Method Statement Demi Water Flushing
Method Statement Demi Water Flushing
Cost Center Name : Layyah CCPP Cost Center No. : 5002 MS No. :
Procedure:
1- Description of Work:
To carryout Flushing for Demineralized Water Piping System using Demi water.
Purpose:
The purpose of water flushing is to eliminate from piping and equipment all foreign matter
such as metal pieces, welding slag, sand, bolts, tools, etc. which may otherwise plug pipes, control
valves and orifices and cause serious damage to moving parts of equipment. Water is a good
flushing medium to remove and carry away loose foreign material but does not eliminate rust or
other matter bonded to surfaces.
Scope:
This procedure applies Flushing for Demineralized Water Piping system marked on the
attached P&ID’s.
The abbreviations
TCCW: Temporary Closed Cooling water
GT: GAS TURNINE
PGB: PUMP KKS
Flushing procedure:
Joint Walk Down with HSE to the area before commencing the activity to ensure the
area are safe.
Issue PTW and STARRT before commencing the activity.
Prior to starting the flushing activities, it shall be ensured that the pump suction pipes
are Visual inspection for pump suction spool from strainer to the pump and cleaning by
air if needed
Permanently installed valves shall be used to establish the flushing flow path as per the
attached marked P&ID’s and ON/OFF Valve list.
The Demi tank filled up from SEWA Demi line
Ensure that all the permanent supports installed.
Ensure Tag Out are in place for open and closed valves and assigned watcher/s to
control opening and closing valves.
List of authorized persons (Day and Night) to be attached along with the PTW and
prevent any other to enter the site.
To achieve the required criteria as per contract and performance of the pumps, we
divided the system to 5 steps, the step complete when the criteria achieved.
Suction line to be flushed by open flushing method depending on water head in the demi tank. The
interconnecting spool between the Pump and suction strainer to be dismantle and cleaned by
manually.
1. A blind flange to be installed on pump suction bore to be isolated and protected.
2. Suction strainer to be removed.
3. A temporary flange with sock-let connected with hose to be installed downstream the
suction strainer, the hose routed to SEWGA existing drain pit.
4. Open common tank suction valve 00GCK01AA009.
5. Open pumps suction valves one by one 00GCK01AA002, 00GCK01AA 003 and
00GCK01AA 004.
6. Monitor the water color at the disposal end and take a sample for test.
Flushing:
Flushing, water will be drained to SEWGA Pit as per agreement with SWEA Via
Email (Will be attached).
Restoration:
After flushing has been complete and accepted by the parties, all temporary
installed devices shall be removed and the system re-instated to normal operating
conditions
Emergency Preparedness:
The area shall be barricaded with proper sign boards.
Walkie talkie radios will be used for communication.
In case of emergency work will be suspended.
Barricading will be done around the loops as per the attached safe distance range.
Attachments:
2- Operational details:
Road Block
Yes X No
Material Safety Data Sheet available (To be attached with MSRA) Yes No
Any special handling procedures available (To be attached with MSRA) Yes No
Electricity Yes No
Lighting Yes X No Tower light, electrical fixtures
Manpower.
4- Applicant responsibility
The Applicant is responsible to ensure that all of the conditions as stated in this MSRA are implemented
and that the full content of the MSRA is transferred to and clearly understood by all personnel involved
via a signed tool-box-talk prior to the commencement of the work. A copy of the MSRA must be
available at the work area at all times for reference and review.