13 - Advanced Capital Bud Class Notes
13 - Advanced Capital Bud Class Notes
13 - Advanced Capital Bud Class Notes
ADVANCED CAPITAL
BUDGETING
Project Evaluation
Technique
Decision:
(i) If IRR > RR Accept the project
(ii) If IRR < RR Reject the project
(iii) If IRR = RR Accept the project
Example:
Calculation:
0 year 1 year 2 year 3 year
(500) 856.32
@ R% [MIRR]
500 x (1 + R) 3 = 856.32
1
856.32 3
(1 + R) = [ ]
500
R = 19.64% (i.e. MIRR)
Decision:
(i) If MIRR > RR Accept the project
(ii) If MIRR < RR Reject the project
(iii) If MIRR = RR Accept the project
FV
Decision:
(i) MNPV = +Ve Accept the project
(ii) MNPV = -Ve Reject the project
(iii) MNPV = 0 Accept the project
Example-2:
0 year 1 year 2 year 3 year 4 year
1y
Difference =?
2Y (?) 3y
Difference = 300
// CA NAGENDRA SAH // WWW.NAGENDRASAH.COM
13.11 AFM | SFM CLASS NOTES
300 1 year
1
50 (300 x 50) = 0.1667 year [i.e. 2 months]
Payback period = 2 year + 2 months
Example:
0 year 1 year 2 year 3 year
Method-1:
80+120+100
Average Annual EAT = = 100
3
Investment (Net of Salvage) = 1000 – 200 = 800
100
ARR (Annual %) = x 100 = 12.5%
800
Method-2:
Average annual EAT = 100
1000+200
Average value of project = = 600
2
100
ARR (Annual %) = x 100 = 16.67%
600
Note: Both methods are acceptable and used by Institute.
Formula:
Average annual EAT
(1) ARR = [ x 100]
Outflow net of salvage
Or,
Average annual EAT
(2) ARR = [ x 100]
Average value of project
Where,
Initial cost + Salvage
Average value of project = [ ]
2
Assume, R = 15%
347 387 567
PV = + +( 1+ 0.15)3 = 967.17
( 1+ 0.15)1 ( 1+ 0.15)2
Assume, R = 13%
347 387 567
PV = + +( 1+ 0.13)3 = 1003.12
( 1+ 0.13)1 ( 1+ 0.13)2
Almost equal to 1000.
Hence, we can say,
IRR is almost 13%.
Comparison:
ARR 12.5% or, 16.67%
IRR 13% (Normally falls between above two rates)
Decision:
(i) If ARR > RR Accept the project
(ii) If ARR < RR Reject the project
(iii) If ARR = RR Accept the project
Conversion of real cash flows into money cash flows or vice versa:
(i) Money cash flows = Real Cash flows x (1 + inflation rate) n
[When there is no Depreciation]
Money cash flows
(ii) Real cash Flows =
(1 + Inflation Rate)n
Example:
Present value = 1,000
Real rate = 4% p.a. ; Inflation rate = 5% p.a.
0 Year 1y end 2y end
0y 1y 2y
• Method - 2
Amount (₹)
Money EBDT [Real EBDT x (1 + Inflation) n] xxx
Less: Tax xxx
xxx
Add: Tax Saving on Depreciation xxx
Money cash Flows xxx
Method-2: Use money cash flows with money cost of capital as discount
rate to calculate PV and then NPV
Note: NPV calculated using both methods remain same when there is no
information of depreciation.
QUESTION- 1A
Interpretation:
If question is silent, assume expected cash inflows are nominal cash
inflows or, money cash inflows.
It means, Annual cash inflows of ₹5,00,000 are nominal cash inflows.
PV = ? ₹5,00,000
@ 15.5%
₹5,00,000
PV =
(1+0.155)2
₹5,00,000
PV = ?
@ 10% (1+0.05)2
₹5,00,000 1
PV = x
(1+0.05)2 (1+0.10)2
Disclaimer:
CMA Institute solution is not correct as it discounted 2nd year Cash
flows but discount factor used for first year.
QUESTION – 1B
40,000−0
Annual Depreciation = = 10,000
4
Calculation of Nominal cash flows:
Year – 1 Year – 2 Year – 3 Year – 4
Revenue with 30,000 x 30,000 x 30,000 x 30,000 x
inf. (1 +0.10)1 (1 +0.10)2 (1 +0.10)3 (1 +0.10)4
= 33,000 = 36,300 = 39,930 = 43,923
PV of inflows = 𝚺 (𝐀 × 𝐁) = 52,945.46
NPV = 52,945.46 – 40,000 = 12,945.46
Advice:- Yes, it is beneficial to accept project as NPV is positive.
QUESTION – 1C
Calculation of Nominal cash flows:
Year – 1 Year – 2 Year – 3 Year - 4
Revenue after 6,00,000 x 7,00,000 x 8,00,000 x 8,00,000 x
inflation (1 + 0.10)1 (1 + 0.10) x (1 + 0.10) x (1 + 0.10) x
(1 + 0.09) (1 + 0.09) x (1 + 0.09) x
(1 + 0.08) (1 + 0.08) x
(1 + 0.07)
PV of Inflows = 𝚺 (𝐀 × 𝐁) = 9,06,738
QUESTION – 1D
Calculation of Depreciation: ( in ‘000)
Year 1 2 3 4 5
Opening 4,000.00 3,000,00 2,250.00 1,687.50 -
(-) Dep 1,000.00 750.00 5,62.50 421.88 -
Closing 3,000.00 2,250.00 1,687.50 1,265.63 -
TS on Dep 300.00 225.00 168.75 126.56
( in ‘000’)
P.V of Future Cash Flow 7135.34
Less: Initial Investment (4000.00)**
Less: Working Capital (261.76)
NPV 2873.58
Example:
0Y 1Y 2Y nY
PV
Discount @ RADR
Risk Adjusted NPV = PV of Inflow – PV of Outflow
PV
Discount @ RF
Risk Adjusted NPV = PV of Inflow – PV of Outflow
QUESTION –2A
Year Project – Y Project – x
Cash flow Risk free cash Cash flow Risk free cash
(Risky) flows (Risky) flows
1 1,80,000 1,80,000 x 0.80 1,80,000 1,80,000 x 0.90
= 1,44,000 = 1,62,000
2 2,00,000 2,00,000 x 0.7 1,80,000 1,80,000 x 0.80
= 1,40,000 = 1,44,000
3 2,00,000 2,00,000 x 0.5 2,00,000 2,00,000 x 0.70
= 1,00,000 = 1,40,000
QUESTION – 2B
A B C
CV 0.40 0.80 1.20
RADR 12% 14% 16%
(a) Annual Inflow 30,000 42,000 70,000
(b) PVIFA (RADAR, 5) 3.605 3.433 3.274
(c) PV of Inflow (a x b) 1,08,150 1,44,186 2,29,180
Less: - Outflow 1,00,000 1,20,000 2,10,000
NPV 8,150 24,186 19,180
QUESTION – 2C
Interpretation (Not for Exam):
Risk Index = Risk factor = Beta
Return of firm Market return
P – II:
PV of inflows = (6,00,000 x 0.870) + (4,00,000 x 0.756)
@15% + (5,00,000 x 0.658) + (2,00,000 x 0.572)
= 12,67,800
NPV = 12,67,800 – 11,00,000 = 1,67,800
P – III:
PV of inflows = (4,00,000 x 0.885) + (6,00,000 x 0.783)
@13% + (8,00,000 x 0.693) + (12,00,000 x 0.613)
= 21,13,800
NPV = 21,13,800 – 19,00,000 = 2,13,800
Advise:- NPV of P-III is higher. Hence project- III should be selected.
Disclaimer: ICAI solution is not appropriate for 4th & 5th Year.
NS Opinion:
* in 4th year PVIF should be 0.778 [.926 × .840] so PV will be 35,788.
** in 5th year PVIF should be 0.720 [.857 × .840] so PV will be 17,280.
In such case NPV would be 154.
Note:-
• We can use second method only when probability of every year
under each cash stream remains same (i.e. P1 of every year is same,
P2 of every year is same. Otherwise, we can use method – 1 only.
• Method – 1 can be used in all situations.
• If we can use method -2 and method -1 in same question then
answers remain same hence, we can use anyone method.
PV
Discount @ CC
SD of Project
Case – (i) Cashflows of one year is dependent on other years (i.e., Cash
flows are correlated (i.e., r = 1)
𝜎 project =
Note: we can link this formulae with 𝜎 portfolio formulae when r =1 and r =0
Note: -
• We can use method - 2 only, when every year probability of CIF1 is
same, similarly every year probability of CIF 2 is also same and so on..
• It is possible in case of dependent cash flows only,
• SD calculated in Method – 2 and case – (i) of Method – 1 remain
same. (i.e., Answer remains same) because volatility of cash flows
and volatility of NPV remains same.
QUESTION – 3A
(i) Expected NPV (X):
= (3,000 x 0.10) + (6,000 x 0.40) + (12,000 x 0.40) + (15,000 x 0.10)
= 9,000
̅̅̅̅̅̅)2 × Probablity
σx = √∑(NPV − NPV
QUESTION – 3B
0Y 1Y 2Y 3Y 4Y 5Y
2
σx =√∑(NPV − NPV
̅̅̅̅̅̅) × Probablity
Coefficient of variation
SD 0.3581
= = = 0.897 (i.e., 0.90)
NPV 0.3992
QUESTION – 3C
(i) Project x is more beneficial as SD is Low. [i.e., Low risk project]
(ii) Coefficient of variation based on decision.
X Y
SD 90,000 1,20,000
CV = = 0.74 = 0.53
NPV 1,22,000 2,25,000
QUESTION – 3D
Interpretation (Not for Exam):
As life of project is not given. We can’t calculate NPV
Hence, calculate desired value (variance, SD etc.) using cash flows:
Standard Deviation:
σ𝐾 = √4.8 = 2.19
σ𝑆 = √20.8 = 4.5
Coefficient of variation
Project – K Project – S
Mean CF 15 17
SD (σ) 2.19 4.56
Coefficient of 2.19 4.56
= 0.146 = 0.268
variation (CV) 15 17
-∞ Mean +∞
𝑥 − 𝑥̅
Z= | | It indicates no. of standard deviation from Mean.
𝜎
-∞ Mean 𝑥̅ x +∞
QUESTION – 4A
̅̅̅̅̅̅
𝐍𝐏𝐕 = 40
σ = 20
(i) Probability of NPV zero or less:
Z
Probability =?
-∞ 0 40 +∞
0 − 40 NPV ̅̅̅̅̅̅
𝐍𝐏𝐕
Z= | |= |−2| = 2
20
Z1 Z2
25 40 45
NPV ̅̅̅̅̅̅
𝐍𝐏𝐕 NPV
25 − 40 −15
Z1 = | | = | 20 | = 0.75
20
45 − 40 5
Z2 = | | = |20| = 0.25
20
QUESTION – 4B
1Y 2Y
Standard Deviation:
Year -1 Year -2
CIF (CIF − CIF ) (CIF − CIF) CIF CIF (CIF − CIF ) (CIF − CIF)
2 2
CIF
60 71 -11 121 50 61 -11 121
70 71 -1 1 60 61 -1 1
80 71 9 81 70 61 9 81
QUESTION – 5A
(i) Expected utilities of project – A:
Cash Flows Utilities Probability
- 15,000 - 100 0.10
- 10,000 - 60 0.20
15,000 40 0.40
10,000 30 0.20
5,000 20 0.10
QUESTION – 5B
Existing Operation New Project
Return 14% 18%
SD (σ) 20% 32%
Investment 75% 25%
3
• For Example:
Year – 1 Year – 2
Inflow Prob. Inflow Prob.
10,000 0.60 8,000 0.20
15,000 0.30
20,000 0.50
20,000 0.40 15,000 0.40
25,000 0.30
30,000 0.30
Decision tree:
Now we can calculate expected NPV using any one of following two
methods.
Method – 1: Branch wise:
Branch – 1 NPV = Using inflows: 10,000 (1Y) and 8,000 in (2Y)
Branch – 2 NPV = Using inflows: 10,000 (1Y) and 15,000 in (2Y)
Branch – 3 NPV = Using inflows: 10,000 (1Y) and 20,000 in (2Y)
Branch – 4 NPV = Using inflows: 20,000 (1Y) and 15,000 in (2Y)
And so on…. Upto Branch – 6
Expected NPV = ∑6i= 1 (NPVi × Joint probability)
Method – 2: Year wise:
Expected CIF (Year – 1) Average of 10,000 and 20,000 using
respective probability.
Expected CIF (Year – 2) Average of all 6 cash inflows using joint
probability.
Important Note:-
Must verify total probability of all possibility while calculating
average. Total probability Always “1”
In both methods NPV remains same.
QUESTION- 6A
(a) Decision tree:
Year 1 Year 2 Joint Prob.
12,000 (.20) .08
(d) Advice:
NPV1 = -7363
NPV2 = (25000 x 0.909) + (16000 x 0.826) – 40000 = -4059
NPV3 = (25000 x 0.909) + (22000 x 0.826) – 40000 = 897
NPV4 = (30000 x 0.909) + (20000 x 0.826) – 40000 = 3790
NPV5 = (30000 x 0.909) + (25000 x 0.826) – 40000 = 7920
NPV6 = 12050 (Calculated above)
Expected NPV = (-7363 x 0.08) + (-4059 x 0.12) + (897 x 0.20) +
(3790 x 0.24) + (7920 x 0.30) + (12050 x 0.06)
= 3112
Advice: Beneficial to invest in project.
QUESTION-6B
A
D
Evaluation
At Decision Point C: The choice is between investing ₹ 20 lacs for a
perpetual benefit of ₹ 4 lacs and not to invest. The preferred choice is
to invest, since the capitalized value of benefit of ₹ 4 lacs (at 10%)
adjusted for the investment of ₹ 20 lacs, yields a net benefit of ₹ 20
lacs.
2,000 4 0.5 10
4,000 5 0.6 9
6,000 6 0.7 8
Draw a decision tree showing the successive drilling decisions to be made
by Big Oil. How deep should it be prepared to drill?
[CMA-RTP-June-2012] [CMA-Compendium]
Ans: 1.8 Mill
SOLUTION
Cost
4 mill 2000 ft
1 mill 2000 ft
1 mill 2000 ft
Decision tree:
Calculation of probability:
(i) Probability of finding oil up to 4000 ft after 2000 ft
Assume, prob = 𝑥
prob. of not finding oil up to 2000 ft.
Decision at D 3:
Outflow = 1 mill
Expected PV of inflow = (8 mill x 0.25) + (0 mill x 0.75) = 2 mill
NPV = 2 – 1 = 1 mill
Advice: Drill up to 6000 ft if oil not find up to 4000 ft.
Decision at D 2:
Outflow = 1 mill
Expected PV of inflow = (9 mill x 0.20) + (1 mill x 0.80) = 2.6 mill
Decision at D 1:
Outflow = 4 mill
Expected PV of inflow = (10 mill x 0.50) + (1.6 mill x 0.50) =5.8mill
NPV = 5.8 – 4 = 1.8 mill
Final Advice: Drill up to 2000 ft. If not find oil, further drill up to
4000 ft. If gain not find oil then drill up to 6000 ft.
• For Example:
NPV = [ (SP – UC) x SV] x PVIFA(DR, Life) – Outflow
Now, we have to find that factor which affects NPV more [i.e., Find
Most sensitive Factor]
Methods – 1:
Calculate % change of each factor where NPV becomes zero (i.e. 100%
down). In same example above, assume following situations:
Factor % change in each factor where NPV will be Zero
SP 5% Decrease
UC 8% Increase
SV 10% Decrease
DR 20% Increase
Life 40% Decrease
Outflow 50% Increase
Here, sale price is most sensitive factor and outflow is least sensitive
factor.
Reason: SP affects NPV 20 times, Outflows affects NPV only 2 times.
Methods – 2:
Calculate change in NPV assuming any fixed % change in each factor
(like 10%, 20%, etc..)
QUESTION-7A
1. Calculation of Net Cash Inflow per year
Particulars Amount (₹)
A Selling price per unit 100
B Variable cost per unit 50
C Contribution per unit (A-B) 50
D No. of units sold per year 5 Cr.
E Total Contribution (C x D) ₹250 Cr.
F Fixed cost per year ₹50 Cr.
G Net cash inflow per year (E-F) ₹200 Cr.
NPV of project:
= 45000 x PVIFA(10%,4) – 1,20,000
= 45000 x 3.169 – 1,20,000 = 22,605
Sensitivity analysis:
(i) Initial project cost:
Assume, increase in project cost = 10%
New project cost = 1,20,000 x 110% = 1,32,000
New NPV = (45,000 x 3.169) – 1,32,000
= 10,605
22605−10605
% decrease in NPV = x 100
22605
= 53.09%
22605−19590
% decrease in NPV = x 100 = 13.34%
22605
Summary:
Factors % change in factor % change in NPV
Outflow 10% () 53.09% ()
Inflow 10% () 63.09% ()
CC 10% () 13.34% ()
Advice:
Inflow affects NPV more. Hence, inflow is most sensitive factor.
QUESTION- 7C
Calculation of NPV:
NPV = [(SP – UC) x SV] x PVIF @ 10% - Outflow
= (60 - 40) x 20000 x 0.909 + (60 - 40) x 30000 x 0.826 +(60
- 40) x 30000 x 0.751 – 10,00,000
= (60 – 40) x [(20000 x 0.909) + (30000 x 0.826) + (30000 x
To save 0.751)] – 10,00,000
time in next
= (60 – 40) x 65490 – 10,00,000
calculated
= 13,09,800 – 10,00,000 = 3,09,800
Sensitivity analysis:
(a) Sales price/unit:
Assume, sale price = 𝑥 [where NPV = 0]
NPV [i.e. 0] = (𝑥 – 40) x 65490 – 10,00,000
10,00,000
or, (𝑥 – 40) = = 15.27
65490
∴ 𝑥 = 15.27 + 40 = 55.27
60−55.27
% decrease in sales price = x 100 = 7.88%
60
(b) Unit cost:
Assume, unit cost = 𝑥 [where NPV = 0]
Summary:
Factors % change in factor where NPV is zero
(a) SP 7.88% ()
(b) UC 11.825% ()
(c) SV 23.65% ()
(d) Outflow 13.09% ()
(e) Life 23% ()
As sales price affect NPV more, sales price is most sensitive factor.
QUESTION-8B
If the project with the highest EV of profit were chosen, this would be
project C.
Outcome Probability Project-A Project-B Project-C
EV EV EV
I (Worst) 0.2 10,000 14,000 18,000
II (Most likely) 0.5 42,500 37,500 50,000
III (Best) 0.3 39,000 42,000 33,000
1.0 91,500 93,500 1,01,000
A table of regrets can be compiled, as follows, showing the amount of
profit that might be foregone for each project, depending on whether
the outcome is I, II or III.
Outcome Project
A B C
I (Worst) 90,000 – 50,000 90,000 – 70,000 90,000 – 90,000
= 40,000 = 20,000 =0
II 1,00,000 - 85,000 1,00,000 - 1,00,000 –
(Most likely) = 15,000 75,000 = 25,000 1,00,000 = 0
III (Best) 1,40,000 - 1,40,000 – 1,40,000 –
1,30,000 = 10,000 1,40,000 = 0 1,10,000 = 30,000
Note: The minimax regret rule aims to minimize the regret from making
the wrong decision. Regret is the opportunity lost through making the
wrong decision.
0 1 2 0 1 2 0 1 2
……………….. ……………….. ………………..
7 8 9 7 8 9 7 8 9
Random no.
Trail run – 1: 1 0 5 105
Trail run – 2: 0 2 3 023
Trail run – 3: 8 0 5 805
and so on……..
// CA NAGENDRA SAH // WWW.NAGENDRASAH.COM
ADVANCED CAPITAL BUDGETING 13.60
(i) For First trail run Randomly select any no. from table and use
first few digit number according to requirement and ignore
remaining digits.
(ii) For second trail run Either proceed row wise or column wise in
sequence
QUESTION- 9A
Calculation of range of random no.
9 90 40,000 33 5
10 58 30,000 52 6
Simulated NPV:
Trial run NPV = Inflow x PVIFA @10% - Outflow
1 30,000 x PVIFA (10%,9) – 1,30,000
= (30,000) x 5.759) – 1,30,000 = 42,770
2 35,000 x PVIFA (10%,10) – 1,30,000
= (30,000) x 6.145) – 1,30,000 = 85,075
3 25,000 x PVIFA (10%,7) – 1,30,000
= (25,000) x 4.868) – 1,30,000 = -8300
4 20,000 x PVIFA (10%,4) – 1,30,000
= (20,000 x 3.170) – 1,30,000 = -66,600
5 25,000 x PVIFA (10%,6) – 1,30,000
= (25,000 x 4.355) – 1,30,000 = -21,125
6 35,000 x PVIFA (10%,7) – 1,30,000
= (35,000 x 4.868) – 1,30,000 = 40,380
7 30,000 x PVIFA (10%,7) – 1,30,000
= (30,000 x 4.868) – 1,30,000 = 16,040
8 30,000 x PVIFA (10%,7) – 1,30,000
= (30,000 x 4.868) – 1,30,000 = 16,040
9 40,000 x PVIFA (10%,5) – 1,30,000
= (40,000 x 3.791) – 1,30,000 = 21,640
10 30,000 x PVIFA (10%,6) – 1,30,000
= (30,000 x 4.355) – 1,30,000 = 650
QUESTION- 9B
Formation of range of random no.
Original Cost Life
Value Prob. Cum. Prob. Range Life Prob. Cum. Prob. Range
60,000 0.30 0.30 00-29 5 0.40 0.40 00-39
70,000 0.60 0.90 30-89 6 0.40 0.80 40-79
90,000 0.10 1.00 90-99 7 0.20 1.00 80-99
For cash inflows
Value Prob. Cum. Prob. Range
10,000 0.10 0.10 00-09
15,000 0.30 0.40 10-39
20,000 0.40 0.80 40-79
25,000 0.20 1.00 80-99
Forecast of cash flows and life for 10 trial run
T. run Original cost Life Inflow
R.N. Value R.N. Life R.N. Value
1 09 60,000 24 5 07 10,000
2 84 70,000 38 5 48 20,000
3 41 70,000 73 6 57 20,000
4 92 90,000 07 5 64 20,000
5 65 70,000 04 5 72 20,000
Calculation of NPV:
Trial run NPV = Inflow x PVIFA @6% - Outflow
1 10,000 x PVIFA (6%,5) – 60,000
= (10,000) x 4.212) – 60,000 = -17,880
2 20,000 x PVIFA (6%,5) – 70,000
= (20,000) x 4.212) – 70,000 = 14,240
3 20,000 x PVIFA (6%,6) – 70,000
= (20,000) x 4.917) – 70,000 = 28,340
4 20,000 x PVIFA (6%,5) – 90,000
= (20,000) x 4.212) – 90,000 = -5760
(i) Cost of Project at which we can buy project at some future date
Strike Price of Call
SP σ2
Ln ( )+ [(Rf −Dy)+ ] ×T
K 2
𝑑1 =
σ × √T
𝑑2 = 𝑑1 - σ × √T
N(d1 ) = Cumulative probability of Area – ∞ to 𝑑1
N(d2 ) = Cumulative probability of Area – ∞ to 𝑑2
SP
EDSP = [eDy.t ]
(91 + 7) = 98
80
(75 + 7) = 82
R−d 1.10−1.025
Prob. of attaining value 98 = = = 0.375
U−d 1.225−1.025
Prob. of attaining value 82 = 1 – 0.375 = 0.625
Since the current value of vacant land is more than profit from 10
units Apartment now, the land should be kept vacant.
QUESTION- 10B
0y 1y
Payoff
195 Cr. 0
150 Cr.
90 Cr. 10
Question – 10 C
The given solution is like valuation of stock option wherein delay in
introduction of drug ‘Aidrex’ shall cause the loss of cashflow which is like
payment of dividend.
To value the patent, we shall use Black Scholes Model for option pricing
as follows:
Inputs
S (Spot Price) = The Present Value of Cashflows = $ 16.7 million
E (Exercise Price) = Cost of Development Formula = $ 12.5 million
2 = 26.8% (i.e., 0.27)
𝜎
R (Risk Free rate of Return) = 7.8%
1
D (Expected Cost of Delays) = = 0.0667 (i.e., 6.67%)
15
1
In (S/E)+ [R−D+( )σ2 ] t
2
d1 =
σ √t
d2 = d1 - σ √t
Accordingly,
1
In (16.7/12.5)+ [0.078−0.0667+( )(0.268)] 15
d1 =
2
√0.268 √15
0.2897+(0.1453)15 0.2897+2.1795 2.4692
= = = = 1.2315
0.5177 ×3.8730 2.005 2.005
Value of Patent
− 0.0667 ×15
= 16.7 x e × 0.8910 – 12.5 x e− 0.078 ×15 × 0.2196
= 16.7 x 0.3677 x 0.08910 x – 12.5 x 0.3104 x 0.2196
= 5.471 – 0.852 = 4.619
Thus, The Value of Patents is $ 4.619 Million.
Question – 10D
Decision Tree showing pay off
Year 0 Year 1 Pay
off
130 0
100
60 80-60 = 20
First of all we shall calculate probability of high demand (P) using risk
neutral method as follows:
8% = p x 30% + (1-p) x (-40%)
0.08 = 0.30 p - 0.40 + 0.40p
0.48
p= = 0.686
0.70
6.28
= = ₹ 5.81 crore
1.08
• Base case NPV NPV under the assumption that the project is
financed by equity only (All equity financed company).
• Adjusted NPV:
Adjusted NPV = Base case NPV
+ PV of tax saving on interest of debt.
Where,
PV of Tax saving on interest of debt can be calculated as follows:
Tax saving on int (TSI) = (Interest x Tax rate)
PV
(?)
Discount @ Kd
Verification:
PV
(?)
Discount @ Kd
(Borrowing
TSI Int x TR
PV of Tax saving on int = =
BR BR
(Debt Amt x BR) x TR
=
BR
= (Debt Amt x TR)
Note:
• If borrowing amount vary time to time to maintain proportion
of debt with equity market value then we have to use cost of
capital [not borrowing rate (K d)] as discount rate because Tax
saving becomes uncertain.
• We can accept project with -ve base case NPV.
Acceptable Adjusted NPV = 0
QUESTION – 11A
0Y 1Y 2Y 3Y
(1,000) 85 L 85 L 85 L
CC = 10%
Kd = 8% - 1% = 7%
9.8 L
PV of tax saving = [0.10 (CC) ] = 98 Lakh
QUESTION-11B
(i) Net Present Value (All Equity Financed) – Base NPV
Particulars Period USD PVF PV (USD
Lakhs @12% Lakhs)
Initial Investment 0 (250.00) 1.000 (250.000)
EBIDTA 1 to 20 33.00 7.469 246.477
Tax 1 to 20 (9.90) 7.469 (73.943)
Depreciation 1 to 10 (25.00)
Tax saving on dep 1 to 10 7.50 5.650 42.375
NPV (35.091)
Method-2:
Particulars ₹
Increase in sale xxx
Decrease in operating cost xxx
Or,
Increase in operating cost (xxx)
Incremental EBDT xxx
Less: Increase in Dep. (xxx)
Incremental EBT xxx
Less: Tax xxx
Incremental EAT xxx
Add: Increase in Dep xxx
Incremental annual cash inflows xxx
Decision:
Incremental NPV = +ve Replace old machine
Incremental NPV = -ve Do not replace old machine
Incremental NPV = 0 Indifference
Note:
Similarly, we can calculate “PI”, payback period also for
incremental cash flows, using same concept studied earlier.
Step III: Present value of benefits = Present value of yearly cash flows
+ Present value of estimated salvage of new system
= ₹ 12,690 × PVIFA (10%, 5) + ₹ 1,000 × PVIF (10%, 5)
= ₹ 48,723
QUESTION – 12B
Machine – R Machine – S
Cost 2,00,000 2,50,000
Life 5 Year 5 Year
Salavage NIL NIL
Production 1,50,000 units Same
Sale valuen 9,00,000 Same
Operating cost 2,00,000 1,80,000
Fixed cost (1,50,000 x 3) 4,50,000 same
(b)
Particulars
Cost of new Machine 30,00,000
Less:- Sale Value 12,00,000
Incremental Outflow(Initial) 18,00,000
(iv) NPV:
Particulars
PV of inflows 23,78,100
Add:- PV of tax saving on depreciation 4,19,623
Total PV of inflows 27,97,723
Less:- Initial Outflow 18,00,000
NPV 9,97,723
Note:- Ignored capital gain tax because question informed there are
several machines in same block of assets.
Disclaimer:
• When old machine will be sold, company will save additional
maintenance cost of 1,00,000 from 3 rd year end. Hence it is
inflow, but institute assumed outflow which is not correct.
• Increase in revenue is in additional to decrease is in operating
cost (according to question). Hence, we have to consider both
saving. But institute ignored 2,00,000 saving which is not
correct.
QUESTION – 12D
Cost of new machine = 26,00,000 + 9,000 + 6,000 = 26,15,000
Outflow in WC = 17,000
26,15,000
Annual Depreciation = = 3,26,875
8
Particulars Amount
Sale value of Old Machine 12,500
Less:- Dismantling cost 4,500
Net sale value 8,000
Less:- WDV in books 76,000
STCL (68,000)
PV of 𝑥 𝑥 𝑥 𝑥
cash
൦ ൪
flows
or, NPV
QUESTION – 12E
This question is simply unequal life project question. Nothing link with
Replacement.
12,35,330 12,35,330
Annual Equal outflow = = = 3,17,647
PVIFA (14%,6) 3.8890
PV of Outflow
= 90,000 + 10,000 x PVIFA (15%,8) – 20,000 x PVIF (15%,8)
= 90,000 + (10,000 x 4.4873) – (20,000 x 0.3269)
= 1,28,335
1,28,335
∴x= = 28,600
4.4873
Interpretation (Note for exam):
0Y 1Y 2Y 3Y 4Y 8Y
QUESTION – 13B
Calculation of cash flows and NPV for each replacement cycle [i.e.,
Replacement every year, Replacement in every 2 years, Replacement in
every 3 years etc.]
QUESTION-13C
Ri = Rf + β(Rm – Rf )
0.14 = Rf + 0.04
Rf = 0.10 or 10 percent
(Sale Price−Variable Cost)
NPV0 = Quantity X – Initial Investment
Risk Free Rate
= [6000 X (10-6)/0.10] - ₹ 1,00,000 = ₹ 1,40,000
[8,000𝑋(11 − 5)/0.10 − 100000]
NPV1 = = ₹ 3,45,454
1.10
[5,000 (9 − 7.50)/0.10 − 1,00,000]
NPV2 = = - ₹ 20,661
(1.10)2
It is better to defer the investment by 1 year and not by 2 years