Process Plan
Process Plan
Process Plan
Process Plan
DOCUMENT APPROVAL
Reviewed by Approved by
Page 1 of 5
Legends:
Process Step
Monitoring Stage
Review Stage
Page 2 of 5
Related
Input Flow Output Personnel Involved
Document/Activities
Resource Mobilization may intervene directly
a. Need Assessment/ Problem
Base Line Survey / by submitting the proposal to donor in case of
Identification/ Situation Survey Reports
(b)
Analysis Preliminary Assessment Resource Mobilization team may be requested
Donor Proposal/
b. Any invitation from donor & Proposal Proposal requirements
by Research Team to develop the proposal and
for expression of interest or Proposal Document
submit to the potential donors in case of (a).
proposal
Direct involvement to immediately response
c. Natural disaster
the situation in case of (c)
Page 3 of 5
Related
Input Flow Output Personnel Involved
Document/Activities
Supervision and
monitoring at field level
Resolve
programme/project
Monitoring
a. MPRs (Community Level)
Monitoring Reports ME&R
issues
Support and guidance to
b. MPRs (DO Level) Corrective Action Concerned Program/project GM and team
programme/project
Reports
staff
Feedback from
community
CPAs
Decisions on:
CE
MCM Project updates,
DEM/DPM
Performance Project
COE, GM Finance and concerned project
a. Project reports Review Performance, MCM Minutes
Finance person
Project Financial
ME & R
concerns, and
Project targets All GMs
PCM
Decisions on: PCM( Project
Project CE, CTE, COE
a. Project progress details Project - HO Committee Meeting)
Review PPM
Level Minutes
Page 4 of 5
Related
Input Flow Output Personnel Involved
Document/Activities
Decisions on:
SCM Project/
a. Project / programme Project programme CE, COE, CTE SCM(Steering
status and progress Review targets and All GMs Committee Meeting)
updates major
issues
ECM
Executive Committee ECM (Executive
Organisation
a. Executive Member’s input Review Executives meeting with CE Committee Meeting)
Progress Review
minutes
Page 5 of 5