BNB - Quotation of Well Header Connection For SECMC

The document provides an estimation proposal for mechanical works related to relocating dewatering wells at a coal mining site. It includes item descriptions, quantities, unit prices, and a total estimated cost of PKR 25,752,802. Payment terms and conditions are also outlined.

Uploaded by

Danyal Nasir
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
57 views6 pages

BNB - Quotation of Well Header Connection For SECMC

The document provides an estimation proposal for mechanical works related to relocating dewatering wells at a coal mining site. It includes item descriptions, quantities, unit prices, and a total estimated cost of PKR 25,752,802. Payment terms and conditions are also outlined.

Uploaded by

Danyal Nasir
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 6

BNB CONSOLIDATE

C-394/1 Block-6 F.B Area, Karachi


Sindh, Karachi, 754000
021-36339999-98
Quote To: SECMC
Ref:

Attn: Procurement Dept


M/s. SECMC
SINDH ENGRO COAL MINING COMPANY LIMITED
RELOCATION OF DEWATERING WELLS AT SECMC SITE THAR COAL

WELL HEAD CONNECTION OF NEW PIPELINE


PIPELINE MATERIAL: HDPE/GRE/GRP/MS WHAT NEED

S.No
A
A-1

A-2

A-3

B
B-1

C
TERM AND CONDITIONS:
• Security for all pipes and accessories within site of CLIENT will be provided by client.
• UMT will be liable to answer the query within 48 hours.
• Political and religious holidays will not be counted in service.
• The quoted amount Is based on Open market dollar rates, which is cited to be 285 PKR to 1USD, if the Dollar rate
period of this quote.
• NO purchase order which has been established to UMT may be cancelled by the purchaser except with the agree
indemnify the UMT in full against all loss (including loss of profit) costs (including the cost of all labor and material
result of cancellation.
• This quote is inclusive of all Government Tax (Income Tax, GST/SST).
• The quote has been build considering to use the UMT existing camp inside the SECMC fence.
• Pipeline and cable purchase shall take 18 to 24 weeks.
PAYMENT SCHEDULE:
Block-6 F.B Area, Karachi
arachi, 754000
39999-98
o: SECMC

ocurement Dept
CMC
SINDH ENGRO COAL MINING COMPANY LIMITED
RELOCATION OF DEWATERING WELLS AT SECMC SITE THAR COAL BLOCK-II CAD
ESTIMATION PROPOSAL FOR MECHANICAL WORKS (CONSTRUCTION)
WELL HEAD CONNECTION OF NEW PIPELINE
PIPELINE MATERIAL: HDPE/GRE/GRP/MS WHAT NEEDED

Item Description
Pipeline Construction
Mobilization
Material supply to site location ( Cost when piping team not demobilized)
Material supply to site location ( Cost for seprate team mobilization for this work only)
Base Camp
Base Camp Establishment for complete Staff
Lodging ad boarding of team along mess (The work is for only 1 month, however if the team has
to stay at site due to restriction from client, then per month charges shall be add as per actual)
Installation Charges
Arrangment of all allied equipment and machinery
Installation of piping connection
Civil work on the well header and well pad at site
Electric connection of the system with main power supply line
Material Supplies
Header Conection Accessories
All Piping Material Including
Well Header with MS plate
Connection box of Panel
HH48X-25R/NO RETURN VALVE HH48X-25R
CARX/EXHAUTS VALVE CARX
D34H-25/BUTTERFLY VALVE D34H-25R
Flow meters (Totalizer)
including nut/bolts, connection pipes, gaskets and etc
TERM AND CONDITIONS:
• Security for all pipes and accessories within site of CLIENT will be provided by client.
• UMT will be liable to answer the query within 48 hours.
• Political and religious holidays will not be counted in service.
• The quoted amount Is based on Open market dollar rates, which is cited to be 285 PKR to 1USD, if the Dollar rates fluctuate, the quo
period of this quote.
• NO purchase order which has been established to UMT may be cancelled by the purchaser except with the agreement in writing of t
indemnify the UMT in full against all loss (including loss of profit) costs (including the cost of all labor and materials used), damages, ch
result of cancellation.
• This quote is inclusive of all Government Tax (Income Tax, GST/SST).
• The quote has been build considering to use the UMT existing camp inside the SECMC fence.
• Pipeline and cable purchase shall take 18 to 24 weeks.
PAYMENT SCHEDULE:
Date 7th December, 2023
Quotation ID QUO/O&M/
Quote Valid Till 2023/1081
22nd December, 2023
Prepared by Ms. Sana Kanwal
Approved By Mr. Faheem Ahmed
For O&M SECTOR

ITED
COAL BLOCK-II CAD
CONSTRUCTION)
NE
NEEDED

Unit Quantity Unit Price Total Amount

Job 1 500,000 500,000


3,500,000

Month 1 1,805,000 1,805,000

LS 3 1,250,934 3,752,802

LS 3 6,565,000 19,695,000

Total Estimated Cost 25,752,802


lar rates fluctuate, the quoted price shall be reevaluate after effective

e agreement in writing of the UMT and on terms that the purchaser will
aterials used), damages, charges and expenses incurred by the UMT as a