Chapter 1 Introduction PSOC
Chapter 1 Introduction PSOC
AND CONTROL
Chapter 1
• Today’s power systems in India are very huge in terms of Installed capacity,
Energy generated, Transmission and Distribution system, Number of customers
and Total investment. As on June, 2020, installed capacity in India exceeds 371 x
103 MW with annual energy generated exceeding 1389 Billion kWh (1389 x 1012
kWh). Transmission network has AC transmission lines rated for 220 kV, 400 kV
and 765 kV along with HVDC lines rated for ± 500 kV and ± 800 kV. Operation and
control of interconnected power system is really challenging task and it cannot
be done manually. Therefore power systems are controlled by using powerful
computers installed at Energy Control Centers.
• The total power system in India is not being operated in totally integrated
manner. However, attempts are being made to achieve full integration.
1. Northern region load dispatching center at New Delhi covering states of HP, J
and K, Haryana, Punjab, Rajasthan, UP, Delhi, Uttaranchal and Chandigarh.
4. Eastern region load dispatching center at Kolkata covering WB, Bihar, Orissa,
Sikkim and Jharkhand.
The third level of consists of state load dispatching stations in each state capital.
• Installed capacity in different regions as on June, 2020 are as follows:
Renewa Grand
Region Coal Lignite Gas Diesel Nuclear Hydro
ble Total
Northern
53440 1580 5781 0 1620 20086 17049 99556
Region
Western
72935 1540 10806 0 1840 7623 26232 120976
Region
Southern
44364 3490 6492 433 3320 11775 42501 112375
Region
Eastern
27285 0 100 0 0 4639 1503 33527
Region
North
Eastern 770 0 1812 36 0 1577 365 4560
Region
Islands 0 0 0 40 0 0 18 58
ALL
198794 6610 24992 510 6780 45699 87669 371054
INDIA
Severe Blackouts
• BRAZIL AND PARAGUAY // NOVEMBER 10-11, 2009
-17,000 megawatts of power, outages quickly spread through both countries
• CHENZHOU, CHINA // JANUARY 24 - FEBRUARY 2008
-two-week blackout for 4.6 million people, death toll exceeded 60
• GERMANY, FRANCE, ITALY, AND SPAIN // NOVEMBER 4, 2006
-10-15 million Europeans lost power
• JAVA AND BALI, INDONESIA // AUGUST 18, 2005
-500 kilovolt transmission line, 5,000 megawatt shutdown
• INDIA // JULY 30-31, 2012
-670 million people
-some states had attempted to draw more power than permitted due to the higher
consumption( Uttar Pradesh, Punjab and Haryana )
-22 out of 28 states in India, were without power.
• Weak inter-regional power transmission corridors due to multiple existing outages
(both scheduled and forced);
• High loading on 400 kV Bina–Gwalior–Agra link;
• Inadequate response by State Load Dispatch Centers (SLDCs) to the instructions of
Regional Load Dispatch Centres (RLDCs) to reduce over-drawal by the Northern
Region utilities and under-drawal/excess generation by the Western Region utilities;
• Loss of 400 kV Bina–Gwalior link due to mis-operation of its protection system.
Power Position (Demand & Availability)
Power in MW
Peak demand Peak met
Region
Apr.2015 Apr. 2016 Apr. 2015 Apr. 2016
3. It must be able to supply the ever changing load demand at all time.
SYSTEM LOAD
1. Domestic
2. Commercial
3. Industrial
4. Agriculture
5. Others - street lights, traction.
Domestic:
Ø Lights,
Ø fans,
Ø mixers,
Ø ovens,
Industrial:
Agriculture:
Connected load
Maximum demand
It is the greatest demand of load on the power station during a given period.
Demand factor
The average of loads occurring on the power station in a given period (day
or month or year) is known as average demand
Daily average demand = (no of units generated per day) / (24 hours)
Monthly average demand = (no of units generated in month) / (no of
hours in a month)
Load factor
The ratio of average load to the maximum demand during a given period is
known as load factor.
Load factor = (average load)/ (maximum demand)
Diversity factor
The ratio of the sum of individual maximum demand on power station is known as
diversity factor.
Diversity factor = (sum of individual maximum demand ) / (maximum demand).
Capacity factor
Ø This is the ratio of actual energy produced to the maximum possible energy that could
have been produced during a given period.
Capacity factor = (actual energy produced) / (maximum energy that have been
produced)
Ø It is the ratio of units generated to the product of plant capacity and the number of hours
for which the plant was in operation.
Monthly load curve–Load curve obtained from the daily load curve
Yearly load curve-Load curve obtained from the monthly load curve
Ø The curve drawn between the variations of load with reference to various time period of day
is known as daily load curve.
Ø Average value of the power at a month for a different time periods are calculated and plotted
in the graph which is known as monthly load curve.
Ø It is obtained from monthly load curve which is used to find annual load factor.
Base Load:
The unvarying load which occurs almost the whole day on the station
Peak Load:
5 kW 5 kW
~
T G
5 kW L
5 kW 5.1 kW 5 kW 4.9 kW
~ ~
T G T G
5.1 kW L Increase in
4.9 kW L
Reduction in
Kinetic energy, Kinetic energy,
speed and speed and
frequency frequency
Excitation ?
V=?
Electric motors will tend to run on over speed when they are fed with higher
voltages resulting vibration and mechanical damage. Over voltage may also
cause insulation failure.
For a specified power rating, when the supply voltage is less, the current drawn
is more and it will give rise to heating problems.
Therefore it is essential to keep the system frequency constant and the voltage
variation within the tolerance.
In order to perform voltage and frequency control, a basic generator will have two
control loops namely:
The Automatic Voltage Regulator (AVR) loop controls the magnitude of terminal
voltage |V|, for varying load conditions. Terminal voltage is continuously
measured, rectified and converted as a dc voltage. The strength of this dc signal,
being proportional to |V|, is compared with a dc reference |V|ref. The resulting
“error voltage” after necessary amplification, serves as input to the exciter. The
excitor applies the required voltage to the generator field winding, so the
generator terminal voltage |V| reaches the value |V|ref.
The automatic load frequency control (ALFC) loop regulates the real power
output of the generator and its frequency (speed) for varying load conditions.
ALFC loop is not a single one as in the case of AVR. A relatively fast primary loop
responds to a frequency (speed) changes via the speed governor and the steam
(or hydro) flow is regulated with the aim of matching the real power generation to
relatively fast load fluctuations. By “fast” we mean changes that takes place in
one to several seconds. Thus, primary loop performs a course speed or
frequency control to maintain the real power (megawatt) balance.
A slower secondary loop maintains the fine adjustment of the frequency, and
also maintains proper real power interchange with other pool members. This loop
is insensitive to rapid load and frequency changes, but focuses drift-like changes
which take place over periods of minutes.
Fig. 1 shows the two control loops, AVR loop and ALFC loop.
The AVR and ALFC loops are not fully non-interacting. Little cross coupling does
exist between AVR and ALFC loops. AVR loop affects the magnitude of the
generator emf E. As the internal emf determines the magnitude of the real power,
it is clear that changes in the AVR loop will be felt in the ALFC loop.
However, the AVR loop is much faster than the ALFC loop and hence AVR
dynamics may settle before they can make themselves felt in the slower load-
frequency control channel.
Chapter 2 and Chapter 3 will deal with LOAD FREQUENCY CONTROL (LFC) and
AUTOMATIC VOLTAGE REGULATOR respectively.
4. ECONOMIC DISPATCHING
Once it is possible to ensure electric power supply with constant frequency and
voltage, next we may be interested to operate the power system in a most
economic manner.
The main aim of economic dispatch problem is to minimize the total cost of
generating real power at various stations considering the system loads and
losses in the transmission network.
There are certain engineering constraints that are to be satisfied while finding the
optimal solution. The problem become complicated when the power system has
different types of generations such as thermal, hydro, nuclear, wind, solar etc.
Optimal Power Flow method, which makes use of optimizing technique, is used
to determine the optimal status of power system for a given load condition.
5. UNIT COMMITMENT
The system load changes in cyclic manner. It is not advisable to keep all the units
available all the time. When system load decreases, it is better to shut down one
or more units and when the system load increases at a latter time, units are to be
brought in.
Unit commitment problem is finding the shut down and commissioning rule so
that the total cost of generation over a period of time, say one day, is minimum.
If the load coming on the system is known in advance, then we can schedule how
to operate various units. But customers used to switch on or switch off the load
as per their requirements. Hence it becomes necessary to forecast the system
load.
Load forecasting is done by analyzing the past load data. Certain load forecasting
techniques are available to find the system loads at different points of time, as
well as peak load, based on the records of past data.
Short term forecasting is carried out to find load for a day while long term
forecasting aims to get load for a month or a year.
When the total load is more than the total generation capacity, then load
shedding has to be resorted. This has to be done to save the electric grid from
collapsing.
8. ISLANDING
Generation shifting
Increase reserve
Restorative Alert
Fault clearing
Load shedding Excitation control
System separation Fast valving
Load shedding
Emergency
Emergency
In extremis
Power systems are operated by system operators from the area control centers.
The main goal of the system operator is to maintain the system in a normal
secure state as the operating conditions vary during the daily operation.
iii) determination of the necessary preventive action in the case of state found to
be insecure.
Substations are equipped with devices called Remote Terminal Unit (RTU) which
collect various types of measurements from the field and are responsible for
transmitting them to the control center.
More recently, the so-called Intelligent Electronic Device (IED) are replacing or
complementing the existing RTUs.
Once the data are collected, they are processed in order to determine the system
state.
It is possible to have a mixture of these devices (RTUs and IEDs) connected to a
Local Area Network (LAN) along with Supervisory Control And Data Acquisition
(SCADA) front end computer, which supports the communication of the collected
measurements to the host computer at the control center.
The SCADA host computer at the control center receives measurements from all
the monitored substations’ SCADA systems via one of many possible types of
communication links such as fiber optic, satellite, microwave, etc.
Fig.2 shows the configuration of EMS / SCADA system for a typical power
system.
Fig.2 shows the configuration of EMS / SCADA system for a typical power
system.
SCADA host computer
Planning
Local Area Network Energy Management CONTROL
and
System (EMS) Functions CENTER
analysis
functions State Estimator
Communications
CORPORATE
Network
OFFICES
SCADA - Front end computer
SCADA - Front end computer of another substation
These raw data and measurements are processed by State Estimator (SE) in
order to filter the measurement noise and detect gross errors. State estimator
solution will provide reliable estimate of the system state based on the available
measurements and on the assumed system model.
This will then be passed on to all the Energy Management System (EMS)
application functions such as the contingency analysis, automatic generation
control, automatic load frequency control, economic load dispatching, load
forecasting and optimal power flow, etc.
The same information will also be available via a LAN connection to the corporate
offices where other planning and analysis functions can be executed off-line.
1. Explain why the frequency and voltage keep changing in the uncontrolled
power system,
6. Name the two control loops in a generator and briefly describe them.
12. With necessary block diagram, explain what do you understand by “Real