Method Statement Demi Water Flushing

The document provides a method statement for flushing a demineralized water piping system. It describes the scope and purpose of the flushing work, outlines 6 steps for the flushing procedure, and provides details on preparations, flushing methods, and monitoring. The flushing aims to remove foreign materials from pipes and equipment to prevent damage.

Uploaded by

MinaShokry
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
92 views6 pages

Method Statement Demi Water Flushing

The document provides a method statement for flushing a demineralized water piping system. It describes the scope and purpose of the flushing work, outlines 6 steps for the flushing procedure, and provides details on preparations, flushing methods, and monitoring. The flushing aims to remove foreign materials from pipes and equipment to prevent damage.

Uploaded by

MinaShokry
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 6

METHOD STATEMENT FORM

Cost Center Name : Layyah CCPP Cost Center No. : 5002 MS No. :

Procedure:

Complete sections 1,2,3 – Method Statement X


Complete Risk Assessment – SI005 Att.02 X
Attach any additional documents and drawing as necessary X
Complete section 5- Sign and submit to Site Management Review X

1- Description of Work:

Civil Electrical √ Mechanical Other (Please specify)

Location of Work: Demi Water Storage tank Start Date: 4/12/2021


End Date: 1/03/2021

Brief Description of Work:

To carryout Flushing for Demineralized Water Piping System using Demi water.

Purpose:

The purpose of water flushing is to eliminate from piping and equipment all foreign matter
such as metal pieces, welding slag, sand, bolts, tools, etc. which may otherwise plug pipes, control
valves and orifices and cause serious damage to moving parts of equipment. Water is a good
flushing medium to remove and carry away loose foreign material but does not eliminate rust or
other matter bonded to surfaces.

Scope:

This procedure applies Flushing for Demineralized Water Piping system marked on the
attached P&ID’s.

The abbreviations
 TCCW: Temporary Closed Cooling water
 GT: GAS TURNINE
 PGB: PUMP KKS

SI 005 Att.01 Rev.01 10 Jun 2019 Page 1 of 6


METHOD STATEMENT FORM

Flushing procedure:

 Joint Walk Down with HSE to the area before commencing the activity to ensure the
area are safe.
 Issue PTW and STARRT before commencing the activity.
 Prior to starting the flushing activities, it shall be ensured that the pump suction pipes
are Visual inspection for pump suction spool from strainer to the pump and cleaning by
air if needed
 Permanently installed valves shall be used to establish the flushing flow path as per the
attached marked P&ID’s and ON/OFF Valve list.
 The Demi tank filled up from SEWA Demi line
 Ensure that all the permanent supports installed.
 Ensure Tag Out are in place for open and closed valves and assigned watcher/s to
control opening and closing valves.
 List of authorized persons (Day and Night) to be attached along with the PTW and
prevent any other to enter the site.
To achieve the required criteria as per contract and performance of the pumps, we
divided the system to 5 steps, the step complete when the criteria achieved.

STEP-01: Demi water pumps Suction pipes Flushing

Suction line to be flushed by open flushing method depending on water head in the demi tank. The
interconnecting spool between the Pump and suction strainer to be dismantle and cleaned by
manually.
1. A blind flange to be installed on pump suction bore to be isolated and protected.
2. Suction strainer to be removed.
3. A temporary flange with sock-let connected with hose to be installed downstream the
suction strainer, the hose routed to SEWGA existing drain pit.
4. Open common tank suction valve 00GCK01AA009.
5. Open pumps suction valves one by one 00GCK01AA002, 00GCK01AA 003 and
00GCK01AA 004.
6. Monitor the water color at the disposal end and take a sample for test.

STEP -02: Demi water pumps Discharge pipe flushing


Discharge line to be flushed by open loop flushing method depending on water head by operate
Demi water distribution pump. Water streams through suction pipe from demi tank, suction
strainer, pump casing and discharge valve till the terminal points
1. All orifices to be removed.
2. A temporary flange with sock-let (with hose connected) to be installed on terminal
points.
3. Flushing discharge line by opening Suction valves 00GCK01AA002, 00GCK01AA
003 and 00GCK01AA 004 and discharge valves00GCK02AA002, 00GCK02AA 003
and 00GCK02AA 004 for each pump one by one.
4. Monitor the water color at the disposal end and ensure no observable debris then take a
sample for test.

SI 005 Att.01 Rev.01 10 Jun 2019 Page 2 of 6


METHOD STATEMENT FORM

STEP-03: Demi water Min flow line flushing:


All min flow line to be closed flushed by operating DW pumps one by one and close all
pump discharge valves system.
1. All orifices be removed.
2. Install temporary mesh before Demi water tank.
3. Flushing Min flow line by opening Suction valves00GCK01AA002, 00GCK01AA 003
and 00GCK01AA 004 and close discharge valves00GCK02AA002, 00GCK02AA 003
and 00GCK02AA 004 for each pump one by one and operate demi water distribution
pumps one by one.
4. Monitor the water color at the disposal end and ensure no observable debris then take a
sample for test.
STEP-04: Temporary Closed cooling makeup line Flushing
Temporary Closed cooling makeup line to be flushed by open flushing method
depending on water head by operate Demi water distribution pump. Water streams
through suction pipe from demi tank, suction strainer, pump casing and discharge valve
till the terminal points at makeup tank.
1. All orifices be removed.
2. A temporary flange with sock-let (with hose connected) to be installed on terminal
points.
3. Flushing Temporary Closed cooling makeup line by opening Suction valves and
discharge valves for each Demi water distribution pumps.
4. Monitor the water color at the disposal end and ensure no observable debris then take a
sample for test.
STEP-05: Denox suction line flushing
Suction line to be flushed by open flushing method depending on water head in the
Denox tank. The interconnecting spool between the Pump and suction strainer to be
dismantled and cleaned by hand.
1.A blind flange to be installed on pump suction bore to be isolated and protected.
2. Suction strainer to be removed.
3. A temporary flange with sock-let connected with hose to be installed downstream the
suction strainer, the hose routed to a tanker truck or nearest drain pit.
4. Open common tank suction valve 00GCK01AA010.
5. Open pumps suction valves one by one 00GCK01AA006, 00GCK01AA007 and
00GCK01AA008.
6. Monitor the water color at the disposal end and take a sample for test.
STEP-06: Denox Discharge line flushing up to water injection skid and Evap
Cooler skid:
Discharge line to be flushed by open flushing method depending on water head by
operate Denox pump. Water streams through suction pipe from Denox tank, suction
strainer, pump casing and discharge valve till the terminal points.

1.All orifices be removed.


2. A temporary flange with sock-let (with hose connected) to be installed on terminal
points.
3. Flushing suction/discharge line by opening Suction valves 00GBB01AA003,
00GBB01AA004 and 00GBB01AA005, and discharge valves for each pump one by
one.
4. Monitor the water color at the disposal end and ensure no observable debris then take a
sample for test.
SI 005 Att.01 Rev.01 10 Jun 2019 Page 3 of 6
METHOD STATEMENT FORM

Preparation for flushing:


 Site note to be prepared in advance of 24 hrs. before start of flushing activity.
 All required documents such as permit, mark up P & ID drawings.
 Temporary Hoses connections shall be prepared and installed at required locations as
per the marked drawings.
 Flushing area will be barricaded with hard barricades and plastic chains and proper
signage’s.
 The flushing will be under 6 bar Max. from the permanent pump.
 Flushing area will be barricaded by using safe distance calculation.
 Warning sign boards to avoid unauthorized entry shall be at placed.
 Only authorized persons shall be allowed inside barricaded area to perform flushing
activity.
 Watchers shall be available at accesses.
 Temporary connections will be made off with metal pipes.
 Visual checking of the temporary connections will be carried out to confirm the flange
tightness before start of the activity.
 Water shall be filled into the water Demi tank by using SEWGA line.
 Demi water will be used for flushing.
 Radios will be used for communication during the flushing.
 Walk down shall be carried out with HSE and Commissioning team before start of
flushing activity.

Flushing:

 Demin water will be used for flushing.


 Demi& Denox water pumps will be used for flushing.
 System to be flushed by open flushing method.
 Continuous monitoring will be carried out in Demi storage tank to maintain the water
level during flushing.
 If the Demi water level decreased SEWGA inlet valve will be open to fill the water into
the Demi storage tank to maintain the water level.
 Manpower with walkie-talkie will be available at all temporary hoses during the
flushing activity.
 Filters will be cleaned by using clean water.
 During cleaning of the filter, the dust particles shall be collected in a plastic cover.
 Flushing will be continued until the cleanliness of the pipe is accepted.
 Cleanliness of the pipes will be determined by taking water sample and analyzed for
Conductivity, Iron and PH and should match with initial water sample before flushing.
 The process should continue until 100% particles free and crystal-clear water appear three
times in a row on the water samples.

Draining of water after flushing:


SI 005 Att.01 Rev.01 10 Jun 2019 Page 4 of 6
METHOD STATEMENT FORM

 Flushing, water will be drained to SEWGA Pit as per agreement with SWEA Via
Email (Will be attached).

Restoration:
 After flushing has been complete and accepted by the parties, all temporary

installed devices shall be removed and the system re-instated to normal operating
conditions
Emergency Preparedness:
 The area shall be barricaded with proper sign boards.
 Walkie talkie radios will be used for communication.
 In case of emergency work will be suspended.
 Barricading will be done around the loops as per the attached safe distance range.

Attachments:

 ON/OFF valves list.


 Marked up P&ID.

2- Operational details:

Permit To Work: Activity Type and Special Needs:


Work at heights Electrical Tools
x Yes Confined Space Electrical Installations Special PPE:
Manual Lifting Welding Equipment
No Crane Operation Gas/Gas Cylinders Co-activity:
High-risk activities Excavator Chemicals
X Plant/Equipment Dangerous Goods X Others:
Other Machines Heavy Transport Site note

Road Block

Using of Hazardous substances

Yes X No
Material Safety Data Sheet available (To be attached with MSRA) Yes No
Any special handling procedures available (To be attached with MSRA) Yes No

Temporary Services Required:

Electricity Yes No
Lighting Yes X No Tower light, electrical fixtures

SI 005 Att.01 Rev.01 10 Jun 2019 Page 5 of 6


METHOD STATEMENT FORM

Water Yes X No Drinking water


Other Yes No

Manpower.

Supervisor 2 Machine operator 1


Skilled Person 3 First Aider 1
Unskilled person / Temporary worker HSE 1

3- Complete the Risk Assessment Form:


Att. 02 the Risk Assessment form by developing all of points mentioned in the section 2, 3 above.
Attach plans and drawing as required.

Number of Risk Assessment pages: 6


List of Attachments:
1. P &ID Drawings.
2. ON/OFF Valve list.
3.

4- Applicant responsibility
The Applicant is responsible to ensure that all of the conditions as stated in this MSRA are implemented
and that the full content of the MSRA is transferred to and clearly understood by all personnel involved
via a signed tool-box-talk prior to the commencement of the work. A copy of the MSRA must be
available at the work area at all times for reference and review.

Applicant Mohamed Reda Commissioning Mech 2.12.2021


Lead
Name Position Signature Date