Final Report Updated Esmf For BRWDLP Phase 2 Clean Oweb
Final Report Updated Esmf For BRWDLP Phase 2 Clean Oweb
Final Report Updated Esmf For BRWDLP Phase 2 Clean Oweb
September, 2023
Addis Ababa, Ethiopia
Borana Resilient Water Development for Improved Updated Environmental and Social
Livelihoods Program (BRWDLP), Part-2 Project Management Framework (ESMF)
September, 2023
Addis Ababa, Ethiopia
TABLE OF CONTENTS
Page
LIST OF TABLES .................................................................................................................................................. VII
LIST OF FIGURES ................................................................................................................................................ VII
ACCRONYMS ....................................................................................................................................................... VIII
EXECUTIVE SUMMARY ...................................................................................................................................... IX
1. INTRODUCTION................................................................................................................................................... 1
1.1 Background ...................................................................................................................................... 1
1.2 The Rationale of the ESMF .............................................................................................................. 2
1.3 Purposes and Objectives of ESMF ................................................................................................... 3
1.3.1 Purposes of the ESMF ............................................................................................................ 3
1.3.2 Objectives of the ESMF.......................................................................................................... 4
1.4 Scope and Principles of the ESMF ................................................................................................... 5
1.4.1 Scope of the ESMF ................................................................................................................. 5
1.4.2 Principles of the ESMF ........................................................................................................... 5
1.5 Approaches and Methodologies during ESMF Preparation ............................................................. 5
1.5.1 Approaches ............................................................................................................................. 5
1.5.2 Methodologies ........................................................................................................................ 6
2. PROGRAM DESCRIPTION ................................................................................................................................. 9
2.1 Program Objective............................................................................................................................ 9
2.2 Location and Water Accessibility of the Program ........................................................................... 9
2.3 Program Design and Components .................................................................................................. 10
2.3.1 Component 1: Water Infrastructure Development and improved sanitation. ....................... 11
2.3.2 Component 2: Integrated Water Resources Management .................................................... 12
2.3.3 Component 3: Project Management ..................................................................................... 12
2.4 Water Supply Components, Routes and Main Activities ............................................................... 12
2.5 Boreholes / Well fields ................................................................................................................... 13
2.6 Wellfield Collector pipes and Primary Transmission mains .......................................................... 14
2.7 The Command Reservoir ............................................................................................................... 14
2.8 The Transmission lines................................................................................................................... 14
2.9 Service Reservoirs .......................................................................................................................... 15
2.10 Part 2 Project Beneficiaries .......................................................................................................... 15
3. POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK ...................................................................... 16
3.1 Constitution of FDRE..................................................................................................................... 16
3.2 National Policy Frameworks .......................................................................................................... 18
3.2.1 Environmental Policy of Ethiopia (EPE) .............................................................................. 18
3.2.2 Water resource policy ........................................................................................................... 19
3.2.3 Public Health policy ............................................................................................................. 20
3.2.4 National Policy on women.................................................................................................... 20
3.2.5 National population policy ................................................................................................... 20
3.2.6 National biodiversity policy ................................................................................................. 21
3.2.7 Land Tenure Policy............................................................................................................... 21
3.2.8 National Social Protection Policy of Ethiopia ...................................................................... 22
LIST OF TABLES
LIST OF FIGURES
ACCRONYMS
EXECUTIVE SUMMARY
Borana Zone of Oromia National Regional State is one of the areas frequently affected by drought as a
result of erratic and unpredictable rainfall and recurrent climate changes. The climate change problems
aggravated human and livestock water supply shortages and life loses. To address these water supply
shortage problems, Borana Resilient Water Development for Improved Livelihoods Program (BRWDILP)
initiated that encompasses 8 districts and their rural areas of Borana.
This ESMF is prepared for Part-2 Projects of the wider program which are to be implemented in three
districts (Dubluk, Elweya and Yabello districts) five kebeles; Kersa Dembi and Gobso kebeles of Dubuluk
district, Sarite and Adde Gelchet kebeles of Elweya district and Hare Wayu kebele of Yabello district of
Borana Zone.
The ESMF serves as a guideline to ensure environmental and social assessment considerations of the
program sub-projects water supply interventions during design and implementations based on the Ethiopian
Legislations and AfDB Operational Safeguards which are elaborated in the policy descriptions of the report.
This Part 2 Project of the wider program generally comprises Water Infrastructure Development for Multi-
Sector Use and Improved Sanitation, Integrated Water Resources Management and Project Management
components. By this Part 2 Project, a total of 7 boreholes, 5 at Gelchet and 2 at Sarite well fields are planned
to be executed with other project components.
The main components and activities of the Part 2 Project are transmission networks (60km), distribution
networks (253 km), construction of public fountains (Six Faucets 200 in number); 130 Double Cattle
Troughs at different sites; construction of ten (10) Standard 1000 m3 Reinforced Concrete Reservoirs with
chlorination plants; construction of VIP Latrines; construction of two BPSs, Buildings and Miscellaneous
Civil Works; watershed management Interventions of about 600 ha; aquifer management systems and
institutional measures in which capacity strengthening and Tariff Systems updating takes place. The project
is expected to benefit 308,576 human and 975,750 livestock from the water supply interventions that will
be implemented in three parts over 4-year durations.
The project area three districts sector stakeholders and project area kebeles community representatives were
consulted to engage them and discuss on potential environmental, social and economic impacts by aiming
at obtaining their views, concerns and opinions on the project. Altogether, 95 males and 29 females a total
of 124 stakeholders were consulted. All consulted stakes seriously raised about the Borana Water Supply
issue dalliances although the case has been raised on every occasion for the last 20 years. In line with this,
they requested the financing agency and the government implementing body to efficiently and effectively
work on the project implementations and shall solve the inhabitants’ severe and critical water supply
shortage problem and lifesaving tasks. They also indicated that all the project possible impacts can be easily
managed through implementing recommended mitigation and enhancement measures through
stakeholders’ participations and commitments although the impacts are easy when compared to the critical
water supply shortage problems of the people and their livestock. The participants, finally, expressed their
promises to participate in the project implementation and concluded that the stakes and community
representatives have positive attitudes on the project.
As in any other project, implementation of the Part 2 Project sub projects can have possible positive and
negative impacts based on the sub projects nature, scale and the project areas biophysical and social
environments. The ESMF report, therefore, addresses guiding role for these expected impacts identification
and their respective enhancement and mitigation measures recommendations as detailed under the section.
As concluded from the stakeholders’ views and the project areas biophysical conditions, settlement patterns
and the communities’ willingness, the project benefits by far outweigh negative impacts and the project
have community acceptances.
In order to guide that appropriate environmental and social management practices are followed during the
subprojects design, construction and operation phases, the ESMF report also contains generic project
Environmental and Social Management Plan (ESMP) that considers possible impacts, mitigation measures,
implementing responsible bodies and budget estimates that serve as a pertinent instrument to guide the
project proponents (OWEB) and other implementers to develop approaches and carry out effective
mitigation measures, design and conduct sound environmental and social monitoring programs during
subprojects design and implementations. The subprojects ESMP shall be prepared for each subproject
following attached ESMP template to this ESMF.
Similar to the ESMP, the Part 2 Project generic Environmental and Social Monitoring Plan was prepared
and included in this ESMF as it is an important tool for monitoring process of environmental and social
management activities of the Part 2 Projects in order to ensure that proposed mitigation measures for
identified impacts and risks are being implemented effectively and fix issues as designed for during the
sub-projects’ implementations. The report also included summary of most important parameters to be
monitored, responsible bodies, monitoring frequencies, monitoring types and budget estimates as generic
indicative project Environmental and Social Monitoring Plan to use as guiding tool in the subprojects
monitoring plan preparations during subsequent construction and operation phases.
As a separate management requirement, the ESMF included activities monitoring indicators during projects
implementations and/or periodic reviews, annual monitoring or auditing to be used as a guide and ensure
effectiveness of the ESMF and guarantee implementations. This section also has annual audit procedures,
end-of-project evaluation, ESMF reporting procedures and requirements, ESMF submission for clearance
are also included in the updated ESMF report to ensure efficient monitoring procedures.
Continuous consultative processes are required for successful identification and assessment of sub projects
specific environmental and social impacts, implementations and monitoring of respective mitigation or
enhancement measures. For effective implementation of these activities, then, the ESMF report also
contains Public Consultation and Disclosure Plan as a separate section with checklists to be used to make
the ESMF uses easier. With this Public Consultations and Disclosure Plan, institutions from Federal down
to project kebele levels were also included in the ESMF report with their roles and responsibilities. ESMF
Implementation Schedule is also included in the report to easily apply and involve relevant stakeholders
during the ESMF implementations.
As budget determines project implementations and attaining development goal, the ESMF budget
requirement was also estimated and included in this Updated ESMF report for its implementations. The
environmental and social management costs of subprojects are not included, as it will be estimated and
covered directly or indirectly during subsequent subproject ESIA studies by including costs for
Environmental and Social management and mitigating measures of the subproject. Accordingly, the ESMF
budget for the Part 2 project period was estimated for capacity building, training as well as Recruitment of
safeguards specialists, annual audit and end of project evaluation and others with 10% contingency. With
these, the budget was estimated at 244,847 USD or Birr 13,532,693.69 based on exchange rate of one
USD=55.27 Birr as detailed in this Updated ESMF report.
Finally, the Part 2 Project ESMF realizes importance of strengthening capacities of institutions that involve
in the subprojects implementations and provide an enabling environment in addressing environmental and
social issues by project implementing body, OWEB, Oromia Regional EPA and line sectors down to the
districts and kebele levels by using the ESMF in the water supply subproject ESIA studies and subsequent
environmental and social management and monitoring.
1. INTRODUCTION
1.1 Background
Borana Zone is one of the Oromia Zones frequently affected by drought as a result of erratic and
unpredictable rainfall and recurrent climate changes. Extreme weather events such as floods and droughts
are increasing and seriously affecting the communities’ livelihoods. Based on Borana Zone Agriculture and
Pastoral Development Office, the recurrent drought cycle is narrowed and started occurring every two to
three consecutive years. From this perspective, climate change is more likely to make the water supply
situation even more precarious than it is today. Water supply schemes based on large and reliable water
sources, will therefore, contribute to alleviating such adverse impacts of the prolonged droughts and other
climate change impacts of the area.
Majority of Borana people are Agro-pastoralists and they often migrate to different areas searching for
water and pasture for their livestock as an adaptation mechanism to drought. The harsh climatic conditions
of the areas not only affect human populations, but also have serious effects on the livestock populations
of the areas. Because of this, the livestock productivity has highly reduced as a result of long migration,
poor body conditions due to travelling long distances and associated disease exposures.
The Government of Ethiopia through the Ministry of Water and Energy (MoWE) has requested support
from the African Development Bank (AfDB) for the Borana Resilient Water Development for Improved
Livelihood Program to be implemented by the regional line program implementing body, the Oromia
Region Water and Energy Bureau (ORWEB), which contributes to improving the water supply schemes
based on large and reliable water sources which will contribute to alleviating adverse impacts of the
prolonged droughts and other climate change impacts in Borana Zone of Oromia region. Therefore, the
provision of sustainable water supply for the community is not simply water but is about improvement of
the whole livelihood and living standards of the community during the Program implementations.
Since the specific location of subproject activities under the Part 2 project of the wider program, are not
known with certainty during this time, the program is being prepared for presentation to the Bank, the Bank
environmental assessment policy requires the borrower to prepare an Environmental and Social
Management Framework (ESMF) to establish mechanisms for assessment and management of the
environmental and social risks and impacts of all sub-projects under the BRWDLP, Part-2 Project
implementation period and to set mitigation, monitoring and institutional measures to be taken during
implementation and operation phases of the program in order to eliminate or minimize possible adverse
environmental and social impacts or reduce to acceptable levels.
The key issues for updating ESMF of the Borana Resilient Water Development for Improved Livelihoods
Program include environmental and social concerns as raised by various legal instruments. This ESMF,
therefore, provides that the expected guidelines and defines the procedures whereby environmental and
social impact assessments (ESIAs) and eventually environmental and social management plans (ESMPs)
will be prepared and implemented for each project of the BRWDLP as may be required. This document is
in compliance with Bank ISS and ESAP, including the AfDB five Operational safeguards and the relevant
Ethiopian environmental policies, laws and regulations as well as the International environmental laws and
conventions applicable.
Furthermore, the OWEB, which is the main program implementing body, given the specific location of the
Part-2 project under the wider program (BRWDLP) will comprise groundwater development in the Gelchet
wellfield and development of the Wellfield area Water Supply Route (includes the project backbone,
comprising the water collection and transmission systems to the Simu Hilltop Reservoir of Yabello district,
main transmission to Dubuluk district and transmissions in the Webe system from the wellfields of Elweya
district) is to undertake an Environmental and Social Impact Assessment (ESIA), identify and evaluate
environmental and social impacts associated with the implementation of the Part 2 project of the BRWDL
program and to recommend mitigation and/or enhancement measures for possible impacts that enable in
harmonizing the problems with the social, economic and ecological conditions of the project from the
wellfield to main reservoir site of Simu Hilltop Reservoir in Yabello district, Dubuluk and Web System of
Elweya districts. This ESMF is prepared and updated for Part 2 projects based on the African Development
Bank environmental assessment requirements as well the Ethiopian environmental management
requirements as outlined in various legal instruments and including considerations for the various
international environmental regulations and requirements as well.
The OWEB is further required to disclose the updated ESMF document as a document in country (OWEB
and MoWE websites) to be accessible to the public, local communities, potential program-affected and
interested groups, local NGOs, and all other stakeholders. It will also be disclosed on the AfDB’s external
website. The date for the disclosure of the report will precede the date for appraisal of the Part 2 investment
program which is mainly in September 2023 and 30 days before Board presentations. Stakeholders have
been consulted during the ESMF preparation (Chapter-6 and Annex-11 to 13) and will have an opportunity
to review and comment on the updated ESMF. The final document will be disclosed at the same locations
and will include summaries of the consultations, comments and suggestions and their disposition.
According to the AfDB’s ISS, operations that finance multiple, small-scale sub-projects whose location,
scope and design are not determined at the time that the Bank appraises and approves the operation should
develop an ESMF. This means that the location and site-specific environmental and social risks created by
the investment will only be known during the implementation of the Project. The features of the Part 2
project ESMF is the appropriate requirement under the AfDB’s Operational Safeguard - Environmental and
Social Assessment (OS 1) are listed below:
This updated ESMF is prepared to serve as a guideline to ensure that the environmental and social impacts
of the BRWDLP, Part-2 Project are properly considered during the program sub-projects design and
implementations. The ESMF guides designing processes of appropriate measures and plans to reduce
mitigate and/or offset adverse impacts and enhance positive outcomes including benefits for program
beneficiaries and the environment. This ESMF thus provides a comprehensive framework on how to
address potential adverse social and environmental impacts associated with the water development and
integrated watershed management sector projects under the BRWDLP, Part-2 Project.
The updated ESMF will also provide compliance requirements for future project sites which would satisfy
law requirements (environmental regulations) enforce in Ethiopia. The environmental and social
assessment and AfDB’s Operational Safeguard measures will be confirmed during the project
implementation phase. The construction and operation of the proposed projects under this program are
expected to bring several significant positive environmental and socio-economic benefits to the respective
Project area of influence as well as to the nation at large. The Program will enhance economic and social
developments along the corridor of the project area and these developments will likely lead to a much-
improved quality of life for local communities. This ESMF will determine the institutional measures to be
taken during the project implementation, including those relating to capacity building as well as expected
to define the requirements that need to be complied with during project implementation so that all
investments financed by the program fully comply with the national and international laws (including
AfDB’s Operational Safeguards requirements).
After undertaking appropriate assessments of the likely social and environmental impacts of the BRWDLP,
Part-2 Project, the updated ESMF proposes relevant mitigation and enhancement measures and strategies
to be considered during the program activity design and implementation. The framework also stipulates
mechanisms for screening, management and monitoring of the likely environmental and social impacts that
may emanate from the project’s activities under the wider program during the implementation phase. The
overall goal of the ESMF is to ensure that decision-making in subsequent stages of the program’s Part-2
Projects is informed and influenced by environmental and social considerations for the implementation of
each project under the program. It aims also to integrate environmental and social concerns into the project’s
design and implementation under this program.
This updated ESMF set out principles, laws, regulations, guidelines and procedures to assess the
environmental and social impacts related to each project under the program. It analyses the environmental
and social policies and legal requirements of the Government of Ethiopia and operational safeguards of the
African Development Bank and ensures that environmental and social issues are dealt within a proper and
efficient manner meeting all the compliance requirements of the Government of Ethiopia and the African
Development Bank.
in accordance with applicable African Development Bank (AfDB) operational safeguard and environmental
assessment guidelines of Ethiopia which involves the following approach and methodologies:
1.5.2 Methodologies
This ESMF is prepared in accordance with applicable Ethiopian Legislations and AfDB Operational
Safeguard. During the preparation of this ESMF, both primary and secondary sources were collected,
collated, analyzed, and discussed. The distinct methodologies adopted for the preparation of this ESMF
include literature review and data gathering; Public consultation and discussions with relevant sector
institutions and key sector stakeholders and beneficiaries; and site visits at the proposed program locations
in the selected potential districts. An account of the existing biophysical and social environment conditions
was gathered and discussed under the baseline information section of this ESMF and used to assess the
potential environmental and social impacts generated from the proposed program’s activities. Consultations
with various stakeholders have been conducted and the outcomes of the consultations are discussed under
the public consultation section (Chapter-6) and list of participants and minutes of the meeting are attached
in Annex 11 to Annex13).
supply project. In addition, with regard to the general environmental management conditions for project,
the policy frameworks in which the environmental policy, the water resources development policy and other
relevant policies, the national environmental laws, regulations proclamation including the constitution of
Ethiopia and guidelines; the African Development Bank (AfDB) safeguard policies, Project Appraisal
Report, AfDB strategies on climate change, water strategy 2021-2025 towards a water secure Africa and
other relevant documents Ethiopia signed shall be collected and reviewed.
Site-specific baseline data on the environmental and socioeconomic characteristics of the project area were
collected through observations. In addition, relevant government offices were contacted and sector related
data was collected. Both primary and secondary data were collected from all possible sources. The collected
data have been used to provide clear description of the baseline environmental and socioeconomic
conditions of the project influence areas in order to assess potential environmental and social impacts of
the intended water supply program respective projects. The study team also undertook preliminary flora
and fauna assessment in order to collect indicative information associated with the specific projects under
the program within the program implementation area.
Similar consultations were conducted during this time with direct project beneficiary kebeles; Kersa Dembi
and Gobso keneles of Dubuluk district, Aadde Gelchet and Serite kebeles or the well field kebeles of Elweya
district and Hare-Wayu kebele of Yabello district. List of participants and minutes of the consultative
meetings are depicted in Annex-11 to Annex-13. Summaries of concerns and views raised by participants
are depicted in section-10 of this ESMF. During these consultative meetings sessions, objectives of the
program were presented by the team and various information including the likely positive and negative
impacts and possible mitigation measures for respective impacts thoroughly discussed by participants.
natural resources development, land administration office, livestock development, health office, water and
energy office, women and youth office and culture and tourism office. The questionnaires were provided
them after stakeholders consultative meeting were conducted and they “the sectors heads or representatives”
were aware through the consultative meetings.
Similarly, kebele level data collection questionnaires were also provided them after participated the kebele
level consultative meetings and they got awareness about the Part 2 project and the program as a whole.
The kebeles are Hara Wayu Kebele of Yabello district, Gobso and Kersa Dembi kebeles of Dubuluk district
and Adde Gelchet and Sarite kebeles of Elweya district. The questionnaires (See Annex-15.1 to Annex
15.10) request baseline data & information as per each sector areas.
2. PROGRAM DESCRIPTION
Borana Resilient Water Development for Improved Livelihoods Program (BRWDLP), Part -2 Project is
continuation of Part-I of the ongoing project by the African Development Bank (AfDB) support. These
Part-2 project activities cover the wellfield (reticulation), Dubulk and Wieb subsystems. The districts and
kebeles included in this Part 2 of the project are Elweya District (Southern part of Sarite kebele, Adde
Gelchet Kebeles), Dubuluk District (Northern part of Gobso kebele, Kersa Denbi kebele based on the
present kebele boundaries arrangement) and Hare wayu kebele of Yabelo District.
This part 2 of the program will be financed through an AfDB grant to cover water development and
sanitation interventions which include the outstanding unfinanced scopes in the Wellfield areas, the Dubulk
and the Web sub-systems which are the epicenters of droughts. The project will support the Government of
Ethiopia to implement the already identified strategic actions in Borana Zone of Oromia National Regional
State. In addition, the program helps in reducing extreme poverty by extending piped water services to the
pastoral communities and low-income households that will be supported by specific activities under the
following sections of the project components. The project contains three components; Water Infrastructure
Development for Multi-Sector Use and improved sanitation, Integrated Water Resources Management and
Project Management.
The program objective is to develop climate resilient and gender sensitive integrated and sustainable water
and sanitation services among pastoralist communities in dry land areas of Borana zone of the Oromia
National Regional State for improved health, livelihoods, and nutrition and food security. The program
focuses on drought impacts sustainable recovery and resilience in water related sectors, using an IWRM
approach. Key project indicators include (i) increased access to potable water and sanitation of the
population, (ii) improve water for livestock and (iii) increased land area under sustainable landscape
management practices.
in the northwest. Most of the project areas can be reached by driving along dry gravel and earth roads
connected to the main highway
The wider water supply program (BRWDILP) encompasses rural areas and 8 district centers and villages
of Borana Zone; Yabello, Arero, Wachile, Gamole Dubluk, Dugda-Dawa, Dire and Elweya districts of the
zone. The Water Supply program is within the geographic coordinates of 5°08' N latitude and 39°03'E
longitude at Surupha and 4°21' N latitude and 38°16'E longitude at Dubuluk; and 5°20'N latitude and
37°38'E longitude at Sarite and 4°32' latitude and 39°03'E longitude at Wachile. The overall Program areas
spatially extend over a large territory; about 19,285 km2 that includes 62 Kebeles, of which 50 rural Kebeles
and 12 small towns and urban centers. In addition, the program also provides water for livestock in
aforementioned districts. The water source is groundwater to be abstracted from 11 Boreholes found at
Gelchet and Sarite areas. The program is designed to create access to safe and adequate water supply service
for 308,576 human and 975,750 livestock populations residing in Borana Zone shown in Figure 2.1 areas.
At this Part 2 Project of the program about 308,576 human and 975,750 livestock are expected to be
benefited from the resilient water supply and sanitation infrastructure, livestock watering and water
resource and micro watershed management subprojects proposed to be funded under the program by 2030.
The program will be implemented in three parts over 4-year duration.
The program components include: (i) Water Infrastructure development for multi-sector use and improved
sanitation, (ii) Integrated Water Resources Management and (iii) Project Management. Part 1 of
Component 1, provides water services for an estimated 24,810 people and 83,000 livestock. The financing
Plan is presented in Table2.1. The wider program will cover an estimated 50 rural villages (kebeles) and 12
small towns of the Borana zone. An estimated 308, 576 human and 975,750 livestock are expected to benefit
from the resilient water supply and sanitation infrastructure, livestock watering and water resource, and
micro watershed management subprojects proposed to be funded under the program by 2030. The program
will be implemented in three Parts over 4-year duration.
The program components include: (i) Water Infrastructure development for multi-sector use and improved
sanitation, (ii) Integrated water Resources Management and (iii) Project Management. The details of
BRWDLP Part 2 project components are discussed below.
Subcomponent 1-2: Investments in sanitation and hygiene services. This subcomponent will finance
works and services for improved sanitation. Interventions will include improving sanitation facilities in
schools, complemented by hygiene education, construction of public sanitation facilities and retrofitting of
existing sanitary facilities in schools and health centers. The sanitation and hygiene education programs
will be deployed through school systems using training, dissemination of materials and public campaigns.
WASH campaigns will target women’s groups for delivery of key messages.
Subcomponent 1-3: Institutional Strengthening. This subcomponent will build the institutional capacity
at regional, zonal and district levels. It will strengthen community-level WASH management systems;
support operational improvements, including non-revenue water (NRW) reduction (details in Annex 1-7).
In addition, technical assistance will support water services regulation at regional and district levels, and
the development of local rural water supply tariffs2 in the form of household contributions to fund the
maintenance of rural water supplies. Training topics will include techniques for leakage control; asset
management; and operation maintenance of the WSS systems. The program will promote private sector
participation through provision of start-up support packages (for example, testing equipment and tools) to
assist with the transition to operations. The program will assign women/youth groups to manage public
water and sanitation facilities - thereby improving income generation and enhancing sustainability.
1 SCADA refers to Supervisory control and data acquisition. It is one of the tools the Bank recommends for digital transformation of WSS and sanitation systems. It helps staff
monitor and address system problems across the network efficiently. Each piece of equipment that requires monitoring, from valves to tanks, is equipped with sensors.
2
The program will support the development of rural water tariffs and will consider a connection subsidy strategy targeting the poorest and most vulnerable residents.
Sub-component 2-2. Catchment management and rehabilitation. This subcomponent aims to rehabilitate
targeted sub-catchments to protect water sources, improve water quality, and increase sustainable water
use, thereby increasing resilience to droughts. Activities will include community mobilization, re-greening
overgrazed areas, managed aquifer recharge, soil and water conservation, training with focus on promoting
fodder production and storage, rangeland management to introduce rotational grazing and stocking rate
limits. The program will support women group participation in the implementation of interventions.
Subcomponent 3-2: Contingent Emergency Response. A zero-cost subcomponent will support rapid
response emergency needs, as needed (Annex 1-8). This will allow for reallocation of uncommitted funds
under the grant in the event of an eligible emergency. Emergencies that may disrupt the development
program for water service delivery could include (i) Droughts—leading to lack of water supply for human
consumption and livestock (ii) Floods—destruction, contamination, and limited access to water supply
services and (iii) Water-borne disease outbreaks—localized epidemics related to consumption of
contaminated water. Interventions would be triggered through formal declaration of a national emergency
and upon a formal request from the GoE to the Bank through the Ministry of Finance. Implementation will
follow an Implementation Plan satisfactory to the Bank that will be prepared for each eligible emergency.
Figure2. 2: Part 2 of the Borana Resilient Water Development for Improved Livelihoods Program
The project proponent needs to ensure that its project activities are in line with all relevant national policies,
legislations and standards operating in Ethiopia, African development Bank’s policies, procedures and
standards and other relevant international standards. In this chapter relevant policies, legal and
administrative framework that are relevant to this project are covered. The project proponent shall observe
these frameworks in the designing and implementing the proposed project activities.
Article 25- Right to Equality: All persons are equal before the law and are entitled without any
discrimination to the equal protection of the law. In this respect, the law shall guarantee to all persons equal
and effective protection without discrimination on grounds of race, nation, nationality, or other social
origin, color, sex, language, religion, political or other opinions, property, birth or other status.
Article 35- Rights of Women: The historical legacy of inequality and discrimination suffered by women in
Ethiopia considered, women, to remedy this legacy, are entitled to affirmative measures. The purpose of
such measures shall be to provide special attention to women so as to enable them to compete and participate
on the basis of equality with men in political, social, and economic life as well as in public and private
institutions
• Women have the right to full consultation in the formulation of national development policies, the
designing, and execution of projects, and particularly in the case of projects affecting the interests
of women.
• Women have the right to acquire, administer, control, use and transfer property. In particular, they
have equal rights with men with respect to use, transfer, administration, and control of land. They
shall also enjoy equal treatment in the inheritance of property.
• Women shall have a right to equality in employment, promotion, pay, and the transfer of pension
entitlements.
Article 37- Right of Access to Justice: Everyone has the right to bring a justifiable matter to, and to obtain
a decision or judgment by, a court of law or any other competent body with judicial power.
Article 39- Rights of Nations, Nationalities, and Peoples: Every Nation, Nationality and People in Ethiopia
have the right to a full measure of self-government which includes the right to establish institutions of
government in the territory that it inhabits and to equitable representation in State and Federal Governments.
Some of the specific objectives of the Policy include sustainable utilization of non- renewable resources,
identifying and developing natural resources that are currently underutilized, accounting for the full costs
and benefits of natural resource development and empowering and encouraging public participation in
environmental management issues.
The section of the EPA concerning EIA sets out a number of policies, key elements of which may be
summarized as follows:
• The need for EIA to address social, socio-economic, political and cultural impacts, in addition to
physical and biological impacts, and for public consultation to be integrated within the EIA
procedures.
• Incorporation of impact containment measures within the design process for both public and private
sector development projects, and for mitigation measures and accident contingency plans to be
incorporated within environmental impact statements (EISs).
• Creation of a legal framework for the EIA process, together with a suitable and coordinated
institutional framework for the execution and approval of ESIAs and environmental audits.
• Development of detailed technical sectoral guidelines for ESIA and environmental auditing, and
• Development of ESIA and environmental auditing capacity and capabilities within the EPA,
sectoral ministries, and agencies, as well as in the regions.
The Policy has been developed as a national instrument enhancing the objectives of the Constitution and
setting out clear cut directions with respect to environmental concerns particularly in terms of regulatory
measures adopted as well as in the process of design, implementation and operation of development
projects. Its recognition of the significance of addressing cross-sectoral environmental issues in the context
of a national approach to environmental assessment and management integrates the efforts of a wide range
of institutions across the country. It provides a sound and rational basis for addressing the country’s
environmental problems in a coordinated manner.
The priority areas of the policy are in the field of Information Education and Communication (IEC) of
health to create awareness and behavioral change of the society towards health issues, emphasis on the
control of communicable disease, epidemics, and on diseases that are related to malnutrition and poor living
condition, promotion of occupational health and safety, the development of environmental health,
rehabilitation of health infrastructures, appropriate health service management system, attention to
traditional medicines, carrying out applied health research, provision of essential medicines, and expansion
of frontline and middle level health professionals.
• Making population and economic growth compatible and the over-exploitation of natural resources
unnecessary;
• Ensuring spatially balanced population distribution patterns, with a view to maintaining
environmental security and extending the scope of development activities;
• Improving productivity of agriculture and introducing off-farm/nonagricultural activities for the
purpose of employment diversification, and
• Maintaining and improving the carrying capacity of the environment by taking appropriate
environmental protection and conservation measures.
The policy provides for guidance towards effective conservation, rational development, and sustainable
utilization of the country’s biodiversity, and contains comprehensive policy provisions for the conservation
and sustainable utilization of biodiversity. Protection of biodiversity-related traditional indigenous
knowledge and communities' benefit sharing arrangements are not yet effective. Similarly, the potential of
biodiversity-related opportunities has not yet been exploited to enhance sustainable livelihood to the desired
level. However, there is a general understanding with respect to changing the management approach in
order to bring about the desired benefits.
Wetlands are considered among the most productive type of ecosystem in the world, providing benefits far
in excess of those obtained from alternative uses to which they are subjected. Ethiopia is endowed with vast
wetlands, including a tract in the project area; however, efforts towards their conservation and sustainable
utilization are very limited, and no clear policy and legislative framework have been designed.
• To conserve, manage, develop and sustainably utilize the wildlife resource so that the country can
derive the socio-economic and ecological benefit from the resource, and
• To enable the country to discharge its obligations assumed under the international treaties regarding
the conservation and utilization of wildlife and pass the resource and benefits to the coming
generation.
3.3 Strategies
3.3.1 Conservation Strategy of Ethiopia
The Conservation Strategy of Ethiopia, which was approved by the Council of Ministers, provided a
strategic framework for integrating environmental planning into policies, programs and projects. With
regard to development of alternative energy resources and their utilization, the relevant strategies include
the following:
• Develop alternative energy sources (e.g., solar power, wind, biogas, agricultural bio-fuel, liquid bio-
fuel or small hydroelectric plants) for towns and villages remote from the national grid;
• Acquire, develop, test and disseminate appropriate and improved energy use technologies (e.g.,
improved stoves, charcoal kilns, solar powered cookers and heaters); and,
• Demonstrate and support the use of other energy sources (e.g., geothermal, solar, etc.) in the various
economic sectors where it is currently little used such as in transportation, irrigation, crop-drying, food
processing, fish drying, and thermal heating.
The law clearly states that women should not be discriminated against as regards to employment and
payment on bases of her sex. Gender norms in Ethiopia vary widely depending on geographic location,
ethnicity, and religion, especially related to property ownership, inheritance, and the division of assets after
divorce. However, the new Family Code has changed all that. Passed in 2000, it gives equal rights to women
in marriage, and it requires all assets be divided equally among both partners in the case of a divorce. By
now, all the states in Ethiopia have approved this new Code. Ethiopia is one of many developing countries
implementing gender policy reforms, especially regarding women’s equal access to assets and resources.
As defined in Article 12, any person shall utilize water resources for the following purposes without
requiring a permit from the Supervising Body:
• Dig water wells by hand or use water from hand-dug wells, and
• Use water for traditional irrigation, artisanal mining, and for traditional animal rearing, as well as
for water mills.
The law also encourages the possibility of designing and administering protected areas by the federal and
regional governments, private investors, and local communities with respect to the criteria maintained in
the proclamation. The law allows some activities; sport hunting under permission of the authority, trade on
wildlife and their products under license, and support benefit sharing mechanisms among federal, regional
and local community from wildlife income.
The Wildlife legislation has been supported by Ethiopian Wildlife Regulation (No. 163/2008). According
to this regulation, inside protected areas (i.e., National Parks, Wildlife Sanctuaries and Wildlife Reserves)
the following activities are prohibited.
• Passing or transferring of any weapon;
• Hunting or fishing;
• Propelling any vehicle, aircraft or boat during hours not allowed;
• Picking, disturbing, destroying, damaging or defacing any natural or manmade object;
• Undertaking agricultural activities or preparing land for cultivation;
• Allowing grazing and watering domestic animals;
• Allowing passing through or keeping any domestic or wild animals those are stranger to an area;
• Undertake exploration and mining in the protected areas;
• Planting, cutting, chopping, removing, taking, damaging or transferring any plant species;
• Setting or attempting to set fire;
The Proclamation has five parts. Part one is called ‗General ‘, and focuses on titles and definitions. Part
two deals with the establishment of advisory Board with powers and duties, whereas Part three is about the
appointment of Inspectors with powers and duties respectively. Part four is very comprehensive with 11
articles and other sub-articles on public health. The major articles under Part four of this Proclamation
include food quality control, food standard requirements, water quality control, occupational health control
and use of machinery, waste handling and disposal, availability of toilet facilities, control of bathing places
and pools, disposal of dead bodies, control at entrance and exit ports, communicable diseases and the
requirement of health permit and registration before resumption and after completion of construction. Part
five is on Miscellaneous Provisions–including obligation to cooperate, penalty, repealed and applicable
laws, power to issue regulations, power to issue directives and, effective date.
Article 41 of the Proclamation deals with Fortuitous Discovery of Cultural Heritages and Sub-Article 1
states that any person who discovers any Cultural Heritage in the course of an excavation connected to
mining explorations, building works, road construction, or other similar activities or in the course of any
other fortuitous event, shall forthwith report to the Authority for Research and Conservation of Cultural
Heritage (ARCCH), and shall protect and keep it intact until the Authority takes delivery thereof. Sub-
Article 2, on the other hand, states that the Authority shall, upon receipt of a report submitted pursuant to
Sub-Article (1) hereof, take all appropriate measures to examine, take delivery of and register the Cultural
Heritage so discovered.
The Guidelines follow conventional patterns adopted in many other countries and make provisions for
screening, scoping, identification and evaluation of impacts, development of environmental management
and monitoring plans, alternatives considerations, ESIA report structure and information requirements, etc.
The procedural guideline details required procedures for conducting ESIA, permit requirements, stages and
procedures involved in ESIA processes and roles and responsibilities of parties involved in ESIA processes.
It also includes categories of projects (schedule of activities) concerning requirements of ESIA and list of
project types under each category.
The technical guideline specifies tools particularly standards and guidelines that may be considered when
engaging in the ESIA process, and detail key issues for environmental assessment in specific development
sectors. The Guideline provides the categories, the relevant requirements for an ESIA and lists project types
under each category. In accordance with this Guideline, projects are categorized into three schedules:
• Category 1: Projects are project that are expected to have adverse significant environmental
impacts and therefore, require a full Environmental Impact Assessment;
• Category 2: Projects whose type; scale or other relevant characteristics have potential to cause
some significant environmental impacts but are not likely to warrant a full ESIA study, and
• Category 3: Projects which would have no impact and do not require an ESIA.
The ESIA laws and guidelines of Ethiopia require the preparation of environmental impact statement (ESIA
report) and its submission to the EPA or REA for projects requiring ESIA. The legal documents also state
that an ESIA report should contain sufficient information that enable the determination of whether or under
what conditions the project should proceed. Furthermore, they include a list of contents that should be in
the report as a minimum requirement.
3.6 African Development Bank Environmental & Social Policies, Procedures & Standards
The environmental and social safeguards of the African Development Bank (AfDB, or the Bank) are a
cornerstone of the Bank’s support for inclusive economic growth and environmental sustainability in
Africa. As the Bank adapts to emerging environmental and social development challenges, safeguards can
quickly become out of date. To this end, AfDB has developed an Integrated Safeguards System (ISS) based
on the two previous safeguard policies namely; Involuntary Resettlement (2003) and Environment (2004)
and other three cross-cutting policies and strategies: Gender (2001), the Climate Risk management and
Adaptation Strategy (2009) and the Civil Society Engagement Framework (2012).
Bank’s sector policies: Health (1996), Integrated Water Resources Management (2000), Agriculture and
Rural Development (2000, 2010), and Poverty Reduction (2004). It brings these policies and strategies into
a consolidated framework that is intended to enhance the effectiveness and relevance of the Bank’s work.
The ISS contains four interrelated components;
• The Integrated Safeguards Policy Statement – Describes common objectives of the Bank’s
safeguards and lays out policy principles. It is designed to be applied to current and future lending
modalities, and it takes into account the various capacities and needs of regional member countries
in both the public and private sectors.
• Operational Safeguards (OSs) – are a set of five safeguard requirements that Bank clients are
expected to meet when addressing social and environmental impacts and risks.
• Environmental and Social Assessment Procedures (ESAPs) – provide guidance on the specific
procedures that the Bank and its borrowers or clients should follow to ensure that Bank operations
meet the requirements of the OSs at each stage of the Bank’s project cycle.
• Integrated Environmental and Social Impact Assessment (IESIA) – Guidance Notes provide
technical guidance to the Bank’s borrowers or clients on standards on sector issues, such as roads
and railways, hydropower, or fisheries, or on methodological approaches clients or borrowers are
expected to adopt to meet OS standards.
The operational safeguards are the major components of the Bank’s ISS intended for:
• Better integrate considerations of environmental and social impacts into Bank operations to
promote sustainability and long-term development in Africa,
• Prevent projects from adversely affecting the environment and local communities or, where
prevention is not possible, minimize, mitigate and/or compensate for adverse effects and maximize
development benefits,
• Systematically consider the impact of climate change on the sustainability of investment projects
and the contribution of projects to global greenhouse gas emissions,
• Delineate the roles and responsibilities of the Bank and its borrowers or clients in implementing
projects, achieving sustainable outcomes, and promoting local participation, and
• Assist regional member countries and borrowers/ clients in strengthening their own safeguards
systems and their capacity to manage environmental and social risks.
sustainability of project outcomes by protecting the environment and people from the potentially adverse
impacts of projects. The safeguards aim to:
• To identify and assess the environmental and social impacts (including gender) and climate change
vulnerability issues of Bank lending and grant financed operations in their area of influence;
• Avoid adverse impacts of projects on the environment and affected people, while maximizing
potential development benefits to the extent possible;
• Minimize, mitigate, and/ or compensate for adverse impacts on the environment and affected
people when avoidance is not possible;
• Ensure that affected communities have timely access to information in suitable forms
• About Bank operations and are consulted meaningfully about issues that may affect them;
• Help borrowers/clients to strengthen their safeguard systems and develop the capacity to manage
environmental and social risks, and
• The Bank requires that borrowers/ clients comply with these safeguards’ requirements during
project preparation and implementation. The Integrated Safeguards Policy Statement sets out the
basic tenets that guide and underpin the Bank’s approach to environmental safeguards.
• Provide for stakeholders’ participation during the consultation process so that affected communities
and stakeholders have timely access to information in suitable forms about Bank operations, and
are consulted meaningfully about issues that may affect them;
• Ensure the effective management of environmental and social risks in projects during and after
implementation, and
• Contribute to strengthening regional member country (RMC) systems for environmental and social
risk management by assessing and building their capacity to meet AfDB requirements set out in
the Integrated Safeguards System (ISS).
This section covers areas related to the general environment i.e., physical (land, water, air, climate,), socio-
economic and cultural (occupational, gender, human well-being, and safety; physical cultural resources) of
the community, trans-boundary, global impacts including pollution control (greenhouse gas (GHG)
emissions), and vulnerability to climate-change effects. Environmental and Social Impact Assessment
(ESIA) is conducted to identify the various hazards or risk assessments and recommended the respective
mitigation measures to be included in the environmental and social management plan (ESMP). The
Borrowers or clients are responsible for conducting environmental and social assessment (Strategic
Environmental and Social Assessment (SESA) or Environmental and Social Impact Assessment, or (ESIA)
and developing as an integral part of project documentation, appropriate plan for managing possible impacts
and additional actions and assessments. The plans and assessments are Environmental and Social
Management Plans, climate change vulnerability assessment, public consultation, community impacts,
appraisal and treatment of vulnerable groups and grievance procedures.
The Project has been subjected to full ESIA to meet this policy requirement which makes the proposed
project eligible for the African Development Bank (AfDB) financing. The environmental and social impact
assessment will include the project area of influence, a comprehensive scoping of the project’s components,
consideration of alternatives, assessment of impacts, including cumulative impacts, where relevant,
mitigation and management measures, etc. In this regard, the Borrower or client (Oromia Water and Energy
Bureau) is responsible for conducting the environmental and social assessment and developing and
disclosing an Environmental and Social Impact Assessment (ESIA), acceptable to the bank standard before
the commencement of project construction.
The safeguard reflects the importance of biodiversity on the African continent and the value of key
ecosystems to the population, emphasizing the need to “respect, conserve and maintain the knowledge,
innovations, and practices of indigenous and local communities to protect and encourage customary use of
biological resources, in accordance with traditional cultural practices that are compatible with conservation
or sustainable use requirements.
3.6.2.4 Operational Safeguards 4-Pollution Prevention and Control, Greenhouse Gases, Hazardous
Materials, and Resource efficiency
This operational safeguard outlines the main pollution prevention and control requirements for borrowers
or clients to achieve high-quality environmental performance and efficient and sustainable use of natural
resources, over the life of a project (specifically to manage and reduce pollutants). It also covers range of
impacts of pollution, waste, and hazardous materials for which there are agreed-on international
conventions and comprehensive industry-specific standards that other multilateral development banks
follow. In addition, it introduces vulnerability analysis and monitoring of greenhouse gas emissions levels
and provides a detailed analysis of the possible reduction or compensatory measures framework. The
objectives of this OS are to:
• Manage and reduce pollutants likely to be caused by a project so that they shall not pose harmful
risks to human health and the environment, including hazardous, nonhazardous waste and GHG
emissions, and
• Set a framework for efficiently utilizing all a project’s raw materials and natural resources
especially focusing on energy and water.
The OS 5 establishes the Bank’s requirements for its borrowers or clients concerning workers’ conditions,
rights, and protection from abuse or exploitation. It covers working conditions, workers’ organizations,
occupational health and safety, and avoidance of child or forced labor. It also ensures greater harmonization
with most other multilateral development banks.
3.6.3 Environmental and Social Assessment Procedures of AfDB on Public Sector Operations
The AfDB Environmental and Social Assessment Procedures (ESAP) on Public Sector Operations of June
2001 main purpose Procedures is to improve decision-making and project results in order to ensure that
Bank-financed projects, plans, and programs are environmentally and socially sustainable as well as in line
with the Bank’s policies and guidelines. The ESAP intends to replace the actual procedures and integrate
all crosscutting considerations into the new assessment process. The ESAP describes the various steps that
shall be followed to mainstream cross-cutting issues along the project cycle, from country programming to
post-evaluation. The first step consists in developing and updating baseline data on Regional Member
Country’s environmental and social components, policies, programs, and capacities to better integrate
environmental and social dimensions into lending priorities during country programming. During the
project identification phase, the screening exercise focuses on the environmental and social dimensions of
a project to categorize it in one out of the four following categories.
Category 1: Projects likely to cause significant environmental and social impacts: Category 1 projects are
likely to induce significant and/or irreversible adverse environmental and/or social impacts or to
significantly affect environmental or social components that the Bank or the borrowing country considers
sensitive. Some program-based operations or other regional and sector program loans have significant
adverse environmental or social risks and are deemed to be Category 1. In some cases, projects are included
in Category 1 because of their potential cumulative impacts or the potential impacts of associated facilities.
Any project requiring a Full Resettlement Action Plan (FRAP) under the provisions of the Bank’s policy
on involuntary Resettlement is also deemed to be a Category 1.
Category 1 program-based operations or regional and sector loans require a SESA, and Category 1
investment projects require an ESIA, both leading to the preparation of an ESMP. For a project requiring a
FRAP, the ESIA includes, and-if there are no other issues requiring assessment—may be limited to, the
social assessment needed to prepare the FRAP.
Category 2: Projects that likely cause less adverse environmental and social impacts than Category 1:
Category 2 projects are likely to have detrimental site-specific environmental and/or social impacts that are
less adverse than those of Category 1 projects. Likely impacts are few in number, site-specific, largely
reversible, and readily minimized by applying appropriate management and mitigation measures or
incorporating internationally recognized design criteria and standards.
An operation that involves resettlement activity for which Resettlement Action Plan (RAP) is required
under the ESAPs is classified as Category 2. Most programmed based operations and regional or sector
program loans designed to finance a set of subprojects approved and implemented by the borrower or client
are included in this category unless the nature, scale, or sensitivity of the intended pipeline of subprojects
involves either a high level of environmental and social risk or no such risk.
Category 2 projects require an appropriate level of environmental and social assessment (ESA) for program
operations, investment plans, and some corporate loans, or ESIA for investment projects tailored to the
expected environmental and social risk so that the borrower will prepare and implement an adequate ESMP
(for an investment project) or ESMF (for a program operation), to manage the environmental and social
risks of subprojects in compliance with the Bank’s operational safeguards.
Category 3: Bank operations with negligible adverse environmental and social risks: Category-3 projects
do not directly or indirectly affect the environment adversely and are unlikely to induce adverse social
impacts. They do not require an environmental and social assessment. Beyond categorization, no action is
required. Nonetheless, to design a Category 3 project properly, it may be necessary to carry out gender
analyses, institutional analyses, or other studies on specific, critical social considerations to anticipate and
manage unintended impacts on the affected communities.
Category 4: Bank operations involving lending to financial intermediaries: Category 4 projects involve
Bank lending to financial intermediaries (FIs) that on-lend or invest in Subprojects that may produce
adverse environmental and social impacts. Financial intermediaries include banks, insurance, reinsurance,
and leasing companies, microfinance providers, private equity funds, and investment funds that use the
Bank’s funds to lend or provide equity finance to their clients.
Financial intermediaries also include private or public sector companies that receive corporate loans or
loans for investment plans from the Bank that are used to finance a set of subprojects. Financial intermediary
subprojects equivalent to Category 1 and Category 2 are subject to the relevant OS requirements as if they
were directly financed Category 1 or Category 2 projects. However, if a client will use a Bank corporate
loan to finance high-risk investment projects known at the time of loan approval, the loan can be considered
Category 1 or 4(1) requiring an ESMS as well as detailed ESA studies. In cases where a Bank corporate
loan will be used by the client to finance low-risk investment projects known at the time of loan approval,
the loan can be deemed to be Category 2 or 4(2) requiring an ESMS as well as a detail abbreviated ESA
studies. In cases where a Bank corporate loan will be used by the client to finance no-risk investment
projects known at the time of loan approval, the loan can be deemed to be Category 3 or 4(3) for which no
ESA studies are required.
FIs are required to apply the Bank’s OSs and equivalent procedures to their subprojects and to comply with
local environmental and social requirements. The FI must demonstrate to the Bank that it has developed
and will maintain an Environmental and
Social Management System (ESMS) is in line with the Bank’s OSs and appropriate for the scale and nature
of its operations – recognizing that FIs’ operations vary considerably and, in some cases, may pose a
minimal environmental and social risk. The FI must also demonstrate that it has the management
commitment, organizational capacity, resources, and expertise to implement its ESMS for its subprojects.
The Bank shall carry out due diligence of the ESMS and the FI’s organizational capacity before approving
the loan. The FI shall make a summary of the ESMS available to the public locally, e.g., on its website,
before the loan can be approved. In addition, for a category 1 project, if an OS is triggered, the requirements
of this specific OS should be met by the project.
In view of the above categorization, a large water supply and sanitation project will possibly fall under
Category I or II depending on the anticipated severity of impacts. Those projects assigned under category
1 usually require a full ESIA study. But those in category II pose medium impacts and require moderate
environmental analysis. However, if a category II project is located in or close to environmentally sensitive
areas it should be treated as equivalent to a Category I project.
The safeguard policies triggered by the Program are highlighted and described.
Safeguard Policies Triggered Yes No TBD
Environmental and Social Assessment (OS 1) X
OS 1 is triggered because of the Program’s planned construction activities which are likely to pose
environmental and social risks associated with the physical, biological, socio-economic and health and
safety profile of the sub-project areas.
These risks will be managed through the implementation of mitigation measures resulting from site
specific Environmental and Social Impacts Assessments (ESIAs) and/or Environmental and Social
Management Plans (ESMPs).
Involuntary Resettlement: Land Acquisition, Population X
Displacement and Compensation (OS2)
The Program is expected to entail limited land acquisition and possible resettlement. Majority of the
land in the affected project area are agricultural lands owned and managed by communities in the rural
kebeles/Districts. The details of the land to be acquired and number of people to be compensated will
be addressed in the site specific ESIAs, ESMPs and RAPs.
Biodiversity and Ecosystems Services (OS 3) X
The planned construction activities may impact the ecosystem service on which the local population
depends in terms of sustenance, livelihood and/or primary income. The associated risks will be avoided
or mitigated in accordance to the measures elaborated in the site-specific ESMPs.
The Borana Resilient Water Development for Improved Livelihoods Program was assessed as category I
according to the Climate Safeguard Screening tool because of the Program’s vulnerability to climate risk.
Following field assessment of climate risks and possible adaptation measures for each sub-project was
undertaken using the Bank’s Adaptation Review and Evaluation Procedures (AREP) under the Bank’s
Climate Safeguards System (CSS).
United Nations Educational, Scientific and Cultural Organization (UNESCO); the International
Council on Monuments and Sites (ICOMOS); the Council of Europe (COE); and national governments.
Most of these standards pertain to material culture, often termed ‘tangible’ cultural heritage; however,
there is increasing attention also to ‘intangible’ heritage, including the products and processes of artistic
and creative expression.
Of the above, the UNESCO standard-setting documents consist mainly of conventions and
recommendations. The five UNESCO conventions regarding cultural heritage include armed conflict
(1954); illicit trade (1970); world heritage (1972); underwater cultural heritage (2001); and intangible
cultural heritage (2003). Of the five, the 1972 ‘World Heritage Convention,’ which provides for the
designation of World Heritage Sites, is by far the most popular and widely known. Ethiopia has been a
member of UNESCO since 1976.
In addition to the conventions, from 1956 to 1980, UNESCO issued recommendations in order to encourage
international and regional cooperation, and especially, improvement in the management of cultural heritage
at the national level. Recommendations were issued on numerous subjects, including international
competitions in architecture and town planning (1956); safeguarding the beauty and character of landscapes
and sites (1962); prohibiting and preventing the illicit export, import, and transfer of cultural property
(1964); preservation of cultural property endangered by public or private works (1968); protection, at the
national level, of the cultural and natural heritage (1968); safeguarding and contemporary role of historic
areas (1976) and protection of movable cultural property (1978).
After approval of the screening report, scoping report shall be prepared and submitted and approved by the
authority. After approval of the scoping report, feasibility stage ESIA study shall be conducted. Outlines of
both screening and scoping reports are annexed in this updated ESMF Report.
With regard to groundwater, as boreholes that draw water from large, permeable aquifers are the most
resilient to all expected climate change impacts, the project is planned on groundwater source. Based on
hydrogeological investigations of the project areas, ample groundwater potential exists within alluvial
deposits; weathered and fractured volcanic rocks weathered and/or fracture basement rocks of the area.
Piping and transmitting to booster reservoirs and the main reservoir networks may be vulnerable to
contamination and will be at increased risk where more frequent flooding occurs. But, based on previous
studies, the ground water source of Part-2 Water Source areas, the wellfields, is potentially resilient to wide
range of climate change impacts. In general, in order to manage impacts of climate related extreme weather
events, adaptation of livelihood systems is very decisive. As described in the main document, the adaptation
mechanisms can include protecting ecosystems, improving agricultural methods, managing water sources,
shifting settlements to relatively more safe areas, developing early warning systems, improving insurance
coverage, developing social safety nets and enhancing public awareness and education.
It is why the watershed management interventions of about 600 ha is planned in Yabello District in this
Part-2 of the wider program to start up the ecosystem protection to start up implementations of the climate
change resilient water. Resilience of water technology to climate change shall consider those shown in
Table4.1 below.
4.1.6 Drought
Drought is one of the major hydro-meteorological hazards often occurs in this Part-2 Project areas. As
described in the wider program document, same views were obtained from the communities and sector
stakeholders during the fieldwork. Based on information obtained from community representatives and
sector stakeholders, drought occurrence frequency of the Borana Zone is increasing from time to time and
currently reached at the stage of threatening the livelihood of the community and resulted in migration of
people with their livestock because of increased pressure on water source and rangelands. The severity was
observed nationally in the last two years. As a result of mobility, lack of forage and water productivity and
livestock deaths were realized. Hence, interventions in water sector will have immense contribution towards
improving the livelihood of the local community.
Based on the information obtained from the three districts of the Part-2 Project areas natural resources
sections plantations like Dhaddacha, Allo, Burquqqee, Saphansa, Qaqalcha, Arooressee, Madheera,
Dheekkaa, Ammarreessa, Ejerssa, Hindeessa, Ammaressa, Biqaa and Ulaagaa were reported with fair to
good distribution excepted for Ejersa or “Tikur Enchet” in Amharic which is with poor distribution. The
plantains are mostly of acacia species.
4.2.2 Terrestrial Fauna
In the case of Terrestrial Fauna, the wild animals commonly observed in lowland areas of the country such
as Bush-pig, Warthog, Anubis baboons, fox, hyena and other small wild animals were reported in Part-2
project areas. Based on Adde Gelchet kebele community consultations there is Sarite park or wildlife
reserved area in Elweya district adjacent to the well field area outside of the raw water main transmission
line from the well field to the main reservoir at Semu Hill Top in Yabello district.
4.2.3 Birds
The project area hosts two endemic birds; the Ethiopian Bush Crew and White-Tailed Swallow. Various
bird species were also recorded and they are the most diverse fauna group in the Part-2 Project area adjacent
in the park. Similar to the birds in different environments, the birds of the project area have ecological and
economic importance. Based on the community responses during the consultative meetings tourists
sometimes visit the area to look for the birds found in the park. Apart from this, birds are also key component
of the ecosystem and also considered as environmental indicators.
The administrative setting of the Part 2 Project of the wider Program area covers the well field kebeles of
Elweya district, the main transmission line to the main reservoir site at Semu Holl Top of Yabello district.
The other Part 2 Project area is Dubuluk district of the Borana Zone of Oromia National Regional State.
The Part-2 project areas of the program are; therefore, include Dubuluk, Elweya and Yabello districts and
the rural kebeles discussed in different section of this ESMF Report.
Ser. Land use / land Part-2 Project districts land use in ha.
No. cover type Dubuluk Elweya Yabello Total area Percent Share (%)
4. Grazing / 230,952 94510 169,657 495,119 50.03
rangeland
5. Others 175,999 -- 47,050 223,049 22.54
Total 205,473.5 314,180 989,615 100.0
Source: Project districts data, June 2023.
Although it is not satisfactory, there are heath institutions and professionals to provide basic health services
in the project area. Based on data obtained from the three project districts of the Part 2 Project of the wider
Program, there is a hospital, 14 health centers, 31 health posts, 15 pharmacies and 14 private clinics in the
three project districts. But the service delivery is very low because of various factors.
The most common diseases of the project area are upper respiratory tract infection, pneumonia, urinary tract
infections, typhoid fever, malaria, diarrhea, internal parasites and common cold. Internal parasite and
diarrhea are the most prevalent disease as the local people use raw water from unprotected sources.
4.3.10 Livestock Health
Livestock healthcare service is of a major economic importance to the community of the Program areas.
One of such services is veterinary service, which is carried out in the form of vaccination (pre-and-post
rains seasons) and various treatments.
4.3.11 Water Supply Situations
The water supply situation of the project area is very poor and almost none. The community depends on
unprotected water sources such as ponds (Haro), traditional wells (Eela), water harvested from roof and
underground cistron. Community members walk about 15 kilometers to get potable water per day if at all
potable water source exists in very limited areas. Water collection is a major work burden on women and
children as they spend several hours per day on fetching water from distances. The water sources of the
project areas are Ela or springs, motorized pump, hand pumps and ponds with overall coverage of 31.79%
for the three districts of which 41.92% coverage for urban and 26.28% for rural as shown in Table4.5 below.
Table4.5: Potable water supply coverage of the project districts.
Ser. Potable water Part-2 Project districts water supply coverage.
No. supply coverage Dubuluk district Elweya district Yabello district Average (%)
1. District total 48% 34.5% 41.5% 31.79%
2. Urban coverage 52% 75% 36.5% 41.92%
3. Rural Coverage 36% 25% 41.5% 26.28%
Source: Collected data of the three project districts, June 2023.
When planning a subproject, among others the following list of issues must be considered. If these issues
are considered early in the subproject cycle, it helps for sustainable implementation of the subproject and
to be accepted by the local community and other beneficiaries. Some of the issues that might be considered
include, but not limited to, the following.
• Natural hazards,
• Preservation of cultural property, biodiversity and habitats,
• Preservation of land use/impact of adjoining uses,
• Preservation of species and natural spaces,
• Community and gender equality issues,
• Building and Construction issues,
• Waste management issues – solid, hazardous, and sewage,
• Location considerations, and
• Public and occupational health and safety, etc.
The implementation of the subproject environmental and social screening and management process will
be attained through the procedures and steps described below along with the project implementation cycle.
The steps of the environmental and social screening process will lead towards the review and
environmental approval by offices and bureaus in charge of environmental protection and management at
various levels, which every potential subproject under each component of BRWDLP to be implemented
by the main project implementing parties (OWEB).
implementation. The Environmental and Social Screening Form (Annex-2) will be completed by trained
and qualified frontline safeguards staff of the OWEB with environmental offices support at regional and
local levels, as required. The screening form, when correctly completed, will facilitate:
i. Identification of potential environmental and social impacts and their significances.
ii. Assignment of appropriate environmental risk and impacts.
iii. Determining appropriate environmental and social enhancement and mitigation measures, and
iv. Need to conduct an assessment and prepare specific Environmental and Social (E&S) safeguards
instruments which may include, but not limited to, an ESIA, ESMPs, etc.
The screening checklist (Annex-2) guides the impact assessment in identifying key environmental and
social issues and impacts associated with projects prior to the final subproject design. The Environmental
and social screening asks key questions on matters that are of fundamental importance to the subproject
and provides responses in the form of “Yes”, “No”, “Unknown” or “NA” (Not Applicable).
When planning a subproject under the BRWDLP, Part-2 projects, then issues that must be considered to
guide the environmental and social assessment (ESA) in identifying key environmental and social risks
and impacts that may be associated with the subprojects under respective components prior to subproject
design (Annex-2), as any identified adverse impacts of the subproject to the nearby environment or to the
community may be minimized through changes to subproject design or with considerations of mitigation
measures to lessen negative effects.
Screening is key environmental and social management process aiming at determining appropriate studies
and follow-up that might be required for sub-project activities. The screening aims at categorizing the sub-
projects into one of the environmental and social risk categories consistent with the National EIA Guidelines
and the AfDB OSs. The screening will be carried out on specific subproject activities once they have been
identified during annual planning phase of the BRWDLP, Part-2 projects of the program. The screening
will be carried out by using the Environmental and Social Screening Form (Annex-2), as stated above.
In order to fulfill requirements of AfDB ISS and ESAP as well as the national EIA guidelines, the
environmental and social screening will follow both the national and AfDB OSs requirements. As per the
AfDB Oss, screening of subprojects will be conducted to categorize respective screened subprojects into
one of the E&S categories “Category 1, Category 2, Category 3”. Completion of the screening form will
facilitate subproject assignment of environmental risk rating category, identification of potential
environmental and social impacts, determination of impact significance, recommendation of appropriate
environmental mitigation measures and decide needs for any further environmental assessment work, as
required.
The screening report to be produced expected to describe (i) The proposed subproject and its potential
impacts, (ii) Characteristics of the location (sensitivity of the area), (iii) Size (small, medium and large scale)
of the subproject, (iv) Degree of public interest, (v) Main environmental impacts and mitigation
considerations and (vi) Categorization of the subproject (Category 1, Category 2, Category 3, category 4
or schedule I, II or III).
Given scale of a subproject, some of the subproject activities particularly those under component 3, the
environmental and social screening results may categorize the subproject as “Category 3, which is supposed
to have Low Risk or schedule III” which implies such subproject activities will have limited or no
environmental and social impacts. Therefore, apart from screening, the subproject may not require further
environmental and social assessment and preparation of safeguards instruments. This is further
demonstrated by respective completed subproject screening form that has only “No” entries, the proposed
activity will not require further environmental assessment work and the technical team of experts will
recommend approval of the subproject and implementation to proceed immediately.
Depending on the field appraisal mission, the assessment of the subproject may be reconsidered by the need
for the development of safeguard instruments such as an ESIA/ESMP for the subproject. Oromia Water and
Energy Bureau (OWEB), as a direct implementer of subprojects under the BRWDLP, will be responsible
for the preparation of the required ESIA/ESMP as per the requirements of the national and AfDB OSs. For
moderate and low-risk subprojects, the ESIA/ESMP will be possibly prepared by a team of experts from
the OWEB, whereas for high and substantial risk subprojects, the ESIA/ESMP will be possibly prepared by
external independent environmental and social safeguards consultant/specialists recruited by the OWEB, as
deemed necessary. If a team of OWEB has limited capacity, they have to be given the necessary training on
ESIA/ESMP preparation and implementation guidelines, national policies and procedures, AfDB ISS,
ESAP, and OSs, etc. before conducting the environmental and social impact assessment study.
At a minimum, the ESIA/ESMP report should consist of i) description of the project activity (with location),
the environmental baseline, the impact identification, mitigating measures, and implementation and
monitoring of the mitigating measures, responsible entities, budget, etc. (Annex-6) for detail information
on the contents of the ESMP/ESIA report. The REPA at regional, Zonal, and District levels will also
supervise further the environmental and social safeguards instruments preparation and implementation work
by OWEB, which may be included in the preparation of subproject ESIA/ESMP, as the situation may
require. A copy of the ESIA/ESMP report will also be submitted to the AfDB for review, approval, and
clearance.
project proponent (OWEB) and/or screening team has thoroughly considered all environmental and social
issues with regards to the identification of potential adverse effects arising from the subproject
implementation as well as proportionate mitigating measures are adequately spell out to address adverse
impacts associated with the subprojects.
Subprojects under BRWDLP may not be eligible for implementation if they have a significant negative
impact on physical cultural resources, natural habitats, biodiversity, forests, and others. Lists of such
subprojects that may not be financed by the project are described in Annex-1 subproject exclusion list of
this ESMF. Although the proposed subproject has no activity, which affects cultural resources, in case of
any events of the potential chance find of physical cultural resources, the contract document for construction
or rehabilitation of infrastructure works is required to include reference to a chance find procedures (Annex-
7) to follow the procedures during the subproject implementation period.
The respective approval entity after reviewing the instruments (ESIA/ESMP) and will make the decision of
subproject approval in various terms, i.e., i) approval of subproject activity (with or without conditions
relating to implementation); ii) recommending to re-design the subproject (with required and/or
recommended amendments), or iii) rejecting the subproject activity (with comments as to what is required
to submit as an acceptable report). As part of the appraisal, the subproject's corresponding ESIA/ESMP has
to be made publicly available in the country (OWEB website) and at a place accessible to local people (e.g.,
at a local government office i.e., District council, and relevant institutions) at the REPA, OWEB, MoWE
website, etc.), and made available in a form, manner, and language they can understand and at the AfDB
external website for public review.
3 (Note: The final documents will be disclosed at the OWEB website and AfDB external website as appropriate.
The local level disclosure of the final ESIA/ESMP will be carried out using appropriate language and culturally
sensitive manner.).
The implementation of the recommended mitigating measures will also be monitored by the approval entity
(REPA), as applicable. The OWEB PMU will have to collaborate in the planning for external compliance
monitoring and inspections that will be conducted by the relevant REA. The planning for external
compliance monitoring/inspection could be initiated by the REPA itself or if this is not feasible, the PIU of
OWEB in line with the M&E system will initiate the collaboration for external monitoring with the approval
entity (REPA).
to evaluate the overall implementation of the ESMF. The annual environmental and social performance
audits will be considered to be the principal source of information for program management for improving
environmental and social performance. It is expected that these third-party annual performance audits will
be carried out by a registered and licensed independent consulting firm that is not otherwise involved in the
Project. The purpose of the annual performance audit includes to assess the OWEB compliance with ESMF
procedures, learning lessons, improving future ESMF implementation performance; and assessing the
occurrence of, and potential for, cumulative impacts due to Program-funded and other development
activities, as necessitated.
Step 1:
BRWDLP Step 10: Submission of Step 11:
Subproject approval decision report Documentation
identification to OWEB by REA and Projects
Effectiveness
Step 2:BRWDLP
Subproject
Screening Step 9: Approval of
Preparation safeguard instruments Step 12: Project
(ESIA/ESMP) Implementation
by REPA
Step 3: Desk
Appraisal Step 13:
(OWEB) Step 8: Submission Supervision
of ESIA/ESMP to and
the REPA by Monitoring
OWEB
Step 4: Safeguard
Screening and Step 14: Annual
prepration of Step 7: Review Auditing/Revie
Screening report w
of screening
(OWEB)
report by the
AfDB
Each consultation was preceded by disclosing project information, environmental and social issues to ensure
that participants understand the project and accept it. Specifically, the stakeholder consultation process
aimed at (i) disseminating information about the scale and scope of Part-2 Project to ensure that the
stakeholders understand the project, (ii) to enhance project ownership and local leadership, (iii) to
understand the stakes concerns and expectations, and (iv) understand and characterize potential
environmental, social and economic impacts of the project.
The districts consultative meetings participants and minutes are annexed. See the Annexes for details.
• Dubuluk District sector stakeholders’ consultation participants and minutes – Annex11.1 and 11.2,
• Elweya District Water, Mines and Energy Office staffs’ discussion participants - Annex12.1,
• Elweya District sector stakeholders’ consultation participants and minutes – Annex12.2 and 11.3, &
• Yabello District sector stakeholders’ consultation participants and minutes – Annex13.1 and 13.2.
Similarly, major issues, the sectors responses and opinions on possible project positive and negative impacts
are summarized in Table6.2 on next page and in Annex 14 of this ESMF report.
Table6.2: Summary of raised issues and opinions of district stakeholders’ consultative meetings
Major project benefits and participants expectations Major raised issues Participants opinions and responses
• Water purchase will be stopped. • As in any town, it may affect • Compensate land by land for land loss
• Decreases diseases outbreaks. fences in residential areas. related issues and
• Enhance and promotes community hygiene. • Compensation shall be the last option
• The prevailing waterborne disease cases will be minimized. if and only if all possible options for
lost resources are failed.
Major project benefits and participants expectations Major raised issues Participants opinions and responses
Major project benefits and participants expectations Major raised issues Participants opinions and responses
Figure6.4: Kersa Dembi kebele of Dubuluk District community representative consultation participants
Figure6.6: Hare Wayu kebele of Yabello District community representative consultation participants
Figure6.7: Adde Gelchet kebele of Elweya District community representative consultation participants
The districts kebeles consultative meetings participants and minutes are annexed. See under annex 11, 12
and 13. Similarly, summary of issues and opinions of the community representatives’ consultative meetings
major positive, negative and responses or opinions given by participants are summarized and presented by
kebele and issue in Table6.3 on next pages and also in Annex 14 of this ESMF.
Table6.3: Summary of raised issues and opinions on each kebele community representatives’ consultations
Major project benefits & participants expectations Major raised issues Opinions and responses
Major project benefits & participants expectations Major raised issues Opinions and responses
• The severe livestock deaths due to lack of water and community awareness in order to consider
grass will be stopped or minimized and the cemetery, religious and cultural sites.
community life will be better.
2. Aadde Gelchet Kebele of Elweya district community representatives’ consultation (26/06/2023)
Few of the water supply project benefits are: - Possible threats of the project Major opinions on possible mitigation or
• The project creates job opportunities for citizens. on inhabitants or the project enhancement measures of the participants are:
• Although Aadde Gelchet village established 60 area on the project itself are • Aware the community before starting
years ago, its development was lagged back due to listed below. surveying to enhance community
potable water problem and the water supply
• The up and down acceptance.
enhances the village development.
• Prevailing severe waterborne and water related topography or Gelchet • Ensuring water supply and distributions
diseases due to unsafe water sources uses will be Mountain Chain of the area systems extended to all service providers of
minimized or solved. can affect the water supply the kebele to promote serve deliveries.
• The project promotes the kebele health center and line distribution. • Land acquisition issues should be managed
school service delivery promoted. • The main transmission line by thorough discussions with community,
• The serious human health problems due to unsafe can pass through elders, religious leaders, clan leaders and
water uses for domestic purposes will be avoided or individuals farm lands, indigenous institutions before starting
minimized. • Lack of trusts on the project implementation of the project activities.
• Solves travelling about 30 kms long distance as repeated previous • Donate lands for the project construction, by
searching for water points that has been exposing
promises were not met so individual land holder.
our women for multiple problems.
• Creates job opportunities for our children.
far and the water supply • As the project issues stayed long years, it
issues delayed for the last shall start soon.
20 years. • Maximize design option to overcome the
topography problems.
3. Sarite Kebele of Elweya district community representatives’ consultation (26/06/2023)
Few of the water supply project benefits are: - Possible threats of the project Major opinions on possible mitigation or
• Solves or minimizes the prevailing severe on inhabitants or the project enhancement measures of the participants are:
waterborne and water related diseases the community area on the project itself are • Awareness creation before project start
suffer due to unsafe water sources uses. listed below. survey and then construction.
Major project benefits & participants expectations Major raised issues Opinions and responses
• Although not serious, land • Land acquisition issues should manage by
• The project promotes the kebele health center and ownership problem exists. thorough discussions with community,
school service delivery promoted. • The Gelchet Mountain Chain elders, religious leaders, clan leaders and
• The serious human health problems due to unsafe indigenous institutions before starting
topography can influence the
water uses for domestic purposes will be avoided or
water supply line implementation of the project activities.
minimized,
• Our livestock get water and their lives will be saved, distribution, and • Land ownership is not serious and should
• Creates job for our children, • Lack of trusts on the project be managed by community by donating.
• Water related health problems will be solved, and as repeated previous • As the project issues stayed long years, it
• The community will get reliable water for human promises were not met so far shall start soon.
and their livestock which are the livelihoods sources and the water supply issues • Maximize design option to overcome the
of the project area community. delayed for the last 20 years, topography problems.
Major project benefits & participants expectations Major raised issues Opinions and responses
• Prevailing severe waterborne and water related issues delayed for the last • The project shall include cattle trough for
diseases due to unsafe water sources uses will be 20 years, their livestock to protect the existing critical
minimized or solved. water shortage for livestock.
• Solves travelling long distance searching for water • Compensate cost of industrial materials such
points that has been exposing our women for as Corrugated Iron and Nails, etc. of
multiple problems. affected individual.
5. Hare Wayu Kebele of Yabello district community representatives’ consultation (27/06/2023)
The project benefits are by far greater than its possible The project stayed ideal for the Major opinions on possible mitigation or
negative impacts and few of the benefits are: - last 20 years. enhancement measures of the participants are:
• As the main livestock death of our kebele is lack of • The project crosses • Ensure community awareness of the project
water, the project solves the livestock death communal and privately before starting surveying.
problems. owned lands. • If mico-irrigation development is
• School, health center and kebele institutions service • The canal can come on considered.
delivery will be enhanced. individual residents and • Land acquisition issues should be managed
• Migration of the village communities to other areas institutions. by thorough discussions with community,
due to lack of water for human and their livestock • Minor land acquisition and elders, religious leaders, clan leaders and
will be minimized. loss issues by water indigenous institutions before project
• Avoids travelling long distance searching for water points transmission and implementation activities.
that has been exposing our women for multiple problems. distribution lines. • Substitute land from communal areas based
• Avoids the currently seen serious sanitation and on community agreement.
health problems and promotes community health. • The project shall include cattle trough for
• The community will get reliable water for human their livestock to protect the existing critical
and their livestock which are the livelihoods sources water shortage for livestock.
of the project area community. • Compensate cost of industrial materials such
as Corrugated Iron and Nails, etc. of
affected individual.
The three project districts key stakeholders’ and the project kebeles community representatives’
consultative meetings created better understanding of the Borana Resilient Water Development for
Improved Livelihoods Program (BRWDLP), Part 2 project objectives. The ESMF consultant identified that
the project areas sectors and the local communities have good attitudes and expressed project benefits,
threats and mitigation measures on possible adverse impacts they considered.
The team; a senior RPF consultant, zone Project Coordinator and the senior ESMF consultant concluded
that the stakeholders’ and community representatives’ consultations created better understanding of the
project objectives and helped in identifying their attitudes on participating in the project implementations.
The consulted officials, sector offices, experts and pastoral community representatives have got better
understanding of the project and expressed broad support of the Program, as the water supply interventions
ensures communities water supply, solve health and economic challenges faced by the communities.
The consultative meetings and discussions outputs generally attested that positive impacts of the project
outweigh the negative and the project has got full consent of the peoples of the Part 2 Project areas. The
participants were also expressed their promises to participate in the project implementation and the team
concluded that the stakes and community representatives have positive attitudes on the project. Lists of
contacted persons and minutes are annexed.
Given the nature and scale of proposed projects under the BRWDLP, Part-2 project and respective activities
over construction and operation phases, both positive and negative impacts are expected to be generated
and affect nearby biophysical and social environment. In this regard, environmental and social impacts that
could be emanated from program activities are expected to be limited. These may stem from ground
disturbance due to construction activities of water supply infrastructure, which include groundwater source
development (boreholes drilling), wellfield area water supply route (including backbone, water collection
and transmission to Simu Hilltop Reservoir, other reservoirs and last-mile connectivity), transmission and
distribution systems, which will include water mains, reservoirs and distribution networks, water
connections, macro and micro metering and pressure monitoring systems, public fountains and cattle and
camel troughs, development of pressurized and gravity Water Supply Collector, Conveyance and
distribution systems, scheme Administration Offices (office, shade, stores, garage and compound works,
auxiliaries structures at satellite offices), Livestock watering troughs and associated infrastructure for
smallholder agriculture, other auxiliaries (pump house, Generator and guardhouses. operators’ dwellings,
Manager dwellings, etc.), sanitation facilities in schools, public places like markets and health facilities,
latrine for Teachers, Girls and Boys students, public Shower Room with Septic Tanks, etc.
Moreover, other potential impacts during construction and operation periods may include health and safety
issues, air emissions, solid waste and wastewater. The stated adverse effects associated with construction
and operation phases of the proposed program will be reversible in nature and no impact is anticipated that
will lead to irreversible negative permanent change. It is foreseen that most of the projects under BRWDLP
are category 2 with the above noted typical impacts which are assessed as localized; varying from small to
moderate scale and mitigation measures could be readily designed.
In any case, all projects will be screened carefully case by case, to determine the appropriate category and
environmental safeguard instruments to manage the potential impacts, as stated in section 5 of this ESMF.
The following potential environmental and social benefits and impacts of the program components were
identified through reviewing relevant documents, comprehensive stakeholders and community
representatives’ consultation processes as well as field visits in selected locations of the project areas.
leads to a sedentary way of life (Reduce mobility for the search of water). During mobility, there are
negative consequences such as resource competition, environmental degradation, the transmission of
diseases, abandoning of farmland, incurring additional expenses, high livestock death, and ethnic conflict.
Hence, the availability of water supply for Borana people will have significant social and environmental
benefits as it alleviates the aforementioned demerits of searching water during the dry season.
Mitigation Measures
Mitigation Measures
Mitigation measures to reduce or prevent impact of land acquisition include:
• Provision of appropriate compensation to land lost and other properties,
• Land acquisition should be limited to only areas that are essential for the project activities, and
• Identify alternative road or detour where there are no residents or perennial crops.
Mitigation measures
Mitigation measures include, but not limited to:
• No clearing of vegetation shall be undertaken outside of marked areas and Limit vegetation clearing
as much as possible,
• Stabilize the soil mechanically to reduce erosion potential,
• Re-grading of slopes and re-vegetation of exposed areas,
• Use excavated materials for backfilling of the trench section around the pipes,
• Spoil earth/rock should be disposed of in appropriate approved area,
• Any tunnels or erosion channels developed during construction or maintenance period shall is
backfilled and compacted and the areas restored to a proper condition,
• Areas where construction activities have been completed and where no further disturbance would
take place are rehabilitated through re-vegetation, and
• Ground leveling is minimized and if possible concentrated only to the specific building foundation
areas when it is necessary.
• Contain all solid wastes at designated location within construction sites.
• All removal of topsoil or vegetation should be kept to minimum to prevent erosion.
• Ensure that the construction crew aware of remaining vegetation which must be conserved.
• Implement water and soil erosion conservation practices, as applicable
• Proper location of material stockpiles, especially sand and soil downwind from the commercial,
residential, and other settlements and receptors like schools and health facilities will be required.
• Frequent wetting of the stockpile and working area, and
• Screening of or providing wind breaks for stockpiles.
Mitigation Measures
The impacts can be reduced or eliminated through:
• use of biodegradable drilling fluids and mud additives;
• drain the water wells area to avoid infiltration of contaminated water;
• restore the site affected by drilling to its initial condition;
• dry drilling fluid, mix with surrounding soil and spread at site;
• construct properly as designed and ensure water tight well head and sealing of pump to well head;
• submerged pump & other equipment into each well should be disinfected at each extraction, and
• Ensure protection and safe management of hazardous materials from entering wells, etc.
Mitigation Measures
In order to control and protect impacts on such respected places:
• Aware community members proposed transmission and distribution routes,
• Collect information on such respected places on proposed alignments, and
• Consult and involve community members during survey.
community water source, Installation of sanitary water treatment facilities in workers’ camps, Contain all
solid wastes at a designated location within construction sites to avoid contamination of water sources
nearby, all removal of topsoil or vegetation should be kept to a minimum to prevent erosion that ultimately
results in sedimentation effect of the nearby water sources, collect wastes and segregate at generation site
in accordance with their types (hazardous, organic and inorganic waste), safely transport and disposed of at
the final dumping or disposal site specified and approved by the local authority to avoid any adverse impact
on health and well-being of people.
Mitigation Measures
The water pollution impacts possible mitigation measures include, but not limited to:
• Avoid unnecessary soil erosion on the community water source and at stream crossings,
• Secondary containment to collect accidental spills,
• Storage and handling of fuel should be kept away from the community water source, and
• Installation of sanitary water treatment facilities in workers’ camps.
• Contain all solid wastes at designated location within construction sites to avoid contamination of
water sources nearby.
• All removal of topsoil or vegetation should be kept to minimum to prevent erosion that ultimately
results in sedimentation effect of the nearby water sources.
• Proper location of material stockpiles, especially sand and soil downwind from the commercial,
residential, and other settlements and receptors like schools and health facilities will be required.
• Provide initial and continuous construction workforce training in handling with waste segregation
and appropriate waste disposal.
• Instruct the construction workforce to dispose spoil soils on approved fill /material disposal
locations and strictly supervise the correct placement of fill, where possible, construction materials
to be reused or recycled.
• Collect wastes and segregate at generation site in accordance with their types (hazardous, organic
and inorganic waste), safely transport and disposed of at the final dumping or disposal site specified
and approved by the local authority to avoid any adverse impact on health and well-being of people.
• Locate disposal sites in areas of land, which, prior to the commencement of the construction works,
were not used for agricultural and grazing purposes or designated for agricultural and grazing
purposes.
Mitigation Measure
Measures to be adopted to minimize dust generation during construction include:
• Intermittent roads watering during construction and machine operations;
• Limiting and controlling vehicle speeds and selecting transportation routes to minimize impacts;
• Covering or watering open disposal sites.
Mitigation Measures
• Improve environmental sanitation through availing appropriate sanitary facilities, refilling pits, and
ensure accommodation of essential sanitary facilities;
• Construction of adequate and properly located refuse disposal pits and creating awareness for the
town inhabitants on solid waste handling and disposal;
• Create awareness towards open deification and others in line with penalty, etc.
Mitigation Measures
The noise pollution impacts possible mitigation measures include, but not limited to:
• Schedule noisy activities to daytime hours,
• Locate noisy installations in adequate distance to residential areas to meet noise limit values,
• Install noise control devices in construction equipment if noise levels exceed existing guidelines
limit.
• Instruct the workforce to avoid unnecessary noise.
• All vehicle and equipment shall be turning off their engines in rest time.
• Appropriate vehicle maintenance to reduce noise emissions.
• To reduce nighttime disturbance from construction noise, that is unavoidable, the practice of
conducting construction activities should be limited between the hours of 2100 and 0600 in areas
which are within 500 meters of residences
• Ensure that all workers wear earmuffs and other personal protective gear/equipment when working
in noisy sections, and
• Equipment normally producing high levels of noise should be suppressed and screened when
working within a distance of 200 meters from any settlement, clinic, religious places or other
sensitive noise receptors.
Mitigation Measures
Impacts of solid wastes possible mitigation measures include, but not limited to:
• Ensure detailed design and specifications are undertaken so as to minimize solid waste generation
of waste during construction,
• Locate material and stockpiling areas within the project construction corridor until its ultimate
destination is determined,
• Manage stockpile areas and storage areas properly,
• Dispose non-recyclable construction materials at a licensed waste facility and avoid fly-tipping,
• Ensure used furniture and equipment from decommissioning is sold off/reused where possible,
otherwise, dispose of at an appropriately recognized landfill,
• Recycle any ballast that cannot be reused as ballast and remove excess ballast and clean fill off site
for reuse, as possible Sustainable use of resources (to reduce the consumption of resources and to
adopt recyclable materials where possible. Water systems comprise significant number of structures
and mechanical fittings),
• Optimize the water supply structures sizes to reduce the volume of construction materials used and
soils to be disposed tore recyclable waste separately from residual/non-recyclable waste, and
• Provide recycling bins around workers ‘camps, offices and amenities.
During the construction phase, noise is generated from vehicular movements, sand and aggregate
processing, concrete mixing, excavation machinery, etc. The presence of the construction workforce will
result continuous disturbance of wildlife and other fauna species. The disturbance is likely to affect wildlife
in general by triggering them to avoid or escape the project area. However, most of the animals and avian
diversity found in the project area can easily adapt the construction site and find equally suitable habitats
nearby. The construction activity and associated movements shall adhere to the rules and regulations so as
to limit vehicle speed, avoiding unnecessary noise and limiting movement of the workforces of the working
area., Posting signposts especially in and around the buffer zone of the National Park and other sensitive
habitats, etc., Create awareness campaigns and for drivers, pedestrians, community members and other
passer-by on wildlife safety, Consider the location of mature trees during site selection for the transmission
line construction and land clearing for borehole, reservoir or other project component activities, Minimize
clearing and disruption of riparian vegetation. Avoid excessive destruction of trees and other vegetation and
minimize clearing of indigenous plant species, and replanting of indigenous plant species in disturbed areas,
Enforcing speed reducing mechanisms (including limiting the vehicle speed to 20 km/hr. maximum, placing
speed bumps, rumble strips, etc. ) to avoid or minimize collisions with wildlife and speed reducing
mechanisms around the project area along the buffer zone, avoiding blowing horns in forest section,
establishing wildlife passes, animal detection system within the project area, support for local environmental
education and wildlife organizations, etc.
Mitigation Measures
Vegetation clearing impacts possible mitigation measures include, but not limited to:
• Vegetation clearing should be minimized as much as possible,
• Limit vegetation clearing for water pipelines required work strip,
• Use only indigenous plant species for re-vegetation.
• The tree planting program shall be planned and implemented with locally adoptable species in the
project areas to replace species that are likely to be affected.
• Awareness campaigns &enforcement of a worker’s code of conduct for the protection of
biodiversity, and
• Include vegetation rehabilitation techniques to recover lost plant cover such as reforestation,
afforestation, offset planting, etc.
Mitigation Measures
Impacts of population influx possible mitigation measures include, but not limited to:
• Establish transparent recruitment procedures to avoid camp followers in form of job-seekers,
• Establish a recruitment policy that gives priority to local residents for less specialized services,
• Recruitment procedures to be shared with the local authorities for further dissemination,
• Award opportunities for sub-suppliers and sub-contractors of local firms which in turn employ local
labour,
• Conduct public health campaigns addressing issues of behavioral change, water and sanitation,
COVID-19, malaria, HIV/AIDS, and
• Develop and Implement Labour Influx Management Plan.
welfare, Ensure workers’ camp standards, quality and provision of basic social services based on existing
standards, guidance on workers’ accommodation, Make an awareness campaign for workers as well as
public about the safety issues related to their activities, provide frequent training about the use of PPE to
workers, Ensure safe and good working conditions at the workplace, Enclosure the area around which work
is taking place to prevent unauthorized access, Hoisting and lifting equipment should be rated and properly
maintained, and operators trained in their use, Frequent maintenance of project vehicles and machinery to
minimize air emissions., develop and implement a Public and Occupational Health and Safety Management
Plan (POHSMP) comprises of monitoring and reporting mechanism of occupational accidents and diseases,
dangerous occurrences, and incidents Increased COVID- 19, STDs and HIV/AIDS Cases.
The project is expecting to employ project staff and casual laborers during construction. Social interactions
among staffs and with locals cannot be avoided. Considering the nature with which COVID-19 and
HIV/AIDS is contracted and spread, workers’ number is significant to make a serious contribution to
COVID-19 pandemic and other communicable diseases. The presence of monetary strength will act as a
catalyst and thus enhance such social interactions between the project workers and people of the nearby
centers. The extent of this impact is localized with a medium intensity. The impact can be highly
improved/eliminated with mitigation. The possible mitigation measures include, but not limited to:
Undertaking periodic awareness creations for the workforce on safe working practices, Promoting health
education and awareness creations, Instilling proper code of conduct and work ethics among construction
workers and ensuring that they are observed, and workers should be aware on their own safety and safety
of others, Develop a comprehensive STDS, HIV/ AIDs and COVID 19 awareness for both workers and
local community, Provision of STDs, HIV and AIDS prevention measures such as distribution of condoms
to workers/local people both male and female, Creation of awareness of STDs, HIV/AIDS, COVID 19 in
worker’s camps through training and installation of posters, Promote continuous sectoral, gender related
Information, Education and Communication (IEC) messages about HIV/AIDS, STDS, COVID 19 infection,
protection, counseling and care, Increase availability and accessibility of condoms, Establish a sectoral
policy that will safeguard human and civil rights and avoid discrimination of workers and community
members who are infected with HIV/AIDS.
Mitigation Measures
The possible mitigation measures include, but not limited to:
• Ensure compliance to occupational health and safety standards,
• Maintain safe workplaces, plant and working systems,
• Providing information, instruction and training enabling employees to work without risks,
• Consulting with employee-elected health and safety representatives and/ or other employees about
occupational health, safety and welfare,
• Ensure workers’ camp standards, quality and provision of basic social services based on existing
standards, guidance on workers’ accommodation,
• Establish workers grievance mechanisms.
• Make awareness campaign for workers about the safety issues related to their activities hence
provide frequent training about the use of PPE
• Ensure safe and good working conditions at workplace.
• Enclosure the area around which work is taking place to prevent unauthorized access.
• Hoisting and lifting equipment should be rated and properly maintained, and operators trained in
their use.
• Frequent maintenance of project vehicles and machinery to minimize air emissions.
• Reduction of engine idling time in construction sites.
• Use of extenders or other means to direct diesel exhaust away from the operator.
• The project shall develop and implement Public and Occupational Health and Safety Management
Plan (POHSMP) comprises of monitoring and reporting mechanism of occupational accidents and
diseases, dangerous occurrences and incidents.
• Undertaking periodic awareness creations for workforce on safe working practices,
• Promoting health education and awareness creations,
• Instilling proper code of conduct and work ethics among construction workers and ensure that they
are observed, and workers should be aware on their own safety and safety of others
• Develop a comprehensive STDS, HIV/ AIDs and COVID 19 awareness for both workers and local
community
• Provision of STDs, HIV and AIDS prevention measures such as distribution of condoms to
workers/local people both male and female
• Creation of awareness of STDs, HIV/AIDS, COVID 19 in worker’s camps through trainings and
installation of posters.
• Promote continuous sectoral, gender related Information, Education and Communication (IEC)
messages about HIV/AIDS, STDS, COVID 19 infection, protection, counseling and care.
• Increase availability and accessibility of condoms, and
• Establish a sectoral policy that will safeguard human and civil rights and avoid discrimination of
workers and community members who are infected with HIV/AIDS.
If children below the age of 18 are employed in construction works, it may lead to the exploitation of
children and, at the same time, it is a violation of National Law. Child labor is illegal and considered harmful
and creates psychological and social problems in the community. The Contractor is required to be non-
discriminatory regardless of race, religion, gender, age, or disability. The Contractor is also expected to
commit itself to identify group of employees or societies that need special labor-management practices
based on their diverse nature; and can give special protection, support, or execute an affirmative action in
labor-management practice.
Women always do not receive equal employment opportunities; and the contractors, in most cases, favor to
employ men rather than women, and female workers do not obtain particular attention due to their biological
and physical condition. Hence, the discrimination against women will negatively affect those women who
want to work in the proposed Part 2 project. Such discriminatory acts and lack of other employment
opportunities may force women to carry out other marginal activities and to be engaged as sex workers for
survival, which exposes them to increased risk of sexually transmitted diseases, HIV/AIDs and unwanted
pregnancies. The perceived negative impacts of the project on women include: increased risk of exposure
to sexually transmitted diseases and unwanted pregnancies; price increase of consumer goods due to the
coming of large number of work force to the area in particular will make Female Headed Households
vulnerable to economic crisis; and most construction companies prefer to employ only men, and this will
lead to unequal treatment women during employment of the construction workforce.
The construction of the project attracts the local population and in particular young people seeking
employment opportunities. It is also true that construction works generate good employment opportunities
for the local population. However, sometimes it would negatively influence and attract the young to drop
out of school. Similarly, children who are below the age of 14 might also be attracted by the availability of
employment opportunities in the locality. If children below the age of 14 are employed in the construction
works, it may lead to the exploitation of children which violates the National law. Child labor can be harmful
and create psychological and social problems in the community. The impact is low.
Mitigation Measure
The possible mitigation measures include, but not limited to:
• Management measures including proper sanitation, waste disposal facilities, awareness campaigns
for the prevention of AIDS/HIV, sexually transmitted diseases and other communicable diseases,
sensitization for health insurance will be needed at the project site.
• The reinforcement of laws on child labour, sexual harassment/prostitutions and gender equity
should be done.
• The Contractor is required to develop and implement the project’s Codes of Conduct (COC), GBV
Action Plan, Grievance Redress Mechanism (GRM) and implement accordingly throughout the
project implementation period.
• All employees attend an induction training course prior to commencing work on site to ensure they
are familiar with the Contractor’s commitments to the project’s Codes of Conduct., and other
standards, such as ESHS and OHS standards.
• Ensure that posted and distributed copies of the Contractor and individual Codes of Conduct are
translated into the appropriate language of use in the worksite areas as well as for any international
staff in their native language.
• All employees should sign the project’s ‘Individual Code of Conduct’ confirming their agreement
to comply with ESHS and OHS standards. This sets stringent standards for personal behavior by
those working on the project so as to avoid GBV, SEA, VAC, and workplace sexual harassment.
• Contractor shall enter into agreement with local recognized NGO to develop training topics and
materials on the mechanism to manage GBV, VAC, SEA, risks and carry out training on GBV,
VAC, SEA for both workers and local people as per the plan, conduct services provider mapping
in the project area, develop a clear referral pathway.
• All forms of SEA, VAC and sexual harassment are unacceptable, regardless of whether they take
place on the work site, the work site surroundings, at worker’s camps or within the local community.
Therefore, the Contractor is required to put in place administrative measures to prevent and
minimize Gender Based Violence (GBV) and Violence Against Children (VAC) with proposed
preventive and mitigation strategies.
• Develop and Implement GBV Action Plan,
• All employees, including volunteers and sub-contractors are highly encouraged to report suspected
or actual acts of SEA, VAC and sexual harassment by a fellow worker, whether in the workplace
or not. Reports must be made in accordance with project’s SEA, child sexual exploitation and abuse
and sexual harassment Allegation Procedures.
• The Contractor is required to strengthen grievance redress and other monitoring mechanisms to
ensure safe and ethical reporting systems to alert cases of GBV and VAC and assure them to access
adequate response.
• Take strict measures against children employment and managers are required to report and act to
address suspected or actual acts of GBV and/or VAC as they have a responsibility to uphold
Contractor commitments and hold their direct reports responsible.
• Contractor social safeguard specialist will monitor provision to mitigate and respond to suspected
case of GBV, VAC, and SEA in workplace.
• In case of SEA, VAC and Sexual harassment acts suspected in the workplace constitute gross
misconduct and are therefore grounds for sanctions, which may include penalties and/or termination
of employment. In addition to Contractor sanctions, legal prosecution of those who commit acts of
SEA or VAC will be pursued if appropriate.
• Prepare and implement action plan for managing GBV, SEA, VAC impact
• Work closely with local authorities to stop recommending underage children for the project
construction works.
• The GBV Action Plan shall reflect adequately
o Existing country gender diagnostics.
o Country-wide and region-specific/District data on violence against women.
o Data and/or information on cultural practices vis-à-vis women (early marriage, physical
practices);
o Existing services available from GBV Services Providers (Health care for GBV survivors,
Psychosocial support, women’s and girls’ safe spaces, justice and legal aid, referral
systems) quality, accessibility and gaps.
• The grievance mechanism shall ensure safe, confidential, non-judgmental and ethical reporting
systems on GBV, sexual abuse and child labor as well as service referral to survivors to alert cases
of prevalence and assure them to access adequate response.
Mitigation Measures
In order to eliminate or control such water supply source shortages:
• Construct access roads to access each borehole sites.
• Ensure reliable power supply sources to overcome problems on water pump stations and on the
whole water supply systems.
Mitigation measures
In order to eliminate or control the problem ensure:
• Regular follow up and monitoring of transmission and distributions lines, and
• Immediate maintenance and replacing lines whenever there are leakages.
8.1 Background
A project Environmental and Social Management Plan (ESMP) is developed to ensure that appropriate
environmental management practices are followed during the project design, construction and operation
phases. It is a key generic document that focuses on identification of impacts and respective measures to be
implemented over the program implementation phase. It ensures that the project impacts are minimized to
an acceptable level during the implementation of the project designed under the BRWDLP in general and
for these Part-2 projects of the program. Thus, ESMP becomes a document for warranting that all the
preceding analysis is used to preserve/improve the quality of the overall biophysical and socio-economic
environment within the program influence area. The general objective of the ESMP is to develop procedures
and plans to ensure that the mitigation measures will be BRWDLP out during the preconstruction,
construction, operation, and decommissioning phase of the proposed BRWDLP.
This generic ESMP serves as a pertinent instrument to guide the project proponents (OWEB) and other
implementers to develop and carry out effective mitigation measures, design, and conduct sound
environmental and social monitoring programs. The ESMP describes the probable adverse impacts, selected
management measures to bring it to an acceptable level, and timelines for implementing the defined
measures. Moreover, it plays a vital role in identifying the roles and responsibilities of each institution,
stakeholders including power developer, contractors, etc., and the required capacity-building components
for implementing parties that warrants sustainable developments of the proposed projects. In accordance
with the above objectives, the ESMP should be prepared and adopted in the following approach:
• Examine the project in terms of its major activities and identify the aspects associated with the
project construction which generate environmental impacts;
• Identify the environmental issues associated with the major activities;
• Develop mitigation measures for the aspects identified as having environmental impacts;
• Incorporate environmental mitigation measures into construction/installation and operation
schedules and activities, develop corrective actions and ensure monitoring;
• Develop further environmental provisions through a series of project Site Environmental and Social
Management Plans and procedures;
• Define the specific actions required, roles and responsibilities for these actions, the timetable for
implementation, and associated costs;
• Describe capacity building and training requirements for the implementation of the ESMP; and
• Define a proposed institutional structure to govern the implementation of the ESMP.
A project-specific ESMP will be prepared once projects under the BRWDLP are identified and that must
be integrated with the bidding document. The building blocks of an ESMP are:
• Potential adverse impacts identified and mitigation measures to be adopted, together with
conditions within which one or other measure would apply and their integration with Part 2 Project
Pre-construction, Construction/ Implementation and Operation;
• Enhancement plans for positive impacts;
• Monitoring Plan with indicators, mechanisms, frequency, locations;
• Budgetary allocations for all the above activities;
• Institutional arrangements for each activity and mitigation measures;
• Implementation schedules for each activity and its integration with the project implementation
timelines, and
• Reporting procedures, including for redressing grievances related to environmental & social issues.
The site specific ESMP would need to be prepared for specific projects as and when identified based on
ESIA. An ESMP document should include:
• Lists of all project-related activities under the program and impacts, for each stage of the
development of Projects, i.e., for the design, construction and maintenance stages;
• A list of regulatory agencies involved and their responsibilities;
• Specific remedial and monitoring measures proposed for each stage;
• A clear reporting schedule, including discussion of what to submit, to whom, and when, and
• Cost estimates and sources of funding for both one-off costs and recurring expenses for
implementation of the ESMPs.
ESMP shall deal with the construction, operations, and decommissioning stage of the project under the
BRWDLP. The extent and timing of mitigation actions should be based on the significance of the predicted
impacts. Some mitigation measures can be incorporated into the design of the project under the program
and can largely resolve the potential anticipated impacts. Other measures require an ongoing
implementation plan to ensure that proposed actions are carried out at the correct times, that environmental
and social safeguards measures such as slope protection, borrow area reclamation, are maintained, and that
prompt remedial actions are taken when the initial measures are not fully effective.
Environmental and social management activities during the implementation of the project of the BRWDLP
will be governed by the possible negative impacts associated with the program’s respective project
construction and operation activities and the corresponding mitigation measures stated under the
environmental and social impact and mitigation measures section of this ESMF. These mitigation measures
could be used as either safety, social or physical measures to avoid/mitigate the anticipated impacts on the
biophysical and social environment within and around the project area.
The Environmental, social, and safety management specification as part of the proposed project under the
BRWDLP contract document shall contain all the necessary clauses relevant to the respective projects
financed under the BRWDLP. The contract document shall be a binding legal document to be signed by
the contractor and OWEB.
Table8.1 presents an indicative environmental and social management and monitoring plan, which can be
used to adapt in the preparation of ESMP during the implementation of the proposed Projects under the
BRWDLP, Part-2 Project. A summary of the likely issues and potential impacts & mitigation measures is
presented in the following Table7.8 to guide the preparation of upcoming ESMPs as more projects get
identified. The generic ESMP is only a guideline document and would require addressing the program
activities anticipated impacts & proposing mitigation measures. A template for the preparation of ESMP is
annexed to this ESMF (See Annex-4).
Vegetation • Vegetation clearing should be minimized as Construction Contractor Included in the Included in the
clearing much as possible, Phase construction construction cost
• Limit vegetation clearing for water pipelines cost (contract (contract
required work strip, and requirement) requirement)
• Use only indigenous plant species for re-
vegetation.
Impacts on • Schedule noisy activities to daytime hours, & Construction Contractors Included in the Included in the
Terrestrial Fauna • Instruct the workforce to avoid unnecessary phase construction construction cost
noises. cost (contract) (contract)
Construction Phase - Socioeconomic Environment
Population influx • Establish transparent recruitment procedures Pre-construction Project Included in the Included in the
to avoid camp followers in form of job- and construction Owner/ construction construction cost
seekers, phase Contractors cost (contract) (contract
• Establish a recruitment policy that gives requirement)
Project Owner
priority to local residents for less specialized
services, Owner’s cost -
part of public
Operation phase
Impacts on water • Ensure early start of the project’s sanitation Operation Phase Proponent Part of
and Sanitation component to cater for influx of workers and Community
Facilities job seekers, and health &safety
• Provide sufficient water supply & sanitation
facilities to workers at all work sites. 2,022,882.00 36,600.00 USD
Inefficient Pump • Change the damaged pumps as soon as Operation phase Proponent Operation Operation budget
Service Impacts possible and if not changed, maintain and all or the water budget
pumps should work as per their design supply
capacities. Office
• Give especial attention on pump types,
capacity and originality during purchase.
The environmental and social monitoring program is an important tool for the monitoring process of
environmental and social management activities of Part 2 of the wider program as it provides basis for
rational management decisions regarding impacts control. In this water supply program, the environmental
and social monitoring plan helps to ensure that the proposed mitigation measures for identified impacts and
risks are being implemented effectively and fix issues as designed for. The environmental and social
monitoring parameters, processes and activities discussed under this plan are indicative and help to be used
as a guide during the development of the monitoring plan for future proposed Part 2 Projects under the
wider BRWDLP.
• Review of the Contractor’s plans, method statements, temporary works designs, and arrangements
relating to obtaining necessary approvals from the Supervisor Engineer, so as to ensure that
environmental and social protection measures specified in the contract documents are adopted and
that the Contractor’s proposals provide an acceptable level of impact control, and
• Systematic observation on a day-to-day basis of all site activities and the Contractor’s offsite
facilities including quarry and borrow areas, as a check that the contract requirements relating to
environmental and social matters are being complied with and that no impacts foreseen and
unforeseen are occurring.
Monitoring is the long-term process that normally begins at the start of the program and should continue
throughout the life of the program. Its purpose is to establish benchmarks so that the nature and magnitude
of anticipated environmental and social impacts are continually assessed. Therefore, monitoring involves
the continuous or periodic review of mitigation activities to determine their effectiveness. Consequently,
trends in environmental degradation or recovery can be established and previously unforeseen impacts can
be identified and dealt with during the project's life.
This section discusses the need for programs covering both internal and periodic external monitoring. The
overall objective of environmental and social monitoring is, therefore, to ensure that mitigation and
enhancement measures should be implemented effectively. Indicative activities and indicators that have
been possibly recommended for the monitoring of the environmental and social management activities are
presented in the below Environmental and Social Monitoring Plan (Table8.1).
The Environmental and Social Monitoring will be carried out for each future project under the program in
order to ensure that all construction activities comply and adhere to environmental provisions and standard
specifications of the Environmental Protection Authority of the country as well as the AfDB Operational
Safeguards so that all mitigation measures are implemented timely and effectively. Such monitoring can
act as an early warning system to management, providing feedback mechanisms to enable damaging
practices to be altered.
The monitoring activities should be fully integrated with other construction supervision and monitoring
activities to be carried out by the construction supervision consultant. The primary responsibility of
ensuring the implementation of sound environmental and social monitoring will rests on Supervision
Engineer (SE), as part of his duties connected with general site supervision. Actual monitoring on a day-
to-day basis will be carried out by the site staff from the construction supervision consultant, under the
direction of the SE. The majority of monitoring will comprise visual observations and will be carried out at
the same time together with the engineering monitoring activities.
A proposed project under the BRWDLP Monitoring Plans will be included in the respective ESMP
specifying the type of monitoring, who will do it, how much it will cost to carry out monitoring, and what
other inputs, such as training, are necessary. Environmental and social monitoring which will be required
to be designed for the future subproject under the program by the respective proponent will focus on the
activities and/or mitigation measures prescribed for the identified environmental and social impacts in the
subproject ESIA/ESMP. Specifically, the monitoring process will include:
• Selection of environmental and social parameters at specific locations and for specific
environmental components, in line with the Program’s respective project ESMPs;
• Visual observations of impacts on environmental and social components;
This chapter sets out requirements for monitoring, evaluation, annual audit, and reporting of this ESMF
implementation. Monitoring of the indicators set out here will be mainstreamed into the overall monitoring
and evaluation system for the project.
10.1 Monitoring
Monitoring is a continuing process throughout the life of the proposed BRWDLP from subproject design
and construction phases, up to operation and decommissioning phases. Its purpose is to establish
benchmarks so that the nature and magnitude of anticipated environmental and social impacts emanated
from subproject activities under BRWDLP can be continually assessed ensuring the achievement of the
ESMF objectives. Monitoring of ESMF as a continuous activity during the proposed program
implementations and/or periodic review as annual monitoring/auditing is used to determine and guarantee
the effectiveness of ESMF measures and procedures. The requirements for monitoring ESMF
implementation are discussed below.
The objectives of ESMF monitoring are:
i) To alert the Program implementer (OWEB) and other relevant counterparts of the program (MoWE,
REA, etc.) by providing timely information about the success or otherwise of the environmental and
social impact management process outlined in this ESMF in such a manner that changes can be made
as required to ensure continuous improvement to proposed program environmental and social
management process (even beyond the project’s life).
ii) To make a final evaluation that helps to determine whether the mitigation measures incorporated into
the technical designs and the project ESMPs have been successfully annexed in the contract
document and implemented. In addition to ensuring the pre-project environmental and social settings
have been restored, improved upon, or if worse than before, to determine what level and type of
further mitigation measures are required.
A number of indicators are presented below as part of the ESMF implementation which will be included in
the overall project monitoring. In addition, an Annual Audit of ESMF Implementation will be conducted
by the OWEB, and other relevant program implementing entities (MoWE), and the report will be delivered
to the REPA, and the AfDB. Any High or substantial-Risk project financed by BRWDLP that has been
subject to an ESIA study will also be required to produce an annual audit report, for delivery to REPA, and
the AfDB. Indicators which will be used during monitoring of the performance of ESMF implementation
include:
• Number of field appraisals conducted;
• Number of ESIA/ESMPs, RAPs and other MSIPs developed;
• Number of written warnings of violations of ESMPs issued to subproject contractors in case of non-
compliance;
• Number of recommendations from the AfDB missions, an annual audit/review that has been
implemented at the beginning of the following year and Quarterly performance monitoring report;
• Number of staff at all levels trained in the implementation of this ESMF;
• Number of chances find procedures for physical cultural resources invoked, if applicable; and,
• Number of staff and other stakeholders at all levels attending a training course, raising awareness
and sensitization program in environmental and social policies and safeguards instruments, ESMF,
RAP, ESMP, ESIA, and other MSIPs.
The indicators are deliberately very simple. Despite their simplicity, the integration of these indicators into
the proposed project planning and its subprojects M and E system provides a guarantee that the ESMF will
be implemented in full.
The suggested annual report template for a Project is depicted in Annex-9. OWEB must submit the annual
audit report to REPA, and the AfDB on time.
To monitor the progress of the implementation of the measures that have been identified in this ESMF,
annual audit/reviews will be carried out as outlined in Annex-8. The principal output of the annual
Audit/reviews is a comprehensive report that documents the Audit/review methodology, summarizes the
results, and provides practical recommendations and more specifically a section referring to the overall
ESMF performance, and mitigation measures, etc. Annexes should provide the detailed results of the
fieldwork and summarize the number of approved projects by the respective national and regional teams
and their characteristics according to the annual audit report format (see Annex-9).
During the implementation of the Project, reports mainly originate from the Supervision Engineer (SE) on
the day-to-day progress of the works. The SE submits reports to the Project office for their follow-up and
review and comments on the reports and subsequently, the project office will submit copies of reports to
the OWEB for action, as applicable. The feedback of reports from the Project office, OWEB should be
provided to the SE within the time stipulated in the contract document. OWEB will also submit copies of
reports to the AfDB. To ensure early detection of critical environmental and social conditions and to provide
information on the mitigation progress and results, reporting deadlines have been specified in the ESMF
implementation schedule.
OWEB, who undertakes program implementation, shall establish a platform for coordination among
stakeholders to strengthen and improve efficiency and transparency of execution of the planned project
activities, which is supported by the Constitution and other proclamations of the country.
It is also a plan within the wider BRWDLP implementation, to improve consultation for the most vulnerable
groups and their communities so that they could benefit even more from program’s activities. More
effective use can be made of women’s groups, youth groups, and community conversations targeting
women, traditional leaders and other vulnerable groups. Involving these groups, with meaningful
representation and participation in public forums will be endorsed as part of program implementation.
• Include attitudes of program affected community and officials so that their views and proposals are
mainstreamed to formulate mitigation and benefit enhancement measures;
• Create a sense of concerns, priorities and aspirations of stakeholders and implementing parties as
they implement the proposed measures and actions;
• Increase public awareness and understanding of the program and ensure its acceptance; and
• Inform relevant authorities the program impacts, solicit their views on the program and discuss
their share of responsibility for smooth functioning of the overall projects’ activities.
Different institutions and stakeholders at the National, Regional, District, and Local levels will be
responsible and play roles during the project design and implementation under the Part 2 Project of the
wider BRWDLP. It should, however, be noted that the degree of influence of various actors does vary both
in terms of the spatial and temporal dimensions. The different actors expected to be the major players during
the design and implementation of the project as well as the implementation of this ESMF are the Ministry
of Water and Energy (MoWE), the Federal Environmental Protection Authority (EPA), the Oromia
Regional State Water and Energy Bureau (OWEB), the Oromia Regional State Environmental Protection
Authority (REPA).
At zone and district levels, the respective water and energy offices and Environmental Protection
Authorities will be responsible for the implementation of the Part 2 Project. In addition, the Community
members, Contractor, Supervision Engineer (SE) and other stakeholders like NGOs will have direct and
indirect responsibility for the sound implementation of projects under the Part 2 Project of the program.
At regional level, the Oromia Regional State Water and Energy Bureau (OWEB), as the Part 2 and the
wider BRWDL program implementer will be the main responsible for the implementation of this ESMF.
As regulatory body and main environmental protection responsible body, the Oromia Environmental
Protection Authority (OEPA) is responsible to protect, manage and control environmental and social
impacts of the Part-2 projects and the wider BRWDLP future undertakings based on roles and
responsibilities given by EPA Proclamation No.295/2002 for each National Regional States and also the
Oromia Region EPA latest EIA guideline and Environmental Audit directive regional Proclamations No.
05/ 2014 (E.C) and Proclamation No. 06/2014 (E.C) respectively for ensuring sound implementation of the
environmental and social risk management measures as well the program compliance to the regional
environmental policy and legal framework.
development activities within the scope of the program. The Directorate is also responsible to ensure the
enactment of environmental and social safeguards legal frameworks and adequate care has been taken by
the OWEB at all Parts of the Project and the wider program execution. Concerning the Part 2 Project and
the wider BRWDLP, the Ministry is responsible to check and oversee the program activities’ compliance
with the environmental and social safeguards policies of the country, through the ECCD. Major
responsibilities, but are not limited to:
• Establishes and leads steering committee at the federal level pertaining to the wider BRWDLP.
• Provides training and undergoes awareness-raising campaigns through various forms of media and
other means.
• Provides overall technical support/assistance for projects under the proposed program,
• Review and provide comments on the safeguard instruments prepared for the proposed program
• Oversee all the environmental and social activities related to the project, and
• Collects reports from OWEB and closely works with them for the successful implementation of the
program.
The Authority has the following powers and duties of which the major once are outlined as follows.
• Coordinate activities to ensure that the environmental objectives provided under the Constitution
and the basic principles set out in the Environmental Policy of the Country are realized.
• Establish a system and follow up implementation for undertaking environmental impact assessment
or strategic environmental assessment on social and economic development policies, strategies,
laws, programs, and project set by the government or Private.
• Prepare a mechanism that promotes social, economic, and environmental justice and channel the
major part of the benefit derived thereof to the affected communities to reduce emissions of
greenhouse gases that would otherwise have resulted from deforestation and forest degradation.
• Coordinate actions on soliciting the resources required for building a climate-resilient green
economy in all sectors and at all regional levels; as well as provide capacity building support and
advisory services.
• Establish a system for evaluating and decision making, in accordance with the Environmental
Impact Assessment Proclamation, the impacts of implementation of investment programs and
projects on the environment prior to approvals of their implementation by the concerned sectoral
licensing organ or the concerned regional organ.
• Prepare programs and directives for the synergistic implementation and follow up of environmental
agreements ratified by Ethiopia pertaining to the natural resources base, desertification, forests,
hazardous chemicals, industrial wastes, and anthropogenic environmental hazards with the
objective of avoiding overlaps, wastage of resources, and gaps during their implementation in all
sectors and at all governance levels.
• Take part in the negotiations of international environmental and climate change agreements and, as
appropriate, initiate a process of their ratification; play a key role in coordinating the nationwide
responses to the agreements.
• Coordinate, and as may be appropriate, carry out research and technology transfer activities that
promote the sustainability of the environment and the conservation and use of the forest as well as
the equitable sharing of benefits accruing from them while creating opportunities for green jobs.
• Establish a system for development and utilization of small and large-scale forests including
bamboo in private, communal, and watershed areas, and ensure implementation of same.
• Establish a system to rehabilitate degraded forest lands and ensure its implementation to enhance
their environmental and economic benefits.
• Designate focal staffs (at least 2 in each region and in the two city administrations) that will take
responsibility for environmental screening and generally for environmental management and get
trained accordingly- this staff will ultimately prepare Environmental and Social Screening Forms
and supervise the implementation by contractors of the Environmental Guidelines for Construction
Contractors
• Designate technical supervisor of works, who, in the absence of the environmental focal staff
mentioned above, will supervise the implementation by contractors of the Environmental
Guidelines for Construction Contractors,
• Prepare (see above) environmental screening forms for all sub-programs and submit them to the
Ministry of Water and Energy and to the African Development Bank,
• Supervise the implementation of environmental mitigation measures at construction and operation
phases, including those related to land occupation and compensation
• Supervise the implementation of monitoring measures
• Provide an annual environmental monitoring report to the review of the Ministry of Water and
Energy
The Project Implementation Unit (PIU) to be established under the OWEB, which will be staffed with E&S
risk management specialists, will be directly responsible for the ESMF implementation for projects under
the program and it will be supported as necessary by the existing Environment department of OWEB or
otherwise ECCD of the MoWE. During the course of ESMF implementation, the reporting arrangement for
Environmental and Social Performance will follow the ESMF, which MoWEB -PIU will prepare and
submit regular E and S performance reports for all the projects under the program.
In the light of this, the Oromia environmental line sector is structured under the Regional Council. The
regional environmental body is entitled to coordinate the formulation, implementation, review, and revision
of regional conservation strategies, as also environmental monitoring, protection, and regulation. The
proclamation also states that regional environmental agencies shall ensure implementation of federal
environmental standards or as may be appropriate, issue and implement their own no less stringent
standards.
As this Part 2 Project influences three districts in Borana Zone; Oromia REPA is responsible for
environmental protection matters in the region together with zonal level line sectors. REPA is responsible
for the review and approval of ESIA of development proposals under the mandate of the Federal State and
follow-up of the implementation of ESIA recommendations of such proposals. Hence, the project proponent
(OWEB) should work in close cooperation with the environmental bodies (At the Region and Zonal level)
to ensure that the adverse environmental and social risks of development proposals are properly identified
and their mitigation or management actions incorporated into the project design under the program or
planning and implementation at the right time.
12.8 Contractor
Contractor is responsible to incorporate environmental and social safeguards management measures stated
under the Part-2 Project ESMP. The pertinent information from the ESMP will be included in the project
contract under the environmental and social clauses and the ESMP document will be annexed and part of
the bidding and contract agreement document. The contractor will also require preparing contractor’s
Environmental and Social Management Plan (CESMP) in line with the recommendations of respective
project ESIA and ESMP. The Contractor is accountable for implementation of these instruments (CESMP,
ESMP and ESIA) and is required to establish an EHS unit staffed with qualified environmental and/ or
social safeguards specialists. After preparing the ESMPs it needs to be approved by the Supervision
Engineers and submitted to the Bank of clearance and public disclosure before starting physical activities.
OWEB shall also provide training and undergoes awareness-raising campaigns on safeguards management
for crew members and the staff.
adequate inclusion of implementations of the environmental and social safeguards clauses in the contract
document and the corresponding supervisory responsibility to confirm sound implementation of all sites’
environmental and social management and monitoring recommendations. The SE approves or rejects
proposals and undertakings of the contractor in relation to the requirements of the contract documents.
Districts generally comprise, sub units called kebeles and is headed by an elected chairman. The main
responsibilities of Kebele administrations include:
• Preparation of an annual Kebele development plan, ensuring collection of land and agricultural
income tax;
• Organizing local labor and in-kind contributions for development activities;
• Resolving conflicts within the community through the social courts, and
• Regarding this specific proposed project where the power line runs through districts and kebeles
will have a great role and interest in the implementation of the project.
The institutional responsibilities of the project areas districts are listed as follows.
• Assist the OWEB-PIU and the water office at the district level in the implementation of the
program.
• Establish a task force/steering committee at the district level.
• Organize the District taskforce/steering committee and chair the meeting related to the
implementation of the programs; and,
• In cases of land expropriation, facilitate the process of valuation and compensation committee
meetings and payment of compensation, and
12.11 Community
Communities of the project areas have the right to be consulted to ensure the overall project acceptability
and sustainable implementation of the Part 2 Project of the program. In general, the community should be
involved at different stages of the Project.
cultural resources. Each project districts culture and Tourism offices involve in protection of cultural
heritage sites in the project areas based on the Authority for Research and Conservation of Cultural Heritage
(ARCCH) and the region rules and regulations.
12.13 Consultants
Consultants have the following roles and responsibilities, but not limited to.
• Supervision and manage all the sites with regard to the administration of the Construction Contracts
including E&S management compliance,
• Review and approve contractor ESMP and other plans,
• Ensure the contractor obtains all the required permits,
• Ensure contractors compliance with the ESIA/ESMP etc. and other laws and regulations,
• Responsible for approvals of the construction materials to be used in the project,
• Responsible for ensuring that, all the proposed construction activities and the associated facilities
are constructed in accordance with the approved designs and contract documents,
• Undertake supervision and monitoring of environmental and social issues and report back to the
Client,
• Clear contractors’ compliance with managing environment and social risks, and
• Provide information to the Client related to HSE performance, and immediately report any
significant environmental incident or worker accident.
13.1 General
Effective implementation of the Environmental and Social Management Framework requires technical
capacity of implementing institutions and there is a need to have people with the right skills and knowledge.
The ESMF success depends on effective capacity building through the training of staff and all other parties
involved in this ESMF, including construction contractor and all subcontractors. Project implementing
bodies need to understand inherent social and environmental issues and values of the proposed Part 2 Project
under the BRWDLP and be able to identify indicators. The suggestions on training and capacity
development requirements under this section are based on observations on similar programs and projects
and consultations, which were conducted as part of the preparation of this ESMF.
All those responsible for management, implementation and operation of any aspect of this ESMF shall be
adequately trained in their role. In addition, before an individual is allowed to work, he/she must be trained
on the program’s E&S needs. During contract, this shall be both assessed and audited regularly, and if
identified corrective measures shall be put into place. It is therefore proposed that a comprehensive
induction and training program is established that prepares the employees for working on the job.
This chapter also sets out training and capacity building that is required to support the implementation of
this ESMF. It states training and capacity development requirement for OWEB, MoWE and other relevant
parties' staff at all levels, who are directly or indirectly engaged in the proposed program implementation.
This capacity development and training plan support implementing institution, OWEB, to develop its
capacity to sufficiently screen, monitor, evaluate, and assess the environmental and social impact of the
Part 2 Project of the wider BRWDLP and any future proposed project under the program.
Lessons learnt from other similar water supply projects of the Oromia Water and Energy Bureau and
preliminary capacity needs assessments undertaken during project preparation and appraisal can suggest
and taken as startup step for significant shortcoming in capacities of Regional Water and Energy Bureau,
Borana Zone Water and Energy and the Part 2 Project of the program district offices water supply officers
to effectively implement the ESMF.
Accordingly, the Borana Resilient Water Development for Improved Livelihoods Program (BRWDILP)
Part 2 Project will: (i) conduct capacity assessment of each district implementing bodies at each level
(district and kebele) to take inventory of existing capacity and identify gaps and (ii) based on the findings
of the assessments tailored capacity building packages that need be provided.
Capacity building and technical assistance for appointed safeguard staffs will be valuable in strengthening
their skills to screen, review and monitor environmental issues in the sub-projects in compliance with
requirements of the Ethiopia’s legislations and the AfDB safeguard policies. The capacity building Program
is also important in relation to development of general environmental management and monitoring
capabilities within the Region.
13.3 Training
In many institutions, staff members have been retained for core activities of their profession whereas little
consideration to directly oversee environmental and social risk management activities has been taken. In
some cases, environment and social safeguards personnel are present but their level of training and technical
capacity on environmental and social safeguards principles and tools is not sufficient. Training and
awareness creation will be undertaken at different levels of project implementation. As stated above, these
levels will entail the national institutions, local authorities, contractors, Consultants, NGOs, community
members, and other grassroots stakeholders. The exercise will be customized according to each level's
needs to ensure adequacy in the implementation of the ESMF and therefore, it is required to indicate detailed
capacity development requirements and recommendations in this ESMF, through customizing several water
and other infrastructure development projects experiences to identify the capacity gap and propose project-
specific training and other capacity development program.
The OWEB-PIU safeguards specialists will require induction training on AfDB and GoE environmental
and social safeguards policies, applicable to the Part 2 Project of the wider BRWDLP, regarding use of
screening and other pertinent checklists, identification of impacts and development and implementation of
relevant safeguards instruments. Annual follow-up training is anticipated. The training will take place in
areas accessible to all participants at national, regional, and/or local levels, as applicable.
Therefore, to ensure proper implementation of environmental and social screening and mitigation measures,
as well as implementation of subprojects in a sustainable manner, OWEB and other relevant respective
project proponents, if applicable will undertake the project environmental and social safeguards
management training and institutional capacity building. The objectives of the training stated under this
ESMF are to:
• Ensure that staff from OWEB, MoWE and other relevant institutions can assist zone and project
districts staffs at local level, contractors and communities to appraise and supervise
implementation of subprojects;
• Representatives and leaders of community members, institutions and associations at local levels
to prioritize their needs to participate in identification of impacts and implementation and
management of the environmental and social risks of the Part 2 Project activities, and
• Support local representatives and relevant committees to have sensitization and awareness
regarding environmental and social aspects indicated in safeguards instruments such as ESIA,
ESMP, ESMF, RPF and RAP and other relevant management strategies implementation plans and
implementations of these instruments that ultimately contribute to ensuring implementation of the
program in an environmentally friendly and socially acceptable manner.
The anticipated capacity building demand of various stakeholders, experts and officials relevant to the
implementation of this ESMF will be managed in terms of technical training, awareness creation and
sensitization for those who will be drawn from the following institutions, but not limited to:
• Environmental and Social Experts of implementing institutions OWEB, Oromia EPA, MoWE and
other pertinent parties;
• Relevant experts and officials from Borana Zone (Water Boards Utility) and project districts Water
and Energy Offices and districts Environmental Protection Authorities;
• Project districts office relevant experts and officials; and
• Representatives from community members, clan leaders, elders, etc.
The first step in pursuing capacity building will be to identify capacity building needs of various
stakeholders. However, in addition to the needs identified, an indicative list of areas of training relevant to
the implementation of this ESMF has been proposed which includes:
• National and AfDB Operational Safeguard as well as implementation and enforcement;
• Project cycle and ESIA/ ESMF (including E&S clauses in the project under the program contracts),
national EIA law, procedures, guidelines and enforcing mechanisms;
• Stakeholder engagement, consultation and partnerships;
• Application of ESMF tools (Screening checklists, ESIA/ESMP), ESIA process, ESIA review,
implementation, assignment of environmental categories and enforcement
• Environmental guidelines applicable to construction contractors,
• Environmental monitoring and evaluation in the context of Borana Resilient Water Development
for Improved Livelihoods Program;
• Mitigation measures and Environmental and Social Management Plans (ESMPs) development,
RAP and other instruments such as Labor laws and working conditions (LLWC); Biodiversity
conservation (BC); Waste Management Plan (WMP) including Medical and Hazardous Waste
Management Plan; Grievance Redress Mechanism; Stakeholder engagement and Public and
Occupational Safety and Health Plan (POHSP), and
• Environmental reporting, monitoring, annual auditing and follow-up of ESMF, etc.
Indicative specific training requirements for respective stakeholders under different categories can be:
1) Technical training (T)-In-depth training to a level that allows trainees to go on to train others,
including technical procedures where relevant;
2) Sensitization (S) in which the trainees become familiar with the issues to a sufficient extent that it
allows them to demand their precise requirements for further technical assistance; and
Training for safeguards officers and other relevant staff drawn from OWEB, MoWE and other institutions
and parties, etc. will be required both on general environmental and social safeguards issues, on the specific
screening procedures and on impact identification and mitigating measures described in this ESMF. Initial
as well as on job and annual follow-up training is also anticipated. The training will provide good
opportunity to conduct required monitoring and evaluation of performance of the project.
Key: T = detailed training, S = sensitization to the issues, A = raised awareness, NA=not applicable
As a general guideline, training, awareness creation and sensitization of environmental and social experts,
officials from relevant stakeholders (OWEB, MoWE, REPA, etc.) at the national, regional, zonal and
district levels, and community members and affected groups on issues of environmental and social impacts
are required. The sensitization or awareness/training will aim to build capacity, create awareness, and
sensitize on the requirements and key aspects of ESMF for a broad audience comprises of experts and
officials from various implementing institutions listed above. In addition, a more detailed and specific
training module will be developed and delivered to OWEB and other direct implementing parties who are
responsible and involved in the implementation of E&S safeguards and implementation of the proposed
program. The project will develop a training plan based on needs identified that includes regular updates
and refresher modules which will be delivered during ESMF implementation. Table13.2 below indicated
proposed training package.
An example of an agenda for a proposed one (1) day training on ESMF implementation and integration of
environment and social management concerns into development planning, which is further amended before
implementation of the training & during preparation of the training plan is provided in Table13-3.
The training will be conducted by OWEB, REPA, Consultant, district environmental offices, Ministry
responsible for Gender, Ministry of Labor (Department of Occupational Health and Safety), etc. The
training activities in Environmental and Social Impact Assessment including environmental project
screening and implementation of ESMF can be conducted by OWEB, REPA, other program proponents, or
Consultants. This will be done before implementation of the project, to apply knowledge/skills during
implementations of the projects. Skills in the screening process will be very useful for assessing
environmental implications of the Project activities at the outset.
Budget requirement is estimated as presented in Table 13.4 that shall be updated by OWEB project
implementing unit (PIU) and relevant experts of the bureau. Contingency is included to cater for training
of new staff from OWEB and other E&S for various relevant water and environment offices at region, zone
and project districts as required on occasions where the first appointed team member has resigned and for
re-training of non-performers.
* Inclusive of participants' transport and per Diems and, if applicable, trainers' (regional water experts and
in the case of initial training of District water team members transport and per Diems.
** The lump sum cost which will be described later during preparation of training proposals should also
include costs of stationery materials, handouts, refreshments, and if there are costs for facilitators.
At the national level, the training activities in Environmental and Social Impact Assessment including
environmental project screening and implementation of ESMF can be conducted by Federal Environmental
Protection Authority (EPA) or private consultant/s under supervision of OWEB with the support of the
MoWE. This will have to be done before implementation of the project so as to apply the knowledge/skills
during implementation of the projects. Skills in screening process will be very useful for assessing the
environmental implications of the Project activities at the outset.
Tasks: Major tasks of the E&S safeguards specialists will be, but not limited to:
• Coordinate and support the system of E&S screening, review and approval process set out in this
ESMF and oversee its smooth implementation including advice to partner and beneficiary
institutions on the procurement of consultants for any required ESIA studies and other E&S
safeguards instruments;
• Liaise with the Federal and Regional environmental protection offices (EPA and REPA) on regular
basis to support implementations of this updated ESMF;
• Ensure ESIAs/ESMPs are carried out, as required, to meet the National and AfDB requirements;
• Develop training plan and lead delivery of capacity building programs on project environmental
and social risk and impacts management for lead and partner implementing institutions as well as
beneficiary and other stakeholders;
• Provide technical advice and support to beneficiary institutions on all technical issues related to
natural resources and environmental and social risk management. These issues will relate to
impacts on surface water, groundwater, biodiversity, natural habitats, soil, vegetation, human safety
and health, ecology and protected areas, land and soil degradation;
• Organize training workshops to raise awareness among officials of project implementation parties
and stakeholder institutions, technical and management officers;
• Liaise with the project beneficiary and stakeholder institutions to ensure the project’s compliance
with the ESMF, RAP, ESMP and all resettlement aspects of the project;
• Liaise with the project beneficiary and stakeholder institutions to ensure gender mainstreaming,
GBV action plan implementation, GRM and Stakeholder Engagement Plan (SEP), WMP, etc.;
• Provide specific technical advice on mitigation measures for subprojects as necessary;
• Spearhead/coordinate commissioning of an independent consulting firm to carry out an
environmental and social safeguards implementation performance audit of the projects under the
Part 2 of the wider BRWDLP on an annual basis;
• Undertake review of ESIA/ESMP/RAP to ensure compliance with ESMF and national and AfDB
environmental policies and in collaboration with the appropriate bodies initiate and carry out
periodic environmental and social monitoring and inspection on selected subprojects, and
• Compile and submit quarterly, biannual and annual E&S performance reports of the Part 2 project
under BRWDLP to the OWEB, MoWE, REPA, EPA, as appropriate.
Consultant Qualifications
Selected Consultant at least should meet the following minimum requirements.
• At least Master’s degree in environmental and social management disciplines. Such as
Environmental Sciences, Environmental Planning and Management, Development/Social Study,
Project Planning and Management or related environmental and social discipline from a reputable
University with about at least 8 years work experience.
• Must registered be registered a senior or lead Expert with Environmental Protection Authority and
must possess a valid and Practicing License in senior level.
• A minimum of five (5) years of relevant professional experience in environment and social
auditing. Experience in the broad areas of environmental and social assessment and in environment
management and monitoring, is an advantage.
• Have good knowledge of environment and social safeguard policies and land management
regulations, ESIAs, ESMPs, RAP of projects. Understands AfDBs and ADF best practices and/or
guidelines and procedures on environmental and social safeguards, social assessment, social
analysis, effective stakeholder participation and complaint resolution systems and regulations and
legal frameworks governing environmental and social management.
• Experience in auditing implementation of ESIAs, ESMPs, RAP of projects.
• Experience of designing and implementing M&E plans and activities (both qualitative and
quantitative) and generating projects monitoring and evaluation reports.
• Experience of assessing and developing approaches to manage risks and their impacts.
• Strong numerical and analytical skills and strong research techniques and skills.
• Computer literacy in standard software such as Microsoft Office (Word, Excel, Access,
PowerPoint, Outlook, etc.) and statistical package (SPSS, STATA).
• Resilience, flexibility and professional integrity, including ability to maintain constructive
approach to work and interpersonal dealings particularly during times of pressure and on sensitive
issues.
• Excellent oral and written communication skills in English language to deliver presentations and
reports.
• Ability to work and deliver results in an environment with multiple and challenging tasks.
• High level of integrity, confidentiality in handling public resources, highly motivated, innovative
and a committed team player.
• Good understanding of structure and organization of environmental protection agencies and other
environmental regulatory bodies in project areas and villages.
• Ability of creative and innovative techniques for planning and auditing environmental and social
management policies.
• Experience in project host country would be an added advantage, and
• Duration of preparing Environmental and Compliance report shall be determined or possible shall
not exceed 60 working days. .
This section of the ESMF describes processes for ensuring that environmental and social concerns are
adequately addressed through institutional arrangements and procedures used by the program for the
identification, preparation, approval and implementation of projects. This section sets out schedules for
ESMF implementation adherence to the program implementation period.
To comply with various technical and performance standards, the proposed Part 2 project activities to be
supported under BRWDLP shall comply with this Environmental and Social Management Framework. The
implementation, monitoring and reporting arrangements for the ESMF have been worked out within the
overall institutional structure for the implementation of the proposed part of the program. The indicative
implementation schedule for the ESMF, which will be further amended before project implementation is
outlined in Table14.1 and takes into account all activities related to the proposed measures (enhancement
and mitigation), the monitoring program, consultations and institutional arrangements.
The summary of the estimated budget requirement for the implementation of this ESMF is provided in
Table15.1 below. The environmental and social management cost is not included in the ESMF budget, as
it will be covered directly or indirectly by the respective subproject budget, i.e., through allocation for
project’s administrative and logistical expenses or through inclusions of cost for E&S management and
mitigating measures in the subproject contracts documents.
Based on the nature of the proposed project sites of the program, significance and scale of anticipated
impacts to be identified during screening of each project, site-specific ESMPs (MSIPs) will be prepared.
This ESMP will use information and template stated under the environmental and social impacts,
management and monitoring sections of this ESMF. Recruitment of environmental and social specialists or
consideration of other alternative means is required to develop site-specific Environmental and Social
Management Plans (ESMPs) for all Part 2 Projects under the program. An independent consultant is also
required for a period of at least one month to undertake an annual environmental and social audit that will
be mainstreamed within the scope of the Program’s Annual Audit.
Budgets for capacity building, training as well as Recruitment of safeguards specialists, annual audit and
end of project evaluation and others with 10% contingency is estimated at 244,847 USD or Birr
13,532,693.69 (based on exchange rate of 1 USD=55.27) as detailed in Table15.1 below.
The budget is estimate actual budget will be determined during implementation phase when specific number
of people required for training will be identified and level of technical assistance required known.
Grievance redressing mechanism (GRM) is designed in view of the fact that Part 2 Project of the wider
BRWDLP program activities may upset the existing balance in society. The resettlement operation will
touch upon property issues, means of livelihood and organization of social and spatial aspects that influence
proximity to a set of environmental, economic, social and spiritual assets. Therefore, grievance redressing
system has been designed in such a way that it functions in a flexible manner and the implementing agency
has to incline to a pro-poor approach in all its decisions. The GRM will have a working place and adequate
budget for implementation.
Grievances will be actively managed and tracked to ensure that appropriate resolution and actions are taken.
A clear time schedule will be defined for resolving grievances, ensuring that they are addressed in an
appropriate and timely manner, with corrective actions being implemented if appropriate and the
complainant being informed of the outcome.
The purpose of the Grievance redressing mechanism is to establish a way for individuals, groups, or
communities affected by the program activities to contact responsible body if having an enquiry, a concern,
or a formal complaint. Grievance handling mechanism should address affected persons’ concerns and
complaints promptly, using an understandable and transparent process that is gender responsive, culturally
appropriate, and readily accessible to all segments of the affected persons.
Grievances may arise from members of communities who are dissatisfied with (i) the eligibility criteria,
(ii) community planning and resettlement measures, (iii) actual implementation, (iv) issues related to
environmental and social concerns and (v) GBV related aspects. This chapter sets out measures to be used
to manage grievances.
Grievance procedure does not replace existing legal processes. Based on consensus, the procedures will
seek to resolve issues quickly to expedite the receipt of entitlements, without resorting to expensive and
time-consuming legal actions. If the grievance procedure fails to provide a result, complainants can still
seek legal redress procedure.
Local Grievance Redress Committee (GRC) will be established, consisting of representatives from OWEB,
Municipality /Zonal /District/ Kebele Administration, District Justice Office, elders or influential
personalities other than displaced persons and Church/Mosque Administration. The Committee will be
headed by City/District/Zonal Administrator. Grievances should be settled amicably whenever possible.
That is, positive discussions are made to convince Project Affected Person/s (PAP) in the presence of the
GRC. However, if the resolution of a case requires additional payment or any form of relocation of
resources, the report shall be sent to appropriate administrative executive for consideration. If the
administrator agrees to the recommendation, he/she shall instruct the resettlement Unit to implement the
amended provision. On the other hand, if the GRC recommendation is such that it upsets legal frameworks,
the aggrieved party may be advised to pursue the case in a normal law court.
Based on Proclamation No.455/2005, Article11, subarticle1: “In rural areas and in urban centers where
an administrative organ to hear grievances related to urban land holding is not yet established, a complaint
relating to the amount of compensation shall be submitted to regular court having jurisdiction.”
In urban areas, a PAP who is dissatisfied with the amount of compensation may complain to an
administrative organ and if the PAP is still not satisfied, may appeal to regular appellate court or municipal
appellate court within thirty days from the date of the decision.
The grievance redressing procedure is developed to meet AfDB and Ethiopian government legal
requirements relating to grievance resolution and international requirements.
A set of forms which will be used for recording grievances and actions taken are prepared for the proposed
program as listed below (shall be translated in local language).
a) Grievance Statement Form,
b) Grievance Receipt Acknowledgement Form,
c) Grievance Investigation Form, and
d) Grievance Investigation Outcome Form.
The grievance mechanism applies to all complaints related to Borana Resilient Water Development for
Improved Livelihood Program (BRWDLP) in general and Part 2 Project activities and is comprised of
the following steps.
17.1 Conclusions
Borana Resilient Water Development for Improved Livelihoods Program in general and the Part 2 Project
Water Supply Project is expected to bring considerable benefits to communities within the three project
districts capital towns, areas as well as adjoining settlements and the district communities in general.
Anticipated benefits include increased access to safe water supply, improvement in public health status and
sanitation conditions, time and energy savings particularly for women and children, among others.
This updated Environmental and Social Management Framework (ESMF) is meant to ensure that the
implementation of the Program will be carried out in an environmentally and socially sustainable manner.
The ESMF provides the project implementers with an environmental and social screening process that will
enable them to identify, assess and mitigate potential environmental and social impacts of sub-project
activities of the Part 2 Project, including preparation of site-specific Environmental and Social Impact
Assessments (ESIA) and Environmental and Social Management Plans (ESMP) where applicable, in
accordance with Ethiopia’s proclamations and policies, as well as AfDB safeguard policies particularly
Environmental Assessment (OS1).
The ESMF recognizes existing gaps and weaknesses for implementing the ESMF under this Part 2 of the
project and realizes importance of strengthening capacity of key implementing institutions and capacitating
stakeholders that provide an enabling environment to address environmental and social issues by project
implementing body, OWEB, Oromia Regional EPA and line sectors down to districts and kebele levels in
implementing the ESMF.
Consequently, in view of the long-term socio-economic benefits that can be gained, there are no significant
environmental and social justifications for not proceeding with the Part 2 Project of the Program. Potential
benefits from the sub-projects of the Program far outweigh negative impacts and inconveniencies that
accompany project implementations in as much as the recommended mitigation measures and mechanisms
are duly considered and implemented using the guiding ESMF Report.
17.2 Recommendation
Based on findings of the stakeholders and community representatives’ consultative meetings on issues of
the Borana Resilient Water Development for Improved Livelihoods Program (BRWDILP), as the Borana
water supply network project issue has been presented for the zone and district sectors officials and experts
and also for grass root communities since the last 20 years, they now considered as no hope for the project
implementations. Therefore, it is recommended that the project plan shall continue with awareness creation
side by side to its planned activities implementations without creating gaps.
ANNEXES
Cause encroachment to, and adversely affect, important natural habitats (e.g., wildlife reserves;
parks or sanctuaries; protected areas; natural habitat areas, forests and forest reserves, wetlands,
national parks or game reserves; any other ecologically/environmentally sensitive areas)
Impact on physical cultural resources (archaeological sites; religious monuments or structures;
natural sites with cultural values; cemeteries; graveyards; graves; and other sites of significance)
Located in protected areas and ecologically sensitive sites
Introduction
This Environmental and Social Screening Form (ESSF) has been designed to assist in the evaluation of
construction and refurbishment/rehabilitation activities under BRWDLP. The form will assist the project
implementers and reviewers to identify environmental and social impacts and their mitigation measures if
any. It will also assist in the determination of requirements for further environmental work (such as
environmental and social management plans) if necessary.
The form helps to determine the characteristics of the prevailing local bio-physical and social environment
with the aim of assessing the potential impacts of the construction and rehabilitation activities on the
environment by the sub-project. The ESSF will also assist in identifying potential socio-economic impacts
that will require mitigation measures and/or resettlement and compensation.
Annex 2.1: Project information for screening potential safeguards impacts (Form 1)
I: Basic Data:
Completeness of project Application: Does the project application document contain, as appropriate,
the following information?
Appraisal Risk / Significance rating
Substantial
No Issues to be considered under AfDB OSs
Moderate
unknown
Yes/No
None
High
Low
1 Environmental Screening
Substantial
No Issues to be considered under AfDB OSs
Moderate
unknown
Yes/No
None
High
Low
wetlands, etc.)?
Substantial
No Issues to be considered under AfDB OSs
Moderate
unknown
Yes/No
None
High
Low
community workers?
3 Resettlement Screening
Substantial
No Issues to be considered under AfDB OSs
Moderate
unknown
Yes/No
None
High
Low
3.2 Loss of properties –houses, structures
Substantial
No Issues to be considered under AfDB OSs
Moderate
unknown
Yes/No
None
High
Low
for those who may be disadvantaged or
vulnerable?
5 Cultural Heritage Screening
5.1 Impact heritage site, graveyard land
5.2 Will the project activities involve
excavations,
demolitions, earth movements, flooding or
changes to physical environment that could
affect cultural heritage values?
5.3 Are project activities likely to affect
tangible and/or intangible cultural heritage
(e.g., archaeological sites that comprise any
combination of structural remains, artifacts,
human or ecological elements, and may be
located entirely beneath, partially above, or
entirely above the land or water surface)?
5.4 Are project activities located in legally
recognized and/or legally protected areas or
defined buffer zones designated for the
protection of cultural heritage?
5.5 Will the project activities affect cultural
heritage in non-designated or legally
recognized areas or protection zones?
5.6 Will the project affect cultural heritage
assets that are movable (i.e., rare books,
manuscripts, paintings, etc.) that could be
endangered by the project?
After compiling the above, if the project under BRWDLP falls under “High, Substantial, Moderate or low”
risk, proceed to determine the environment category of the project based on the environmental categories
of AfDB ISS (Category 1, Category 2, Category 3, Category 4) and (Schedule I, II or III) based on the
National and Regional EIA procedural guideline issued by the EPA and REPA.
components that the Bank or the borrowing country considers sensitive. Some programme-
based operations or other regional and sector programme loans that have significant
adverse environmental or social risks and are deemed to be Category 1. In some cases,
projects are included in Category 1 because of their potential cumulative impacts or the
potential impacts of associated facilities. Any project requiring a Full Resettlement Action
Plan (FRAP) under the provisions of the Bank’s policy on involuntary resettlement is also
deemed to be Category 1.
If the Bank operations likely to cause less adverse environmental and social impacts than
Category 1 – Category 2 projects are likely to have detrimental site-specific environmental
and/or social impacts that are less adverse than those of Category 1 projects. Likely
impacts are few in number, site-specific, largely reversible, and readily minimised by
applying appropriate management and mitigation measures or incorporating
internationally recognized design criteria and standards. An operation that involves
Category 2
resettlement activity for which an Abbreviated Resettlement Action Plan (ARAP) is
required under the ESAPs is classified as Category 2. Most programme-based operations
and regional or sector programme loans designed to finance a set of subprojects approved
and implemented by the borrower or client are included in this category unless the nature,
scale or sensitivity of the intended pipeline of subprojects involves either a high level of
environmental and social risk or no such risk
If the Bank operations with negligible adverse environmental and social risks – Category
3 projects do not directly or indirectly affect the environment adversely and are unlikely
to induce adverse social impacts. They do not require an environmental and social
Category 3 assessment. Beyond categorisation, no action is required. Nonetheless, to design a
Category 3 project properly, it may be necessary to carry out gender analyses, institutional
analyses, or other studies on specific, critical social considerations to anticipate and
manage unintended impacts on the affected communities
The Project can be considered for approval. The application is complete, all significant
environmental and social issues are resolved, and no further Project planning is required:
Approved without condition (Project activity is not of environmental and social concern and
approved)
ESMP required:
Others (specify):
CERTIFICATION
I/We certify that I/we have thoroughly examined all the potential adverse effects of this Project. To the
best of our knowledge, the Projects plan as described in the application and associated planning reports
(e.g. ESMP, RAP/ARAP/WMP/SMP,), if any, will be adequate to avoid or minimize all adverse
environmental and social impacts.
A Field Appraisal report will be completed and added to the Project file.
Name of desk appraisal officer (print): …………………………………………………………...
Signature: …………………………Date: ………………………………
OWEB/MoWE/Regional Environmental offices representative
Name: ………………………...
Position: …………………………………………………
(signature): ……………………………………………………
Date: …………………………………………………
Annex-3: Suggested Environmental and Social Field Appraisal Form for a Subproject
PART 1: IDENTIFICATION
1. Subproject Name: (……………….)
2. Subproject Location: (…………………)
3. Reason for Field Appraisal:
4. Date(s) of Field Appraisal:
5. Field Appraisal Officer and Address:
6. Extension Team Representative and Address:
7. Community Representative and Address:
PART 2: DESCRIPTION OF THE SUBPROJECT
8. Project Details: ___________________________________________________________________
______________________________________________________________________________
PART 3: ENVIRONMENTAL AND SOCIAL ISSUES
9. Will the Subproject: Yes No
• Need to acquire land?
• Affect an individual or the community's access to land or available resources?
• Displace or result in the involuntary resettlement of an individual or family?
If "Yes", tick one of the following boxes:
The Resettlement Action Plan (RAP) included in the Project application is adequate. No further
action required.
The RAP included in the Project application must be improved before the application can be
considered further.
An RAP must be prepared and approved before the application can be considered further.
Before it is considered further, the application needs to be amended to include suitable measures for
addressing these environmental or social issues.
An ESMP needs to be prepared and approved before the application is considered further.
ESMPs should demonstrate that proposed environmental and social management and monitoring activities
will encompass all major impacts and how they will be integrated into project supervision. The ESMP
should also describe proposed measures, methods, and actions to facilitate public consultation. It is
important that the ESMP identify linkages to other social and environmental safeguards plans relating to
the project, such as plans to deal with resettlement issues. Given the scale and nature of the project and the
significance of the potential anticipated impacts, OWEB in collaboration with Regional Water and Energy
Bureaus are responsible for preparing a project-specific ESMP for identified projects in a format suitable
for inclusion as technical specifications in the contract of each project beneficiaries, if applicable and
required. ESMPs should be finalized and approved after considering comments from the Ministry of Water,
and Energy (MoWE) at the national level and from Regional Environmental offices at regional level. The
AfDB safeguards team will review and provide comments on draft site-specific instruments (if required)
and monitor safeguards compliance, among others. Given below are the important elements that constitute
an ESMP:
i) Description of the project under BRWDLP: Scale nature and type of projects implemented under
the proposed programs are summarized.
ii) Description of Project implementation area: The Biophysical and social environmental setting of the
specific project implementation area are summarized
iii) Impacts: Predicted adverse environmental and social impacts (and any uncertainties about their
effects) for which mitigation is necessary should be identified and summarized.
iv) Description of Mitigation Measures: Each measure should be briefly described in relation to the
impact(s) and conditions under which it is required. These should be accompanied by and/or referenced
to designs, development activities, operating procedures, and implementation responsibilities.
Proposed measures and actions to facilitate public consultations should be clearly described and
justified. Feasible and cost-effective measures to minimize adverse impacts to acceptable levels should
be specified with reference to each impact identified. Further, the ESMP should provide details on the
conditions under which the mitigation measure should be implemented. The ESMP should also
indicate the various practicable measures applicable to the proposed projects at each project phases
(design, construction and/or operation). Efforts should also be made to mainstream environmental
aspects wherever possible.
v) Description of monitoring program: The ESMP identifies monitoring objectives and specifies the
type of monitoring required; it also describes performance indicators which provide linkages between
impacts and mitigation measures identified in the ESA report, parameters to be measured (for example:
national standards, extent of impacted area to be considered, etc.), methods to be used, sampling
location and frequency of measurements, and definition of thresholds to signal the need for corrective
actions. Monitoring and supervision arrangements should be agreed by the Bank and the borrower to:
ensure timely detection of conditions requiring remedial measures in keeping with best practice;
provide information and the progress and results of mitigation and institutional strengthening
measures; and, assess compliance with National and AfDB environmental safeguard policies and IFC
performance standards
vi) Institutional arrangements: Institutions responsible for implementing mitigation measures and for
monitoring their performance should be clearly identified. Where necessary, mechanisms for
institutional coordination should be identified, as often, monitoring tends to involve more than one
institution. This is especially important for projects requiring cross-sectoral integration. The ESMP
specifies who is responsible for undertaking the mitigation and monitoring measures, e.g., for
enforcement of remedial actions, monitoring of implementation, training, financing, and reporting.
Institutional arrangements should also be crafted to maintain support for agreed enforcement measures
for environmental protection. Where necessary, the ESMP should propose strengthening the relevant
agencies through such actions as: establishment of appropriate organizational arrangements;
appointment of key staff and consultants.
vii) Implementing schedules: The timing, frequency and duration of mitigation measures and monitoring
should be included in an implementation schedule, showing phasing and coordination with procedures
in the overall project implementation/operations manual. Linkages should be specified where
implementation of mitigation measures is tied to institutional strengthening and to the project legal
agreements, e.g. as conditions for loan effectiveness or disbursement.
viii) Reporting procedures: Feedback mechanisms to inform the relevant parties on the progress and
effectiveness of the mitigation measures and monitoring itself should be specified. Guidelines on the
type of information required and the presentation of feedback information should also be highlighted.
ix) Cost estimates and sources of funds: Implementation of mitigation measures mentioned in the ESMP
will involve an initial investment cost as well as recurrent costs. The ESMP should include cost
estimates into the Project design, bidding and contract documents to ensure that the contractors will
comply with the mitigation measures. The costs for implementing the ESMP will be included in the
Project design, as well as in the bidding and contract documents. It is important to capture all costs –
including administrative, design and consultancy, and operational and maintenance costs – resulting
from meeting required standards or modifying project design.
To ensure unique identification and to cater for changes in administrative borders or names, the ESMP
further requires entering of GPS coordinates of the location, if applicable.
For each potential impacts of the project, corresponding mitigation measures, and who is responsible for
implementation is indicated. For each potential environmental and social impact, there can be more than
one mitigation measure. Responsibility for implementation of mitigation measures will typically rest with
the contractors during construction and operation phase.
The monitoring section of the ESMP prescribes indicators for monitoring the environmental and social
impact and the effects of mitigation measures. The responsibility for this will typically rest with the OWEB.
A template for ESMP is depicted in annex 5.
Project identification
Project title/Name
Region Zone District
Kebele/community Location GPS coordinates
Description of planned mitigation measures and monitoring along with institutional responsibilities
and capacity/training requirements
Institutional
Mitigation
frequency
measures
location
Pre-construction/ activities
Construction/ activities
Operation and
maintenance/ activities
Total monitoring costs
Based on the screening and scoping study results, ESIA terms of reference will be prepared. The terms of
reference will have the following contents. Please refer to “Ethiopia’s Environmental and Social
Safeguards Framework for the CRGE Initiative” (MEF, 2015) for detail information on the ESIA process
steps (Screening, Scoping, Impact study, Reviewing, Decision-making, Monitoring and reporting, and
Auditing and Reporting). Further, please refer to the Guideline Series Documents for Reviewing
Environmental Impacts Study Reports (EPA, 2003) for detail information on contents and descriptions of
ESIA report (EPA, 2003). Review and use Oromia latest guideline as need be.
I. Objective of the TOR: This section should state the scope of the ESIA in relation to the screening
category and the proposed program activities. It needs to stipulate the process and the timing of the
ESIA preparation and implementation stages in order to adequately address the safeguards requirements
of the GoE and the AfDB.
II. Introduction and Context: The ToR needs to provide information on program activity objective, the
name of the program activity proponent, the rational for conducting the ESIA, specific components of
the program activity, program activity area with location map, short briefing of social and
environment of settings and applicable national and international safeguard policies.
III. Location of the study area and likely major impacts: State the area involved and the boundaries
of the study area for the assessment. Identify adjacent or remote areas which should be considered with
respect to impacts of particular aspects of the program activity.
IV. Mission/Tasks: The ESIA study team/consultant should clearly execute the following tasks.
Task A: Description of the proposed program activity: Describe the location, size and nature of
the program activity, environmental assessment category, brief description of program activity
alternatives, time schedule for phasing of development (i.e., preconstruction, construction,
operation/maintenance, decommissioning), and resources (finance, human, material and technology)
required for the program activity, among others.
Task B: Baseline information/Biophysical and social-economic description: Describe the
baseline/biophysical and socio-economic characteristics of the environment where the program activity
will be implemented; and area of influence. Include information on any changes anticipated before the
program activity commences.
Task C: Administrative and legal Policy framework: In addition to the required
administrative and institutional setup for the implementation of the program activity, this part needs to
identify pertinent policies, regulations and guidelines pertinent to the study that include:
✓ National laws and/or regulations on environmental and social assessments;
✓ Regional environmental and social assessment regulations;
✓ Environmental and social assessment regulations of any other financing organizations
involved in the program activity;
✓ Relevant international environmental and social agreements/conventions to which
✓ Ethiopia is a party;
➢ An account of the prediction and assessment of each impact at all stages of the program
activity cycle for each alternative
➢ Description of the methodology and techniques used in assessment and analysis of the
program activity impacts
➢ Description of environmental and social impacts for program activity
➢ Environmental and Social Management Plan (ESMP) for the project including the proposed
management and mitigation measures and the respective costs;
➢ Environmental and Social Monitoring Plan for the project including the proposed
monitoring measures and the respective costs;
➢ Institutional responsibilities for monitoring and implementation; Summarized table for ESMP.
➢ Conclusions and recommendations
➢ References
➢ Annexes
✓ List of Persons/Institutions met
✓ Minutes of consultations
✓ List of ESIA report preparers – individuals and organizations.
✓ Record of stakeholder and community consultation meetings, including consultations
for obtaining the informed views of the affected people and local nongovernmental
organizations (NGOs). The record specifies any means other than consultations (e.g.,
surveys) that were used to obtain the views of affected groups and local NGOs.
✓ Tables presenting the relevant data referred to or summarized in the main text.
✓ List of associated reports (e.g., ESMP, RAP, socio-economic baseline survey, WMP,
SEP, etc.)
✓ List of the ESIA study team members
Note:
The above ToR outlines the minimum content that should be included in a full-fledge ESIA report (i.e.,
Schedule–I sub-projects). For Preliminary ESIA report (i.e., Schedule-II subprojects), early consultations
would need to be carried with the relevant federal, regional or zonal EPA offices to determine the minimum
content for such report.
Given the proposed project activities under the BRWDLP are implemented in areas where potential land
acquisition is required, the project activity may have an impact on cultural resources, particularly for
unknown cultural heritage. The Project activities are required to comply with all the requirements under the
Bank policy throughout the program implementation period, expecting that unforeseen impacts might occur
during the construction activities of projects. Within the scope of the proposed Programs, any project
activities that will impact the cultural resources are not eligible for funding (for a list of projects that are
not eligible for funding, please refer to Annex 1). In case of any possibility of the chance find of physical
cultural resources, most notably during excavation as part of construction activity, the chance finds
procedures is one of the instruments to be used during the Program implementation period.
Such physical cultural resources may take the form of works of art, building structures, natural features and
landscapes, graves or aesthetic, cultural and architectural sites, including sites of archaeological, historical,
or religious significance.
All chance finds of such physical cultural resources will lead to the temporary suspension of all activity
that will adversely impact the cultural resource. Contractors will include detailed procedures for ensuring
the protection of the cultural resources, including cessation of activities until the significance of the find
has been determined and until appropriate mitigating measures has been implemented. This Annex contains
standard provisions to be annexed to contract documents that potentially will lead to chance finds of
physical cultural resources, as required. Therefore, the attachment outlined below will be annexed to the
contract document to manage in case there is the possibility of chance find of physical cultural resources.
Attachment to contracts in case of potential chance find of physical cultural resources
If the Contractor discovers archaeological sites, historical sites, remains and objects, including graveyards
and/or individual graves during excavation or construction, the Contractor shall:
1: Excavation in sites of known archaeological interest should be avoided and as stated in annex 1, such
projects are not eligible for funding. Where historical remains, antiquity or any other object of cultural,
historical or archaeological importance (including graveyards) are unexpectedly discovered during
construction in an area not previously known for its archaeological interest, the following procedures
should be applied:
a) Stop the construction activities in the area of the chance find.
b) Delineate the discovered area.
c) Secure the area to prevent any damage or loss of removable objects. In cases of removable antiquities
or sensitive remains, a night guard shall be present until the responsible national and regional
authorities and the Ministry of Culture and truism to take over.
d) Notify OWEB environmental and social safeguards specialist who in turn will notify the MoWE and
OWEB respective relevant institutions to contact the responsible local authorities and the Ministry
of Culture and Tourism immediately (less than 24 hours).
e) The Ministry of Culture and Tourism will be in charge of protecting and preserving the area until
deciding on the proper procedures to be carried out. This might require an evaluation of the findings
to be performed by the archaeologists of the relevant Ministry Culture, and Tourism (within 1 week).
The evaluation of the findings will take in consideration various criteria relevant to cultural heritage,
including the aesthetic, historic, scientific or research, social and economic values as decided by the
Ministry of Culture and Tourism.
f) Decisions on how to handle the finding are taken by the responsible authorities and the Ministry of
Culture and Tourism (within 2 weeks). This could include changes in the location of the project
layout (such as when the finding is irremovable remains of cultural or archaeological importance),
conservation, preservation, restoration and salvage.
g) Construction or rehabilitation work will resume only after authorization is provided by the
responsible local authorities and the Ministry of Culture and Tourism concerning the safeguard of
the heritage.
h) Authorization to resume work shall be communicated to the contractor and/or regional and District
energy experts in writing by the Ministry of Culture and Tourism.
2: In case of delays incurred indirect relation to any physical cultural resources findings not stipulated in the
contract (and affecting the overall schedule of works), the contractor/masons may apply for an extension
of time. However, the contractor will not be entitled to any kind of compensation or claim other than
what is directly related to the execution of the physical cultural resources findings works and protections.
Objectives
The objectives of annual reviews of ESMF implementation are two-fold:
a) To assess the Part 2 Project of the wider BRWDLP performance in complying with ESMF
procedures, learn lessons, and improve future performance; and
b) To assess the occurrence of, and potential for, cumulative impacts due to scaling solar and wind
energy development projects.
The Programs management is expected to use the annual reviews to improve on procedures and capacity
for integrating natural resources and environmental/social management into proposed program operations.
It is also be a principal source of information to Bank supervision missions.
Scope of Work
ESMF Performance Assessment
The overall scope of the performance assessment work is to:
a) Assess the adequacy of the project approval process and procedures based on interviews with Project
participants, Project records, and the environmental and social performance of a sample of approved
projects;
b) Assess the adequacy of ESMF roles and responsibilities, procedures, forms, information resource
materials, etc.;
c) Assess the needs for further training and capacity building;
d) Identify key risks to the environmental and social sustainability of projects; and
e) Recommend appropriate measures for improving ESMF performance.
c) Interview national, regional and District officials responsible for project appraisal and approval to
determine their experience with ESMF implementation, their views on the strengths and weaknesses of
the ESMF process, and what should be done to improve performance.
Improvements may concern, for example, the process itself, the available tools (e.g. guidelines, forms,
and information sheets), the extent, and kind of training available, and the amount of financial resources
available.
d) Develop recommendations for improving ESMF performance.
Outputs:
The principal output is an annual review report that documents the review methodology, summarizes the
results, and provides practical recommendations. Distinct sections should address;
a) ESMF performance and
b) Cumulative impacts.
C) Measures to be taken
Annexes should provide the detailed results of the fieldwork, arid summarize the number of approved
projects by state and their characteristics according to the annual report format.
Copies of the annual review report should be delivered to the OWEB management, MoWE, to each national
and regional office directly or indirectly responsible for appraisal, approval, and implementation of projects,
and to the AfDB. The project management (OWEB) may also want to host national or regional workshops
to review and discuss the review findings and recommendations.
an ESMF checklist
Field Appraisal
Specific TA
Types of Project Activities
Remark
ESMP
RAP
6. Were there any unforeseen environmental or social problems associated with any Project approved and
implemented this year? If so, please identify the Project (s) and summarize the problem (s) and what
was or will be done to solve the problem (s). Use a summary table below.
Project Problem(s) Actions taken Actions to be taken
7. Have any other environmental or social analyses been carried out by other public or private agencies in
your District/region? If so, please describe them briefly.
………………………………………………………………………………………………………………
……………………………………………………………………………………………………………
…………………………………………………………………………………………………………
8. Have you noticed any problems with implementing the ESMF in the past year (e.g. administrative,
communications, forms, capacity)? If so, please describe them briefly.
……………………………………………………………………………………………………………
……………………………………………………………………………………………………………
…………………………………………………………………………………………………………
9. Training: Please summarize the training received in your Institution, District/Region in the past year, as
well as key areas of further training you think are needed.
Group Training Received Training Needed
OWEB
MoWE
Zonal Water Board Unit
Regional, Zonal and District
environment team
Community Members, elders, clan
leaders
NGOs/Associations
Etc.
This annex contains three templates to be used in conjunction with monitoring and reporting and follow for
ESMF implementation.
Annex-11: Dubuluk district key sectors stakeholders’ & project kebeles community
representatives’ consultation
Annex-11.1: Dubuluk district key sectors stakeholders’ consultative meeting participants
Annex-12: Elweya District key sectors stakeholders’ & project kebeles community
representatives’ consultations
Annex-12.1: Elweya District Water and Energy Office Staffs discussion participants
Annex-12.7: Minute of Elweya district Sarite kebele community representative consultative meeting
Annex-13: Yabello District key sectors stakeholders’ and project kebele community
representatives’ consultations
Annex-13.1: Yabello District key sectors stakeholders’ consultative meeting participants
Annex 14: Summary of issues, opinions & responses raised on districts & kebeles consultations
Concerns and Views Raised Responses to address concerns and issues
1. General views on the project
I. Elweya District-
• This project is very important for the community, especially irrigation will • If OWEB efforts on selection of target areas and screening
be very important for agricultural sector. process were not enough to inform the project; OWEB shall
• We have no information about this project and the level of target achievement address through additional stakeholder and community
in comparison with its objective is key for the evaluation of the project. consultation sessions at region, zone and district level
II. Dubluk District consultation sessions, and
• This project is very important for the community; it adds a great deal of • Lack of trusts on the water supply project issue as repeated
value to the ongoing community development initiatives. previous promises were not met and delayed for the last 20
• We have no information about this project. years.
2. Project Benefits
I. Yabello District The project is expected to potential resilience through increased
The project would benefit the whole community in: groundwater access for consumption and production. The project
• Providing fresh and clean water through water supply and infrastructure will contribute to improve pastoral and agro-pastoral livelihoods
building, and through community level sub-projects to increase groundwater
• Improve agricultural activity and increase utilization of underground water. supply and use, involving targeted communities in the
II. Dubluk District development, management, and maintenance of water supply and
• The project benefits both the community and government institutions on sanitation investments.
improving the GW resources management and use practice.
3. Risks and Concerns
I. Elweya District
• Conflicts of interest among clans on water supply infrastructure building,
well drilling and irrigation; there could be a concern. Anticipated risks addressed in the ESMF, are expected to be easily
II. Dubluk District mitigated. Towards addressing the risks, the following instruments
• Similar risks and concerns can arise while implementing this project, hence have been prepared and pending for approval by the Bank: RPF and
there is need to take lessons from previously implemented AfDB-financed ESMF.
2. District land use and land cover area in hectare and percentage.
Land use type Area (ha) %
Forestland
Arable land
Shrubs and fallow
Wetlands
Grazing land
Water bodies’
Others
Total
5. Agrochemicals use:
5.1 Rate of fertilizers uses by types.
DAP: /ha Urea: /ha Pesticides = /ha.
Excellence Environment and Development PLC September, 2023 194
Level-I Consultancy Service Firm, Addis Ababa
Borana Resilient Water Development for Improved Updated Environmental and Social
Livelihoods Program (BRWDLP), Part-2 Project Management Framework Final Report
5.2 Amount of fertilizers and pesticides used in previous two consecutive years in the district.
• 1st year: DAP qt. Urea= qt. Pesticides =
• 2nd year: DAP qt. Urea= qt. Pesticides =
3 Oil Crops
3.1
3.2
3.3
8. Expected potential impacts of the project on the agricultural activities and pastoral
development of the district.
8.1 Positive impacts on agricultural and pastoral development activities of the district.
8.2 Negative Impacts on agricultural and pastoral development activities of the district.
9. What should be done to minimize or eliminate expected negative impacts of the project?
1. List sites with cultural and religious importance (if any) in the district and especially in the
project kebele/s. ______________________________
2. List sites with historical and archaeological importance (if any) in the district and especially in
the project kebele/s.
3. List sites with recreational importance (if any) in the district and especially in the project
kebele/s.
4. Major ethnic groups and their percentage share in the district and the project kebele/s.
5. What are the positive and/or negative impacts of the project on cultural and tourism resources of the
district and the project kebele/s?
6. What should be done to overcome the problems (i f any) of the project on the cultural and tourism
resources of the district and/or the project kebele/s?
a. Positive impacts of the project on the district population livelihood and development.
4. Trend of Basic Health Service Coverage percentage (%) of the district for the last three years.
Periods Urban (%) Rural (%) Total (%)
13. Number of people’s death by Covid-19 in the kebeles under the project influence.
a. ______________ Male: ______ Female: _____ Total: _____
b. ______________ Male: ______ Female: _____ Total: _____
c. ______________ Male: ______ Female: _____ Total: _____
14. The major problems for promoting health service development program in the district
_____________________________________________________________________________________
____________________________________________________________________________________
15. Solution done/to be done to solve health related problems of the district.
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
7. Benefits from livestock for the project area society in private and in gross.
_____________________________________________________________________________________
_____________________________________________________________________________________
___________________________________________________________________________________
8. Expected potential impacts of the project on livestock resources of the district.
8.1 Positive impacts on livestock _________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
8.2 Negative Impacts on livestock ________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
________________________________________________________________________________
9. What should be done to minimize or eliminate expected negative impacts of the proposed project?
____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
10. Any general additional comment regarding the study please?
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
2. District land use and land cover by area in hectare and percentage.
Bush trees
Weeds
7. What should be done to minimize or eliminate expected negative impacts of the proposed project?
_____________________________________________________________________________________
_____________________________________________________________________________________
________________________________________________________________
8. Any general additional comment regarding the study please?
_____________________________________________________________________________________
_____________________________________________________________________________________
________________________________________________________________
Annex-15.7: District Water and Energy Sector baseline data collection questionnaire
__________National Regional State
_________ Zone _________District _________ Kebele ____________
Project ESIA Study Data Collection Questionnaire
District Water Supply Office
Project name: ___________________________________________
5. List of organizations engaged in the water supply and sanitation projects in the district:
_________________________________________________________________________________
_________________________________________________________________________________
6. List of water sources for livestock in the district.
_________________________________________________________________________________
_________________________________________________________________________________
7. Main water supply problems of the district.
_________________________________________________________________________________
_________________________________________________________________________________
_______________________________________________________________________________
Annex-15.8: District Women and Youth Sector baseline data collection questionnaire
Project: __________________________
1.3 Property ownership right of women in the district and the project kebele/s.
2.3 What do women of the district expect from the coming project?
3. With regard to potable water, what are the district and the project kebele/s women’s problems?
4. Problems on youths of the district and in rural kebeles related to potable water problems.
_________________________________________________________________________
5. Solutions for solving the potable water problems of the district & the rural & urban kebeles.
6. Solution or measures to be taken to solve and avoid the potable water problems of the district and the rural and
urban kebeles of the district.
7. Any general or additional comment/s regarding the study and the project?
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
1.2 Negative Impacts of the project on the zonal population livelihood and development.
__________________________________________________________________________
__________________________________________________________________________
__________________________________________________________________________
__________________________________________________________________________
10 Is land ownership case be major problem with respect to the project?
b. Yes b. NO
11 Explain and justify your answer for the above question number 8.
_______________________________________________________________________________
_______________________________________________________________________________
12 What should be done to minimize or eliminate expected negative impacts of the project on
zonal population land ownership if the problem found significant?
19. Current problems related to water supply for human and livestock.
_________________________________________________________________________________
______________________________________________________________________
20. Outstanding development needs (by priority order)
Ser. Development needs Priority Remark
1. Water supply sources development
2. Irrigation development
3. Livestock development
4. Animal feed development
5. If any other needs, explain.
______________________________________________________________________
______________________________________________________________________
21. Rural land related possible conflicts of the project site such as:
a) Cultivable related conflict;
b) Grazing land loss related conflict or
c) Community dislocation related conflict;
so far and how was the dispute solved or to be solved, if any?
_________________________________________________________________________________
_________________________________________________________________________________
22. Is there any other resource use-based community conflict?
a) Yes b). No
23. Major community conflict bases of the area (by priory order)
Ser. Development needs Priority Remark
1. Grazing areas
2. Water points
3. Both grazing area and water points
4. Irrigable farmland
5. If any, explain briefly
24. Major expected benefits of the water supply project in the kebele.
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
25. Major expected problems or impacts expected from the water supply project.
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
26. What solutions or mitigation measures must be implemented to overcome the problems?
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
________________________________________________________________________________
27. Any general comment regarding the project. ____________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
• Commercial Registration
• Trade License
• TIN Number
• VAT Registration