Kaizen Event Criteria
Kaizen Event Criteria
Implementation
This page intentionally left blank
Kaizen and Kaizen
Event Implementation
Chris A. Ortiz
Preface xi
Acknowledgments xv
About the Author xvii
Introduction xix
Production Supervisor 23
Contents
Operator Representative 24
Introducing the Kaizen Champion 24
Tracking 25
Kaizen Event Selection 26
Date and Length 28
Kaizen Event Team Leader 28
Kaizen Team Members 28
Preplanning and Preplanning Responsibility 29
Pre-event Goals 30
Actual Results 30
Event Budget and Event Spending 30
Action Items, Responsibility, and Status 31
Kaizen Communication 33
Kaizen Communication Boards 34
Kaizen Newsletter 34
Kaizen Suggestion Box 35
Contents
Training 50
Kaizen Monthly Meeting 51
Communication Boards 51
Kaizen Newsletter 51
Kaizen Suggestion Box 52
Kaizen Event Tracking Worksheet 52
Team Leadership 52
Action Item Follow-up 52
Monitoring Other Lean Initiatives 53
Alternatives 53
Why a Kaizen Champion? 54
5 5S Kaizen Events 69
Four Weeks to Go 70
Select the Area 70
Select the Team Leader 70
Tentatively Select the Team Members 71
Establish Goals 71
Event Spending and Supplies 71
Update the Kaizen Communication System 72
Identify the Kaizen Team Meeting Space 72
Schedule Outside Assistance 72
Two Weeks to Go 72
Finalize Kaizen Team Members 72
Get an Update on Supplies and Outside Resources 72
Ask Team Members to Walk Through the Selected Area 73
One Week to Go 73
Gather Current State Information 73
Meet with the Kaizen Team Members 73
Place All Supplies in the Team’s Meeting Room 74
Meet with the Plant or General Manager 74
Let It Begin! 74
Day One: Sort 74
Day Two and Day Three: Set in Order and Scrub 79
Day Four: Standardize 83
Day Five 84
Maintenance 5S Events 84
Day One: Sort 85
Day Two and Day Three: Set in Order and Scrub 86
Day Four: Keep Going 87
Day Five 87
ix
5S Sustaining Tips 87
Contents
Create an End-of-Day Cleanup Procedure 88
Conduct a Daily/Shift Walk-through 88
Establish a 5S Audit Sheet 88
Create and Maintain a 5S Tracking Sheet 89
Develop a 5S Incentive Program 90
8 Conclusion 131
Index 133
Preface
How long do new ideas, once implemented, last? Many of you may
have embarked on lean manufacturing journeys over the years, imple-
menting 5S, single-piece flow, standard work, kanban, or something
else, but you find that nothing seems to “stick.” Let me illustrate a
familiar manufacturing situation.
Each team was assigned tasks the company deemed important to imple-
P re f a c e
menting lean. Each team met regularly to discuss its projects and possi-
ble improvements, not knowing what the other groups were addressing.
It is pretty clear that a company like this needs better ways of imple-
menting lean manufacturing processes. Yet implementation of lean does
not necessarily guarantee success if there is no support from top man-
agement. Without that support and a foundation for change, new ideas
will fall by the wayside. There has to be focus, dedication, and commit-
ment to making and sustaining long-term improvements.
3. Train employees.
P re f a c e
Employees in Company A, including operators, need to understand
fundamental lean and kaizen concepts such as 5S, standard work,
visual management, waste reduction, and takt time. As time goes on,
more and more employees will begin to understand the importance
of lean and kaizen, and a culture of change agents is created.
4. Hold monthly meetings.
Company A’s kaizen committee should meet once a month and
schedule kaizen events. All kaizen events should be scheduled four
weeks in advance for planning purposes. Team members should be
selected two weeks in advance, to allow them to plan accordingly
and so that their managers can prepare for their absence. Vacation
time can be verified to ensure that team members are available for
the event. This two-week time frame allows the team members to
make arrangements at home if the team is to work an off shift.
5. Conduct kaizen events.
Kaizen events are used to implement continuous improvement on
the factory floor. Holding an event every month will help the organi-
zation’s culture evolve into one of continuous improvement. Before
anyone can go back to the old ways of working, another kaizen event
is going on. Over time, new standards and procedures will be cre-
ated and resisting change will become harder.
6. Develop vision and focus.
The keys to implementing lean are vision and focus. Company A
had some vision, but no focus. Permanent changes will not happen
if a company simply “grazes” along with improvement initiatives. A
company can be staffed with the best lean talent, but without the
infrastructure to encourage and sustain improvements, the grazing
will continue. Developing a company kaizen program to act on this
vision and focus is essential to lean success.
Second, I want to thank the staff at Prentice Hall who first took interest
in this book for their professional approach to making it become a
reality. I want to acknowledge my editor, Bernard Goodwin, for his
passion for lean manufacturing and for taking on my project.
xv
This page intentionally left blank
About the Author
xvii
This page intentionally left blank
Introduction
• Kaizen
• 5S
• Standard work
• Setup reduction and quick changeover
• Kanban
• Quality at the source
• Total productive maintenance (TPM)
Kaizen
Kaizen is a Japanese word for “continuous improvement.” Kaizen
involves all employees in a company focusing on process improvements.
This first piece of the lean journey is often confused with lean itself, but
xix
xx
kaizen is not lean. Lean is about removing waste; kaizen is about contin-
I n t ro d u c t i o n
• Sort: the act of removing all unnecessary items from the work area
• Straighten: organizing what is needed so everything has a home and
its identity and location are clearly marked
• Scrub: cleaning everything
• Standardize: maintaining consistency in the visual workplace
• Sustain: maintaining improvements and continually improving
upon them
Standard Work
Another powerful improvement tool is standard work. Standard work is
essentially “best practice.” It is an agreed-upon set of work procedures
that establishes the most efficient, most reliable, and safest methods and
sequences for each process and each worker. In a standard work envi-
ronment everyone has clear roles and responsibilities. More important,
people and machines are used to their fullest potential, and workloads
are evenly spread out. For instance, work content required in each
workstation on an assembly line should be outlined in detail, and
cycle times should be as even as possible. This allows for better flow,
and it places the same workload on each individual. If one operator
has 5 minutes’ worth of work in a workstation and another one has
31⁄2 minutes, then they are not evenly balanced; either the person with
5 minutes of work is overloaded, or the operator with 31⁄2 minutes of
xxi
I n t ro d u c t i o n
the person with 31⁄2 minutes of work is not maximized; hence the com-
pany is less productive.
Material handlers should have specific routes and routines and assigned
areas of responsibility. A person operating a piece of equipment should
follow certain setup and machine-run tasks, and this work should be
associated with a time standard. To ensure higher productivity and bet-
ter use of time, the machine operator needs to follow this standard
work. Standard work is supported through the proper documentation of
work instructions that outline the requirements of the work. These
instructions could be in the form of assembly instructions, setup
instructions, changeover instructions, material handling maps and
routes, cleanup procedures, and start-up procedures. The list can go on
and on. Standard work is an integral part of lean and must be incorpo-
rated at some point.
it’s too late. So reducing the time associated with setups and
I n t ro d u c t i o n
Kanban
Kanban is a material replenishment system that incorporates signals,
pull instructions, visual cues, bins, carts, containers, etc., to help coor-
dinate material and parts transactions throughout the factory and with
suppliers. Material and parts are kept in specified quantities and con-
tainers when needed. Implementing a kanban system will help your
company reduce the amount of inventory and help predict better flow
of material. It will help simplify scheduling and improve productivity.
The amount of material or parts for each kanban item depends on prod-
uct volume, size of the part, lead time from the stockroom, supplier
lead times, supplier quantities, market trends, and variations in your
model mix. Each kanban system, like all lean systems, must be tailored
to each business model and structure. There is no “one size fits all.”
may have just relied on end-of-line checks to ensure quality. In this lean
I n t ro d u c t i o n
system, quality is everyone’s job.
A TPM program should have three levels. The first level is the TPM
required by the machine operator. These tasks include daily cleanup
and checking operating conditions such as fluid levels, heat, and power.
First-level TPM is relatively simple and should be performed daily. The
second level of TPM is the work performed by a maintenance depart-
ment less frequently, maybe once a week or month, depending on the
machine’s use. Sometimes second-level TPM requires a total or partial
teardown of the machine for repairs or replacing parts. The third level
of TPM is the work performed by the manufacturer of the machine.
This may be done once or twice a year. All levels of this TPM program
are worth the investment in time and money to ensure that your equip-
ment can operate at optimum productive levels and last the length of its
life cycle.
seven wastes, as they are the focal point of all improvement initiatives
I n t ro d u c t i o n
In the course of your lean journey, you will learn of other lean philoso-
phies and tools that can be used to reduce waste.
How you use and mix these tools depends on your culture, company,
and processes. More important, they are all simply part of the lean phi-
losophy. This book is dedicated to teaching you about kaizen and
kaizen events. The first chapter will outline a company’s struggle with
how lean is applied in its organization. As employees juggle multiple
projects, deal with day-to-day issues, and are asked to wear many hats,
finding time for lean is difficult. The chapter will then dive into the fine
detail of kaizen and kaizen events, comparing the two and showing you
common mistakes made in developing a kaizen program.
xxv
I n t ro d u c t i o n
2. Topics will include the kaizen event steering committee and a kaizen
champion who is 100 percent dedicated to continuous improvement.
It will also discuss tracking and scheduling kaizen events as well as
kaizen communication. This chapter will give you information on how
to piece together the program that will embrace ongoing change.
The first four chapters lay the groundwork for the remainder of the
book. Chapters 5 and 6 will describe how to use kaizen events for the
implementation of 5S, standard work, kanban, and a new line design.
They will help you see how kaizen events are used for implementation
and ongoing improvements to your organization. Each kaizen event con-
cludes with a formal presentation, called a report out, and a tour. It is
important to invite as many employees in the company as possible to
this report-out session so that the team can discuss their accomplish-
ments and how they improved the performance and culture of the busi-
ness. Chapter 6 will conclude with this information.
1
This page intentionally left blank
1 o n
I am not implying that lean journeys do not involve setting goals for
improvement such as increasing productivity, reducing scrap, improv-
ing on-time delivery, reducing inventory, or decreasing throughput time,
for example; but how each company works to accomplish these types of
metrics is different. You cannot adopt one organization’s practices and
apply them to your own organization in exactly the same way. I often
see this confusion when teaching the “phenomenon” of lean. People
struggle to connect the dots and see how it will work in their organiza-
tion. It is this first misconception I would like to discuss in this chapter.
3
4
Kaizen
Chapter 1: Kaizen and Kaizen Events
People of Kaizen
Kaizen
Some companies place the responsibility for process improvements on
manufacturing engineers and managers. These individuals generally
come up with the initial ideas to improve a work area, conduct the
analysis and preplanning, and then implement the change. Production
workers feel that the new process is being “pushed” on them because
they were not given the opportunity to suggest improvements. This is
not the case across all spectrums, but it is still a very common practice.
In kaizen-based organizations, process improvements involve everyone
from executive leadership down to the entry-level production worker.
This includes the creation of the improvement idea, process analysis,
preparation phases, implementation, and training. The kaizen philoso-
phy not only encourages production workers to suggest improvements
but requires that they do so. This can be difficult for some leaders to
swallow because it essentially means relinquishing some of their
authority in the improvement process. I have come across many plant
and other upper managers who find it difficult to delegate decision
making for the company. The most successful lean journeys occur, how-
ever, when upper and even executive managers back off and provide an
environment that fosters change. When people are allowed to speak
openly and make changes from their own perspectives, the possibilities
are endless. Managers who allow and encourage this behavior will see
far more progress in their organization’s lean journey than those who
tend to make all the decisions themselves.
Leaders of Kaizen
Becoming a leader of kaizen takes time because leaders are part of com-
pany culture just like engineers, maintenance personnel, and produc-
tion workers. Transformation into a kaizen leader does not happen
overnight. As I mentioned in the preceding section, kaizen leaders must
learn to release some of their hold on authority and give it to everyone
in the company so that change and improvements can spread through
the organization. Next, kaizen leaders must not focus on the financial
gain from lean but rather on using kaizen to help develop their people.
I took all that I learned from my experiences and use it now to lead
companies in a manner that seems fair and just. Organizations embark-
ing on lean need effective leaders who understand the importance of
employee contributions and how much their efforts and attitudes affect
the success or failure of a company. Certain corporate leaders need to
realize that although aggressive practices may result in short-term finan-
cial success, they also place the company on the path toward a precari-
ous future.
Lean leaders are only human beings; therefore, they typically conduct
themselves in a manner that reflects their personality. If individuals are
generally grumpy and negative to change, their management techniques
will reflect those characteristics, and they will affect the morale of oth-
ers through their body language as well as their words. Individuals who
7
are happy and positive tend to lead in the same manner. Lean leaders
Kaizen
who do not let negativity influence their actions will create a following
of positive thinkers.
Benefits of Kaizen
Kaizen teams are created to provide a quick and positive impact on the
organization. Each team member is handpicked according to his or her
ability to make both measurable and nonmeasurable improvements.
Kaizen events teach people the concepts of teamwork, meeting dead-
lines, interacting with different personalities, and pursuing excellence
8
Kaizen Events
Learning the theory behind kaizen is important as you begin your lean
journey. Now let’s talk about how to turn that philosophy into action.
Often called a rapid improvement project, a kaizen event is a set time
frame that is scheduled to allow a group of employees to come to
together and implement lean and remove waste. The core of this book
outlines how to create a company kaizen program and, more impor-
tantly, how to schedule, conduct, and follow up on kaizen events.
Ideally, a company should try to get to the point where it can conduct
kaizen events every month. Don’t expect to do this in the first year.
Maybe scheduling kaizen events once a quarter or every other month is
best in the beginning. It depends on your culture, production schedules,
and what other important projects and activities are going on in the
company. My job in this book is to provide you with information that
will allow you to schedule monthly kaizen events. As time goes on, you
will become better at planning and conducting them.
Many organizations use kaizen events but still cannot create a culture
that embraces change, and many improvement efforts fall short of their
cultural and financial goals. The reason behind this is that the company
did not have the infrastructure in place to keep everyone involved,
9
Kaizen Events
become annoying to some if the events are disorganized and under
management that does not support the efforts. Management must set
clear direction on why kaizen events are important and place specific
goals in front of each team. I will outline these important ingredients of
the program in this book.
• Lack of communication
• Lack of planning
• Poor team selection
• No goals
Lack of Communication
Lack of Planning
Kaizen Events
product, and creating their early buy-in is a key ingredient to sustaining
improvements. Each team will need a maintenance person, line opera-
tors, engineers, managers, material handlers (if applicable), and maybe
another office employee. The number of team members will depend on
the complexity of the kaizen event and what needs to be accomplished;
I will discuss this in greater detail in Chapter 3. By having a diverse
kaizen team, you enable the group to come up with a greater variety of
improvement ideas than would probably come from a team consisting
of just managers and engineers.
No Goals
Improvement Improvement
Metrics
Chapter 1: Kaizen and Kaizen Events
Productivity
Productivity is improved when more products are made and more serv-
ices are provided with less effort. The less material, parts, manpower,
time, utilities, paperwork, processes, and steps that are needed, the
more costs can be reduced. Quality is improved because the opportuni-
ties for error are decreased. Fewer steps mean faster throughput and
better delivery. Kaizen teams should always pursue productivity
improvement goals.
Inventory/WIP
There are essentially three types of material: raw material, partially fin-
ished goods, and 100 percent finished goods. Sheet metal, the raw mate-
rial, can be cut into small pieces such as brackets, plates, or covers.
These parts then become work in process (WIP) and can be placed into
a product and moved on to another processing step. Partially completed
products move through various stages of assembly or processing until
they become a finished product ready for sale. Regardless of the stage
that this material is in, it costs money. Inventory should be kept at a
minimum throughout the plant regardless of its phase in manufacturing.
Manufacturing processes should be short with minimal steps so that
unnecessary WIP does not build up. WIP can hide quality errors that
may eventually lead to rework. Kaizen teams can focus their efforts on
reducing inventory levels and WIP. Obviously a lower level of inventory
can reduce cost, but it can also improve quality by creating better visi-
bility of problems that can potentially hide in excess WIP. And large
clumps of WIP are stopping points or slow-moving points that can
adversely affect delivery.
Quality
Kaizen Events
larly a mind-set of proactive error prevention rather than reactively
dealing with problems. Errors will occur if human beings are part of the
manufacturing process. Even in highly automated environments,
machines and equipment require human interaction such as setup,
maintenance, programming, cleanup, and changeover. An automated
process’s output is only as good as the human input.
Floor Space
increases can take place. When floor space use is reduced, cost is
Chapter 1: Kaizen and Kaizen Events
Workstations
Station reduction or better use of stations goes hand in hand with floor
space use and productivity. Having fewer stations means less “stuff”—
fewer workbenches, parts, shelves, tools, paperwork, fixtures, lights, etc.
Using the appropriate number of workstations limits the number of peo-
ple in the process and therefore decreases the opportunity for error.
Again, I am not implying job loss, just smarter use of people and the
work they perform. Kaizen teams can have a goal of reducing the num-
ber of workstations, consolidating processes, or coming up with a more
balanced workload among operators. Reducing the number of worksta-
tions reduces the cost associated with extra items and too much labor.
Quality is improved and work content among workers is balanced and
better defined, so work areas can be better used. Fewer stations and
processes required to complete products mean faster delivery.
Travel Distance
Kaizen Events
takes more time for something to travel 300 feet than 30 feet. The longer
a product is in the building, the more money it costs. As an example, I
led a kaizen event where the team was required to reduce travel dis-
tance by 30 percent. It was a reasonable goal, and the team focused their
waste reduction efforts on achieving that goal. After they calculated the
correct number of workstations for the assembly line, balanced the work
between stations, and converted to single-piece flow, travel distance
went from 350 feet to 50 feet. By eliminating 300 feet of travel distance,
the team reduced the throughput time by 82 percent, from 11 hours to
2 hours. Think about the customers waiting for their products on these
lines . . . delivery, delivery, delivery!
So, kaizen teams can have travel distance reduction goals based on the
respective product line. Cost is reduced simply because it requires less
effort to complete the product. Quality is improved because there is less
distance to travel and fewer chances for error. And delivery—well, I
think I have said enough about that.
This page intentionally left blank
2 t w
17
18
I will then address how to customize the program for your organization.
Organizational structures vary in size and in the titles they use for dif-
ferent positions, so there is no perfect committee structure that can be
used in every company. However, certain disciplines and areas of
responsibility need to be accounted for on the committee. So before I
can outline the requirements of the committee, here is a list of titles and
why the people who have these titles should be members. Again, look
at why each position is on the committee and decide who in your
organization can fulfill that role.
• Production supervisor
All lean projects and initiatives being conducted throughout each year
must fall in line with your company’s lean strategy. This lean strategy is
based on measurable results that were discussed in Chapter 1; produc-
tivity, quality, throughput time, floor space, inventory, and workstation
quantity are all metrics that, when improved, can make positive
changes to on-time delivery, cost, and overall quality for your cus-
tomers. A lean strategy outlines the lean goals for the company, and all
efforts at continuous improvement should be directed to those goals.
Don’t forget that the committee will also track and monitor the smaller
projects outside of structured kaizen events as well. So the plant man-
ager’s job is to ensure that whatever is planned by the kaizen event
steering committee is driven by the strategy.
Quality Management
The quality manager can provide a lot of information during the pre-
planning phase. Kaizen teams will need information about internal and
external quality on each product and process. Internal quality data such
as rework, scrap, defect rates, first-pass yield, and reject rates is valu-
able information to gather so that the teams can make improvements to
these metrics. Also, information collected from customers can poten-
tially be used. The number of complaints, on-site technical service
calls, and warranty claims, for example, can help kaizen and kaizen-
event-related efforts. Not all quality issues in the field or with the cus-
tomers are directly related to the factory, but external data can still play
a role in improving quality.
Like all the other managers on the kaizen event steering committee, the
quality manager must provide the right people from his or her depart-
ment to assist the team in developing new work instructions and testing
and inspection procedures. The quality manager can also provide ade-
quate support to guide the team in the correct approach to part protec-
tion when constructing new workstations or work cells.
21
Kaizen events will use production workers, and the production manager
will have to adjust his or her workforce during the kaizen event. Like
all other managers, the production manager is responsible for training
employees at some level. As changes are made to the line or process,
new training will be needed, and the production manager can allocate
the resources to help. The main reason the production manager is on
the kaizen event steering committee is that he or she will make or break
the improvements that are implemented. The people who report to the
production manager must know that their leader is behind the changes
100 percent.
The human resources (HR) department plays a vital role in the continu-
ous improvement efforts in the company. The obvious reason is that HR
is responsible for all the employees, including the plant manager, and
has information about each employee specifically. For instance, during
22
There may also be a need to remove items from the stockroom that are
stored up high. If the team decides to move large equipment around, a
forklift is most likely needed. The purchasing or materials manager may
be the one kaizen event steering committee member responsible for
ordering supplies for the kaizen team. After the area has been selected
and goals are established, this person can begin the preplanning work
for purchasing.
Production Supervisor
Operator Representative
C h a p t e r 2 : T h e C o m p a n y K a i z e n P ro g r a m
The kaizen event steering committee is a vital part of the lean journey.
It is a great outlet for gathering ideas and developing a culture of team
players. As the company moves toward an overall approach to making
decisions, the lean journey is strengthened and accelerated. With my
clients, this committee is created very quickly and early in the process.
I encourage you to put together your committee soon after reading this
book to get things moving.
Once the kaizen champion has been identified, he or she becomes the
Tr a c k i n g
leader of the kaizen steering committee and runs all the meetings. It is
the job of the champion to ask the committee for assistance and to keep
the members accountable for contributing. The kaizen champion should
have a high level of authority, being able to go directly to the plant man-
ager to get what is needed. It is a kind of gray position, since the kaizen
champion is not a manager but has the “pull” of an upper manager.
This type of authority is needed to keep management committed to the
lean journey.
The kaizen champion is the “torchbearer” of lean and drives all kaizen-
related initiatives. He or she essentially is the director of the lean pro-
gram. This position is so important that I dedicate an entire chapter
(Chapter 3) to it. However, please remember that it is not a requirement
to have a champion; some companies cannot justify the new position or
the added salary regardless of the cost savings and other improvements
that will result. Chapter 3 will also provide alternatives to a kaizen
champion for companies that need another option. Either way, lean
needs resources and people to make it happen. I will show you how to
allocate the time and delegate accordingly.
Tracking
A lot of effort and time will be put into kaizen events, and it is impor-
tant to track progress and the effects on the company. This fundamental
aspect of project management falls on many people. I recommend that
you put together a kaizen event tracking worksheet that can be used to
measure event success. Remember that this tracking worksheet is to be
used to measure kaizen event results, not the overall lean journey. As I
mentioned in Chapter 1, it is important to encourage and allow people
to improve the company all the time, outside of kaizen events. This is
an event tracker only.
delivery, floor space use, and possibly travel distance. How much over-
Tr a c k i n g
time is being worked? Do operators leave their workstations a lot? Is
there excessive inventory or WIP piled up? Is the work area cluttered
and unorganized (5S)?
The traditional kaizen event is about five days long, but events can last
from four hours to four weeks. It depends on the work area, goals, the
product, floor space, and the level of waste. Simply place in this cate-
gory of the tracking worksheet the day and week or weeks when the
event will be held. It is also good to write in the hours that will be
worked: 8:00 a.m.–4:00 p.m., 10:00 a.m.–6:00 p.m., and so on.
• Forklift driver
Tr a c k i n g
• Shipping employee
• Manager
Each kaizen event will require some level of preplanning, which is usu-
ally the responsibility of the kaizen event steering committee. A multi-
tude of tasks need to be completed prior to the kaizen event. Special
tools may need to be reserved. Employees from sister plants can be
invited. Adjusting production schedules and people to accommodate
the event time frame will have to be addressed. Conducting an evalua-
tion of the work area in order to assess current state performance may
be needed. During kaizen events the teams will need certain supplies
such as bins, racks, shelves, tape measures, paint, and floor tape. These
30
should be ordered ahead of time so that they are available on day one of
C h a p t e r 2 : T h e C o m p a n y K a i z e n P ro g r a m
Pre-event Goals
During the early planning phase of any project, generating goals can be
difficult. Forecasting, in any form, can be lucky or lousy. It is important
that each kaizen team be faced with some moderate challenges. These
events are being conducted to improve your business, so don’t be afraid
to set those goals! It is best practice to refer back to the established shop
floor metrics, as discussed in Chapter 1, as a guide for improvements.
Be sure to establish realistic goals, as unattainable goal setting will only
serve to destroy the effort. An attainable goal might be improving pro-
ductivity 20 percent by reducing waste in a line or a process. Yet there
is no real guide for establishing your team goals. Simply set goals that
you feel are realistic and attainable, and make sure that you plan ade-
quately to ensure success.
Actual Results
After the kaizen event is complete and the workers go back to their nor-
mal jobs, the company should immediately begin to monitor progress to
see how quickly the goals are achieved. This column in the tracking
worksheet may not get filled in until the process or work area has con-
sistently met the expected goals. Are the new output requirements
being met? How are productivity and WIP levels? Is quality improving?
Did the team save the proposed amount of floor space and reduce
throughput time? It is important to realize that even if certain goals are
not met, the team did not fail. As your organization becomes more
experienced at kaizen and kaizen events, you will become better at esti-
mating metric and performance improvements.
improvement, and each kaizen team will need access to these funds
Tr a c k i n g
during the event. Spending for most kaizen events ranges from $0 to
$1,000, depending on what is necessary. Just allocate some money to a
kaizen budget. The rate of return will be great, and any money spent
will be quickly recouped from the improvements.
These last three columns in the tracking worksheet are used to monitor
any unfinished work from the kaizen event. Rarely does a kaizen team
finish every task during the kaizen event. Minor disruptions during the
project will make the team change course a little. Team members will
come up with many improvement ideas along the way, and not all of
them may be finished. All action items should be completed within
30 days of kaizen event completion; this is called the 30-day mandate.
The kaizen event steering committee can discuss this issue during their
monthly meeting.
The workers in the process will be the ones most affected by the
improvements, as they will have to adjust to a new way of working.
As waste is reduced, new ways of working have to be implemented to
ensure that the “lean process” will meet their output and quality expec-
tations. The committee needs to invite the previous team leader to the
meeting and have a discussion on progress. Once the update is com-
plete, the team leader can leave and the second phase of the meeting
can begin.
All action items from an event must be completed within 30 days. Each
item needs a person assigned to it and a firm deadline for completion.
To ensure that the new process can produce the required results, these
action items have to be completed on time. The team members who
have responsibility for action items should now be invited into the
meeting to discuss their progress. It is the job of the kaizen event steer-
ing committee to clear any obstacles that impede the completion of the
33
action items and provide any support necessary. Once all action item
Kaizen Communication
issues have been updated, the team members can leave and the commit-
tee can begin the last part of the meeting: planning future kaizen events
and other lean projects.
The kaizen event tracking worksheet is the only document needed for
the monthly meeting. During this last part of the meeting, the commit-
tee can discuss and possibly begin planning future kaizen events. As I
mentioned earlier, try to schedule kaizen events at least four weeks in
advance to allow for team selection and for the various preplanning
items to be completed. However, it is perfectly healthy to discuss events
two, three, and four months away. Just make sure, when your commit-
tee is planning future events and filling in the tracking worksheet, that
if any kaizen event already scheduled is coming up on its four-week
window, to start picking the teams and working on preplanning issues
at that point.
Kaizen Communication
Kaizen- and lean-related activities should be continually communicated
to the entire organization. As your culture slowly becomes more aware
that lean is a way of thinking and working, you have to learn how to
keep the momentum going. Develop what I call a kaizen communica-
tion system that works as an information delivery apparatus for your
company. Often when I conduct lean assessments of organizations I find
that general communication is lacking between departments. There is a
clear division between the operations/manufacturing side and the
administrative side. This gap in information and communication needs
to be bridged to ensure that everyone knows what is going on every-
where. Your company as a whole needs to realize that it wins or loses
as a team, and each department must contribute to team-based activities
to improve the operation. In regard to kaizen communication, I recom-
mend three items you can put in place:
• Area selected
• Date and length
• Kaizen team leader
• Kaizen team members
• Team goals and objectives
Kaizen Newsletter
Kaizen Communication
the communication boards: areas, team leaders, team members, etc.
More important, it should feature pictures of the team working, as well
as write-ups of individual accomplishments and how their efforts are
helping the plant. One unique approach to the kaizen newsletter is to
allow previous kaizen team members to write about their successes.
This will help further engage your people, as those who read the
newsletter will read about their buddy or colleague who works with
them. This is very powerful and it will speak volumes to the employees.
Line operators are often left out of the design and planning phase of
kaizen events. I have discussed the importance of placing operators on
kaizen teams, and it is my opinion that they should be involved with
deciding what area is scheduled for a kaizen event. Operators are usu-
ally confined to their workstations or areas on the production floor and
typically have little or no contact with management or engineers. Any
contact that occurs is usually initiated by the support staff in the work
area. How can you get operators and other floor employees involved
Much like a voting box, where ballots are submitted, the employee sug-
gestion box is used to collect ideas coming from the floor, ideas that can
be considered for future kaizen events. The box should be placed near
the communication boards or in operator break rooms for easy access. A
simple suggestion form should be placed near the box; see Figure 2-3
for an example.
When using any suggestion system, the company must develop a way to
communicate back to the workers about whose ideas are being selected
for a kaizen event, which ideas have been passed on to engineering,
maintenance, or purchasing, for example, and which ideas will be
addressed later. As this system becomes more and more popular, you
will get flooded with suggestions, especially when the workers see their
ideas actually being implemented. People by nature like information
even if it is not what they want to see or hear. Don’t leave employees in
the dark. Let them know if their idea is a go or not.
Employee Date
Department
Improvement Idea
W o u l d Yo u I m p l e m e n t ? Ye s No
Kaizen Communication
not difficult, but it will take some time. It also has to be made to fit the
culture you have to ensure that lean and kaizen will thrive. Remember
the following key points:
With this said, I am also aware that not all companies can afford to cre-
ate a new position for a kaizen champion. A good kaizen champion
who can produce results is not cheap, even if the return on investment
41
is well worth the new addition. There are alternatives, which I will dis-
This one is a no-brainer, but simply knowing the seven wastes is only
part of the game. Understanding where waste exists and how to reduce
or remove it is another. One of the biggest mistakes with regard to waste
is not knowing when it is necessary. Necessary waste is waste that is
either impossible to remove or is literally part of the process. An organi-
zation has to learn to prioritize its waste reduction efforts and decide
what waste is realistic to keep. For instance, workers in a company that
manufactures aircraft will have to walk up and down inside the air-
plane to install components. This movement in and out of the plane is
wasted motion, but I don’t see these actions ever being eliminated. A
factory will always have some level of raw material, WIP, and finished
goods. These may sit around for a very short period of time, but they
still constitute waste. Products will have to move from one work area to
42
The kaizen champion must have the ability to redirect the kaizen event
steering committee to ensure that any lean strategy that was created is
being fulfilled. He or she knows how to garner support and resources,
prepare for each project, and guide kaizen teams so that everything falls
in line with the business model. Kaizen champions are like the
guardian angels of lean.
Data Collection
• Spaghetti diagrams
Not all processes involve manual assembly. Companies that use auto-
mated manufacturing processes where machines and equipment do the
bulk of the production should have a kaizen champion who under-
stands the importance of reducing setup and shrinking changeover
times. These are tricky subjects, and it may take time to really get a firm
understanding of the two. Setup and changeover are two separate steps,
but they are often considered to be the same thing. Setup is the work
performed before a new product run is needed. Changeover is the actual
act of removing items such as fixtures and parts from the machine, and
then placing new fixtures and parts for the next run. This portion of
machine work must be fast and efficient so that the machine can be
turned on again. The more efficient the setup steps are, the faster the
changeover.
Material Replenishment
Proper material presentation in the work area is also part of this system.
Obviously material should be at point of use, and the replenishment of
this material should not be done by the production worker. Material
and parts quantities should be kept to a minimum. Large pallets and
bins of excess parts simply take up floor space and extend the length of
the line. Quantities in the work area are also based on supplier perform-
ance, but customer demand and delivery frequencies also are part of the
calculation. Your kaizen champion should be strong in inventory reduc-
tion and material replenishment, and he or she should have a working
relationship with the purchasing department and suppliers.
47
Project Management
So there you have it. Although this was a short description of the
kaizen champion, it gives you an idea of the type of individual needed
for this role. Some companies take a while to find the right candidate.
There is no hurry. As for any other position in the company, make sure
the person you pick can fulfill the requirements of the job.
When selecting the kaizen champion you can go in two directions. You
Chapter 3: The Kaizen Champion
can select someone who currently works in the company; let us call this
employee the internal option. Or you take the external option and find
someone totally new to the company. Either option has it pros and cons.
Internal Option
Pros:
Cons:
External Option
If you are not able to find someone in the company to take on the role
of kaizen champion, it is not a poor reflection on your current culture’s
abilities. The kaizen champion’s job is not easy. It can be stressful at
times and a lot is riding on its success. If you decide to go outside of
the company, this option also has its pros and cons.
Pros:
Cons:
You are probably thinking that this approach is expensive. Well, it can
be, depending on results and leadership support. But if, through the
leadership of the kaizen champion, lean implementations save the com-
pany $500,000 to $1,000,000 a year from waste reduction, it seems to
me that it is worth an $80,000 investment.
But don’t forget the other hiring costs involved in the external option.
You may need to relocate the candidate and his or her family as well.
After multiple interviews, travel expenses, moving household goods and
cars, lease termination fees, closing costs on selling and buying a house,
and other miscellaneous moving expenses, a company could spend an
50
additional $20,000 to $30,000 to get the ball rolling. However, with the
Chapter 3: The Kaizen Champion
right person, these costs will be returned 50-fold. Of course, I realize the
investment must be done in the first place and it may not be economi-
cally feasible for the company; this is why the last portion of this chap-
ter is dedicated to discussing alternatives to the kaizen champion.
• Training
• Kaizen monthly meeting
• Communication boards
• Kaizen newsletter
• Kaizen suggestion box
• Kaizen event tracking worksheet
• Team leadership
• Action item follow-up
• Monitoring other lean initiatives
Training
As time goes on, the champion should work with the HR department to
help create training for new employees regardless of their titles or
51
where they work. This also includes creating ongoing refresher training
Your kaizen event steering committee should meet once a month to dis-
cuss all lean initiatives, including kaizen events. This meeting is run by
the kaizen champion, and he or she is responsible for scheduling the
meeting, creating the meeting agenda, and sending out meeting notes.
During the meeting the kaizen champion should get status reports from
all the committee members on any lean projects in process. Discussing
kaizen events is a given, as I detailed earlier in this book; even small
improvement initiatives need to be discussed. It is critical to the suc-
cess of your lean journey to have this meeting regardless of the amount
of waste reduction effort that is going on. The kaizen champion is also
responsible for keeping the other members of the steering committee
engaged.
Communication Boards
Kaizen Newsletter
Team Leadership
In the early stages of your lean journey, the kaizen champion is the ideal
person to lead kaizen teams. The kaizen champion also develops team
leader criteria that can be used to select future team leaders. If you do
not have a champion at a given time or at the beginning of the lean jour-
ney, simply make a list of criteria that will work until a champion is
selected. Criteria or not, good team leaders are developed over time with
kaizen event experiences—successful ones and not-so-successful ones.
Even when the kaizen champion is not the team leader, he or she should
be available to support and encourage the members of an event team.
Alternatives
progress. The champion needs to help clear any obstacles that might be
impeding completion of the items and decide if the kaizen event steer-
ing committee needs to help.
Alternatives
Some of you may be thinking, “There is no way we would be able to
have a kaizen champion.” Well, you are not in the minority here; and to
be honest, most firms cannot. I know for a fact that a good kaizen cham-
pion will pay for him- or herself and then plenty more, but if you fall
into the no-kaizen-champion category, you will be happy to know that
there are alternatives. However, you must assign ownership of lean in
some fashion or it will fall apart.
Think about all the requirements of the kaizen champion, and then
think of those people in your company who already possess these skills.
One of my clients has no champion, but the company is “doing” lean
with great success. Its journey is slower than that of companies that do
have a champion, but it is still progressing with waste reduction.
54
The talent exists in your company; just tap into it and make sure the
people have the time to work on lean- and kaizen-related items. I also
recommend hiring interns from the operations or engineering depart-
ments of a local college who can be used for—well, anything. A lot of
my clients use interns to conduct value stream mapping and time stud-
ies while they search for a kaizen champion. Or they simply use interns
on an ongoing basis for a variety of tasks. Interns are eager to use what
they have learned in school and to begin fleshing out their résumés for
other career opportunities. It is always good to use a consultant when
needed as well (though I am not attempting to market my services to
you). A consultant helps get the journey going, and a good consultant
knows when to step back and let a client continue on its own.
Kaizen events require solid up-front planning to ensure that they are
successful. Traditionally, it was taught that there should be no activities
prior to the event. With this approach, a kaizen team would begin day
one of the project with confusion and little direction. Often working
12 to 16 hours a day, the kaizen team would go through a series of trials
and errors until coming up with a final layout or a handful of solutions
to reduce waste. They would be exhausted and often bitter as a result of
these kaizen events. I am a firm believer in and practitioner of prepara-
tion and planning for every kaizen event a company conducts. This
does not mean that the answers should be provided to the team.
Depending on the goals of the team, certain tasks should begin at least
four weeks before the event.
Some kaizen events can be planned even further out than four weeks,
depending on the complexity of the work area, the length of the line,
and the amount of floor space the cell takes up; the consolidation of two
processes would probably require more preplanning. As I mentioned in
Chapter 2, kaizen events consist of structured time, a selected area, and
a talented team. Waste removal initiatives between kaizen events are
simply the practice of kaizen. These activities do not necessarily take a
lot of preparation, just some effort to continue improvements. Kaizen
events take a different tack.
55
56
First, you can evaluate sales and output. Does the product or line or
area contribute a large portion of your overall revenue and/or the total
output? Be careful, because a high-volume product may have very little
effect on total revenue as it could be a low-priced item. On the other
hand, the product line could represent a large portion of revenue, but
57
Fo u r We e k s B e f o re t h e K a i z e n E v e n t
sales product is a good starting point.
Third, how many of the seven deadly wastes are consuming the lives of
the production workers? More important, how much of their overall day
is lost to non-value-added activity? Leaving the work area, reworking
products, overbuilding and overprocessing, sharing tools, and waiting
on product, parts, and information are examples of things that will
negatively affect cost, quality, and delivery. It will require some initial
analysis of the process to get a firm grasp of how much waste there is;
I will discuss this data collection exercise in Chapter 6.
Fourth, what are the production workers telling you in the suggestion
system I outlined in Chapter 2? Their suggestions may bring to the sur-
face a plethora of problems that are unknown to management and other
support staff, such as problems with equipment, suppliers, parts, tools,
part presentation, the order of the work, and imbalances in the process.
These four factors should be all you need to make a decision. Do not
wait to have 100 percent of the information before you make a decision
or you will never make one. Simply look at sales, output, performance,
waste, and employee suggestions in some mix and make a move!
Having all of the selected team members on the kaizen event is the sole
key to success. The committee should create a tentative list of potential
58
members four weeks before the event to ensure their availability. During
Chapter 4: Kaizen Event Scheduling
this time, managers and HR can verify any vacation schedules that have
been submitted for the week of the kaizen event. Also, certain employ-
ees may be on light duty due to injury or illness; this is the time to
check paperwork and employee records for this information.
Once the area and the team members have been selected, you can move
on to selection of the team leader. Picking employees to be team leaders
is not as simple as it appears. Kaizen events are very intense and
require good leaders who can assess situations and direct people to
ensure success. Often your kaizen champion is the best choice, but as I
said earlier, not all companies can have this type of position. It is then
smart to develop criteria for kaizen event team leadership. Important
attributes of a kaizen event team leader are
When selecting the team leader, you don’t necessarily have to pick the
line or area supervisors. As long as the team has members who work on
a regular basis in the area that is the focus of the event, your team
leader can be anyone as long as he or she has the qualities listed above.
Good team leaders are also developed over time, and as you circulate
59
different people into kaizen event leadership roles, you will develop a
Fo u r We e k s B e f o re t h e K a i z e n E v e n t
powerful pool of change agents from which to pick for the future.
The two disappeared for a while, about two hours, and then I found
them in the maintenance department. They were clearly building some-
thing for the event. At the end of the day, they came out to the assembly
line with a cart full of what appeared to be white PVC pipes. They had
gone to a plumbing supply store and purchased two different sizes of
PVC pipes and some hardware. Figure 4-1 is a simple illustration of
what they built.
60
Chapter 4: Kaizen Event Scheduling
10
Each workstation would have one of these signs—a simple solution and
very creative. They had used the money that had been budgeted for the
kaizen event to buy the supplies for this idea. Usually the bulk of the
event budget is for feeding the team, but there should also be enough
for those small projects that come up during each event.
Order Supplies
Every kaizen team will require some supplies. Teams use a variety of
things to eliminate waste or to implement a lean practice. For instance,
during the implementation of 5S, kaizen teams will need floor tape,
paint, labels, laminating material, markers, tape measures, and box
cutters. These items are good to have for every kaizen event, and they
should be placed in a “kaizen event supply box.” This box is an invalu-
able asset to any company conducting kaizen events. It has yet to fail
me or my clients. It is best to custom-build one if you have the mainte-
nance support, but you can buy something at any home improvement
store.
visual tool boards are also good examples. The list could go on and on.
Fo u r We e k s B e f o re t h e K a i z e n E v e n t
Make sure to begin the supply-ordering phase at this point.
When the event is four weeks away, update the communication boards,
generate a new newsletter, and collect the suggestions in the kaizen
event suggestion box. Start sending e-mails to the employees who are
not on the team so that they know about the event. It is good for every-
one to be aware of all events so that they know not to make decisions
that will pull team members off the event or make the event hard to
complete.
A variety of people who do not even work in the plant can be team
members. Workers from sister or parent companies can be invited to
contribute to the kaizen event. This is a smart approach when organiza-
tions are trying to standardize lean implementations somewhat. I say
somewhat because every journey is different, but it still allows for best
practices. Currently, Kaizen Assembly has a client with a plant in
Ferndale, WA, and Lafayette, LA, and they help each other during
kaizen events. (See Chapter 7.)
Often before a kaizen event, value stream mapping and time studies are
Chapter 4: Kaizen Event Scheduling
Waste analysis of any kind should be done at least four weeks before
the event. Depending on resources, an organization should have some-
one focused on collecting this information on an ongoing basis to help
prepare teams and to conduct other continuous improvement efforts.
With two weeks to go, the kaizen team should be finalized. They should
know that their expertise is needed on the team and that they have been
selected. Consider as you go along your lean journey that some compa-
nies get to a point in their kaizen program when kaizen event participa-
tion is voluntary. As people see the improvements being made and how
63
Tw o We e k s B e f o re t h e K a i z e n E v e n t
events.
At this point get a status report on all supplies or equipment ordered for
the kaizen event. Most important, the kaizen event supply box should
be stocked. Verify participation from potential outside resources who
may be traveling to the kaizen event. If for some reason they cannot
make it, you still have time to select others to take their place. That is
not an ideal situation but it could happen, and with this approach to
planning you can still have a full team.
Have the team members spend some time in the area selected for the
kaizen event. Companies that have a large manufacturing facility or mul-
tiple buildings should encourage employees to visit processes outside of
their normal assigned area, especially in preparation for a kaizen event.
Having the team members walk through the area ahead of time will give
them a feel for how things operate. Granted, if the plant is small,
employees would probably be familiar with everything already. Once the
kaizen event starts, you want the team to have some idea of what kind of
machines, equipment, tools, and people are used to build the products.
During a kaizen event, the team will require two places to work. The
first work area is generally the process, assembly line, or area that has
been selected as the focus for the kaizen event. Sometimes working in
the actual process is difficult, so pick a place where the team can work
that is in close proximity to the line. The second area is a conference
room or training room where the team can place their belongings. This
place is also needed to conduct group discussions, eat lunch, and have
meetings. Often a company has a reservation system for securing rooms.
Customers, suppliers, and other employees use the rooms, so reserving
one ahead of time is smart. Nothing is more annoying than not having a
“war room” for the kaizen team once the week begins. Secure the room
ahead of time so there is no confusion or, more important, no interrup-
tion for the team.
64
Depending on the event and the goals of the team, a current state analy-
sis of the process may have been done ahead of time. This could have
been in the form of value stream mapping (discussed in Chapter 3),
time studies, waste analysis, or other flow and time evaluations. At this
two-week point, start looking over the information even if it has not
been completed. What can be done with this information before the
event starts? Is it clear that there are too many workstations or imbal-
ances in the work content between operators, or is there a lot of walking
around? Sometimes very little can be derived from the information, but
it is good to review it early. Again, I will discuss data collection exten-
sively in Chapter 6.
One week from the event, get an idea of the process’s current state. The
kaizen event steering committee should have set goals for the team in
regard to productivity increases, quality improvements, floor space
reduction, travel distance reduction, setup reduction, or inventory
reduction, for example. Depending on the metric(s) selected, the kaizen
champion or the appointed kaizen team leader should gather this cur-
rent state information, which will be presented to the team during this
one-week point and during the kaizen event. The current state informa-
tion provides a starting point for the team.
65
O n e We e k B e f o re t h e K a i z e n E v e n t
At this point, all team members should know about their participation.
If not, your company has other planning issues. There should be no
confusion about who is on the team, the area selected, and the time slot
for the kaizen event. Invite the team into a conference room for about 30
minutes. The team leader and/or the kaizen champion should review
the following information:
This is best done the afternoon before the first kaizen event day. Place
laptops, printers, the kaizen event supply box, laminators, etc., in the
conference room where the team will meet on day one. When the team
arrives, it is nice to have everything ready to go so they can begin work
immediately.
The team leader and/or the kaizen champion should meet with the
plant manager and give the final “go” on the project. Although the plant
manager should be aware of any changes at this point in the game, it is
always healthy to meet with this individual and go over any final
thoughts. The plant manager needs to provide total support for the proj-
ect, so any final words of wisdom from either the team leader or the
plant manager should be said at this time.
66
As your organization has more and more kaizen events, and more peo-
ple become team members, everyone will get this fringe benefit. Try to
avoid going out for lunch, because this tends to be a time-consuming
affair requiring transportation and eating time. The lunch is also a good
time to have your midday meeting anyway.
67
This page intentionally left blank
5 f
5S Kaizen Events
i v e
69
70
Four Weeks to Go
Chapter 5: 5S Kaizen Events
fine for leading a 5S kaizen event. You can pick the area supervisor, an
Fo u r We e k s t o G o
engineer, or a lead operator; whoever it is must be trained in 5S and
ideally has seen it implemented somewhere.
Establish Goals
Each kaizen event is designed to improve the work area and the com-
pany and to reduce waste. 5S is a very powerful improvement tool that
has the ability to reduce all of the seven wastes, as well as improve pro-
ductivity, reduce floor space and product travel distance, and enhance
quality. It is sometimes hard to quantify the results after a 5S implemen-
tation. I have no doubt that there will be major metric gains after 5S if
the team does its job correctly. Goals for a 5S kaizen event could be
floor space reduction, travel distance reduction, and productivity gains.
The most common is floor space reduction.
A 5S team will need a place close to the work area selected where the
laminator, some laptops, a printer, and the team members’ personal
items can be put. Ninety percent of the team’s work will be done in the
work area that is the focus of the event, but the team will also need a
place for making large labels, laminating, and storing personal items
such as water bottles, food, etc.
If your organization has multiple plants and the first 5S kaizen event is
the first for the entire corporation, then invite employees from sister
plants to witness and participate in the proceedings. They can learn
valuable information from the event which they can begin to apply at
their respective facilities. This approach is smart if you are attempting
to standardize the 5S program throughout multiple factories. It is also
good to bring in salespeople, suppliers, and customers at some point
during your kaizen events.
Two Weeks to Go
Finalize Kaizen Team Members
With two weeks to go, the 5S supplies that will be used during the
implementation should also be finalized. Make sure that all necessary
supplies are on their way or have arrived. Certain supplies will be
73
O n e We e k t o G o
ordered at this point. It is also good to confirm the participation of
those who do not work in the plant who are coming in for the event,
especially if they are included in the final roster of team members.
Airline tickets, hotels, and car rentals should be arranged at this point.
Ask the final 5S team to start spending time in the work area selected. If
they have been fully trained in 5S and all of its implementation tech-
niques, they will see ample opportunity for improvement. This walk-
through may not be needed if the facility is small. But some companies
are quite large, and it is always smart to allow the team to spend time
there as the event gets closer.
One Week to Go
Gather Current State Information
Most of the more complex preplanning tasks should be nearing comple-
tion by the one-week point. With a week to go, the kaizen champion
should collect some vital information about the work area selected for
the 5S implementation. Most kaizen events will require some current
state information in regard to floor space use, product travel distance,
productivity, quality, and inventory levels. Once improvements are
made and the workers have worked within a new 5S environment, these
key shop floor metrics should be positively affected. Have the current
state information available for the team on day one of the kaizen event.
This meeting is scheduled by the event’s team leader and/or the kaizen
champion. It is a formal meeting to allow team members to meet each
other if they do not already know each other. It is also an opportunity
for the team leader to discuss the goals for the team as outlined by the
kaizen event steering committee and go over any other relevant infor-
mation regarding the project.
The team leader can discuss what types of preparations were made to
ensure that the team will have the time, resources, and supplies needed
74
This particular task should really be done the day before the event
begins. If the kaizen event is to start on a Monday, the team leader and
kaizen champion should place all appropriate supplies, equipment, the
kaizen event supply box, and other miscellaneous tools in the team’s
chosen work area on the preceding Friday. Printers, laminators, label
makers, and even laptops can also be placed and made ready the day
before the event begins.
It also good for the team leader and the plant manager to meet just
before the event. The team leader confirms that the kaizen event is a
“go,” and the leader and the plant manager can then discuss any final
preparations. This is not the time to tell the plant manager that the
event is to be canceled for whatever reason. The need for a cancellation
should be apparent long before this meeting, but if not, that would
mean that the preplanning fell apart in the four- and two-week timeline.
Events are usually canceled because preplanning items did not get
completed.
Let It Begin!
The ultimate goal of any 5S team is to have the chosen area “5S-
compliant” by the end of the kaizen event. Essentially this means that
every item that is required to perform the work in the work area has a
home, and the location and item are clearly marked. It is important to
complete each S in the implementation in order before moving on to
the next—or at least to do the best you can.
The team leader should break the team into two sub-teams to begin the
Sort portion of 5S. During the sorting phase, all items deemed unneces-
sary should be removed from the work area, as well as any items that
75
are questionable. Questionable items are items that are not used very
Let It Begin!
often, as opposed to everyday necessities. The team needs to decide
what the home location will be for infrequently used items. The two
sub-teams are as follows:
• Sorting team
• Collection team
Sorting Team
To conduct the sorting activity, the team should use what is called a
red-tag campaign. A red-tag campaign is an organized approach to sort-
ing; it allows a lot of people to be involved in the sorting process and it
keeps items being taken from the workstations organized. There are
three parts to a successful red-tag campaign:
• Red tags
• Red-tag area
• Red-tag removal procedure
Red tags are visual indicators that a kaizen team has “tagged” the item
and deemed it unnecessary to perform the work in the workstation. It is
literally a red-colored tag. The sorting team places these tags on items,
removes the items, and brings them to the red-tag area for further evalu-
ation. Figure 5-1 shows what a red tag might look like.
5S Red Tag
Name Date
Kaizen Event
Station/Area
Circle One
Work In Process
Raw Material
Finished Goods
Documentation
To o l s a n d F i x t u r e s
C u s t o m e r To o l s a n d F i x t u r e s
Office or Computer Equipment
Storage Material
Unknown
Other
Part Number:
Part Description:
The list could go and on and on. Cabinets, drawers, and tool chests
Let It Begin!
should be completely emptied out, and items should be sorted to iden-
tify only the bare essentials. Always start with the small items. And I am
serious about sorting things like extra pens, pencils, and wrenches. As
insane as it may appear, a collection of these small items requires
medium-sized storage such as bins, organizers, shelves, and tables.
Medium-sized items require large storage such as workbenches, cabinets,
tool chests, and racking. Large items require floor space, and finally floor
space requires buildings and facilities. Do you see my point?
Place red tags on all items pulled from the workstations, fill out the
appropriate information, and place the items in the red-tag area.
Collection Team
Red-Tag Area
The red-tag area should be marked off with red tape and a sign hung to
identify it clearly. The collection team should inventory the items
brought there so that the team as a whole can decide on the fate of each
item. The inventory list provides insight into the amount of money tied
up in unnecessary supplies, tools, workbenches, etc.
Most of the first day will be spent sorting, and the team should focus on
its completion by day’s end. During lunch, the team leader needs to get
an update on progress from each sub-team and provide support, includ-
ing shifting people between teams if necessary. One of the critical attrib-
utes of a good kaizen team leader is the ability to evaluate progress and
make sure the team members are working on the correct items at the
right time.
78
Ideally, by the end of the day one, the team should be in a position to
Chapter 5: 5S Kaizen Events
After the first day, the team leader and/or kaizen champion should
begin putting together a removal procedure for the items in the red-tag
area. This task does not need to be completed during the event, but
when creating this procedure there are a couple of criteria that need to
be established:
• Deadline
How long do you want to hold on to your junk? Do not get into a
vicious cycle of moving garbage from one place to another in the fac-
tory. Establish a deadline for removal: 30, 45, 60 days—something. I
have seen some red-tag areas last one week. It depends on the items
and what kind of “bond” the company has with the items. If any-
thing is now deemed unwanted, get rid of it.
• Removal options
■ Auction the items off to employees or simply give them away.
■ Have a “garage sale.”
■ Donate to local nonprofit organizations and colleges.
■ Give items to a local recycling organization.
■ Send the items to a sister plant.
■ As a last resort, throw them in the garbage.
Let It Begin!
As mentioned before, make sure all the sorting activities are complete
so the team can see what remains to be organized. The Set in Order
phase takes the longest and often can be the most tedious of the work.
The goals of Set in Order are to organize the area so that everything has
a home and to improve the flow of incoming and outgoing
material/products/finished goods. Most important is the need to reduce
floor space use and product travel distance. It really does not matter if
you are working on an assembly line, a work cell with machines and
equipment, or a shipping department—you can apply Set in Order to
all of these.
Before you can get into the fine detail of Set in Order, begin with the
floor items. Decide what surfaces are needed in the workstations and
area to be used for the actual work. Always evaluate the size truly
needed to perform the job at hand. The team should come up with a
few layout designs to choose from. Once they decide what the flow of
material and parts will be, they can begin piecing together the process.
Begin with the large items:
Any items that will go on the floor should be the first items placed in
Chapter 5: 5S Kaizen Events
the work area. Nothing really is permanent at this point, so don’t start
marking the floor with designations and identifications; try to make
some tentative decisions about placement.
This portion of Set in Order may take part of or even all of day two.
Once the team has decided on the locations of the floor items, they
should lay out all the necessary tools, supplies, and various worksta-
tion-related items in the workstation to get a look at what needs to be
organized. By going into the Set in Order phase with the mind-set of
going vertical and avoiding flat surfaces, you challenge the team to
come up with creative and innovative approaches to organizing. Only
as an absolute last option should the team bring in a cabinet, shelf, or
tool chest. The key to 5S is visibility, and tool chests and cabinets do
not allow you to see where things are and what is missing.
Break out the kaizen event supply box, Peg-Board, paint, cleaning sup-
plies, and any miscellaneous supplies. The Set in Order and Scrub
phases can be done together. Always paint when possible to create a
showroom appearance. Cleaning can only get you so far; painting work-
benches, shelves, metal stands, etc., can make the area appear very clean.
As you can see, there is a clear outline of the items on the floor. The
kaizen team should place labels or stencils on the floor describing the
address. In this example, A1 and A2 are used. A1 and A2 are locations
for important work-related items that are needed in the workstation.
Whatever goes there, that will be its location. So if a calculator, tool, or
bin full of material goes in A1, the item is also physically marked “A1.”
If these items are not returned to their locations for some reason, any-
one who notices that they are out of place can quickly find their home.
This approach to “addressing” is extremely powerful in saving time and
reducing motion and confusion, and it can help reduce purchasing and
81
Let It Begin!
tions up high so that they can be seen from a distance and not just on
the floor.
Wire Harness
48-0269-87
Qty: 1 Pallet A1
Location: O p-A1
Plastic Tote
Work-
bench
Parts
Rack
A2
Figure 5-2 Floor identification
Tool Boards
1. Paint the board: Use any color; I have seen red, yellow, black, blue,
green, and orange shadow boards. The team leader should pick some
team members to begin painting the Peg-Boards at the beginning of
day two so that they have time to dry before being used.
2. Lay out the tools: Once the boards are dry, lay them on the floor or
another flat surface and lay out the tools and supplies on them. And
I mean everything: tools, tape, scissors, calculators, clipboards,
whatever. Your supply box should have pegs, double-back tape,
Velcro tape, and other things that can be used to hold items verti-
cally. You are basically making a cookie-cutter tool board to identify
the exact surface needed to hold the workstation’s supplies.
82
Chapter 5: 5S Kaizen Events
3. Cut the Peg-Board: Now remove the tools from the Peg-Board and
cut a nice square piece for the workstation.
4. Install the tool board: If a tool board will be hung on a wall, use
1-by-1 studs or some other kind of wood frame to hold it. The pegs
that will be used to hang items need clearance behind the board to
lock into place. Tool boards can go anywhere. I have seen them
installed on the side of workbenches and cabinets (if present), and
on casters (wheels). As long as the location is accessible, at point of
use, and does not disrupt the operator, the placement is good.
5. Hang the items: Now the team members can hang and organize the
tools and supplies on the tool board. Leave room for labels between
the items and enough space to draw a shadow or outline of each
one. This process is relatively slow but it is critical to any 5S imple-
mentation. After placing the tools on the board, use the paint pens
that should be in the event supply box to outline each tool on the
83
board. When the tool is off the board because it is being used or is
Let It Begin!
missing, these outlines will make the tool’s absence visible. Next,
make a label with the name of the tool and place it near the tool’s
location on the board.
6. The last step is to designate a location for the tools, such as B5, J7,
L3. This “address” must physically go on the tool as well as the
label so that people know where it belongs. Figure 5-3 is a good
example of a tool board that was built using these six simple
guidelines.
The kaizen team must continue organizing all remaining items. Always
thinki about reducing special needs. Use square bins to organize items
that cannot go vertically on boards. When placing anything on a flat
surface, mark off the area, generally using smaller-width colored tape.
All items must be marked with their home location, and a label must be
placed on the flat surface identifying what goes there. Everything—
everything—has a home.
Day 4 is for fine-tuning and ensuring that the team is completing all the
tasks in a way that is consistent. For instance, all tools should be hung
vertically on Peg-Boards, the backs should be painted, there should be
an outline of every tool, and the tools and board should be labeled
appropriately. The tools on each board may be different but the general
appearance is the same. Also, all items on the floor should be clearly
marked with a location and identified with their names. The uses of
floor tape should be consistent. Maybe yellow is for caution, black is for
finished goods, and red is for items in the workstation. Try to standard-
ize your approach.
The team leader should begin to create the report-out presentation that
will be given to the company to outline the team’s accomplishments.
84
on day five:
Day Five
Try to schedule the report-out presentation for a time when a lot of peo-
ple can attend. On day five the team leader completes the presentation
and can take any final pictures of the area to be used in the report out.
Team members can use this time to clean up the area, finalize any label-
ing or other 5S items, and put together an action item list of anything
that did not get done.
This action item list, or 30-day mandate, outlines what each unfinished
task is, who is responsible for completing it, and the deadline for com-
pletion. Companies that struggle to see things through to completion
can use this mandate as an opportunity to teach their people to better
follow through on tasks. Completing the tasks on this list is vital to the
success of the team and those who will now be working in a new area.
After the presentation to the company, the team should invite the atten-
dees to the work area that now has a new look. A tour helps people to
see the tangible element of lean and allows them to ask questions and
give comments based on what they see. Explain the importance of this
organization and how it benefits everyone. Congratulate the team on
their accomplishments and get some rest.
Maintenance 5S Events
Maintenance departments are perfect candidates for 5S implementa-
tions and practices. Often these departments employ multiple people
85
Maintenance 5S Events
Their work area is a community space where tools and supplies are
shared. Sharing tools and supplies in an assembly line where there are
definable workstations is very dangerous. It promotes lots of wasted
motion, the chance of losing tools, and lost production and concentra-
tion. Work in these types of manufacturing processes is clearly outlined,
and the workstations should have exactly what is needed to perform
the work.
As for any other event, make sure you follow the preparation guidelines
that were outlined at the beginning of this chapter: the four-week, two-
week, and one-week requirements. The only real difference is that I
usually advise my clients to sort a little earlier, about a week before the
event. Maintenance commonly becomes the dumping ground for things
over time, and maintenance personnel like to stock up for what-ifs.
Often these what-ifs never materialize, and unused items just build up.
In a typical five-day event, most teams should be given the first day for
sorting, but I recommend that a maintenance department start this
activity early, being fully aware that the kaizen team will do more on
day one of the event.
The team leader should break up the team into two sub-teams, as
described earlier in this chapter. One team places red tags on those
items being removed, and the other team places the items in the red-tag
area. The creation of the inventory list for this type of 5S event is criti-
cal because a lot of expensive items may be eliminated. Final removal
of items from this red-tag area may take longer; it may take more time
86
just to decide what to do. Don’t be afraid to remove that $10,000 brake
Chapter 5: 5S Kaizen Events
press if it is not used anymore. This can be very hard for people
because of its monetary worth, but if it is not used, remove it. The space
it occupied can be used for equipment that is frequently used or just to
make more work space.
Let the insanity begin. Break out the paint on this one for sure. The
kaizen team job here is also to create showroom conditions, and often
cleaning the maintenance department is not enough. There are often a
lot of stands, equipment, workbenches, and other items that are made of
steel tubing and metal. Paint away, and I recommend bright colors like
yellows, reds, and light blues. I remember a kaizen event where all the
team did was sort and paint. Without rearranging the area at all, they
incurred a 10 percent increase in productivity and output. Bright, well-
lit work areas just breed better performance. Go into any fitness center
and you will see my point.
All tools must be visible and hung vertically to save space. However,
if there are delicate testing and measuring devices that do need to be
behind doors for protection, then so be it. Everything else must be visi-
ble. Start constructing the tool boards as described previously in this
chapter.
While some team members are putting together tool shadow boards,
other team members can be cleaning and painting equipment and reor-
ganizing shelving that may be needed to hold big and bulky items such
as saws, drills, and heaters—larger items that cannot be hung vertically.
The key here is no doors.
87
When organizing items that sit on shelves or multiple shelves, have the
5S Sustaining Tips
team make cubbyhole sectional pieces to maximize shelf space. Often in
shelving there is a lot of dead space between the shelves. Maximize this
space by make sub-shelving, and you just might see a tremendous
amount of consolidation. Sorting includes substituting unnecessarily
large tables and storage areas with sizes that are smarter for their
intended use.
As in most five-day events, the Scrub and Set in Order phases will take
at least two days and may even last into the fourth day.
Day Five
Spend the last day of the event completing any unfinished labeling and
start cleaning up. As mentioned before, conduct a report-out presenta-
tion and tour of the area.
5S Sustaining Tips
My last recommendations in this short explanation of a 5S event for
maintenance are guidelines that you can incorporate into the depart-
ment to improve performance. Just like maintaining anything new in a
culture, sustaining the 5S program is hard. Your sustaining efforts will
never end, including continually improving upon what was already
implemented, but each company must find a way to do it. Here are a
few recommendations:
For each area, put together a list of tasks workers must complete
roughly 15 minutes prior to leaving. This cleanup procedure goes
beyond simply sweeping the floor and dumping garbage. Some possible
items that could be added to the procedure are the following:
I recommend that you post these procedures and allow the operators
time to conduct the cleanup to help sustain the improvements made.
Each area supervisor should take a few minutes after everyone has left
to walk through the work area and verify that the end-of-day cleanup
was completed and all items were returned to their home locations. If
your company implements 5S to the detailed level described in this
chapter, this supervisor walk-through should be quick. Any small devia-
tions from 5S can be quickly resolved during that walk-through.
If you are still looking for more ideas or a better way to sustain 5S, then
you can incorporate a weekly or monthly 5S audit. Develop a 5S audit
sheet with information similar to the cleanup procedure. Figure 5-4 is
an example of a potential 5S audit sheet that can be used.
89
5S Sustaining Tips
5S Audit Sheet
Te a m
Audit Date # o f Ye s e s /16 = %
Auditors
Sort (Get rid of unnecessary items)
Workstation and/or area is clear of all non-production-required material Yes No
Obsolete or defective parts have been removed and tagged Yes No
Unnecessary equipment has been removed from the area Yes No
Straighten (Organize)
Cabling/air lines are routed neatly Yes No
All equipment and tools are clearly marked and well organized Yes No
Tools are on shadow boards or other designated locations Yes No
Queue levels have been set and are clearly marked and organized Yes No
Scrub (Clean and solve)
Floors, work surfaces, equipment, and storage areas are clean Yes No
Garbage and recyclables are collected and disposed of properly Yes No
Excess pallet and packaging materials are cleared out of the area Yes No
Standardize (Tasks)
An end-of-day cleanup procedure is posted Yes No
5S audit scores are posted Yes No
Sustain (Keep it up)
Previous 5S audit scores are reviewed for improvement opportunities Yes No
Production control boards are being used on a daily basis Yes No
Work instructions are displayed with correct revision Yes No
Work area is clean, neat, and orderly with no seriously unsafe conditions observed Yes No
Based on the scores from the 5S audits, display the results on a tracking
sheet that is visible to the whole company. This creates awareness and
healthy competition between the areas, and everyone can see how the
plant is doing overall. Figure 5-5 is a simple example of a 5S tracking
sheet. It becomes a nice visual reminder of the progress being made
with 5S.
90
AREA
Chapter 5: 5S Kaizen Events
Line A
Work Cell 5
Warehouse
Brake Press Area
Maintenance
Engineering
Boiler Line
Figure 5-5
5S tracking sheet
• Effective time
• Volume requirements
• Takt time
• Process analysis
91
92
Preplanning
C h a p t e r 6 : S t a n d a rd Wo r k K a i z e n E v e n t
Effective Time
Effective time is often called touch time; it is the amount of clock time
in the day that is available for operators to perform their work on the
line. Here is an example.
Volume Requirements
Takt Time
Takt is a German word meaning “rhythm.” Takt time is the pace of the
line required to achieve the design rate based on customer require-
ments. The calculation of takt time is the following:
P re p l a n n i n g
20 units
Process Analysis
Before any design or construction can take place, you must first select
the assembly line and product that will be put through the rigors of a
kaizen event. Second, the work associated with building this product
needs to be timed. Time and motion studies are an absolute requirement
for improving the assembly operations in the factory and should be
done about three weeks prior to the event. I am a firm believer in mak-
ing decisions based on data; good solid data can never fail you.
Time is everything. Time and motion studies are the foundation of any
manufacturing process improvements and have been an early stumbling
block for many companies. Top management generally perceives time
studies as a wasted task. I don’t agree. Time studies should be at the top
of your preplanning list, but they can be difficult. Many facilities either
lack this information, or the time studies were acquired incorrectly.
1. Use a stopwatch.
2. Use a time study collection sheet.
94
Use a Stopwatch
Raw data should be documented and saved for future reference. You
will see that a time study collection sheet is very easy to use. It contains
all the information needed for designing an assembly line. Microsoft
Excel works well for setting up such a sheet, which should contain the
following columns:
• Sequence number
• Work content
• Value-added work
• Non-value-added work
• Sample quantity
• Average
A mistake that many people make when performing time studies is try-
ing to capture too much information at once. It is important to remem-
ber that collecting this data takes time, and you should never rush the
process. I have learned from experience to write down the work content
95
first and then return later to time. Once you are confident that the work
P re p l a n n i n g
content, both value-added work and non-value-added work, has been
identified, simply go back and time all the steps.
Seek the advice of the operators during the data collection phase. Let
them know that you need to know what work is performed at their
station. Allow them to discuss problems that hinder their ability to
perform efficiently, and ask lots of questions about their responsibilities.
Take a general interest in what they do, and let them know that you are
collecting data to help them in the future.
This is also a good time to let the operators know that you will be con-
ducting time studies on the work content. Explain that it is not an
attempt to see how fast they are, but to document how long it takes to
build the product. If you present yourself professionally, taking into
account their concerns, when you return to time them, you will get
their support.
Now that all the work content is documented, return to the first work-
station and start timing. You should have spoken with all the operators
at every station. Be smart in your timing. Do not hinder the work of the
operators, because they still have to work while you are timing them.
Some people are uncomfortable being timed because they feel they have
to work faster. Use your best judgment when timing; if an operator is
clearly stumbling about or working too fast, go to another station and
come back later. Since you have all the work content written down, you
can really time anywhere within the assembly line. Reassure the opera-
tors that this is not about speed and that their name and station will not
96
not getting caught up in operator names and stations. The operator will
feel more comfortable knowing it is an anonymous task. Just make sure
the operator is experienced enough to provide an efficient time for
designing an assembly line.
Timing work content once or twice will not yield accurate data for
design purposes. Operators are faced with obstacles and challenges all
day, so their work does not always take the same amount of time to per-
form. Time the same work content eight times to ensure that different
situations are accounted for. Always stop timing when the operator
drops a tool, looks confused, or walks away to talk with someone. Try
to distinguish the abnormalities that would not be considered during
assembly line design. This does not mean to skip timing non-value-
added work like walking and waiting. Capture all the work involved in
building the product and separate the useless acts.
Many companies offer their customers various options for their prod-
ucts. Some options are used so often that they are virtually standard;
however, some options are very rare. It is important to document and
time all options regardless of their frequency. I realize that this may be
difficult depending on what is being built at the time of your observa-
tions, but do your best. There may come a day on the new assembly
line when there is a large number of a rare option, and if it was not
accounted for in the design, there will be bottlenecks, workstation
imbalances, quality problems, and possible line shutdowns. Time the
worst-case scenario for the product.
After all eight samples have been timed, remove the highest and lowest
times, unless the high and low times are close to the remaining six sam-
ples. They represent the rare and unusual circumstance. Do not confuse
the high and low times with times for infrequent options. An example
of an unusual circumstance that would result in an unusually high time
is if an operator is struggling to fit a part into the unit because of a one-
time defect from the supplier. Although such things will happen from
time to time, do not include them in the design. Take the remaining six
97
samples and average the times. This average will represent the standard
P re p l a n n i n g
time for the work.
Time studies are so important, and the accuracy of this data will make
or break the new assembly line. Errors in time studies will show up very
quickly after the new line is up and running. Do not rush this analysis,
but then again do not take four months to conduct the study. The time
study collection sheet will be the foundation for designing an effective
assembly line, so take care with the information that will go in it.
Line Balancing
Once the time and motion studies are complete, look over the informa-
tion and come up with waste reduction ideas. Try to discover possible
ways to reduce the amount of time people leave the workstation to
retrieve parts and tools. Identify potential rework reduction opportuni-
ties and better ways to present tools in the workstation. Make a list for
the kaizen team to review.
About a week before the event, try to generate options for preliminary
line balancing. When balancing workloads among stations, there are a
few rules you can follow that can make the process easier:
1. Balance by time
2. Balance by work content
3. Balance by inventory
Balance by Time
The first pass of balancing is to use the time study information to add
up the time associated with the work until takt time is reached. More
than likely, the times will add up to a little less or more than takt time
because of the nature of the individual time standards. Don’t worry; this
is just the first pass at balancing. What you are basically doing is identi-
fying potential workstation work content. Continue with this exercise
until you have gone through the whole sheet.
The second phase of line balancing is to identify the work in the time
study sheet that can be shifted from one workstation to another without
affecting quality. Basically, you are moving the old sequence around to
98
help balance the workloads in the new line. This step takes a little more
C h a p t e r 6 : S t a n d a rd Wo r k K a i z e n E v e n t
Balance by Inventory
Your last pass at balancing is to buffer the stations with inventory. For
instance, if building the product requires a testing procedure that is
double the cycle time of takt time, then make space in the workstation
to test two units at the same time. As long as product is heading into
the testing area and product is leaving every takt time, the process will
still be balanced.
The kaizen team can look over the line balancing information and come
up with further improvement ideas; however, conducting the exercise of
balancing at least will give the team and the company an idea of work-
station requirements to support volume.
Day One
The team leader should start the kickoff meeting by introducing the
team members to one another. If the company is relatively small, the
team members may recognize each other. Each team member should
explain what his or her title is and where he or she works in the facil-
ity. The team leader should spend about an hour discussing 5S, stan-
dard work, the seven wastes, and visual management. This orientation
will help the team members get a better understanding of why kaizen is
important and what tools and methods they will be using to meet the
objectives of the event. Even if people have been through training ses-
sions in lean methods prior to the event, it is still good for the team
leader to review the tools so that everyone has a fresh perspective on
how to proceed.
Make sure the team understands any constraints that may exist related
to moving machines and changing the plant layout. The team will have
to be smart in their approach so that operators are allowed to continue
working. Good teamwork will make the event more enjoyable as well as
productive.
99
After introductions, the team leader should begin the kaizen event
Day One
overview and describe the objectives the team will be required to com-
plete by the end of the week. The team leader should already have com-
pleted a schedule for the week, which should be posted on a flip chart
or a presentation board. The events of each day should be outlined with
a list of the intended objectives.
Try to stagger the start time so that the team is working during the last
few hours before the operators leave. They can interact with each other
about issues before the line workers go home and the kaizen team starts
moving things around. The schedule is a general outline because activi-
ties during the event may change.
All team members should be present when the event starts, during
meetings, and at the end-of-day closeout meeting. Since team members
were selected two weeks prior to the event, there should be no excuses
for absenteeism. The first day of the kaizen event involves two major
activities. First, sort out all the unnecessary items in the old line by
conducting a red-tag event. Second, review the line balancing informa-
tion, or standard work sheet, that was prepared the week before, and
search for errors and other improvement opportunities. Split the team
into two sub-teams to work on the two activities. The team leader
should assign roles to each team member as well as their respective
goals. Both teams should reconvene at a designated time for lunch to
give a brief status report.
Red-Tag Team
Sorting does not necessarily mean just throwing things away. In a future
event, items removed during the red-tag campaign might find a use
somewhere else. Sorting is a method of identifying potentially unneces-
sary items in the facility, assessing the need for them, and dealing with
them effectively. Select an area in the plant where tools, workbenches,
jigs, dies, rejects, parts, and any other items that are no longer used can
be placed. This will be the red-tag area. Tape off the area with red tape
and post a sign indicating its use. This area is off-limits to everyone in
the plant except for the kaizen team.
100
The team leader should hand out a box of red tags that the red-tag team
C h a p t e r 6 : S t a n d a rd Wo r k K a i z e n E v e n t
will use to identify the items to be removed. I have seen many success-
ful kaizen events where the sorting activity was conducted without red
tags. However, once the kaizen event was complete, it was difficult to
evaluate the items and decide what needed to be done with them. A
red-tag event simply organizes the sorting activity in a more productive
manner.
The removal of WIP during the first day can cause a conflict. Although
WIP is non-value-added, allow the operators to work through the WIP
during the kaizen event. Day two and day three of the week are good
times to pull out WIP from the line and filter it back through during the
implementation of single-piece flow.
The sorting team should spend the first half of the day placing red tags
on unnecessary items. They should report back at lunch with informa-
tion on their activities and results.
Once the sorting team has been released to the production floor, the
team leader should hand out the line balancing information to the
remaining team members, who will be the review team. Again, having
operators from the line on the team will be a very valuable resource for
sifting through the information. They may find errors that can be
resolved prior to assembly line construction. The review team should
look for opportunities for waste reduction and mistake-proofing. Make
sure to have the original time and motion study data. The kaizen cham-
pion should have removed a lot of the walking data with the assump-
tion that the parts and subassemblies will be placed at point of use.
Also, the packaging removal operations will now be done in the receiv-
ing area, not by the operator, so that work content will not be included
in the design.
Part of the review process is to go out to the assembly line and verify
the work content and time studies. This is also a good time for some
101
people on the review team to go to the floor and document the non-
Day One
value-added work. They can also use the old time and motion data to
find areas of waste. This exercise is good for verifying that the line
balancing information is accurate. The review team should take stop-
watches, randomly select a few operators, and time their work. This
exercise will be the final check of the data, and any changes to the line
balancing sheets should be done during this time. The review team
should spend the first half of the day looking over the standard work
sheets and analyzing the assembly line.
The team leader should leave the two teams alone and allow them to
work on their assignments. This is a good time for the team leader to
take current state photos of the assembly line for the report-out presen-
tation. The team leader should also participate in both activities to
ensure that the work is being done effectively.
The team needs to move quickly and start pulling the red-tag items
away before operators remove the tags. People become accustomed to
working in waste because it creates a buffer for their inefficiencies.
A red-tag campaign will provide insight into the amount of waste that
has accumulated over time. The red-tag area will fill up quickly. Two
team members should be assigned to the area to monitor items as they
come in and verify that the red tags have been filled out properly. These
two people can help organize and maintain order so that items do not
simply pile up.
During the red-tag removal phase, the members of the kaizen steering
committee and other top management should be invited to see the
mountain of waste that has accumulated. The team leader should take
photos of the red-tag area for the report-out presentation on Friday.
done. By the end of the first day, the kaizen team should have success-
fully completed the red-tag event and finalized the line balancing infor-
mation. The operators will be a little confused the next day. Just
remember that each event is thoroughly planned four weeks in advance,
and the production supervisors and operators are aware that there will
be some added stress during the event.
End-of-Day Meeting
The day should conclude with an overview of the day’s results and set-
ting of the action items for the second day. The team leaders should
leave information for the production manager outlining what has been
done to his or her work area.
Day Two
The team should start the day as always in the breakout room at the
time designated by the team leader. Day two is the first day of laying
out the new line. The team will conduct the second and third Ss of the
5S program: Scrub and Set in Order. Maintenance projects should also
begin on day two. The first assignment of the second day is to go over
the line balancing information and come up with at least two line
design ideas. Depending on how big and complex the line is, sometimes
it is good to have these line design ideas done before the event. I have
even conducted line design kaizen events to make sure that the imple-
mentation team had everything they needed for construction. However,
most of the time there is plenty of time during the implementation
event to come up with line designs that will work. Just use your best
judgment when making this decision.
Line Design
U-shaped cell operators are generally more flexible and can shift from
D a y Tw o
station to station.
However, not all assembly “lines” can be converted into U-shaped con-
figurations. Product lines that are big and bulky may require physically
bigger assembly workstations and material storage, which would not
allow operators to have close contact with each other. Also, U-shaped
work cells should not consist of more than eight workstations. I have
seen U-shaped cells that were quite large because of the size and quan-
tity of parts in the cell. The operators were not close and could not see
one another well.
It is a good idea for the team to draw up the line design on CAD soft-
ware. Make sure that they draw in any expansion joints and retaining
poles that are on the production floor. If your company does not have a
plant layout, measure the area where the old line used to be, and stay
within those boundaries. The red-tag campaign from the previous day
should have freed up a lot of floor space, so it should not be difficult to
fit the new line layout into the area.
After discussing the preferred design, the team leader should assign the
action items for the day. The assembly process needs to be pieced
together into the shape of the new layout. The team leader should hand
out one or two standard work sheets per team member, and the team
members should go out onto the floor and measure the items needed to
construct the line—part racks, workbenches or lift tables, computer
stands, pallets, bins, totes, garbage bins, etc. Again, the standard work
sheet will outline everything that is necessary.
Midday Meeting
After lunch, the team should meet and discuss the action items for the
second part of the day. Putting together the new line will take two days.
Five stations a day is a good goal. There are two objectives for the team.
First, the team will construct the workstations. Second, the work-
stations will be set up with the required parts and tools.
104
Scrub/Shine
C h a p t e r 6 : S t a n d a rd Wo r k K a i z e n E v e n t
Before the team begins construction of the assembly line, clean the floor
to give it a showroom shine. Many factory floors are painted, and I
highly recommend this for the sake of appearances. Painting a factory
floor can be very expensive and should be done at some point in the life
the factory, but do not attempt this during a kaizen event because the
paint will not cure in time. Computer equipment, tools, fixtures,
machinery, and any other mechanical objects should be cleaned as well,
not only for appearance but for functionality. Workbenches, shelves,
tables, and storage racks need to be clean and free of dust and debris.
This act of cleaning is the Scrub/Shine function of the 5S campaign.
The assembly line should be pieced together starting from the last work-
station. Find a starting point to measure for correct placement of the
line; expansion joints or retaining poles work well. Allow four feet of
space from the workstation to any material storage. This will allow the
assembler to easily turn and maneuver within the workstation. Let the
material dictate how big the workstation area should be. Do not design
every workstation to the same dimensions. Some workstations could
have large bulky parts, and others could have small brackets and
hardware.
Tool Presentation
At this point the area will still be a little cluttered. Excess parts and
tools left over from the old assembly line will be lying around, taking
up unnecessary space on the new assembly line. Although the red-tag
campaign will have eliminated a majority of the tools, more than likely
part quantities may still be too high. Split the team into two groups.
One group should work on tool presentation and the other on part pres-
entation. Tools and parts should be presented in similar ways.
Ideally, tools are positioned over the operator’s head and at arm’s
length. This is good for small handheld air tools. Large tools will need
105
D a y Tw o
wrenches, wire cutters, etc., should also be at arm’s length but necessar-
ily overhead. Have team members take the standard work sheets out to
the new workstations and formulate ideas for tool positioning. The
operators who are included on the kaizen team are the best resource for
this exercise. There are a variety of options for tool presentation, and
every workstation will be different depending on the tool requirements.
The two most common approaches to hanging tools overhead are tool
balancers and tool retractors.
Tool balancers are good for positioning hand tools overhead. Hand tools
are connected to the balancers with small clips, and the operator can
simply pull the tool down to do the work. Once the operator has fin-
ished the work, the tool balancer will simply pull the tool back into
position overhead. However, there is one negative aspect to tool bal-
ancers: They tend to tug on the tool, and sometimes the operator feels
as if he or she is fighting with it. It is good practice to use lightweight
hand tools when dealing with tool balancers.
Tool retractors are a great alternative to balancers. They are very similar
in regard to placement and function; however, they are designed to lock
into position once the tool is pulled down. This enables the operator to
maneuver around the product without fighting with the retractor. The
operator then pulls down a little to unlock the retractor cord and the
tool can roll back into the static position.
Shadow Boards
Small tools and other devices needed for the assembly line may not be
good candidates for overhead presentation. Shadow boards like those
described in the previous chapter can be used to store tools in an organ-
ized fashion. They can be installed on the parts racks next to the opera-
tor. A missing tool becomes very noticeable at the end of the day.
Subassemblies
should also be assigned a bin. After the bins have been selected and the
team has filled the parts to the required quantities, a parts rack needs to
be chosen. Mobile parts racks of some kind should be used when possi-
ble. A variety of racks can be ordered from material storage suppliers.
Day two is action-packed for the kaizen team. The team should meet in
the breakout room before leaving to discuss the results of the day. The
team leaders should explain to the team that day three will go more
smoothly, because all the training on workstation construction and part
and tool presentation happened on day two. The team should be able to
complete construction of the assembly line on the third day.
Day Three
As always, the team should gather in the breakout room and discuss the
action items for the day. Since all visual aids, signals, labels, and other
visual management tools will be done on day four, the operators need to
look around to see if they have questions about how the workstations
are set up. Even though the line is more organized than before, without
the correct visual management it may become disorganized very
quickly. Have some of the team members on the line until the shift is
done for the day. The team needs to apply the same dimensional rules
as they did on day two to complete the line.
The team should take its usual lunch break and have a midday meeting.
At the end of the third day, the line should be ready for the implementa-
tion of visual management. The team should gather in the breakout room
and discuss the day’s events. Did they complete line construction? Has
maintenance finished installing the tools and creating the shadow boards
for each station? The team leader should take the team out to the pro-
duction floor and walk through the line. Although there is one more day
of work to go, the team should be happy about their accomplishments.
Day Four
Visual management is the key to running a lean assembly line. It
reduces the amount of firefighting and provides real-time information
on the progress of the line. The key to visual management is to be cre-
ative. We use visual aids every day and sometimes forget that they are
107
even there. Imagine what it would be like driving to work every day
D a y Fo u r
without road signs, speed limits, road dividers, turn lanes, car signals,
off-ramp signs, and all the visual aids we use on the road. A manufac-
turing floor should be set up to run itself and allow management and
engineers to react to the visual aids. Visual management is generally
associated only with making production information visually available
to track progress, but it goes further that that. Not only does it provide
real-time information on daily performance; visual management is
about having the appropriate signals and cues to allow the manufactur-
ing process to operate on its own, with people directing the processes
as needed.
This exercise is easy and the team leaders should allow the team mem-
C h a p t e r 6 : S t a n d a rd Wo r k K a i z e n E v e n t
bers to come up with creative ways to identify the workstations and all
parts racks on the floor. As long as there are no duplications, anything
really is acceptable.
This exercise will require two team members. Anything that is sitting
on the floor has to be identified in the same manner. Lift tables, parts
racks, pallets, disposal bins, workbenches, the exit conveyor, etc.—all
should be identified. Floor tape comes in a variety of colors and styles.
Yellow floor tape is the most popular as it creates a bright outline
around the items on the floor. After every item is outlined with yellow
tape, the two team members should create floor signs that identify the
items. All labels, signs, and other identification should be laminated to
protect them from damage. Floor signs may become dirty or torn. The
lamination material will protect the signs, allowing them to last longer.
Make sure the surfaces are clean, and use double-sided tape to secure
the signs to the floor. It is also good to place clear packaging tape over
the floor signs for added protection.
Floor signs for parts require a part description, part number, and quan-
tity. Parts racks and workstations should be similarly designated. It is
good to place two floor signs for all the items on the floor so that they
can be seen from any side. This exercise should take the two team
members most of the day to complete.
If the proper visual aids are not put in place, the operators may over-
build items that are not needed and slow the main assembly line down.
In conditions like this, it is good to create build levels for the operators.
This tells them when to stop and start building subassemblies. They can
switch back and forth as a team, building the appropriate quantity at
the appropriate time.
The team leaders should select people to create and implement the
visual aids for the subassembly operators and for the main assembly
line operators who install them. There are two designated racks in the
subassembly work cell for placing finished goods. Based on the quanti-
ties above, build level signs should be made to direct the operators.
109
D a y Fo u r
Maintenance should have the shadow boards ready for installation by
day four. Since most of the air tools are hanging above the workstations
on retractors, the shadow boards will be small. They can be installed on
the parts racks of the workstations or any other area that is effective.
Tower lights are a critical aspect of visual management. They are very
common but are frequently used incorrectly or not at all. Tower lights
are the communication system between operators and the rest of the
plant. There is a variety of tower lights on the market, and every com-
pany attaches different meanings to each color.
Red can be used for signaling that there is a major problem in the work-
station. There could be a quality problem or a tool or lift table malfunc-
tion; the operator may have run out of parts or needs to speak to the
production supervisor. When the red light is on, any support staff in
the area must drop what he or she is doing and address the operator’s
concerns.
Yellow can be used when there is a minor issue. This color can also be
used to signal a material handler that more parts are needed in one bin
or a subassembly is getting low. The material handler can go to the
workstation in question and find out if the operator needs material
assistance.
The team should try its best to complete the items listed in this chapter
on day four. About an hour before the end of the day, the team should
finish in the breakout room. The team should take a moment to reflect
on what they have just accomplished. The team leader should make a
list of the individual achievements of the team to include in the report-
out presentation for day five.
110
Day Five
C h a p t e r 6 : S t a n d a rd Wo r k K a i z e n E v e n t
Closing out the kaizen event is an important part of any project. This is
the team’s opportunity to showcase their accomplishments. There are
two parts to a report-out presentation: the presentation itself and a tour.
The team should be allowed to get some rest and come to work as
needed. The team leader may need to meet with the kaizen champion
(unless the kaizen champion led the event) to go over how the presenta-
tion should be put together.
1. Names of the team leader and team members, and everyone’s title
2. Name of the assembly line or area
3. Kaizen event date
4. Anticipated results
5. Actual results
6. Before and after pictures
7. Lessons learned
8. Thirty-day mandate (to-do list)
The 30-day mandate is a list of items that were left unfinished from the
kaizen event. Every event will have a to-do list, and team members
should be assigned to complete the items on the list within 30 days.
There are rare occasions when these items will require more than
30 days; however, the kaizen steering committee should try to assist
the team in completing their tasks within the time frame.
7 s e
The company kaizen program illustrated in this book has not changed a
whole lot; I have made just a few modifications over the last three years.
The company described in Kaizen Assembly was a manual-assembly-
based manufacturer with no equipment or automation. This chapter
will be dedicated to describing the lean journey of Samson Rope
Technologies, Inc., headquartered in Ferndale, WA, with another facility
in Lafayette, LA. Samson Rope is not the traditional manual-assembly-
based operation. It operates highly automated processes to manufacture
commercial-strength rope for customers in the commercial marine, off-
shore rigging, commercial fishing, arborist, utility, safety, rescue, and
recreational marine industries. Samson has been around for more than
100 years and is recognized as the leader in developing and manufactur-
ing high-performance ropes. The company’s unwavering commitment to
111
112
Here is the story of how they used our company kaizen program
approach. The names and content of this chapter were approved by the
organization prior to publication.
January 2007
It was winter 2007, and I had just completed relocating my company,
Kaizen Assembly, to Bellingham, WA. I had grown up there but had
spent about four years in the South, living in Georgia and North
Carolina. Kaizen Assembly was entering its second year and was grow-
ing like a weed. Our customer base had grown, and I was excited about
continuing its success in the Pacific Northwest. It was around this time
that I also began teaching lean manufacturing at the local technical
school in its professional development program. This training outlet
was and is a very exciting and nice complement to my company’s cur-
rent consulting services.
I arrived at the facility and met with the plant manager, Ken. We sat
down and had a brief discussion of the kaizen course, the number of
113
K a i z e n a n d K a i z e n E v e n t I m p l e m e n t a t i o n Tr a i n i n g
complete, I was taken into the manufacturing facility.
Ken explained that the company had just finished a very aggressive re-
layout of the plant to incorporate individual work cells to reduce trans-
portation, motion, and travel distance. Those moves prior to my arrival
were really their first pass at lean, so they already had created a good
foundation for future changes. Samson Rope had a large maintenance
department of highly skilled employees who supported the operation
on all three shifts, including any special projects that were needed to
improve the facility.
The tour lasted about an hour, and we concluded our meeting with a
quick discussion of the training requirements for room space, booklets,
and AV equipment. It was a great start to our relationship.
They were quiet at first, as most new students are, and I am sure there
C h a p t e r 7 : C a s e S t u d y : S a m s o n R o p e Te c h n o l o g i e s , I n c .
Once we broke the initial theory portion and got into the “how-to” part,
the questions and comments began to formulate. I described in detail
who is required on the kaizen event steering committee and their roles
and responsibilities. We had a discussion about the importance of the
kaizen champion and how they could distribute the responsibilities of
this person among multiple people in the beginning. The communica-
tion system was outlined as well as the supply box and the kaizen
monthly meeting. These are all familiar to you from reading this book.
The Samson Rope people were convinced that good communication
was needed to support future improvements and they were happy with
the detail. We finished up with some final questions, and I thanked
them for the opportunity to speak to them and wished them good luck
on their lean adventures.
The following week I arrived once again at the Ferndale facility to dis-
cuss a potential partnership. Ken and I went over the details and agreed
on a contract. The Samson Rope and Kaizen Assembly bond was cre-
ated in late February 2007. I was to conduct a full lean assessment of
the company, facilitate a strategy session, conduct a series of training
classes, and facilitate a few kaizen events. It was a good start.
115
The assessment took a whole day, and once it was complete, I had iden-
tified a few areas as potential starting points that would consume the
rest of the year. From the assessment I concluded that the focus for the
first year should be on the implementation of 5S, developing the com-
pany’s kaizen program, and training the employees on the fundamentals
of waste reduction, value-added and non-value-added work, perform-
ance metrics, 5S, kaizen, and kaizen events.
Communication
Kevin and his maintenance crew began the construction of the kaizen
event supply box. They made it out of wood and installed wheels on it
so that it could be moved around as needed during the kaizen events. It
was designed to have a top lid that could be locked and that allowed for
a writing surface. The box was constructed nicely and as I was shown it
for the first time, I thought, “This thing is going to be used a lot.” It
wouldn’t look new for long.
Monthly Meeting
The newly formed kaizen steering committee scheduled its first meeting
to discuss the training schedule and the first kaizen event. I was
impressed with their motivation to get going. We agreed to start with an
introductory course on lean that would address the concepts. It was
intended for the whole company, so they rented a large conference hall
at a local hotel and packed the room. Once that course was complete,
we scheduled the kaizen course and the 5S course. Once we completed
that first round of training, we were ready for the first kaizen event.
There was a lot of fanfare and communication for this first event. Day
one started out as planned, with all three teams sorting through the
cells looking for anything and everything that was not needed. The
splicing team had a much larger area to work in. Kevin was the leader
for that team and he knew he had his hands full. The splicing area was
complex since the work was a manually intensive process of “splitting
rope” and customizing it for customers. The work varied from one week
118
to another; one job required very little material and supplies, but the
C h a p t e r 7 : C a s e S t u d y : S a m s o n R o p e Te c h n o l o g i e s , I n c .
next needed a work area in which to place material and supplies. Kevin
and his team began sorting.
Teresa had cell 5 and her team started off well. Teresa was eager for 5S
but was having a hard time taking the idea from training to incorporat-
ing it into her area, a perfectly normal response to 5S.
Bill was leading the cell 8 team. Cell 8 was where the larger rope in the
facility was made, so his goal was floor space reduction to provide bet-
ter transportation in and out of the cell. 5S can be challenging when the
product manufactured is big and naturally consumes floor space. Like
the other teams, his team started the sorting portion nicely.
As day one slowly came to an end, the teams had done what I had
asked of them: completed sorting by the end of the day. All teams had
successfully removed a variety of things into a designated red-tag area
for review. Day one ended with a quick team meeting to discuss
progress and to see if we needed to shift people around or get more sup-
plies. Kevin had supplied the event box well, and so far we were look-
ing good. Kevin felt that his team might need to sort more on day two
since it was a larger area. I could tell that the splicing team needed
some extra help, but I wanted to see how Kevin would react to the
amount of work still to do. There were a lot of items to set in order in
splicing. Rather than interfere, I wanted to gauge Kevin’s project man-
agement abilities.
Set in Order was the name of the game for the next two days. Since the
work cells used mostly mechanical equipment, there was enough oil and
dust on the floor that the team would have to use spray paint, rather
than floor tape, for floor identifications. Floor tape was still used in some
areas, though. Each team began identifying the items that would go on
tool boards. Bill’s team wanted to put new aisleways in the cell for
improved flow, so some of his team members began to lay down masking
tape to mark where the aisles would go. They also began to identify
where carts, garbage cans, pallets, and any floor items would be located.
Kevin’s battle continued in splicing. He had torn the place apart and
was slowly putting the area back together. His approach was good, as I
119
always encourage my 5S teams to clear the area and start from scratch.
Day four was now all about the splicing team. The other teams were
still working hard to finish up, so we focused on Kevin’s team. As in a
lot of kaizen events, sometimes it feels as if there is too much to do
with no end in sight. And then, almost magically, something happens:
The team unites even more and boom! It gets done. This is what hap-
pened on Kevin’s team. By the end of day four, the splicing area looked
great and the other two teams were nearing completion.
The teams came in on day five and finished what they could, knowing
that some amount of unfinished work would go on an action item list.
The kaizen event ended with a great presentation by the three team
leaders. The company had shown up in force, and they packed the
120
break room for the first kaizen event report out. The teams provided a
C h a p t e r 7 : C a s e S t u d y : S a m s o n R o p e Te c h n o l o g i e s , I n c .
tour for the employees and a lot of questions were asked. Mostly, there
were a lot of shocked faces and expressions. 5S had begun—with more
to come.
5S Continued
It was back to work for the people at Samson Rope, as they entered the
most difficult part of the process: sustaining and continually improving.
The kaizen steering committee scheduled another meeting to discuss
the development of the 5S audit and tracking system. They developed a
preliminary 5S audit form and an audit schedule and posted a tracking
sheet. The tracking sheet was placed in the company’s information area
and near each work cell. I explained that they should start auditing
only those areas that had had the 5S implementation. We also discussed
the next kaizen event and how 5S would be implemented in other areas
outside of events. Teresa was the supervisor for three work cells, and
she now had experience with 5S as a kaizen event team leader, so she
committed to implementing 5S with her employees in her other areas of
responsibility, on her own. Teresa was quickly becoming the 5S cham-
pion at Samson Rope. We had faith that she would forge ahead.
The committee encouraged the plant to look at what the teams did on
the first event and begin to apply 5S. The culture of change was
beginning.
The next official kaizen event was scheduled for September, and the
area selected was the maintenance department.
area where people share tools and supplies depending on the need for
So we began. The sorting process was less crazy than I was anticipating.
It was not the first time in my journey with Samson Rope that I found
their resistance to change to be very low. They found the whole process
of sorting out maintenance to be somewhat invigorating. Old tools,
machinery, fixtures, parts, bins, and shelves were all removed. The red-
tag area for this event was filling fast. There were three distinct areas in
the maintenance department: the actual workbench/tools area, a parts
room, and a small machine shop. Like a lot of other maintenance areas, it
was dirty from all the work that they do, so I knew that cleaning would
get us only so far. Paint, paint, paint would be the name of the game.
By the end of day one, the team had accumulated a very large pile of
stuff. A significant amount of money was connected to those items, but
there was no love lost there; if something was not used anymore, it left.
The real fun began on day two. Set in Order would be taken to a whole
new level as this team was to seriously raise the bar on designations
and identification. The tools boards were to be monstrous. The sheer
number of tools needed to support the hundreds of machines in the
plant was overwhelming, even after some healthy sorting. It was a
three-shift operation with multiple employees; this department needed
extra sets of tools in some cases. They had already started a tool board
prior to the kaizen event after witnessing what went on during the first
event in May, but there were still two to be made.
Each board was painted black to make the outline of the tools stand out.
Each tool was marked based on the board to which it was assigned (i.e.,
board 1, board 2, etc.). Labels were placed above each tool, and every-
thing had a home. Completing the tool boards took time, so Mike
assigned a small group to focus just on them.
Other team members were organizing the cabinets that were used to
hold larger, more expensive tools. I asked the team to seriously consider
removing the doors to continue the theme of visibility. They decided to
keep the doors because the items inside were expensive. I continued the
fight but eventually gave in. It is important to learn to strike a balance
between applying lean and giving a little to ensure that change is
122
Dan, the operations analyst for Samson Rope, seemed to take on a com-
mon role with the kaizen events. He took part in the previous event and
was also part of this project. He seemed to become the dirtiest of all
team members on every event. Dan cleaned, sorted, and volunteered for
a lot of the manually intensive work, often covering himself in dirt and
grease. His contributions to the lean journey would become a huge
asset. I helped Dan finalize locations for various tools and supplies on
shelves and racks.
The team pushed hard into the third day, spray-painting equipment to
give it a showroom look, painting the floor, stenciling, and organizing
the parts room.
Kevin stayed focused on this parts room, organizing items based on use
and labeling everything so people could find the items they needed
faster. The maintenance department was beginning to look like some-
thing other than a maintenance department. Toolboxes and tool chests
were disappearing. Drill presses and other machines in the work area
that were previously out in the open, disrupting movement, now could
be placed out of the way because of the floor space being opened up.
Cleaning supplies, brooms, dustpans, paint cans, mops, jacks, etc., were
all going vertical on boards or getting new homes. Ken made his usual
walk-through and was happy with the progress.
Completing 5S
With the fourth quarter now within view, the sense of urgency picked
up to get the 5S initiatives done. There were still a couple of areas to
finish. Teresa had successfully completed 5S in her other cells with the
help of her workers. Her enthusiasm for 5S was great, and we did not
have to worry about her areas anymore. Dan and Kevin had also been
working on the 5S audit system and began sending me the results of the
weekly audits on all shifts. As in all journeys, there was some level of
resistance to having to put things back all the time, but it was minor.
123
The groups spent a whole day finishing up the areas. As the groups fin-
ished, they decided to schedule one more event. What remained was
the coating department that was supervised by Ray. This event was
slated for December.
Sorting was light in this event and the Set in Order phase began
quickly. Half the team worked on 5S, and by now it was like old news
to them. They had become solid veterans of 5S. Another group worked
on a signal system to help the workers know what rope to coat in which
order, based on color and deadlines. The 5S team marked off a holding
zone for incoming WIP that would then be placed into a queue in a des-
ignated lane for a specific coating machine. This would allow the super-
visor to place things in order as needed, and the workers could simply
work on the items in the queue, reducing confusion.
124
The event moved along fine as we watched the coating area become the
last piece of the 5S puzzle. The area was completely changed to accom-
modate better flow, and the 5S implementation was complete.
2007 Complete
The 2007 lean journey with Samson Rope was quite amazing. The com-
pany saw record improvements in productivity, output, and delivery.
5S was not the only contributor to its success as other aspects of the
business improved as well. As the year ended the Lafayette, LA, plant
was beginning to get anxious about when it would happen for them. It
was at this point that the alignment of the organization’s 5S programs
would begin.
I met with Mark and Paul, the new purchasing manager (Ferndale).
They were going down for other reasons, but Mark wanted to show his
support for this new initiative. I conducted my day-long assessment to
provide the company with a lean baseline; one of its findings was the
need for 5S.
I spoke considerably about waste, floor space reduction, 5S, and kaizen
K a i z e n E v e n t 1 , Fe b r u a r y 2 0 – 2 2 , 2 0 0 8 : L a rg e R o p e 9 0 1
events. I also included total preventive maintenance training. Mark was
eager to get moving with 5S. It was needed in the plant and he had a
vision of helping Lafayette become a showroom facility. As at Ferndale,
we wasted very little time and scheduled the first kaizen event. Ron,
Mark, Paul, the now newly formed Lafayette kaizen steering committee,
and I assessed potential areas. Since I had not spent a lot of time there,
I suggested a three-day kaizen event to get our feet wet. We picked the
Large Rope area called 901. It would also involve a small splicing area.
The Lafayette kaizen steering committee consisted of the following
people:
We got right to sorting and opened all cabinets, drawers, tool chests,
and storage units. Dan, from Ferndale, continued his role as the dirt
man; he climbed up on the large machines in the Large Rope area and
began to clean and blow out the dirt that had accumulated over time.
Everyone else started identifying unnecessary items and placing them
in a red-tag area. The process was moving fast—so fast that the team
126
had to go to the outside garbage cans and pull out things that did not
C h a p t e r 7 : C a s e S t u d y : S a m s o n R o p e Te c h n o l o g i e s , I n c .
get evaluated long enough in the red-tag area; there were some things
that needed to go to maintenance. This was somewhat comical as far as
I was concerned, and it does happen when people get excited.
We flew through the sorting and met up for lunch to discuss progress.
Most of the sorting was complete, and we started the Set in Order phase
right away. Byron focused on cleaning machinery and applying new
paint. Other team members began tool board construction, trying to use
the same approach as the Ferndale maintenance team had. People were
marking off the floors and making homes for all supplies. The 901 area
had a community gear supply in a cabinet, and a lot of walking back
and forth was necessary during the day to set up machines. So the oper-
ators on the team identified those gears needed at each machine and
installed gear racks right next to the machine controls to eliminate
wasted motion. Everything was painted, and I mean everything.
Dan continued his cleaning work. Janet from Ferndale focused on label-
ing. Chris was a great team leader. His ability to manage the crew and
keep people focused was exceptional. I had to intervene a few times but
the incidents were minor in nature.
The team had cleared out the small splicing area and made some
changes to layout to improve overall flow for people and material.
Incoming and outgoing locations for WIP were located and tool boards
were getting made. We pressed on into the second day. A level of com-
petition was quickly forming between the plants as the Lafayette crew
wanted to really show their stuff. They had an equal amount of enthusi-
asm for what was to be done.
It was also important to recognize the work they had done on their
kaizen supply box. Marty, one of the maintenance employees, built
probably the biggest supply box I have seen, and it was loaded up for
the event. However, the committee underestimated the amount of paint
needed, necessitating a couple of runs to the local hardware store.
Again, this is a common occurrence during kaizen events.
We wrapped up the kaizen event on the third day with few to no action
items. It was a great start for them, and they were excited about the next
kaizen event. Before heading home, I spent some time with Ron dis-
cussing the pros and cons of the event and the expectations of
his newly formed committee. Ron was giving full support and we
127
K a i z e n E v e n t 2 , A p r i l 7 – 1 1 , 2 0 0 8 : A re a G , A re a D , A re a B
meeting. I boarded a plane the next morning and headed home.
We showed up in force and we started day one with the usual activities.
In preparation for the event, a lot of sorting had been conducted, as the
people in Lafayette were getting excited about improvement and could
not wait. That type of enthusiasm is great and I always encourage peo-
ple to sort early if they want. On day one, Lisa, the safety and quality
supervisor, came up to me and asked me to come see her department.
She had already started on her area and was in the process of imple-
menting 5S in her spare time with the help of her employees. I was
happy see other activities going on outside of kaizen events. Motivation
was high in Lafayette.
The teams worked hard sorting and moved into Set in Order by the end
of day one. Teresa and Kevin from Ferndale became co-facilitators,
helping the team leaders find their way. They did not need to help too
much, but when they did, they made decisions as needed.
As in the first event, masking tape was used to outline aisles and floor
locations. Equipment was getting cleaned and painted. Gears were being
pulled from community holding areas and being placed right at the
machines for point-of-use applications. Tool boards for tools and clean-
ing supplies were getting constructed and slowly being filled with the
necessary items. Ron, the plant manager, was seen a lot on the floor,
assessing the progress and showing his support for the project.
128
There were no real stoppages, just a few redirects here and there to keep
C h a p t e r 7 : C a s e S t u d y : S a m s o n R o p e Te c h n o l o g i e s , I n c .
things moving. As kaizen events near the end, people need to be work-
ing on important items. For instance, if the team is in day four and peo-
ple are wiping down hand trucks, but no tool boards are up, the event
leader must redirect. It happened a few times on this event but there
was nothing major. It was the second event at Lafayette and the team
leaders were learning as they went, and doing very well. As the event
was nearing its end, some of the teams were finishing early, and we
shifted people around to help other teams that had not yet completed
their work.
The Ferndale plant spent 2008 learning about value stream mapping,
time studies, and increasing uptime, and we conducted a few kaizen
events to further reduce waste, create visual production boards, and
look at material replenishment systems. Ferndale also refined its 5S
auditing system, which incorporated a rotational auditor program, and
quarterly incentives for the highest 5S scores. Outside of this great
story, both plants had challenges, setbacks, and struggles as in any
lean journey. Lean is truly a battlefield and it can be harder once 5S
is complete.
Both plants have to balance running the business and conducting con-
tinuous improvement. Lean is about two steps forward, one step back.
Resistance will appear at every level along the way. Change is always
tough, even for those organizations that have been practicing lean for
many years. The bottom line is that Samson Rope has proved to itself
129
that it can practice lean. And it is this continued push toward being the
My goal in writing this book was to provide you with the foundational
elements needed to support continuous improvement. The company
kaizen program has proven to be very successful in giving organizations
the vision, focus, and drive to make lean a part of doing business. It is
also important to understand that taking lean in its “textbook” version
is dangerous, as any journey must be custom-fit to the company’s needs,
processes, products, customer base, and employees. I hope that you will
take the concepts of the kaizen steering committee, the kaizen cham-
pion, lean communication system, tracking, team selection, team leader
selection, kaizen event facilitation, and many of the other ideas
described here and make them fit the unique culture within your com-
pany. Only then can you succeed with kaizen and lean. I wish you the
best of luck with your lean endeavors.
Chris Ortiz
Kaizen Assembly
131
This page intentionally left blank
Index
133
134
Index
Floor taping and designations champion skills, 42
5S events, 80, 83 leadership, 5–7
standard work events, 108 Samson Rope Technologies, Inc.,
Follow-up for action items, 52–53 115, 124–125
Food preparations, 66 transformation to, 5–6
Length, tracking, 28
G Lessons from a Lean Consultant, 6
Garbage cans, 79 Line balancing
Gathering data reviewing, 100–101
5S events, 77 rules, 97–98
current state, 44, 64, 73 Line designs
time study, 94 champion skills for, 46
General managers standard work events, 102–103
meeting with, 65, 74 Line operator input, 35
on steering committees, 19 Lowest sample removal from time
Goals, 11 studies, 96
establishing, 59, 71
tracking, 30 M
Green color for tower lights, 109 Machine shop projects, 104
Maintenance events
H 5S, 84–85
Highest sample removal from time Samson Rope Technologies, Inc.,
studies, 96 120–122
Hiring costs for champions, 49–50 standard work events, 102, 104
Human resource managers on Maintenance personnel on steering
steering committees, 21–22 committees, 22
Managers
improvement responsibilities, 5
I meetings with, 65, 74
Incentive programs, 90 on steering committees, 19,
Internal options for champions, 48 21–22
Internal quality information, 57 Manufacturing engineers
Inventory, 12, 98 responsibilities, 5, 17
Investments in champions, 49 on steering committees, 19–20
Materials
K champion skills for, 46
Kaizen Assembly: Designing, organizing, 83
Constructing, and Managing a Materials managers on steering
Lean Assembly Line, 34, 111 committees, 22
Kaizen overview Measurable improvements, 7–8
benefits, 7–8 Meetings
leaders, 5–7 end-of-day, 99, 102, 119
overview, 4 kickoff, 98–99
people, 5 with managers, 65, 74
Kickoff meetings, 98–99 midday, 103–104
monthly, 31–33, 51, 117
L Samson Rope Technologies, Inc.,
112–113
Leaders, 5–7 space selection, 72
champion responsibilities, 52 team, 64, 73–74
selection, 28, 58–59, 70–71
standard work events, 103
tracking, 28
136
S meeting space, 72
Index
Sales and output evaluation, 56–57 process/department/work area,
Samples in data collection, 96 56–57
Samson Rope Technologies, Inc., rooms, 63
111–112 Set in Order events
area events, 127–128 S5, 79–83, 86–87
audit and tracking system, 120 Samson Rope Technologies,
cells and splicing, 117–120 Inc., 123
coating, 123 standard work events, 102
communication, 116–117 Setup reduction skills for
completing, 122–124 champions, 45
event supply box, 117 Seven deadly wastes
implementation training, 5S events, 71
113–114 champion skills for, 41–42
initial meeting and tour, evaluating, 57
112–113 non-value-added, 62
Large Rope area, 125–127 Samson Rope Technologies,
lean assessment, 115, 124–125 Inc., 117
maintenance, 120–122 standard work events, 98
monthly meetings, 117 Shadow boards
progress, 128–129 5S events, 81–83, 86
return visit, 114 standard work events, 105, 109
steering committee, 116 Shift walk-throughs, 88
strategy sessions, 115 Shine function, 104
Schedules, 55–56 "Shock and awe" effect, 8
collected data analysis and Signs, 107–108
design ideas, 64 Skill sets for champions, 41–47
communication system Sort events
updates, 61 5S events, 74–77, 85–86
current state information red-tag areas, 77–78
gathering, 64 Samson Rope Technologies, Inc.,
events, 33 123, 125–127
food preparations, 66 Spaghetti diagrams
outside assistance, 61, 72 for area selection, 70
plant and general manager for current state, 45
meetings, 65 Spending
process/department/work area 5S events, 71
selection, 56–57 estimating, 59–60
room selection, 63 tracking, 30–31
spending estimates, 59–60 Splicing in Samson Rope
supplies, 60–61 Technologies, Inc., 117–120
supply placement, 64 Standard work events, 91
teams. See Teams action items, 102–103, 106–107
updating supplies and outside closing out, 110
resources, 63 end-of-day meetings, 102
waste analysis, 61–62 floor taping and designations,
Scrub event 108
S5 events, 79–83, 86–87 kickoff meetings, 98–99
standard work events, 102, 104 line designs, 102–103
Selection maintenance and Machine shop
areas, 70 projects, 104
champions, 47–49 midday meetings, 103–104
events, 26–27 preplanning, 92–98
leaders, 28, 58–59, 70–71 red-tag teams, 99–100
138
Index
Training rooms, 63 Walk-throughs, 88
Travel distance, 14–15 Waste analysis, 61–62
Waste elimination, 4. See also
U Seven deadly wastes
U-shaped cells, 102–103 Work area selection, 56–57
Updating Work content, documenting, 94–95
communication systems, 61, 72 Work flow skills for champions, 46
supplies and outside resources, Work in process (WIP), 12, 99
63, 72–73 Work surface evaluation, 79
Worksheets
V champion responsibilities, 52
tracking, 25–26
Value-added work, 62
Workstations
Value stream mapping (VSM), 44, 62
overview, 14
Visibility
signs, 107–108
5S events, 86
champion skills for, 42–43
standard work events, 106–107 Y
tools, 79–81 Yellow color tower lights, 109
Volume requirements, 92