This document discusses the customizing and process flow of SD scheduling in SAP ERP. It explains how to activate scheduling by document type and for deliveries and stock transport orders. It also covers the relevant calendars, working times, and how the system determines dates like the goods issue date, loading date, material availability date, and delivery date through backwards and forwards scheduling.

Uploaded by

bojadzi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
10 views

SD Scheduling

This document discusses the customizing and process flow of SD scheduling in SAP ERP. It explains how to activate scheduling by document type and for deliveries and stock transport orders. It also covers the relevant calendars, working times, and how the system determines dates like the goods issue date, loading date, material availability date, and delivery date through backwards and forwards scheduling.

Uploaded by

bojadzi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

2018-02-08 2221849 Page 1/6

2221849 - Customizing and process flow of ERP SD


scheduling
SAP Knowledge Base
Version 4 Type
Article
Master
Language English English
Language
Release
Released to Customer Category Problem
Status
LE-SHP-GF-DS (Delivery and transport
Component Released On 28.08.2017
scheduling)

Please find the original document at https://launchpad.support.sap.com/#/notes/2221849

Symptom

This Knowledge Base Article explains the relevant customizing and the process flow of SD scheduling in the
ERP system.

Environment

Sales And Distribution (SD)


Logistics Execution (LE)
SAP ERP SD scheduling (LE-SHP-GF-DS)
SAP R/3
SAP R/3 Enterprise 4.7
SAP ERP Central Component
SAP ERP
SAP Enhancement package for SAP ERP
SAP Enhancement package for SAP ERP, version for SAP HANA
SAP S/4 HANA

Resolution

The aim of the scheduling is to determine the goods issue date, loading date, material availability date, the
transportation planning date and when necessary a new delivery date.

Customizing:

Sales documents:
The delivery and transportation scheduling can be activated in transaction OVLY.
Customizing path: Sales and Distribution -> Basic Functions -> Delivery Scheduling and
Transportation Scheduling -> Define Scheduling By Sales Document Type
It is controlled by the document type.
Deliveries:
For deliveries you have to consider the setting in transaction 0VLK. Field 'Rescheduling' controls
whether a new scheduling is carried out.

© 2018 SAP SE or an SAP affiliate company. All rights reserved


2018-02-08 2221849 Page 2/6
Stock transport documents:
In stock transport documents you also have the possibility to use the SD scheduling functionality. If
you do not activate it then an MM scheduling is carried out.
Customizing path: Materials Management -> Purchasing -> Purchase Order -> Set up Stock
Transport Order -> Assign Delivery Type and Checking Rule
or when using the functionality of Stock transport orders between storage location:
Materials Management -> Purchasing -> Purchase Order -> Set up Stock Transport Order -> Set
Up Stock Transfer Between Storage Locations -> Assign Delivery Type and Checking Rule
According to Storage Location
Replenishment deliveries:
Regarding replenishment deliveries please have a look at SAP Note 215664.
Calendar
During SD scheduling the system can take into account three different calendars:

Calendar at the shipping point: The calendar for the shipping point you can maintain under the
following customizing path: Sales and Distribution -> Basic Functions -> Delivery Scheduling and
Transportation Scheduling -> Maintain Duration
This calendar is used for the calculation of the transportation planning date, material availability
date, loading date and goods issue date.

Calendar at the route: This calendar is used for the calculation of the transportation. You can
maintain this under:
Customizing path: Sales and Distribution -> Basic Functions -> Delivery Scheduling and
Transportation Scheduling -> Maintain Duration
If no calendar is maintained at the route then the calendar at the shipping point is used.

In the customer master you can define Unloading Points. The unloading point determines when
your customer is able to receive the goods. You have the possibility to assign a factory calendar
and working hours to your receiving point.
The requested delivery date is checked against the factory calendar at the unloading point. If no
calendar is maintained then the requested delivery date can lie on non-working days due to your
calendar assigned to the shipping point. Please check SAP Knowledge Base Article 1579665.
The check happens in function module SD_DELIVERY_DATE_CHECK.
The calendars must be maintained at least three years into the future!
Working times:
SD scheduling can be carried out exact to days or exact to seconds. This depends on whether you
are working with working times. In the customizing you have to define working times for your
shipping point.
Customizing path: Sales and Distribution -> Basic Functions -> Delivery Scheduling and
Transportation Scheduling -> Maintain Working Hours
These working times you have to assign to the shipping point under:
Sales and Distribution -> Basic Functions -> Delivery Scheduling and Transportation Scheduling ->
Maintain Duration

Determined dates:
Goods issue date
In case of backwards scheduling: goods issue date = delivery date - transit time
In case of forwards scheduling: goods issue date = loading date + loading time

The transit time is the time that is required to deliver the goods from your site to your customer.

© 2018 SAP SE or an SAP affiliate company. All rights reserved


2018-02-08 2221849 Page 3/6
The transit time is defined in the route.
Customizing path: Sales and Distribution -> Basic Functions -> Delivery Scheduling and
Transportation Scheduling -> Maintain Duration

The loading time is the time that is required for loading the shipment. It can be maintained as
default for the shipping point, for the combination of shipping point and route or for the combination
shipping point, route and loading group.
Customizing path: Sales and Distribution -> Basic Functions -> Delivery Scheduling and
Transportation Scheduling -> Maintain Duration
Loading date
In case of backwards scheduling: loading date = goods issue date - loading time
In case of forwards scheduling: loading date = transportation planning date + transportation
planning time

The loading time is the time that is required for loading the shipment. It can be maintained as
default for the shipping point, for the combination of shipping point and route or for the combination
shipping point, route and loading group.
Customizing path: Sales and Distribution -> Basic Functions -> Delivery Scheduling and
Transportation Scheduling -> Maintain Duration
Material Availability date
In case of backwards scheduling: material availability date = loading date - pick pack time
In case of forwards scheduling: material availability date = loading date - pick pack time or current
date

The pick/pack time is the time that is required for allocating goods to a delivery as well as the time
that is required for picking and packing.
The pick/pack time can be maintained as default for the shipping point. Furthermore for the
combination of shipping point and route or the combination of the shipping point route and weight
group.
Customizing path: Sales and Distribution -> Basic Functions -> Delivery Scheduling and
Transportation Scheduling -> Maintain Duration
Transportation Planning date
In case of backwards scheduling: transportation planning date = loading date - transportation
planning time
In case of forwards scheduling: current date or transportation planning date = loading date -
transportation planning time

Delivery date
If the requested delivery cannot be kept a forwards scheduling will calculate a new delivery date:
Delivery date = goods issue date + transit time

Process logic of the scheduling:

Usually the system starts with a backwards scheduling starting from the requested delivery date.

Exception: Transaction Co06 always carries out ONLY a forwards scheduling.

The requested delivery date will be checked against the factory calendar of the unloading point, and the

© 2018 SAP SE or an SAP affiliate company. All rights reserved


2018-02-08 2221849 Page 4/6
arrival time will be set according to the beginning of the receiving hours, in other words, to the opening
time of the unloading point. From coding point of view this happens in subroutine function module
SD_DELIVERY_DATE_CHECK. Please also consider SAP Knowledge Base Article 1579665.

All other dates and times will be determined in backwards scheduling. If one of the dates or times lies in
the past the system automatically switches to forwards scheduling. In transaction OVLY (Customizing
path: Sales and Distribution -> Basic Functions -> Delivery Scheduling and Transportation Scheduling ->
Define Scheduling By Sales Document Type) you can control that the system does not switch to a
forwards scheduling when the material availability lies in the past. Please also check the related
debugging guide (SAP Knowledge Base Article 2220102) for further information. If the system has to
switch to forwards scheduling then the transportation planning date or the material availability date will be
set to the current date. Starting from this the other dates will be calculated considering the maintained
times. The newly calculated delivery date will be checked against the factory calendar at the unloading
point and also against the working times. It can happen that the delivery date and time has to be shifted
further into the future. In other words, to the next working day and time of the unloading point. In this case
a new backwards scheduling is carried out from that date and time.

These dates and times can still be changed by the route schedule scheduling which is called right after
SD scheduling. Regarding route schedule determination please check SAP Knowledge Base Articles
1750978, 2150219.

Please consider the document for route schedule scheduling.

The final result of the scheduling, or better to say, the determined material availability date will be passed
over to the ATP check. The ATP check is carried out for this date. If the date can be confirmed everything
is fine. If the ATP check can only confirm on a later date then the new material availability date will be
passed again to the scheduling and a forwards scheduling is carried out starting from this date.

Time stream:
Scheduling uses time streams. The time streams are stored in table TTSTR. Please consider SAP Note
169885 and SAP Knowledge Base Article 2140434.

Troubleshooting Guide:
Delivery Date or another date falls on a non-working date
Please check the customizing and the time stream according to SAP Knowledge Base Article
1579665.
Changes in the factory calendar are not considered while scheduling
The system works with streams during the scheduling. When you e.g. change the factory calendar
in your test system then the time stream will be deleted and will be newly generated when needed.
But when you move the changes of the factory calendar to another system (e.g. productive
system) via a Transport then the time stream will not be updated. You have to delete the time
streams manually. Please consider SAP Note 169885. Whenever you carry out such changes it is
recommended to delete the streams via the report mentioned in the SAP Note. The reports run
only a few seconds and you will not get any success information when the report has finished. The
report can be used safely at any time. The time streams will be automatically generated when
needed.
Unexplainable dates are determined while scheduling
There are several cases where the time stream cannot be built up correctly or where you receive
not explainable dates. Usually this is caused by wrong customizing:

© 2018 SAP SE or an SAP affiliate company. All rights reserved


2018-02-08 2221849 Page 5/6
Factory calendar validation is not sufficient. Please make sure that the factory calendar is
maintained at least three years into the future.
Factory calendars (shipping point, route, unloading point) are not harmonized. The same is
valid for the working times and the factory calendar at the unloading point. It makes no
sense to maintain e.g. working times for Monday whereas it is a non-working day due to the
factory calendar.
Shift definitions for the shipping point are not valid any more. Please make sure that the
shifts are valid (Customizing path: Sales and Distribution -> Basic Functions -> Delivery
Scheduling and Transportation Scheduling -> Maintain Working Hours).
Inconsistencies in the time stream -> See SAP Note 169885
Confirmed delivery date lies before requested delivery date
This can happen when you are using rout schedules and the specific transit time of the route
schedule is not the same as the transit time in the route. Please consider SAP Note 146829.
Issues regarding route schedule scheduling
Please check SAP Knowledge Based Article 1880353 and SAP Note 146829.
Delivery date is earlier then the Goods Issue Date
This can happen when you are working with time zones. The delivery date is displayed in the time
zone of the ship-to-party. All other dates will be displayed in the time zone of the shipping point.
Please consider SAP Knowledge Based Article 1890212.

Keywords

Versandterminierung, Transportterminierung, Vorwärtsterminierung, Rückwärtsterminierung,


Verfügbarkeitsprüfung, Materialbereitstellungsdatum, Transportdispositionsdatum, Ladedatum,
Warenausgangsdatum, Einteilungsdatum, Verkaufsbeleg, Lieferbeleg, Einkaufsbeleg, Nachschublieferung,
Fabrikkalender, Versandstelle, Arbeitszeiten, Wunschlieferdatum, Richtzeit, Ladezeit, Transitzeit, Teitstrahl,
Vorwärtsterminierung, Rückwärtsterminierung, Verfügbarkeitsprüfung, Auftragsart, Zeitzone, 311, EWM,

Products

SAP ERP Central Component all versions


SAP ERP all versions
SAP R/3 Enterprise all versions
SAP R/3 all versions
SAP S/4HANA all versions
SAP enhancement package for SAP ERP all versions
SAP enhancement package for SAP ERP, version for SAP HANA all versions

Other Components

Component Description

MM-PUR-GF-STO Stock Transfer

SD-BF-AC Availability Check

© 2018 SAP SE or an SAP affiliate company. All rights reserved


2018-02-08 2221849 Page 6/6

This document refers to

SAP Note/KBA Title

2220102 Debugging guide for SD scheduling

2150219 Troubleshooting guide for route schedules (ERP)

2140434 Troubleshooting guide for ERP SD scheduling

1890212 Delivery date / goods issue date seems to be incorrect

1880353 Delivery date shifted into the future with route schedules

1750978 Route Schedule does not populate on sales order

1579665 Scheduling - Date lies on a non-working day