Game Design and Development Capstone Project Assessment Using Scrum

Uploaded by

John Adam Morata
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 11

Paper ID #12938

Game Design and Development Capstone Project Assessment Using Scrum


John Glossner, Daniel Webster College
Dr. John Glossner is Associate Professor of Computer Science at Daniel Webster College. He also serves
as CEO of Optimum Semiconductor Technologies. Prior to joining OST John co-founded Sandbridge
Technologies and served as EVP & CTO. Prior to Sandbridge, John managed both technical and business
activities in DSP and Broadband Communications at IBM and Lucent/Starcore. John was also an adjunct
professor at Lehigh University. John received a Ph.D. in Electrical and Computer Engineering from TU
Delft in the Netherlands, M.S degrees in E.E. and Eng. Mgt from NTU, and a B.S.E.E. degree from Penn
State. He has more than 120 publications and 36 issued patents.

Prof. Nicholas Bertozzi, Daniel Webster College


Nick Bertozzi is a Professor of Engineering at Daniel Webster College (DWC) and Dean of the School
of Engineering and Computer Science (SECS). His major interest over the past 18 years has been the
concurrent engineering design process, an interest that was fanned into flame by attending an NSF faculty
development workshop in 1996 led by Ron Barr and Davor Juricic. Nick has a particular interest in help-
ing engineering students develop good communications skills and has made this a SECS priority. Over
the past ten years he and other engineering and humanities faculty colleagues have mentored a number
of undergraduate student teams who have co-authored and presented papers and posters at Engineering
Design Graphics Division (EDGD) and other ASEE, CDIO (www.cdio.org), and American Institute of
Aeronautics and Astronautics (AIAA) meetings as well. Nick was delighted to serve as the EDGD pro-
gram chair for the 2008 ASEE Summer Conference and as program co-chair with Kathy Holliday-Darr
for the 68th EDGD Midyear meeting at WPI in October 2013. Nick is currently serving as the Vice Chair
of the ASEE EDGD.
Prof. Charles N Stevenson P.E., Daniel Webster College

Page 26.809.1

c American Society for Engineering Education, 2015


Game Design and Development Capstone Project Assessment
Using Scrum

Abstract
This paper discusses the transition of a senior game design and development course project to a
scrum-based methodology from the traditional waterfall process. The paper explains the scrum-
based tools used to facilitate the project and observations on the transition. Examples are given
of student documentation and the methodology used to generate them. The prototype game will
be demonstrated at the presentation. In game design and development, by always producing an
iterated playable game, students are able to focus on “finding the fun” in the game. Using the
Scrum methodology all course outcomes were achieved.
Introduction
Our Game Design and Development (GDD) program and the complementary Game
Programming (GP) program are housed in the School of Engineering and Computer Science
(SECS). Game design students focus on art, game design, storyboards, and the development of
games. They also take entry-level programming and computer science courses. Game
programmers focus on programming, computer science and some game design aspects. The
senior year capstone project brings together both GDD and GP students, blending both artists
and programmers with the goal of producing a fully working game. Students are grouped into
cross-functional teams of nine to ten students and work together for two semesters.

Figure 1. Cynefin Complex Domain (used with permission Cognitive Edge Pte Ltd
http://cognitive-edge.com/ as published in Essential Scrum: A Practical Guide to the
Most Popular Agile Process1)
Page 26.809.2
Many projects can be partitioned into domains according to their complexity and uniqueness.
The Cynefin framework partitions projects into five domains based on their complexity: Simple,
Complicated, Complex, Chaotic, and Disorder. In the Simple domain the correct solution is
obvious and generally undisputed. Best practices and continuous business process improvement
methodologies tend to work well in this domain. In the Complicated domain there may be
multiple correct answers that typically require experts in the field to determine the best approach.
In the Complex domain a solution can typically only be determined with hindsight. There are
often more unknowns than knowns, and finding a solution requires invention. This is a perfect
domain in which to use Scrum. In the Chaotic domain crisis intervention is required. This may
come about from a program producing errors or an algorithm being incorrect. In the Disorder
domain it is impossible to identify any particular domain in which to classify a problem. Any
project in this domain has a goal of partitioning the problem such that the subdivided problem
will fall into any of the other four domains. In summary, Scrum is well suited to complicated
problems with many unknowns. This includes new engineering product development, software
development of new products, and particularly large student-led projects.

Figure 2. Waterfall Development Process2


Waterfall method
Historically our capstone project has been taught using a traditional waterfall software
engineering process. As shown in Figure 2, a requirements document is first generated and is the
contract between the customer and the design team. Once this document is approved, the Design
phase is started. A comprehensive design document is produced that details every item of what
will be developed. In the context of the game design project, this includes completion of the
Baldwin game design document3 including:
1) An overview of the game including concept, vision, target audience, look and feel
2) Gameplay and mechanics including game progression, structure, objectives, play
flow, physics, movement, objects, actions, combat strategy, options, replays, and
Page 26.809.3

game cheats
3) Story, setting, and character including back story, plot, storyboard, world design,
character stories, animations, and relationships between characters
4) Levels including for each level objectives, synopsis, introductory materials, map,
walkthrough, encounters, critical path, and opening/closing material
5) Interface considerations including menus, rendering system, cameras, lighting,
character controllers, sound effects, music, and a help system
6) Artificial intelligence (AI) including opponent AI, enemy AI, non-player
character AI, player collision detection and path finding
7) Technical considerations such as platform (PC, mobile), game engine, and
scripting languages
8) Game art including characters, style guides, and equipment
9) Miscellaneous including test plans and design software required
The aforementioned items are not exhaustive but meant to provide insight into the large amount
of work involved – and this is just the documentation phase. After the requirements document
and design document are complete, the implementation phase begins. In the context of game
design, this means both the game programming and art assets are implemented. Once all the
design is completed, the process moves to the verification phase during which the program and
assets are validated to work as specified in the design document. Finally a maintenance phase is
entered.
A key point of the waterfall process is that each subsequent stage is only entered upon the
completion of the previous stage. Thus any changes made may affect all stages. For example, a
project in maintenance phase that requires a change to the requirements should stop all work and
regress to the requirements phase.
Scrum methodology
A scrum-based methodology has been shown to be successful in a Cynefin complex environment
where there are many undefined and unknown features1. Using a traditional methodology may
result in changes to specifications late in the process, making the integration of individual parts
of the process difficult.
In Scrum, there are three primary roles. The product owner represents the customer and is
responsible for prioritizing product features. The development team completes all work in time-
boxed units of development called sprints. The scrummaster acts as a coach to both the
development team and the product owner. The scrummaster also facilitates removing obstacles
impeding the progress of the development team.
A key feature of scrum is a focus on iterative development with the output of each sprint being a
potentially shippable product. Game features are described in terms of user stories and estimated
using either T-shirt sizes (small, medium, large, extra-large) or story points (1, 2, 3, 5, 8, 13, 21,
50, 100). User story sizing is meant to be relative to other user stories. A numerical value of 2
story points would roughly represent an easy-to-implement user story that is twice as difficult as
Page 26.809.4

a numerical value of 1. A key point is that the development team must come to a unanimous vote
on the number of story points required for a user story. While there are different estimates the
team is encouraged to discuss why their votes are different. Re-votes are taken followed by more
discussion. The process repeats until everyone agrees.

Figure 3. Example User Story with Conditions of Satisfiability


Story points are not intended to be directly correlated with time, although some organizations
using scrum do estimate user stories with time. The list of all user stories is called the product
backlog. Each user story in the product backlog is called a Product Backlog Item (PBI).
Figure 3 shows an example user story with conditions of satisfiability meant to clarify the scope
of the user story. The user stories are prioritized by the product manager in a process called
product backlog grooming. Stakeholders and the development team members are encouraged to
participate in the prioritization, but the product manager has final authority for the prioritization.

Figure 4. Sprint Tasks


Before the sprint begins, the development team performs sprint planning. Sprints are a fixed time
duration, usually between two and four weeks where all of the work is implemented. The
development team decides how many user stories can be completed in a single sprint. Sprint
planning transforms the user stories into a set of sprint tasks. Unlike user stories that represent
customer features, sprint tasks represent the tasks the development team must perform to
implement the user stories. Figure 4 shows an example of sprint tasks at a snapshot of a sprint.
The sprint tasks are estimated in ideal hours shown in the brackets. Ideal hours are the
uninterrupted amount of time estimated to do the task. Just as with user stories, the development
team must come to a unanimous estimate on ideal hours, or they discuss their reasons for
differences and vote again. A link to the original user story is denoted by the PBI label. The
prioritized list of sprint tasks is called the sprint task backlog. Each sprint task within the sprint
task backlog is called a sprint task backlog item.
Once sprint planning is complete, the development work can begin. Sprint tasks are assigned to
development team members in user story priority with some allowance for the capabilities of
Page 26.809.5

individual participants. On each day from the second day until the end of the sprint, the
development team meets for a time-boxed meeting called the daily scrum. To facilitate a short
meeting, all participants are required to stand up in a circle.
During the daily scrum each development team member, in no specific order, answers three
questions for the team: 1) what did I do since yesterday? 2) What I am going to do today? And 3)
is anything impeding my progress? It is important that the team members talk to each other and
not to the scrummaster or product owner. The product owner is encouraged to attend but is not
required. The daily scrum should last no more than fifteen minutes. Complicated discussions can
be side-lined and resumed after the daily scrum by those affected. If any development team
member has impediments, those become the responsibility of the scrummaster to resolve.

Figure 5. Sprint Burn Down Chart


A key metric discussed at each daily sprint is the team’s velocity. During the sprint this is the
number of ideal hours completed toward the sprint goal divided by time. This is captured in a
burn down chart. Figure 5 shows an example burn down chart from a successful sprint. The
vertical axis measures ideal hours for the total sprint. The horizontal axis is the date of the daily
scrum meeting where the remaining sprint task hours are measured. Typically the burn down
chart measures sprint task hours. It is also possible to measure the “burn down” of user story
points. The observation that this is not recorded “daily” is discussed in the section scrum as used
in the game design project.
As each sprint task is completed, the development team decides how to prioritize and assign
sprint tasks with the understanding that higher priority user stories are worked on first. Should
the development team run out of sprint tasks before the end of the sprint, then additional user
stories may be added. Should the development team have incomplete or partially completed user
stories, the entire user story is returned to the product backlog list.
At the end of the sprint, two meetings are held. The first is the sprint review. At the sprint review
Page 26.809.6

the entire team attends, including the development team, scrummaster, product owner,
stakeholders, and customers. A development team member reviews what user stories went into
the sprint and what user stories were completed. A demonstration of the potentially shippable
product is given. Customer feedback is then received for consideration in future sprints.
After the sprint review meeting, the entire scrum team holds a sprint retrospective meeting. The
scrummaster, development team, and product owner all attend. The purpose is to determine what
went well in the sprint and what needs improvement from a development process perspective.
Generally the team will select one or two observations to improve in the next sprint.
After the sprint retrospective the process begins again with product backlog grooming.
Scrum as used in the game design project
The two-semester game design and development class meets twice a week for 110 minutes each
class. Typically a single team of 9 to 10 students is involved. The objective of the course is to
develop a portfolio that includes game concepts and art as well as to expand experience in
teamwork, game engine skills, and software engineering skills.
At our school we desire to give students ownership of their projects, including making decisions
about the type of projects they work on. In the game design and development project, this means
they can choose the style of game (RPG, FPS, etc.), target platforms (XBOX, PC, etc.) as well as
character stories and plots. Since this is all unknown at the start of the project, this corresponds
to the Complex domain in the Cynefin classification and thus is a perfect candidate for scrum.
Since scrum is being used in a university setting, some modifications have been implemented.
The process is described in this section.
When first transitioning to scrum, a few classes are used to teach the scrum methodology while
the students begin to brainstorm a vision for their game. In both Computer Science (CS) projects
and GDD projects, multiple competing visions often emerge. In this case the students are asked
to vote. If no clear choice emerges, discussion is invited before a re-vote. Gradually the options
are eliminated until one project is chosen. It has been observed that the vision statements may be
combined or characteristics of one game vision adopted into a revised vision statement prior to
re-voting.
The students function primarily as the development team in the scrum methodology. The
instructor facilitates the roles of product owner and scrummaster. Students are involved in some
of the product owner roles such as writing user stories, product backlog grooming, etc. While
ultimately the instructor owns the product backlog, input from the students should be
encouraged.
An initial exploratory sprint lasting about a week is run to familiarize students with the process.
Prior to beginning the exploratory sprint, the students spend one or two class periods creating
user stories. They are encouraged to put themselves in the perspective of the game player. When
estimating user stories in a classroom environment, we prefer t-shirt sizes so that there is no
confusion that the estimates may correlate to time.
The exploratory sprint “dry run” is not graded and serves a dual purpose of exposure to the
Page 26.809.7

scrum process and a dynamic exploration of the game design proposal. In one particular case,
students were allowed to “fail fast” whereby during the exploratory sprint they realized their
initial game concept could not be implemented within the two-semester sequence. The entire
team agreed to select the second place vision statement as their game project. Using traditional
software engineering methodologies may not have allowed the students sufficient time change
the game proposal. We discuss one such case in the results section. Using Scrum and the
exploratory Sprint, they were able to choose a new game concept without academic penalty. It
also helps students learn that their initial design idea might not always be the best choice.
With a vision statement unanimously agreed upon, the classroom structure becomes: 1) write,
prioritize, and estimate user stories, 2) convert user stories to prioritized, estimated sprint tasks,
3) sprint to complete development work, 4) hold a sprint review meeting, and 5) hold a sprint
retrospective meeting.
Writing user stories and sprint planning each take one to two hours of class time, primarily in the
beginning of the project and less after students are familiar. Google documents have been found
to be indispensable for this process, as it allows concurrent editing of the document. Since there
is no actual customer for the project, we hold the sprint review meeting and sprint retrospective
meeting in a single 110-minute class period, but the instructor specifically announces the end of
the review and transition to the retrospective.
At the beginning of the first semester, we use about 30 minutes of class time during every class
to go over the scrum methodology. We suspend these lectures during sprints and pick them up in
between each sprint. By the time students complete the exploratory sprint, they have enough
knowledge to enter their first graded sprint.
Because the class meets twice a week, the “daily” scrum is held only on class days. Students are
given a few minutes at the start of class to update the burn down chart, and each student answers
the three questions: 1) what have I done since the last scrum meeting? 2) What am I going to do
today? And 3) is anything impeding me. It is often uncomfortable for students to stand in a
circle, but they will get used to it. There is also a tendency for the students to “report” to the
instructor. This should be highly discouraged, and before the start of each scrum meeting, the
student should be reminded that he or she is talking to the development team and not the
instructor. It is sometimes helpful for the instructor to not make eye contact with the student
speaking.
Occasionally an impediment will arise during a scrum meeting. If it is valid, the instructor should
take an action item to resolve it. One case involved software limitations. The instructor requested
that the school install software on lab machines. This was done quickly and removed the
student’s impediment. Often false impediments such as “not enough time” or “other class
demands” may arise. The instructor (as scrummaster) should gently remind the students that
these are not valid impediments.
Page 26.809.8
Figure 6. Game Design Project Course Evaluation
Course evaluation is primarily based on running three or four sprints (depending upon the
semester) and the outcome of the sprints. Figure 6 shows the second semester course evaluation
metrics. Four product backlog item lists containing the list of prioritized user stories are turned
in, each worth 2.5% of the grade per team. Similarly, four sprint task backlog lists (one per team)
are graded for a small percent of the grade. A single group grade is also given for the Trailer and
demo day presentation. The Trailer is a short video advertisement for the game the students are
developing. It makes up 15% of the overall grade.
The majority (60%) of the student’s grade is based on the outcome of the sprint. To assess
individual contributions to a sprint, we use CATME developed by Purdue University4. In this
methodology students evaluate both themselves and their teammates. CATME is able to identify
conflicts within groups as well as dysfunctional teams. Students who wish to dispute the peer
rating must keep a journal of activities. Students receive a team grade that is individually
adjusted according to their CATME assessed contribution. The team grade is assessed 80% by
sprint results and 20% by the sprint report write-up. Even a sprint that completes all user stories
may not receive full credit if the burn down chart is not linear. Thus, students who wait until the
project deadline and complete all tasks with one heroic effort jeopardize the overall sprint grade.

Figure 7. Game Design and Development Project Course Outcomes


Observations and results
The Game Design and Development program is relatively new at our school. In the incubation
period students were primarily from the GDD program, and course outcomes #4 and #5 shown in
Figure 7 were not fully achieved. With the inclusion of GP students in the capstone project and
the transition to a scrum-based project methodology, we have achieved all program outcomes
prior to the end of the second semester. In particular, students using the scrum-based
methodology have had a working, potentially shippable game since the end of their second
Page 26.809.9

sprint. This is a significant improvement over previous years.


Having a working prototype at an early stage also allowed students to more easily envision and
write user stories. Iterating simultaneously on the game’s vision statement and user stories
allowed the game to evolve. At the beginning of the project, it was difficult for students to see
everything they wanted to develop within the game. Allowing inspect and adapt iterations at the
end of every sprint allowed them to refine their game.
As the semester progressed, having fixed time periods of work helped the students to set goals
and prioritize development. While not all Sprints were as successful as that shown in Figure 5,
the general capabilities of the group were better estimated for each sprint, and the user stories
selected for each sprint were generally completed on time.
Related work
Scrum has been used extensively in industry – including the gaming industry11. Scrum has also
been used with positive outcomes in academia5,6. Scrum was first described by Takeuchi and
Nonaka for product development in automotive and printer industries7. It was quickly adopted
for software development and shown to be effective8. It has been shown that 70% of projects
using the waterfall process fail to meet their objectives9. It is also noted when the two processes
are combined, the failure rate of “scrummer-fall” or “water-scrum” may also be 70%10.
Conclusions
In the game design and development course we followed a pure scrum methodology. Using this
methodology students were successful in iterating a working game that was always in a
potentially shippable state. Students were able to change their game objectives and refine
features over the course of the project, resulting in all expected outcomes being achieved.

Bibliography
1. Rubin, Kenneth S., Essential Scrum: A Practical Guide to the Most Popular Agile Process,
Addison-Wesley Professional; 1st edition (August 5, 2012), ISBN-10: 0137043295.
2. Waterfall method. http://en.wikipedia.org/wiki/Waterfall_model
3. Baldwin game design document available from http://baldwindesignconsulting.org
4. http://cateme.org
5. Grimheden, M.E., Mutual learning experiences – Mechatronics capstone course projects
based on Scrum, American Society for Engineering Education, 2012.
6. Reichlmayr, T., Working towards the student scrum – Developing agile android applications,
American Society for Engineering Education, 2011.
7. Takeuchi, Hirataka and Nonaka, Ikujiro, “The New New Product Development Game”,
Harvard Business Review, January, 1986.
Page 26.809.10
8. Sutherland, Jeff and Schwaber, Ken, The SCRUM Development Process,” at Object-
Oriented Programming, Systems, Languages & Applications (OOPSLA) Conference ‘95 in
Austin, Texas.
9. Serena Corporation, An Introduction to Agile Software Development, June 2007. Available
at http://www.serena.com/docs/repository/solutions/intro-to-agile-devel.pdf
10. Denning, Steve, “Scrum Is A Major Management Discovery”, Forbes magazine, April, 2011.
Available at: http://www.forbes.com/sites/stevedenning/2011/04/29/scrum-is-a-major-
management-discovery/
11. Agile Game Development with Scrum by Clinton Keith Addison-Wesley Professional; 1st
edition (June 2, 2010), ISBN-10: 0321618521, ISBN-13: 978-0321618528