on assembling form
Checklist 2.1-3
panels and stiffeners.

5. Show your output to the facilitator for


feedback

CARPENTRY MODULE Date Developed:


Core Competency Module 2 May 2024 Page 9
of 15
Fabricate, Install and Developed by:
Remove Wooden Formworks Argie L. Lacasandile
INFORMATION SHEET 2.1-3

ASSEMBLING FORM PANELS AND STIFFENERS

Learning Objectives

After reading this information sheet, you must be able to:

 Know on how to perform the procedure in assembling form panels and


stiffeners.

A. Procedure in Assembling Form Panels and Stiffener using Plywood


and Lumber

1. Prepare all the materials and tools needed.

2. Position materials such as form sheeting and stiffener correctly.


The stiffener should be consistent with standard spacing for
studs or nailer with tolerance of 10 mm.O.C.
3. Assemble form panels. Check for squareness, levelness and
alignment to specified tolerance. Make sure that the smooth
side of the board is placed outside the frame.
4. Nail the form sheating to the stiffener using as many nails as
necessary to make the panel Istable stable in in itself. Fasten
first the two sides of the form sheating with the stiffeners
making sure it is flushed to its edges. Then fasten the ribs for
strength at 50 cm. apart. Drive 3° CWN to fasten it.
Note: Always check for squareness.
5. Clinch the nail tips. Tum over the panel and clinch the
penetrated nail tips.
6. Check form panels in compliance with job requirement.
7. Label the finished form accordingly as specified in the working
drawing.

B. Procedure in Assembling Form Panels using Forming Boards


1. Prepare the work. Make available the tools and materials. A
work table is to be manufactured.
2. Enter all sizes required into the working drawing. Derive the
sizes from the dimensions of the beam for which the formwork
is to be made. Prepare the size distribution of the cover straps
in particular.
3. Cut up the boards. The board width should not exceeded 140
mm. Do not place the rough edge of the board to the inside of
the formwork.
4. Cut the stiffening cover straps to length. Cover straps to have a
width of approx. 55 mm with 25 mm projection for comer joints!
CARPENTRY MODULE Date Developed: Page
Core Competency Module 2 May 2024 10 of
Developed by: 15
Fabricate, Install and
Remove Wooden Formworks Argie L. Lacasandile
5. Put the cover straps on the arranged boards according to the
size distribution made. Use measuring rod, if necessary!
6. Nail the cover straps on the board-panel. It is provisional nailing
with short nails (40 mm). Use as many nails as necessary to
make the panel stable in itself.
7. Nail the cover straps on the boards from the opposite side. Tum
over the provisionally nailed board-panel and nail it with 70 mm
long nails. Two nails per board are to be diagonally arranged at
the cover strap joint!
8. Clinch the nail tips. Tum over the panel again and clinch the
penetrated nail tips!

JOB SHEET 2.1-3

TITLE Assemble Form Panels and Stiffeners

Given the necessary supplies, tools and equipment, you


PERFORMANCE should be able to:
OBJECTIVE
1. Assemble form panels and stiffeners

Working Drawing/Plan
SUPPLIES Lumber
Plywood
Fasteners
Hammer
Marking Tools
TOOLS & Measuring Tools
EQUIPMENT Steel Square
Try-Square
PPE

REFERENCES CBLM

STEPS/ You need to demonstrate the assemble form panels


PROCEDURES and stiffeners:

1. Prepare all the materials and tools needed.


2. Position materials such as form sheating and
stiffener correctly. The stiffener should be consistent
with standard spacing for studs or nailer with
CARPENTRY MODULE Date Developed: Page
Core Competency Module 2 May 2024 11 of
Developed by: 15
Fabricate, Install and
Remove Wooden Formworks Argie L. Lacasandile
tolerance of 10 mm. O.C
3. Assemble form panels. Check for squareness and
alignment to specified tolerance. Make sure that the
smooth side of the board is placed outside the frame,
4. Nail the form sheating to the stiffener using as
many nails as necessary to make the panel stable in
itself. Fasten first the two sides of the form sheating
with the stiffeners making sure it is flushed to its
edges. Then fasten the ribs for strength at 50 cm.
apart. Drive 3” CWN to fasten it. Note: Always check
for squareness.
5. Clinch the nail tips. Tum over the panel and
clinch the penetrated nail tips.
6. Check form panels in compliance with job
requirement.
7. Label the finished form accordingly as specified in
the working drawing.

ASSESSMENT
METHOD Demonstration

CARPENTRY MODULE Date Developed: Page


Core Competency Module 2 May 2024 12 of
Developed by: 15
Fabricate, Install and
Remove Wooden Formworks Argie L. Lacasandile
PERFORMANCE CRITERIA CHECKLIST 2.1-3
ASSEMBLE FORM PANELS AND STIFFENERS

Trainees
Date:
name:

After accomplishing the Job Sheet 2.1-1, Did you do the following:

CRITERIA YES NO

Did I?
1. Did lay-out the panels and stiffeners properly before
pre-assembly?
2. Did I check the measurements of the members of the
form panels prior to assembly?
3. Are the form panels and stiffeners assembled according
plans?
 Squareness of forms?
 Smooth side of the board is placed outside the
frame?
 Stiffeners are flushed to the edges of panels?
 Ribs are spaced at 50 cm on center?
4. Did responded to unexpected situations accordingly?
5. Did I label the form panels according to plans?

CARPENTRY MODULE Date Developed: Page


Core Competency Module 2 May 2024 13 of
Developed by: 15
Fabricate, Install and
Remove Wooden Formworks Argie L. Lacasandile
DEFINITION OF TERMS

Assemble means to fit together as the part of the mechanism.


Dimension any measurable extent or magnitude, as the length, breadth or
thickness.
Fabricate means to make, assemble or manufacture.
Form is a temporary boarding, sheathing or pan used to produce the
desired shape and size concrete.
Lumber is sawed or sliced to board, plank.
Plywood is a materials composed of a number of thin sheets of wood glued
together with the grains of adjacent sheets at right angles.
Sheet is a board, piece of any thin materials
Stable means standing firmly in place; not easily moved, shaken,
overthrown; fixed
Stiff means not moving easily.

CARPENTRY MODULE Date Developed: Page


Core Competency Module 2 May 2024 14 of
Developed by: 15
Fabricate, Install and
Remove Wooden Formworks Argie L. Lacasandile
REFERENCES

Fajardo, Max Jr. 1995, Simplifies Construction Estimate, 3 rd Edition: 5138

Merchandizing
view-source:http://engg-material.blogspot.com/2011/03/chemical-
composition-and-its-function.html

http://www.pearsonschoolsandfecollege.co.uk/FEAndVocational/
WorkBasedLearning/BuildingServices/Level3CarpentryandJoinery/
Samples/CarpentryandJoineryLevel3CandidateHandbook2ndEdition/
CanJL3_CH^_pp168_169.pdf

http://www.thinkbrick.com.au/why-are-bricks-sustainable-4/

CARPENTRY MODULE Date Developed: Page


Core Competency Module 2 May 2024 15 of
Developed by: 15
Fabricate, Install and
Remove Wooden Formworks Argie L. Lacasandile