Project : ABU DHABI MARINA BLOOM PROJECT
Contractor AL SHAFAR GENERAL CONTRACTING
MEP Contractor : NATIONAL PROJECTS & CONSTRUCTION
CHECKLIST FOR - Installation of Electric Water Heaters
NPC/WIR/MECH- Location: Date:
Acceptable
[ ] Comments by
SN Works To be checked Cleared
Not Consultant
Acceptable
[X]
1 Components,
access
including solar storage and backup tanks, are located to allow
2 Installation of Heaters and accessories are as per approved drawings.
3 Water heater is installed in proper level.
4 Water heater is provided with proper and adequate supports.
5 Valves are installed to facilitate isolation of equipment.
6 Installation of piping is complete as per the approved drawing.
7 Electrical
required.
connections including earthing are completed and tightened as
8 Adequate access available for maintenance and removal of water heater/
heating elements.
9 Drain of water heater is connected to nearest drain
supporting frame is strong and properly attached to roof
Material is at right location and no leaks
connection of pipes from storage tank to collector and user points are as per
specs and shop drawings
NRV installed at right position
right slope of circulation pipes b/w collector and tank with no sharp bends
circulation pipes properly insulated
collector sensors correctly attached to hot and cold water circulation pipes
no corrosion and paint/coating in good condition
Electrical connections are completed and tightened as required.
N/A denotes work not being available at the time of inspection
For Final Approval
Contractor Rep: Consultant Rep:
Signature: Date: Signature: Date:
REV-0 page 1 of 7
Hotel, Serviced Apart
Plot No. C7-C102
INSPECTION & TEST PLAN OF
Activity
Installation of Hot water solar system
Inspection & Test Plan Number: Reference
SECTION 1 - REFERE
Method Statements Drawings
Reference
Method Statements of Installation of Hot water solar
system
SECTION 2 -
Hold Point: Stop work until inspected and QA documents approved. Surveillance: Ensure the activ
Witness Point: Inspection Requested - work can continue Review Point: Results to be re
PRIMARY CONTROL
Activity to be checked
MATERIAL SUBMITTAL APPROVAL
SHOP DRAWING APPROVAL
METHOD STATEMENT APPROVAL
MATERIAL DELIVERIES
STORAGE OF MATERIAL
INSTALLATION/TESTING OF HOT WATER SOLAR SYSTEM
COMPLETION OF WORK
This work has been undertaken and completed in accordance with t
Name:
QA/QC Department site representative
Serviced Apartments and Mixed Use Development
ot No. C7-C102 W35 Al Bateen, Abu Dhabi UAE
& TEST PLAN OF HOT WATER SOLAR SYSTEM INSTALLATION
Prepared by Checked by Approved By
(QA/QC Dept) (QA/QC Dept) (Project Manager)
r solar system
nce Name: Name: Mr. Beshoy Isaac Name Mr.
Date Date Date
ION 1 - REFERENCES AND CONTROL DOCUMENTS
Specifications
VOLUME MEP 2 PART 2 SECTION 22 33 31
SECTION 2 - INSPECTION & TEST PLAN
llance: Ensure the activity is reviewed to allow works to continue.
w Point: Results to be reviewed by a 2nd party.
RY CONTROL SECONDAR
Inspection Details
Freqency Checksheet/Verifying Document ASGC Consultant
Code Code
PRIOR TO START
APPROVED MATERIAL SUBMITTAL HOLD HOLD
ACTIVITIES
PROJECT TECHNICAL
PRIOR TO START
SPECIFICATIONS/ SHOP HOLD HOLD
ACTIVITIES
DRAWINGS
BEFORE FIRST MOCK-
APPROVED METHOD STATEMENT HOLD HOLD
UP INSTALLATION
ALL DELIVERIES MATERIAL INSPECTION HOLD REVIEW
PROJECT TECHNICAL
SPECIFICATIONS/
ALL AREAS OF THE
MANUFACTURER SURVEILANCE SURVEILANCE
PROJECT
RECOMMENDATIONS/METHOD
STATEMENT
ALL AREAS OF THE
METHOD STATEMENT WITNESS SURVEILANCE
PROJECT
ALL AREAS OF THE
INSPECTION REQUEST HOLD HOLD
PROJECT
ted in accordance with this ITP and all associated reference documents. Completed checksheets etc are available.
Date:
site representative
proved By
Project Manager)
Mr.
SECONDARY CONTROL
Inspection Details
Consultant Client
Code
HOLD N/A
HOLD N/A
HOLD N/A
REVIEW N/A
SURVEILANCE N/A
SURVEILANCE N/A
HOLD N/A