TNRI Final Design Report R01
TNRI Final Design Report R01
TNRI Final Design Report R01
Republic of Tajikistan
Mother-Child-Care and Emergency Care VI - TNRI
1. EXECUTIVE SUMMARY.......................................................................................................1
2. INTRODUCTION...................................................................................................................2
2.1. PROJECT BACKGROUND...........................................................................................2
2.2. THE SITE.......................................................................................................................2
2.3. ARCHITECTURAL DESIGN STATEMENT....................................................................3
3. CONTEXTUAL PLANNING...................................................................................................4
3.1. DESIGN (OVERALL).....................................................................................................4
3.2. SERVICES ORGANIZATION IN THE FINAL DESIGN..................................................4
3.3. DESIGN PARAMETERS CONSIDERED.......................................................................5
4. ARCHITECTURAL.................................................................................................................7
4.1. INTRODUCTION...........................................................................................................7
4.2. PLANNING PARAMETERS...........................................................................................7
4.3. BUILDING PROGRAM (SRP) SUMMARY....................................................................8
4.4. HEALING ARCHITECTURE, INTEGRATION OF NATURE AND GREEN....................9
4.5. FLOOR LAYOUT OF ANNEX BUILDING (PLANS, SECTIONS, AND ELEVATIONS). .9
4.5.1. BASEMENT FLOOR..............................................................................................9
4.5.2. FIRST FLOOR.......................................................................................................9
4.5.3. SECOND FLOOR................................................................................................12
4.5.4. THIRD FLOOR.....................................................................................................13
4.5.5. CONNECTION BRIDGE......................................................................................14
4.5.6. ELEVATIONS.......................................................................................................15
4.5.7. SECTIONS...........................................................................................................16
4.6. ENERGY-EFFICIENT BUILDING DESIGN..................................................................18
4.7. DESIGN PRINCIPLES.................................................................................................21
4.7.1. EXTERNAL WALLS (CAVITY WALL)..................................................................21
4.7.2. PARTITION WALL................................................................................................21
4.7.3. WINDOWS...........................................................................................................21
4.7.4. DOORS................................................................................................................22
4.7.5. FLOOR.................................................................................................................22
4.7.6. EPS ROOF...........................................................................................................23
4.7.7. PLASTERING......................................................................................................24
4.7.8. PAINTING............................................................................................................24
4.7.9. SUSPENDED CEILING.......................................................................................24
5. STRUCTURAL.....................................................................................................................25
5.1. PROJECT SCOPE.......................................................................................................25
5.2. GENERAL CONDITION...............................................................................................25
5.3. DESIGN CRITERIA.....................................................................................................25
5.4. ANTI-SEISMIC MEASURES........................................................................................26
5.5. FOUNDATIONS...........................................................................................................26
5.6. REINFORCED CONCRETE SLABS...........................................................................26
5.7. REINFORCED EXTERNAL WALLS............................................................................27
6. ELECTRICAL.......................................................................................................................28
6.1. INTRODUCTION.........................................................................................................28
6.2. ELECTRICAL DESIGN ASPECTS..............................................................................28
6.3. DESIGN CONSIDERATION & PARAMETERS FOR ELECTRICAL WORKS.............28
6.4. CONDUITS..................................................................................................................29
6.5. GROUNDING SYSTEM...............................................................................................29
6.6. EMERGENCY POWER SUPPLY................................................................................29
6.7. LIGHTNING PROTECTION SYSTEM.........................................................................29
6.8. FIRE ALARM SYSTEM................................................................................................30
6.9. TELECOMMUNICATION SYSTEM.............................................................................30
6.10. NURSE CALLING SYSTEM........................................................................................30
7. MECHANICAL.....................................................................................................................31
7.1. HVAC SYSTEM...........................................................................................................31
7.1.1. STANDARD AND CODES...................................................................................31
7.1.2. DESIGN CONDITION..........................................................................................31
7.2. AUTOMATION SYSTEM.............................................................................................32
7.3. HEATING SYSTEM.....................................................................................................33
7.4. MEDICAL GAS SYSTEM.............................................................................................33
7.4.1. OXYGEN GENERATOR......................................................................................33
7.4.2. MANIFOLD SYSTEM...........................................................................................34
7.4.3. MEDICAL AIR PLANT..........................................................................................34
7.5. PATIENT TRANSFER LIFT SYSTEM..........................................................................35
8. PLUMBING..........................................................................................................................36
8.1. STANDARD AND CODES...........................................................................................36
8.2. PUMPING UNITS........................................................................................................36
8.3. HDG WATER TANK.....................................................................................................36
8.4. DECENTRALIZED HOT WATER SUPPLY (BOILER TYPE).......................................36
8.5. FIREFIGHTING SYSTEM............................................................................................37
8.6. WASTE WATER TREATMENT....................................................................................37
8.7. CLEAN WATER TREATMENT SYSTEM (SOFTENER)..............................................37
8.8. SEWERAGE SYSTEM................................................................................................38
9. COST ESTIMATE................................................................................................................39
9.1. SUMMARY OF CONFIDENTIAL COST ESTIMATES.................................................39
9.2. COST ESTIMATE PER SQM.......................................................................................40
9.3. FINAL COST ESTIMATE (OVERALL-CIVIL WORK)...................................................40
ANNEXES
I. Detailed Drawings
There exists a clear need for expansion in infrastructure and equipment to address the current
as well as future services demand.
The investment measures foreseen in this project will address these needs.
1
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
2. INTRODUCTION
2.1. Project Background
The German Financial Cooperation (FC) Mother and Child / Emergency Care Programme
Phase VI builds on the ongoing Mother and Child / Emergency Care Programme Phases II-V.
The overall program objective is to improve accessibility of all population groups and genders,
especially in rural areas, to basic and sustainable health services of international quality.
The Tajik National Research Institute for Obstetrics, Gynecology and Perinatology (TNRI) is the
key institution providing maternal and child health services in Tajikistan and serves as a tertiary
referral level. The institute is a national training institute for medical staff and provides
supervisory services for lower- level health facilities. The institute conducts research on matters
related to obstetrics, gynecology, and perinatology. It furthermore provides support to health
authorities and participates in working groups for the development of norms and regulations.
Currently the TNRI is limited in serving as a central (tertiary level) referral center for Mother and
Child Health (MCH) services because of deficiencies in both infrastructure and equipment.
2
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
2.3. Architectural Design Statement
The final design considered the project's goals and requirements, the optimal functional and
spatial relationship between the two buildings, the constraints of the TNRI site, and compliance
with international and national regulations. The new design concept for the TNRI Hospital
focused on the development of a new building.
The L-shape with a wing on the right side of the building provides the opportunity for a direct
access for vehicles and ambulances other than the creation of a garden in front the
reception/admission area.
The annex building will be connected to the existing building on the 2nd and 3rd floors through a
bridge.
The workflow in the new building was worked out keeping in mind the scope of reorganization of
services in the 2nd and 3rd floors of the existing building while keeping in mind the inter-
relationships and inter-dependencies of the functional areas in the new building vis-à-vis those
post partial reorganization of functional areas on the 2nd and 3rd floors of the existing building.
3
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
3. CONTEXTUAL PLANNING
3.1. Design (Overall)
The design took into consideration the following which was further incorporated in the detailed
drawings:
Improving the indoor air quality by providing natural ventilation in the majority of the rooms
and internal circulations
Improving the user well-being and reduce the need for energy consumption by providing
natural light in all rooms
Reducing the circulation area (corridors) in order to reduce construction costs and to
increase space for clinical and patient care areas
Having a modular structural net with a simple shape to reduce the time for construction and
construction costs.
Incorporation of additional requests from the TNRI administration like additional storages
and wardrobes room
3.2. Services Organization in the Final Design
The proposal for the distribution of the services between the new and the existing buildings
intended to create an optimal organization of clinical activities between the two buildings. The
proposed allocation of services per floor/building was planned in a way that the existing building
serves as a support to the critical services performed in the new building, especially on the
second and third floor. Additionally, the design presented aimed to reduce as much as possible
the need for modifications of the layout in the existing building, thus reducing the need for
rehabilitation/construction works in the existing building.
The following table summarizes the allocations for the different functional areas in the new
building while providing a comparison between the original request, preliminary design and final
design
Surgical Suite
OT 4 4 4
Preoperative Care beds 4 4 4
Post-Anesthesia Care 5 5 5
beds
4
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
Admission &
Emergency
Procedure Room 0 2 2
Observation room 0 2 2
The following table summarizes the number of beds allocated across the different floors by
functional area concerned:
5
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
11 SNaR 31-02-2007 Public buildings and constructions
12 SNaR 21-01-2007 Buildings and constructions fire safety
13 SNIP 41-01-2003 Heating, ventilation and conditioning
14 Guidelines for Design and Construction of Hospital and Health Care Facilities - The
American Institute of Architects Academy of Architecture for Health
The Facility Guidelines Institute.
15 IHFG guideline
6
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
4. Architectural
4.1. Introduction
The design of the proposed development has evolved following a full analysis of the land and its
surrounding landscape, the team took the location and surrounding areas into consideration
especially factors such as topography, existing building engineering systems, existing layout of
civic amenities (electrical supply lines, plumbing lines, sewage system) climate and building
codes, taking into account the basic principles described below:
Space availability for fire point
Space availability for parking
Availability waste water connection to the main public line
Availability fresh water connection to the main public line
Availability of electricity connection to the main public line
Reduced dust and noise impact for the existing hospital due to short distance from main
entrance
Improve privacy, dignity, and comfort of patients
Minimize the risk of healthcare-associated infections
Enhance the Prevention and Control of Infections (IPC)
Promote good practice and safe health care delivery
Increase the efficiency of operation.
4.2. Planning Parameters
The following planning parameters were applied in developing the final design (An excerpt from
the Preliminary Design Report):
1 Construction of a new three store building in addition to the basement floor.
2 New construction of the sheds for generator and transformer.
3 New construction of the sheds for waste disposal structure.
4 New construction of the sheds for medical gas system
5 Patients and staff privacy needs and maximization of natural light in order to provide
comfortable spaces to support not only patient recovery and adequate working
environment for staff but also contribute to energy efficiency.
6 Ancillary spaces, such as mechanical and electrical installation rooms, storage and
cleaning rooms as well as waste management spaces.
7 Compliance with the requirements of the building permit authority and exterior design
authority of the city of Dushanbe
8 International standards or guidelines where Tajik regulations are not available.
Compliance with standards and guidelines of the Republic of Tajikistan with regard to
distances to neighboring buildings on site, distances to site boundary walls, fire
protection, escape routes, and urban planning aspects.
9 Construction dimensions that allow the use of prefabricated elements that are common in
Tajikistan.
10 Use of locally available and produced building materials to minimize construction delays
related to material supply.
11 Creating a patient-friendly environment through interior color schemes and exterior
landscaping and recreational areas for patients and their families.
12 Improved accessibility for people with special needs.
13 Construction of the internal water supply system, including all plumbing and sanitary
fixtures for the new three-store building, and necessary connections to the existing
7
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
external system. An additional booster pump will be installed to increase water pressure.
14 Installation of a new internal power supply system with switches, sockets, distribution
panels and fuse boxes with redistribution of load transfer.
15 The sewage from the annex building will be connected to the existing municipal sewage
system for Dushanbe city. The sewage discharge from the annex building is estimated at
32m3/day at this stage. The Design Organization Department in Dushanbe re-confirmed
the additional sewage discharge loads can be tolerated by the municipal sewage system.
16 Design Organization Department in Dushanbe re-confirmed additional loads, which can
be tolerated based on the existing capacities of the city heating plant.
17 Connecting the new annex building to the city's power supply through new transformers
(2x620 kVA) and (2x350 kVA) generators. The approximate calculated load of the annex
building is at 620 kVA; the capacity of main power line is sufficient to bear the additional
loads (The Design Organization Department in Dushanbe confirmed that the additional
loads can be tolerated.)
* The size of the basement was increased by +92 m2 to accommodate additional storage space
at the request of the TNRI working group.
** Increasing the insulation of the external wall in annex building 5cm to 10cm led to an increase
in calculation of gross area.
8
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
4.4. Healing Architecture, Integration of Nature and Green
All patient areas have adequate window openings to provide natural light and the connection to
the outside greenery. Avoiding noisy environment will be considered especially in the NICU /
ICU environment. For privacy, interior roller blinds as well as perforated privacy screens are
considered for lower windows on the first floor while maintaining the architectural aspect of the
hospital.
The basement is providing all needed technical and store rooms as follows:
Electrical room, stabilizer and UPS system, pump room, water tank Room, firefighting room,
workshop and staff room, additional storages and mechanical room.
This arrangement has ensured a compact arrangement and connection of building engineering
as well as support systems with the functional areas across the three floors above.
4.5.2. First Floor
Based on discussions with the TNRI working groups and MoHSPP, the revised concept for the
new annex building considered bringing critical services like emergency, admission, delivery
care, surgical services, critical care and sterilization under one roof to enhance workflow
efficiency and optimize the transfer of patients between admission and delivery/labor
department and surgical suite. This led to the following agreed upon changes:
9
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
1 Admission and emergency were relocated to the new building from the existing building
(1st floor)
2 Allocation of delivery services space in the new building (1st floor)
3 Relocation of surgical suit coupled with its expansion in the new building (2nd floor)
4 Relocation of sterilization services to the new building (1st floor) instead of a separate
building originally proposed
5 Centralization of the entrance/reception on the first floor of the new building
6 Assembling all the waiting areas and visitors' amenities foreseen to be located on the 1st,
2nd, and 3rd floors in one central waiting area on the first floor
10
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
3 Provision for separate circuit/flow for the admission of patients (especially emergency
cases arriving by ambulance) and for visitors, guaranteeing privacy and security
4 Improvement in overall circuit of sterilization services particularly functional relationship
of CSSD services with critical care areas and surgical suit through provisions of material
movement via two lifts (one each for dirty and clean items)
5 Optimal space allocation for the different functional areas, overall functional efficiency
11
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
4.5.3. Second Floor
Optimized workflow efficiency was further addressed through location of the critical care area
(ICU for post-surgical patients and high-risk pregnancy patients) along with the surgical suit in
two separate sections of the same floor divided by a cross-cutting corridor. Connectivity for
users to the floor above and below is ensured through staircases and two lifts (both can be used
as patient lift).
It has been recommended that the 2nd floor of the existing building continues to support the
high-risk pregnancy cases. This has ensured the following:
1 Minimized needs for any services reorganization on 2nd floor of existing building
2 Easy access to patient wards in existing building through bridge connection
3 Scope for fast and efficient transfer of emergency admissions to the surgical suit or
critical care area as necessary
4 Enhanced IPC
12
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
4.5.4. Third Floor
The functional areas allocated to the 3rd floor focused on neonatal critical care including
provision for mothers to stay with their new-born with introduction of NICU, Level I NICU and
Level II NICU. Connectivity to the existing building has been ensured through provisions of a
bridge. It has been recommended that the wards in the third floor of the existing building
continue to support the NICUs in third floor of the new building. This approach has ensured the
following:
1 Minimized need for any services reorganization on 3rd floor of existing building
2 Even within the building section housing the NICU and NICU Level I, these two services
could be completely segregated from each other
3 NICU and NICU level I with the more critical patients remains separated completely
from NICU level II (mothers staying with babies) by the cross-cutting corridor thus
ensuring better IPC
13
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
4.5.5. Connection Bridge
The new building will be connected to the existing building at level of the 2nd and 3rd floors
through a bridge. Location and design of the bridge took into account the following:
1 Consideration of connecting point with existing building directly in front of the existing
staircases and elevators
2 Existing functional areas in the existing building and need to minimize any rehabilitation
of existing building due to bridge connection
3 International regulations on permissible slope / inclination percentage
14
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
4.5.6. Elevations
15
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
4.5.7. Sections
16
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
17
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
4.6. Energy-Efficient Building Design
To improve energy efficiency in the final design of the annex building, the following approaches
have been considered:
Building - This will include insulation of the building envelope, high-performance
Envelope windows and doors, and building materials that reduce heat loss and in
Design the interior solid stone masonry walls to increase the heat storage
capacity.
- The optimization of the building envelope can be achieved at relatively
reasonable cost especially for annex building. The measures also
result in relatively low operating costs. All necessary materials and
expertise are available in Tajikistan.
Lighting Design - The intelligent lighting solutions, such as motion sensors and automatic
timed daylight-dependent sensors are considered in the design.
- All patient rooms are naturally lit.
- High-efficiency LED lighting fixtures.
Green Spaces - Incorporated plants and green space to improve air quality, reduce the
and heat island effect, and promote patient and staff wellness.
Landscaping - In addition, it was important to take a holistic approach to energy
efficiency, considering all aspects of the building and its systems to
achieve the best possible results with the available budget. This means
considering the orientation of the building, its location, the materials
used, the building systems and infrastructure, and the staff who will use
the building.
The heat losses for the components are assumed as follows:
18
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
The design principles and coefficients are the basis of our design, the window area does not
exceed 40% on each side of the facade which is currently achieved with the values mentioned
below on each side of the façade.
Building aesthetics
Providing compatibility of the exterior design with its physical surroundings which means
an outdoor area concept which is adapted to the hospital environment
Creation of bright, open, generously-scaled public spaces
Use of natural light, natural materials and textures in patient rooms, corridors and the
entry areas.
19
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
The fire protection system is used to extinguish or control the fire and prevent further
spread. For the active firefighting, powder fire extinguishers will be available in the corridor
of our hospital every 10 m
Another active fire protection system is a smoke detector system which will be installed in
the hospital in each patient and examination room as well as in storage rooms and
corridors. It will be evaluated further if it is possible to also install a fire alarm control panel
collecting all information about smoke and fire. This panel would be installed centrally and
allow an overview of the whole building.
Staircases can be reached quickly and safely. All fire protection and evacuation stair cases
are reachable in less than 25 m distance.
20
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
4.7. Design Principles
4.7.1. External Walls (Cavity Wall)
4.7.3.
Windows
Double-glazed aluminum window (6mm+12mm+6mm) will be
used.
21
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
The gap between glass in will be filled with argon gas.
Input Parameters Double Glazed Window: U Value 1.9 W/ m2.K
4.7.4.
Doors
Non-combustible rock wool insulation should be applied for all steel and wood doors. Heat
Transfer Coefficient: U-value 1.48 W/m²K
Single Door - 6mm thick L 120cm, H 220cm for Standard LDR and Patient Rooms
- 6mm thick L900cm, H 220cm for Standard Patient Toilet
Sliding Door - Hermetically sealed Manual sliding door for operating theatre
Swing Door - Swing leaf door in 2 nr side hung panels glazed with laminated clear
glass, 5mm thick for the corridor’s accesses.
Fire Door with - L 120, H 215 Single leaf fire door 60 min (EN 1634-1) for all
Panic Bars Emergency Exit Doors.
Automatic - Automatic sliding double-glass door for Patient and Emergency main
Sliding Door entrance (DW. L1 - Room No 104)
Revolving doors - Standard annual revolving doors for the visitor entrance (DW. L1 -
Visitors Lounge Room No. 100)
4.7.5. Floor
Matte surface anti-skid, acid-resistant and wear-resistant hospital floor porcelain Min. 10mm
Hydro insulation of 2 layers of bitumen under the floor finishing in all wet areas
Epoxy paint (antibacterial, antifungal & waterproof) for all mechanical rooms and storages in
basement floor
22
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
4.7.6. EPS Roof
U= 0,219 W/(m²·K)
The flat roof is insulated against water infiltration with a layer of vapor retarder and bitumen
sealing, insulation over the last reinforced concrete monolithic floor with 130mm thick of
Polystyrene sheet and a layer of expanded clay gravel of fraction along the slope, on top of
polyethylene film screed made of cement-sand mortar M150 will install 2 layers of bitumen
sealing and 50mm gravel (Round Stone Ballast).
(Refer to detailed drawings- architectural drawings- sheet No 20 -27 for more details)
4.7.7. Plastering
Mix of cement and sand in the ratio of 1:5 (1 part cement and 5-part sand) used for inner
plastering of brick wall. Thickness of plastering 20mm.
23
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
4.7.8. Painting
One coat of primer and two coats of Microbicide/ Antibacterial paints to internal faces of walls.
Colors and codes will be selected during the construction period.
24
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
5. Structural
5.1. Project Scope
Tajikistan is located in a seismically active zone. Therefore, the structural design considers
concrete columns and beams with reinforced masonry and the chosen grid ensures a high level
of earthquake safety. The Earthquake design is based on loads (i.e. acceleration, so called
peak ground acceleration) which results from statistical evaluations of earth-quakes and
judgments of the situation of faults and continental shifts. For the peak ground acceleration
(PGA) a value of 10 % probability of occurrence in 50 years is normally used as value given in
earthquake zoning maps. Mostly 4 to 5 zones are used and also the steps be-tween the zones
indicate that it is a realistic approach.
The material used in Tajikistan is reinforcement steel A 3 for the main reinforcement and A 1 for
stirrups and distribution reinforcement. A 3 is a well-known and good quality steel with 390
N/mm² (3,900 kpa/cm²) yield stress and ultimate strength of 590 N/mm² (5,900 kpa/cm²) and
minimum 14 % elongation. Tests show normally even much more elongation, which is good for
earthquake resistance. As earthquake secure construction requires a safety factor, a partial
factor of about 1.3 is used for reduction, which allows to use the admissible stress tables for the
German steel BSt 500. The A 1 is a mild steel of little requirements and adequate for the
elements for which it is used.
The project is designed for construction in IVA climatic region with design temperature - 9,5 °С
25
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
5.4. Anti-seismic measures
Anti-seismic measures are envisaged in accordance with the requirements of the chapter of
ICSH CHT 22-07-2018 "Construction in Seismic Areas"
5.5. Foundations
Compacted soil from local soil 30%,
gravel 70%, the thickness of each layer is
no more than 20 cm, density Р=1,90-
1,95т/м³
The foundations are designed for gravelly
soils, monolithic reinforced concrete
(class B 20). The foundations are
prepared with 100 mm thick concrete of
class B 7.5
Porches are made of concrete of
class B 15
Around the building there is a
concrete pavement on a layer of
crushed stone 0.15m thick. The mark
of the pavement edge should exceed
the planning mark of the ground by
0.05m. Pavement slope is not less than 0.03. The width of the pavement is not less than
1,000m, with the edge of the trench overlapped by at least 30cm.
Waterproofing of foundations from ground moisture is carried out by bituminous mastic in 2
layers on the prepared surface.
Welded connections of reinforcement and embedded parts shall be made in accordance
with the requirements of GOST 14098-85. In accordance with SNiP 2.03.11-85 all metal and
embedded parts should be protected against corrosion by a zinc coating with a thickness of
140 microns.
In the specifications, the length of the structures is given taking into account the overlapping
of overlaps on the installation products.
Grids should be connected by overlap with overlap of not less than 40d of working
reinforcement.
26
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
5.7. Reinforced External Walls
Walls and partitions 250mm and 120mm thick - reinforced with vertical cores of concrete
class B15 and reinforced with horizontal grids of Ø5 Vr-I wire every 3 rows (w.630mm) of
masonry, made of cement block on M50 mortar. Category of masonry II. Normal adhesion
180 kPa>Rr>120 kPa (1.2 kgf/cm2).
Partition walls reinforced brick thickness δ = 120 are made according to the series 2.130-2T
issue 2 "Details of walls and partitions of buildings"
The ends of the longitudinal reinforcement of the cores should have a rigid connection with
the slab and foundation.
27
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
6. Electrical
6.1. Introduction
The design concept consists of two major sections:
a) Electrical Design
b) Telecommunication Design
6.2. Electrical Design Aspects
The electrical installation will be done as a TN-S system (5 wire).
All LV cables are low smoke, zero halogen - XLPE/SWA/PVC Type (CU). Wires shall be copper
PVC insulated and max. allowable voltage drop shall not exceed 3%.
TN-S describes an arrangement where separate conductors for Protective Earth (PE) and
Neutral are run to consumer loads from a site’s power supply (i.e. generator or transformer).
The PE and N conductors are separated in nearly all parts of the system and are only
connected together at the supply itself. This type of earthing is typically used for large
consumers who have one or more HV/LV transformers dedicated to their installation, which are
installed adjacent to annex building.
The project is designed for voltage 380/220 kV with blind grounding of transformer neutral. The
voltage at the lamps is 220 V.
There are several design aspects, which were considered while designing lighting, socket and
fire alarm layouts. All these are discussed hereunder:
Emergency loads are fed by generators as a backup in case of regular power loss. This
type of load consists of:
Lighting Load
Lifts
OTs Load (Further backed up with UPS)
Water Supply Pumps
Power Load (sockets load)
f) Each DB is provided with spare breaker as backup.
g) Each floor have is own distribution board for power and light circuits.
28
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
h) Main Panel Boards are also provided with spare breakers and additional room for breakers
for future extensions.
i) Lighting levels have been calculated as per requirement and lights are proposed
accordingly.
The illumination levels are listed as follows:
General areas such as stairs and corridors 100-200 lux
General infant areas 300 lux
LDR Room 600 lux
OT 1000 lux
Investigation and treatment areas 500-1000 lux
Waiting areas 300 lux
Toilet and wash rooms 200 lux
Offices 500 lux
The typical patient room installation for a bed is with a unit comprising
1 bed light (reading) with integrated switch and plug
1 nurse call system
4 single plugs (for over beds only + patient room plugs as distributed in the drawings)
Power outlets for medical gas have been provided where required.
The sockets should be mounted above the bed at the height of 1.2 meters.
6.4. Conduits
Conduits shall be heavy gauge PVC-U/ Fire prevention conduits- fire rated type - UL 94V-0
(ASTM D 3801) the product is self-extinguishing and will not support burning. In addition, we will
insist the contractor to use heat resistant PVC wiring cable according to IEE wiring.
29
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
Earth Termination Network
Bonding (to prevent side flashing)
In addition, the following areas will be considered during the implementation
Corrosion
Inspection, Testing, Records and Maintenance
Lightning protection system will need to be provide for minimum 1 standard active lightning
point.
Active lightning rods. It should be an electrostatic active lightning rod with early streamer
warning (ESE). Absolutely not contain radioactive material.
ΔL values, in accordance with local regulation of Tajikistan or NFC 17-102 standard.
The lightning rod will be placed on a pole with a minimum length of 5 meters and a diameter
of at least 2”. If the lightning rod is higher than 7mt, it will be fastened with tension wires
from at least three points. The lightning rod will carry the lightning rod safely, it will be
durable and robust against all weather conditions and external factors.
A schematic drawing above mentioned assembly is shown along with the layouts for each
floor (refer drawing # Nurse Call Button/ System page/2)
Voice and data facility is also provided at each nurse station and in each Doctor and
treatment room.
Cat VI twisted pair copper cable is used for wiring of data points.
30
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
7. Mechanical
7.1. HVAC system
All facilities located on the first, second and third floor must be equipped with a ventilation
system and necessary filters as per Tajik regulations.
A central air conditioning system VRF will be integrated in the above system.
7.1.1. Standard and Codes
СНиП(BC) 41-01-2003' - "Heating, ventilation and air conditioning"
СНиП(BC) 23-101-2004' - "Design thermal protection of buildings"
СНиП(BC) 31-05-2003 - "Public Buildings and Structures"
СНиП(BC) 3.05.01-85 - "Internal sanitary and technical systems"
“Mechanical Air Handling Units (AHUs) consume approx. 50% of the hospital's total energy
which is estimated at about 850 kVA, in addition to the high cost of regular maintenance
services. With such units in place, the occasional voltage fluctuations as well as city power
outages cause cooling system failures. In such situations, given the high-power demand,
running the generators becomes very costly (198 liters per hour at 80% load) “
Keeping the above situation in mind, the design considers a combination of the ERV (Energy
Recovery Ventilation) and VRF (Variable Refrigeration Flow) systems in the new building to
minimize the risks without affecting performance needs.
Discharge Airflow (full fresh air) in OT 1400m3/h (As per Tajik regulations for OTs)
Pressure Relationship to Adjacent Areas: Positive
Air filtration Standard F7, Maximum F9
Design Temperature (overall) 22°C ± 2°C
Airflow Average Discharge Velocity 127 L/s·m2
Humidity Shall not exceed 50%
Person-oriented rate 503/hP
The OTs will be equipped with Medical Air Handling Units OHA51aH type, which provides
100% filtered air cooled or heated and will be under positive pressure.
The ICUs and NICUs (including the insolation rooms) will be equipped with ERV and VRF
systems, which will be compatible for use with necessary filters
LDR will be equipped with supply air as per Tajik regulations (СНиП (BC) 41-01-2003)
31
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
The isolation rooms will be equipped with exhaust fans to create negative pressure and
avoid contamination of the outside air (extracted air needs to be filtered) before being
exhausted
Variable Refrigerant System (VRF) Units for cooling has been considered for hospital
facilities
All shower rooms and toilets will have exhaust fans separate from the main duct system
“The shop drawings (design and installation) will be provided by the contractor during the
implementation of protection system required for full and safe operation in all facilities”
All the above will help to achieve efficient climatic performance and comfortable room
environment. Smoke dampers, fire dampers, and combination of fire and smoke dampers will be
provided in accordance with the local code and in line with the Tajik Fire and Safety regulations.
32
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
7.2. Automation system
The HVAC Control System shall include control and supervision of each air handling unit (and
interconnected exhaust fans) individually, through automatic control panels strategically located
in different parts of the building and AHU control panel.
7.3. Heating System
The new hospital building will be connected to the heating source of the Dushanbe city grid.
Design Organization Department in Dushanbe has
confirmed that the additional loads can be tolerated
based on the existing capacities of the city heating
plant.
The oxygen generators are new generation stations that allows on-site production of oxygen.
This helps hospitals to supply oxygen from their own automated system independently. These
systems are generally combined with cylinder systems for instant back up.
The oxygen Generators will deliver oxygen in a purity up to 96% independent from the
consumption. The system consists of two air compressors (+ back up), dryers, O2 generator,
active carbon tower, tanks and filters.
33
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
7.4.2. Manifold System
Automatic Changeover Manifold has been considered to provide a continuous supply of Oxygen
in the new building. The manifold shall consist of two banks of cylinders located on each side of
the pressure control assembly. These pressured gases will be used in Operation Theatres,
Intensive Care Units, Neonatal Care Units, Emergency Rooms and Patient Rooms in the new
building only. The Automatic Changeover Manifold will be in compliance with
HTM 02-01
MDD 93/42/EEC
EN ISO 7396-1
7.4.3. Medical Air Plant
The design of Medical Air Plant shall comply with
ISO 13485 Quality Management System
MDD 93/42/EEC.
The estimated capacity requirement is 2x117 m3/h – 10 bars (1working, 1 backup)
34
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
7.5. Patient Transfer Lift System
The design of Lift System shall comply with
GOST 22845-85. Electric passenger and goods lifts. Arrangement for assembly, assembly
and acceptance.
GOST 8823-85. Electric goods lift. Basic parameters and dimensions.
GOST 22011-95. Passenger and goods lift. Specifications.
Total 4 elevators in the annex building, 2x1000 kg elevators will be installed between 3 floors
including the basement. 2x 480 kg elevators will be installed on the first and second floors
Lifts with regenerative converters have been considered for the new building at the time of
planning in light of the scope to energy savings. Should the availability of the lifts with
regenerative converter be an issue for the works contractor selected for works execution,
provisions have been kept to install the usual lifts available.
35
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
8. PLUMBING
8.1. Standard and Codes
BC(TJK) 2.04.01-85 "Internal water supply and sewerage of buildings"
ГОСТ 21.205-93 "Sanitary-technical systems"
Designed for thread rolling ГОСТ (regional states standards) 3262-90
8.2. Pumping Units
Water Pumps: HYDRO MPC-E 2 CRIE10-12 component with vibration dampers
The centralized hot water supply was not planned for the following reasons:
Higher chances of heating energy loss in preparation, circulation and distribution especially
due to long water lines + large water tanks + Excessively high-water temperature = Energy
and higher water wastage due to heating energy lost in circulation
Works continuously due to ongoing demand for hot water in different sections of the hospital
leading to higher energy requirement
Lack of maintenance or any malfunction will lead to the shutdown of the hot water supply for
the entire hospital.
The temperature requirement can to set to a fixed figure only at the central point
36
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
For hygienic reasons, the water boiler will be concealed type and installed in an easily
accessible cupboard.
The automatic fire pumps will be powered by electricity and connected to the insulated water
tank in the basement (technical floor of new building) and will be connected through metal pipes
to the fire cabins on each floor.
The water storage tank will be used for both supply to the hospital and fire-fighting purposes. It
will be monitored for high and low water level. The capacity of the tank is calculated based on
regular water usage in the new building (estimated at approximately 350 liters/patient/day) +
additional water to have in reserve in case of fire according the Tajikistan fire regulation –
Rules of the state supervision of fire safety of PGNPB - P-1-10
BC RT 21-01-2007 "Fire safety of buildings and structures "
Fire extinguishers of different sizes will be used, the locations and distances will be selected
according to national regulations.
*The waste water treatment unit will not be required for the new building.
** The sewage discharge from the annex building is estimated at 32m3/day at this stage.
37
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
The hospital complex is already connected to the main clean water supply line of the city. As
confirmed by the planning department, the supply line to the hospital has enough flow rate and
pressure to supply water to the new building also.
38
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
9. Cost Estimate
The latest cost estimation is the outcome of the detailed design developed based on the
approved preliminary design. The details are provided below.
The cost estimates were verified on site and take into account
Market prices for major inputs for civil work
Other necessary aspects such as MGPS, firefighting, HVAC, water
supply/purification/storage systems, generators, stabilizer, UPS and transformer.
Geological survey results.
The price increase margin (PIM)/ cost escalation per year of Approx. 3% has been
calculated and added to the cost of civil works.
9.1. Summary of Confidential Cost Estimates
Total Cost
№ № Work Item/ Description
Estimate /Euro
1 2 4 5
No. 1 ESTIMATE CALCULATION
General construction works (Architectural
1 № 1-1 1.025.282
part)
2 № 1-2 General construction works (Structural part) 1.224.485
3 № 1-3 Medical gas system 335.295
4 № 1-4 Water supply and sewerage system 155.645
5 № 1-5 Heating and ventilation system 721.675
6 № 1-6 Internal power supply 177.876
7 № 1-7 Fire alarm system 13.207
8 № 1-8 Notification system 5.161
9 № 1-9 Telephony 2.079
1 Television
№ 1-10 2.963
0
11 № 1-11 Internet 42.998
1 Video surveillance
№ 1-12 11.865
2
1 Nurse call button
№ 1-13 15.932
3
1 Installation of elevators
№ 1-14 124.559
4
1 Waste collection facilities
№ 1-15 3.684
5
1 Facilities for diesel generator
№ 1-16 2.431
6
TOTAL NUMBER 1: 3.865.138
No. 2 OBJECT ESTIMATE CALCULATION
1 External power supply
№ 2-1 226.403
7
39
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
1 Lighting of the territory
№ 2-2 10.447
8
1 General construction works of Transformers
№ 2-3 29.319
9
2 Installation-transformer equipment
№ 2-4 74.311
0
2 Facade lighting
№ 2-5 8.548
1
TOTAL NUMBER 2: 349.028
OBJECT ESTIMATE CALCULATION No. 3
2 External communication networks
№ 3-1 7.924
2
TOTAL NUMBER 3: 7.924
OBJECT ESTIMATE CALCULATION No. 4
2
№ 4-1 External water supply and sewerage systems 8.419
3
2 External heating systems
№ 4-2 22.492
4
TOTAL NUMBER 4: 30.911
2 Road surface
№ 5-1 71.632
5
2 Landscaping of the territory
№ 5-2 4.022
6
2 № 5-3 Small architectural forms
1.254
7
TOTAL NUMBER 5: 76.909
TOTAL 4.329.908
1 Annex Building
EUR 4.329.908,00
2 Secondary Building
3 Project Contingency (civil work) 15% EUR 649.486,20
40
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024
Total EUR 4.979.394,20
41
TNRI Mother-Child-Care and Emergency Care VI – Detailed Design Report/ Feb 2024