Sub:-WRD- Kadapa "' Investigation and Construction of Lift Schemes to lift water from
GNSS-HNSS under EPC Turnkey system -Kaletivagu Reservior- Head Sluices
@KM.0.100- Design and Drawings of EM Parts and Hoist Mechanism for Service and
Emergency Gates-Mechanical Design and Drawings of Service Gate &Emergency gate
of [email protected] Approval for Service gate &roller Assembly of -
Kaletivagu Reservior- Put up for approval-Regarding.
Ref:-1)LrNo:CE(P)//WRD/KDP/SE(D&QC)/DW/EE(D)/DEE1/AEE/Kaletivagu
Dt:01-02-2023.
2)
****
showing the details of Block out & Embedded parts for Emergency gate.
Further, it is submitted that the fouling of rope is observed when the gate is resting on sill
as per General arrangement drawing. As such the proposed C/C of lifting as 3500mm is
modified to 2100mm to avoid fouling of rope. Hence CE/NTRTGP may be requested to
revise the hoist &hoist bridge duly considering C/C of lifting as 2100mm and to furnish
the revised designs and drawings of hoist & hoist bridge of Service gate along with
revised general arrangement drawing at the earliest for according approval.
The Mechanical Design and Drawings of block out and Embedded Metal parts
and Gate and roller assembly of Emergency and Service gates pertaining to OT Sluice@ Km
0.100 of Kaletivagu Reservoir were received vide reference 1st cited.
Now, the design and drawings of Block out and Embedded Metal parts of emergency
and Service gates are examined with respect to the vetted civil Drawing No: GNSS-HNSS-
KLTV-CIV-OTS-1011 and the following is submitted for favor of kind perusal and approval.
The sill level of Gate is +242.992 M and FRL is +263.00M and MWL is +265.50M.
The Gate is designed for FRL condition. As the head of water is 20.008 m, the Gates are
designed as Medium head fixed wheel gates. The OT Sluice @ Km 0.100 on Kaletivagu
Reservoir consists of one No. of Service Gate & emergency gates. The Hoist Bridge level is
tentatively indicated as +269.00M.
DESIGNS:
The service gates are proposed with D/S sealing and emergency gates are proposed
with U/S sealing. The hydraulic thrust acting over service gate is worked out to be 34.98 T and
for Emergency gate 32.71 T. The agency has considered wet and inaccessible condition for
design of embedded metal parts of Service and Emergency gates and wet accessible condition
for design of gates.
The groove size is proposed as 510X450 mm duly providing offset on D/S side of
groove as per IS:9349 is verified.
Service Gate E.Mparts:
1. Roller track S.S plate:- The thickness of roller track S.S plate of 130mm X12 mm with
material 20cr13:IS 1570 part V is verified.
2. Roller track: - The proposed roller track section with 150 x 16 mm plates for U/S and D/S
flanges and 150X16 mm plate for web is verified.
3. The proposed welding of 6 mm for roller track flanges and web is found to be inadequate
and modified with 10 mm weld.
Emergency Gate E.M.Parts:
1. Roller track S.S plate:- The thickness of roller track S.S plate of 130mm X12 mm with
material 20cr13:IS 1570 part V is verified.
2. Roller track: - The proposed roller track section with 150 x 16 mm plates for U/S and D/S
flanges and 150X16 mm plate for web is verified.
3. The proposed welding of 6 mm for roller track flanges and web is found to be inadequate
and modified with 10 mm weld.
4. The Top seal S.S.plate and back plate shall be plug welded.
Subject to compliance of certain observations, the following 5 No’s of
drawings pertaining to block out and Embedded Metal parts of service and Emergency gates
furnished are verified and corrections in view of modifications indicated in the drawing and
are herewith put up for conditional approval.
DRAWINGS:
1. Drawing No: KALETIVAGU RESERVIOR/OFF TAKE SLUICE@KM 0.100/LAYOUT/
01/2022 showing the details of General plan of Block out and E.M. parts for Service gate.
2. Drawing No: KALETIVAGU RESERVIOR/OFF TAKE SLUICE@KM 0.100/SG/EMP/
02/2022 showing the details of Block out & Embedded parts for Service gate.
3. Drawing No: KALETIVAGU RESERVIOR/OFF TAKE SLUICE@KM 0.100/SG/EMP/
03/2022 showing the details of Block out & Embedded parts for Service gate.
4. Drawing No: KALETIVAGU RESERVIOR/OFF TAKE SLUICE@KM 0.100/EG/EMP/
07/2022 showing the details of Block out & Embedded parts for Emergency gate.
5. Drawing No: KALETIVAGU RESERVIOR/OFF TAKE SLUICE@KM 0.100/ 08/2022
showing the details of Block out & Embedded parts for Emergency gate.
Sub:-WRD- Kadapa "' Investigation and Construction of Lift Schemes to lift water from
GNSS-HNSS under EPC Turnkey system -Kaletivagu Reservior- Head Sluices
@KM.0.100- Design and Drawings of EM Parts and Hoist Mechanism for Service
and Emergency Gates-Mechanical Design and Drawings of Service Gate
&Emergency gate of [email protected] Communication of
copies of Conditionally approved drawings of Service gate &roller Assembly and
of Emergency gate &roller Assembly of Kaletivagu Reservior -Regarding.
Ref:-1)LrNo:CE(P)//WRD/KDP/SE(D&QC)/DW/EE(D)/DEE1/AEE/Kaletivagu
Dt:01-02-2023.
****
The mechanical Design and Drawings of Block out and Embedded Metal parts
and Gate and roller assembly of Emergency and Service gates pertaining to OT Sluice @KM
0.100 on Kaletivagu Reservoir were received vide reference 1st cited.
Now the design and drawings of Block out and Embedded Metal parts of
Emergency and Service gates are examined with respect to the vetted Civil Drawing No.
GNSS-HNSS-KLTV-CIV-OTS-1011 and the following is communicated for necessary
action.
DRAWINGS:
1. Drawing No: KALETIVAGU RESERVIOR/OFF TAKE SLUICE@KM 0.100/LAYOUT/
01/2022 showing the details of General plan of Block out and E.M. parts for Service gate.
2. Drawing No: KALETIVAGU RESERVIOR/OFF TAKE SLUICE@KM 0.100/SG/EMP/
02/2022 showing the details of Block out & Embedded parts for Service gate.
3. Drawing No: KALETIVAGU RESERVIOR/OFF TAKE SLUICE@KM 0.100/SG/EMP/
03/2022 showing the details of Block out & Embedded parts for Service gate.
4. Drawing No: KALETIVAGU RESERVIOR/OFF TAKE SLUICE@KM 0.100/EG/EMP/
07/2022 showing the details of Block out & Embedded parts for Emergency gate.
5. Drawing No: KALETIVAGU RESERVIOR/OFF TAKE SLUICE@KM 0.100/ 08/2022
showing the details of Block out & Embedded parts for Emergency gate.
Extra notes regarding material specifications etc. are mentioned in the
drawings. Further, it is informed that the suitability of these drawings with respect to the
field conditions shall be ensured by the field authorities of the project before fabrication,
erection and execution. If there is any deviation, it needs revision and same is to be referred
to CDO.
This conditional approval does not preclude enforcement of agreement
conditions. Any variation in the agreement conditions should be taken care of, by the field
officers as the onerous responsibility lies on them. The copies of the above conditionally
approved drawings are herewith enclosed with a request to furnish two sets of fresh drawings
with signatures of field officers duly incorporating/attending all the corrections/ omissions
and remarks along with a soft copy in AUTO CAD format for final approval.
Further receipt of the copies of the conditionally approved drawings may please be
acknowledged and also the feedback form now enclosed to be returned duly filled in.
Encl:1. Drawing (5 No.)
2. Feedback form.
Yours faithfully,
Sd/- 16-03-2023.
Chief Engineer,
Central Designs Organisation,
Vijayawada.
//TCF//
Executive Engineer,
Division - 3,
Central Designs Organisation, Vijayawada.
//DFA//
GOVERNMENT OF ANDHRA PRADESH
WATER RESOURCES DEPARTMENT
From To
T.V.N.A.R.Kumar, The Chief Engineer,,
Chief Engineer(FAC) NTRTGP,
Central Designs Organisation (AP), Tirupathi.
Sri Sai Balaji Complex, 2nd floor,
Bhavani puram
Vijaywada – 520012.
*********
In continuation to the T.O. Lr 3rd & 4th cited, where in copies of
conditionally approved drawings of Block out & EM parts drawings of Service & Emergency
Gates and Gate and Roller assembly of Service gate of Off take Sluice @ KM 1.325 of
Nethiguntapalli Balancing reservoir were communicated duly requesting to furnish corrected
drawings for according final approval which are yet to be received.
Now, the mechanical design and drawings of Gate and
Roller assemby for Emergency gate pertaining to Off take Sluice @ KM 1.325 of
Nethiguntapalli Balancing reservoir are examined with respect to the approved civil drawings
received vide reference 1stcited and the conditionally approved Block out & EM parts
drawings and the Service Gate & Roller assembly drawings and following is communicated
for taking further action.
TEFLON CLADDING ON RUBBER SEALS:
The fabrication of Teflon cladding for the rubber seals shall be done properly,
otherwise it results in “peeling-off” of Teflon cladding and the rubber will have direct contact
with seal track; which will increase the seal friction abnormally, and affects the lifting
capacity of hoist mechanism, drastically. And while lowering, for self-closing of gate also it
requires additional effort in the form of ballast, resulting in operational failure of the gate. As
such necessary care shall be taken by the field officers to fabricate the Teflon cladding seals
perfectly by providing with sufficient anchorages, for ensuring trouble free operation of gate.
Factors to be considered by the field officers / agency for fixing of Teflon cladding to
rubber seals.
1. Necessary care shall be taken by the field authorities for the qualitative fixing of Teflon
cladding over rubber seal, duly providing with sufficient anchorages.
2. After erection of the gates, while in trial runs (including light test & water jet tests) the
field officers shall carefully observe the working of seals and it should be immediately
rectified if any deviations are found for avoiding the above effects
Subject to the compliance of certain observations the following drawings are
conditionally approved.
showing the details of General plan of Block out and E.M. parts for Service gate.
2. Drawing No: NETHIGUNTAPALLE/OFF TAKE SLUICE@KM 1.325/SG/EMP/ 02/2022
showing the details of Block out & Embedded parts for Service gate.
3. Drawing No: NETHIGUNTAPALLE/OFF TAKE SLUICE@KM 1.325/SG/EMP/ 03/2022
showing the details of Block out & Embedded parts for Service gate.
4. Drawing No: NETHIGUNTAPALLE/OFF TAKE SLUICE@KM 1.325/EG/EMP/ 07/2022
showing the details of Block out & Embedded parts for Emergency gate.
5. Drawing No: NETHIGUNTAPALLE/OFF TAKE SLUICE@KM 1.325/EG/EMP/ 08/2022
showing the details of Block out & Embedded parts for Emergency gate.