Project Management Numericals Software Engineering
Project Management Numericals Software Engineering
Numerical Problems
(i)Organic Mode
(ii)Semidetached Mode
E = 3.0 * (400)1.12=2462.79 PM
D = 2.5 * (2462.79)0.35=38.45 PM
Answer: The semidetached mode is the most appropriate mode, keeping in view
the size, schedule and experience of development time.
Hence
E=3.0(200)1.12=1133.12PM
D=2.5(1133.12)0.35=29.3PM
= 38.67 Persons
Productivity = KLOC/E
= 200/1133.12 KLOC/PM
=0.1765 KLOC/PM
Example 3:
Answer:
Solution:
Example:
The following details are available regarding a project:
Determine the critical path, the critical activities and the project completion
time.
Solution
First let us construct the network diagram for the given project. We mark the
time estimates along the arrows representing the activities. We obtain the
following diagram:
Consider the paths, beginning with the start node and stopping with the end
node. There are two such paths for the given project. They are as follows:
Compare the times for the two paths. Maximum of {22,19} = 22. We see that
path I has the maximum time of 22 weeks. Therefore, path I is the critical path.
The critical activities are A, B, D and F. The project completion time is 22
weeks.
Therefore, together the non- critical activities can be delayed upto a maximum
of 3 weeks, without delaying the completion of the whole project.
Example:
Draw the network diagram and determine the critical path for the following
project:
Solution
We assert that there are 4 paths, beginning with the start node of 1 and
terminating at the end node of 9. They are as follows:
Compare the times for the four paths. Maximum of {16, 22, 16, 13} = 22. We
see that the following path has the maximum time and so it is the critical path: