Grid Code
Grid Code
NOTIFICATION
CHAPTER I
GENERAL
1.1 Introduction
1.2 Objective
1.3 Scope
IEGC 1
i) All parties that connect with and/or utilize the ISTS are required to
abide by the principles and procedures defined in the IEGC in so
far as they apply to that party.
ii) For the purpose of the IEGC, the Damodar Valley Corporation
(DVC) will be treated similar to an STU/SEB, in view of the fact
that DVC is a vertically integrated utility like an SEB and has its
own generation, transmission and distribution in the identified
command area.
iii) For the purpose of the IEGC, the generating stations of the
Bhakra Beas Management Board (BBMB) and Sardar Sarover
Narmada Nigam Ltd. (SSNNL) shall be treated as intra-State
generating stations, but their transmission systems shall be a part
of the ISTS. This is because of the fact that only some of the
States of Northern Region/Western Region have a share in
BBMB/SSNNL, and their generating units have to be scheduled
and dispatched in a very special manner (in coordination with the
irrigational requirements). The scheduling and despatch of the
BBMB/SSNNL generation shall continue to be the responsibility
of the BBMB/SSNNL, with a proviso that it shall be duly
coordinated with respective Regional Load Despatch Centre and
the beneficiaries.
IEGC 2
iii) Connection Conditions
IEGC 3
This section contains the procedures to be adopted
following a major grid disturbance, for black start and
resynchronization of islands, etc.
(i) Event Information
This section indicates the procedure by which events
are reported and the information exchange etc. takes place.
1.5 Non-compliance
IEGC 4
i) All thermal and hydro (except those with zero pondage)
generating units: with effect from the date to be separately
notified by the Commission.
ii) Any exemption from the above may be granted only by CERC for
which the concerned constituent/ agency shall file a petition in
advance.
1.8 Exemptions
ITEM DEFINITION
Act The Electricity Act, 2003
Agency A term used in the various sections of
the IEGC to refer to ISGS/Licensee
that utilize the ISTS.
IEGC 6
Demand The demand of Active Power in MW
and Reactive Power in MVAR of
electricity unless otherwise stated.
Despatch Schedule The ex-power plant net MW and
MWH output of a generating station,
scheduled to be exported to the Grid
from time to time.
Disturbance Recorder A device provided to record the
(DR) behaviour of the pre-selected digital
and analog values of the system
parameters during an Event.
Data Acquisition System A device provided to record the
(DAS) sequence of operation in time, of the
relays/equipments/system
parameters at a location.
Drawal Schedule The, ex-power plant, MW that a State
is scheduled to receive from the
ISGS, including bilateral exchanges
from time to time.
DVC The Damodar Valley Corporation
established under sub-section (1) of
Section 3 of the Damodar Valley
Corporation Act, 1948.
Entitlement Share of a beneficiary (in MW and
MWH) in the installed capacity/output
capability of an ISGS.
Event An unscheduled or unplanned
occurrence on a Grid including faults,
incidents and breakdowns.
Event Logger (EL) A device provided to record the
sequence of operation in time, of the
relays/equipments at a location
during an Event.
Ex-Power Plant Net MW/MWH output of a generating
station, after deducting auxiliary
consumption and transformation
losses.
Fault Locator (FL) A device provided at the end of a
transmission line to measure/indicate
the distance at which a line fault may
have occurred.
Flexible Alternating Current Facilities that enable power flows on
Transmission (FACT) A.C lines to be regulated, to control
loop flows, line loadings, etc.
IEGC 7
Force Majeure Any event which is beyond the
control of the agencies involved
which they could not foresee or with
a reasonable amount of diligence
could not have foreseen or which
could not be prevented and which
substantially affect the performance
by either agency such as but not
limited to :-
a)Acts of God, natural phenomena,
including but not limited to floods,
droughts, earthquakes and
epidemics;
b)Acts of any Government domestic
or foreign, including but not limited to
war declared or undeclared,
hostilities, priorities, quarantines,
embargoes;
c)Riot or Civil Commotion
d)Grid’s failure not attributable to
agencies involved..
Forced Outage An outage of a Generating Unit or a
transmission facility due to a fault or
other reasons which has not been
planned.
Generating Company Generating Company means any
company or body corporate or
association or body of individuals,
whether incorporated or not, or
artificial juridical person, which owns
or operates or maintains a generating
station.
Generating Unit An electrical Generating Unit coupled
to a turbine within a Power Station
together with all Plant and Apparatus
at that Power Station (up to the
Connection Point) which relates
exclusively to the operation of that
turbo-generator.
IEGC 8
Good Utility Practices Any of the practices, methods and
acts engaged in or approved by a
significant portion of the electric utility
industry during the relevant time
period which could have been
expected to accomplish the desired
results at a reasonable cost
consistent with good business
practices, reliably, safely and with
expedition.
Governor Droop In relation to the operation of the
governor of a Generating Unit, the
percentage drop in system frequency
which would cause the Generating
Unit under free governor action to
change its output from zero to full
load.
Grid Standards Grid Standards specified by the
Authority under clause (d) of the
Section 73 of the Act.
Extra High Voltage (EHV) Where the voltage exceeds 33,000
volts under normal conditions,
subject, however, to the percentage
variation allowed by the Authority.
Independent Power Producer A generating company not owned/
(IPP) controlled by the Central/State
Government.
Indian Electricity Grid Code (IEGC) A document describing the
philosophy and the responsibilities for
planning and operation of Indian
power system specified by the
Commission in accordance with sub
section 1(h) of Section 79 of the Act..
Inter-State Generating Station A Central/other generating station in
(ISGS) which two or more states have
shares and whose scheduling is to be
coordinated by the RLDC.
IEGC 9
Inter State Transmission System Inter-State Transmission System
(ISTS) includes
IEGC 10
Operation Co-ordination A committee of RPC with members
Committee (OCC) from all the Constituents which
decides the operational aspects of
the Regional Grid.
Operating range The operating range of frequency
and voltage as specified under the
operating code (Chapter-6)
Pool Account Regional account for (i) payments
regarding unscheduled -
interchanges (UI Account) or (ii)
reactive energy exchanges (Reactive
Energy Account), as the case may
be
POWERGRID Power Grid Corporation of India
Limited which has been notified as
CTU.
Power System Power System means all aspects of
generation, transmission, distribution
and supply of electricity and includes
one or more of the following, namely:
(a) generating stations;
(b) transmission or main
transmission lines;
(c) sub-stations;
(d) tie-lines;
(e) load despatch activities;
(f) mains or distribution mains;
(g) electric supply lines;
(h) overhead lines;
(i) service lines;
(j) works.
Reactor An electrical facility specifically
designed to absorb Reactive Power.
Regional .Power Committee (RPC) “Regional Power Committee” means
a Committee established by
resolution by the Central Government
for a specific region for facilitating the
integrated operation of the power
systems in that region.
RPC Secretariat The Secretariat of the RPC.
IEGC 11
Regional Energy Account (REA) A regional energy account, for the
billing and settlement of ‘Capacity
Charge’, ‘Energy Charge’, ‘UI
Charge’ and ‘Reactive Charge’.
Regional Grid The entire synchronously connected
electric power network of the
concerned Region, comprising of
ISTS, ISGS and intra-state systems.
Regional Load Despatch Centre ‘Regional Load Despatch Centre’
(RLDC) means the Centre established under
sub-section (1) of Section 27 of the
Act.
Share Percentage share of a beneficiary in
an ISGS notified by Government of
India or as agreed to in the
agreement between ISGS and its
beneficiaries.
Single Line Diagram (SLD) Diagrams which are a schematic
representation of the HV/EHV
apparatus and the connections to all
external circuits at a Connection
Point incorporating its numbering
nomenclature and labelling.
Site Common Drawing Drawings prepared for each
Connection Point, which incorporates
layout drawings, electrical layout
drawings, common protection/control
drawings and common service
drawings.
Spinning Reserve Part loaded generating capacity with
some reserve margin that is
synchronized to the system and is
ready to provide increased
generation at short notice pursuant to
dispatch instruction or
instantaneously in response to a
frequency drop.
Standing Committee for A Committee constituted by the CEA
Transmission Planning to discuss, review and finalise the
proposals for expansion or
modification in the ISTS and
associated intra-state systems.
SEB The State Electricity Board including
the State Electricity Department.
SERC State Electricity Regulatory Commission
IEGC 12
SSNNL Sardar Sarover Narmada Nigam Ltd.
State Load Despatch Centre ‘State Load Despatch Centre’ means
(SLDC) the Centre established under sub-
section (1) of Section 31 of the Act.
State Transmission Utility ‘State Transmission Utility’ means the
(STU) Board or the Government Company
specified as such by the State
Government under sub-section (1) of
Section 39 of the Act.
Static VAR Compensator (SVC) An electrical facility designed for the
purpose of generating or absorbing
Reactive Power.
Technical Co-ordination The committee set up by RPC to
Committee (TCC) coordinate the technical and
commercial aspects of the operation
of the regional grid.
Time Block Block of 15 minutes each for which
special energy Meters record
specified electrical parameters and
quantities with first time block starting
and 00.00 Hrs.
Transmission License A Licence granted under Section 14
of the Act to transmit electricity.
Transmission Planning Criteria The policy, standards and guidelines
issued by the CEA for the planning
and design of the Transmission
system.
User A term utilized in the various sections
of the IEGC to refer to the
persons/agencies using the ISTS, as
more particularly identified in each
section of the IEGC.
CHAPTER-2
2.1 Introduction
2.1.1 In the light of the Electricity Act, 2003, it has become necessary to re-
define the role of Regional Load Despatch Centres (RLDCs), Regional
Power Committees (RPCs)/Regional Electricity Boards (RPCs), the
Central Transmission Utility (CTU) etc. and their organizational linkage
so as to facilitate development and smooth operation of Regional Grids
and National Grid at large. This Chapter defines the function of the
various organizations so far as it relates to the Grid Code.
IEGC 13
2.2. Role of RLDCs
(1) The Regional Load Despatch Centre shall be the apex body to
ensure integrated operation of the power system in the
concerned region.
(2) The Regional Load Despatch Centre shall comply with such
principles, guidelines and methodologies in respect of wheeling
and optimum scheduling and despatch of electricity as may be
specified in the Grid Code.
(4) The Regional Load Despatch Centre may give such directions
and exercise such supervision and control as may be required
for ensuring stability of grid operations and for achieving the
maximum economy and efficiency in the operation of the power
system in the region under its control.
2.3.2 The following functions which go to facilitate the stability and smooth
operation of the systems are identified for the RPC:
2.4.1 As per the section 38 of Electricity Act, 2003, the functions of the
Central Transmission Utility (CTU) shall be –
IEGC 16
(d) to provide non-discriminatory open access to its
transmission system for use by-
(1) (i) CEA shall formulate short-term and perspective plans for
development of the electricity system and co-ordinate the
activities of the planing agencies for the optimal utilization of
resources to subserve the interests of the national economy and
to provide reliable and affordable electricity for all consumers.
(ii) to specify the technical standards for construction of
electrical plants, electric lines and connectivity to the grid ;
(iii) to specify the safety requirements for construction,
operation and maintenance of electrical plants and electric lines;
(iv) to specify the Grid Standards for operation and
maintenance of transmission lines; and,
(v) to specify the conditions for installation of meters for
transmission and supply of electricity.
(vi) to promote and assist in the timely completion of schemes
and projects for improving and augmenting the electricity
system;
(vi) to collect and record the data concerning the generation,
transmission, trading, distribution and utilisation of
electricity and carry out studies relating to cost, efficiency,
competitiveness and such like matters;
(vii) to carry out, or cause to be carried out, any investigation
for the purposes of generating or transmitting or
distributing electricity.
IEGC 17
(2) CEA shall prepare a National Electricity Plan in accordance with
the National Electricity Policy prepared by the Central
Government under the provisions of section 3(1) of Electricity Act,
2003. The CEA shall notify the National Electricity Plan once in
five years.
2.6.1 As per section 32 of Electricity Act, 2003, the State Load Despatch
Centre (SLDC) shall be the apex body to ensure integrated operation
of the power system in a State.
2.6.2 SLDC shall exercise supervision and control over the intra-State
transmission system. SLDC will be responsible for carrying out real
time operations for grid control and despatch of electricity within the
State through secure and economic operation of the State grid in
accordance with the Grid Standards and the State Grid Code. The
SLDC shall comply with the directions of the RLDC.
2.7.2 Section 39 of the Electricity Act, 2003, outlines that the functions of the
State Transmission Utility (STU) shall be –
IEGC 18
(ii) any consumer as and when such open access is
provided by the State Commission under sub-section (2)
of section 42 of the Act, on payment of the transmission
charges and a surcharge thereon, as may be specified by
the State Commission .
CHAPTER – 3
PLANNING CODE FOR INTER-STATE TRANSMISSION
3.1 Introduction
iv) In accordance with Section 39(2)(d) of Electricity Act, 2003, the State
Transmission Utility (STU) shall inter-alia provide non-discriminatory
open access to its transmission system for use by –
IEGC 19
(b) any consumer as and when such open access is provided by
the State Commission under sub-section (2) of Section 42, on
payment of the transmission charges and a surcharge thereon,
as may be specified by the State Commission.
vi) In accordance with Section 3 (4) of Electricity Act, 2003, CEA shall
sinter-alia prepare a National Electricity Plan in accordance with the
National Electricity Policy and notify such plan once in five (5) years.
As per Section 3 (5) of Electricity Act, 2003, CEA may review or revise
the National Electricity Plan in accordance with the National Electricity
Policy.
viii) The Planning Code specifies the policy and procedures to be applied in
planning of Regional Grids and Inter Regional links.
3.2 Objective
3.3 Scope
IEGC 20
The Planning Code applies to CTU, other Transmission licensees,
Inter-State Generating Station (ISGS), connected to and/or using and
involved in developing the ISTS. This Planning Code also applies to
Generating Companies, IPPs, SEBs/STUs and /licensees, regarding
generation and/or transmission of energy to/from the ISTS.
(b) The CTU shall carry out planning process from time to time as
per the requirement for identification of major inter-State
transmission system including inter-regional schemes which
shall fit in with the perspective plan developed by CEA. While
planning schemes, the following shall be considered in addition
to the data of authenticated nature collected from and in
consultation with various agencies / Regional Constituents by
CTU:
(f) All Constituents and agencies will supply to the CTU, the
desired planning data from time to time to enable to formulate
and finalize its plan.
(h) The plan report shall also indicate the action taken to fulfill the
additional requirement and actual progress made on new
schemes. These reports will be available to any interested party
for making investment decision/connection decisions to the
ISTS.
General Policy
(a) The planning criterion are based on the security philosophy on which
the ISTS has been planned. The security philosophy may be as per the
Transmission Planning Criteria and other guidelines as given by CEA.
The general policy shall be as detailed below:
IEGC 22
i) As a general rule, the ISTS shall be capable of withstanding and
be secured against the following contingency outages without
necessitating load shedding or rescheduling of generation
during Steady State Operation:
(b) The ISTS shall be capable of withstanding the loss of most severe
single system infeed without loss of stability.
(c) Any one of these events defined above shall not cause:
i) Loss of supply
ii) Prolonged operation of the system frequency below and above
specified limits.
iii) Unacceptable high or low voltage
iv) System instability
v) Unacceptable overloading of ISTS elements.
(d) In all substations (132 kV and above), at least two transformers shall
be provided.
(e) CTU shall carry out planning studies for Reactive Power compensation
of ISTS including reactive power compensation requirement at the
ISGS’s Switchyard.
IEGC 23
ii) Standard planning data covering (a) preliminary project planning
data (b) committed project planning data and (c) connected
planning data should be furnished by the State Electricity
Boards/STU, and Generating companies connected to the ISTS.
This data shall be furnished to CTU from time to time in the
standard formats supplied by the CTU.
iii) The standard formats for submission of this data have been
developed and approved by the CERC (August, 2001).
CHAPTER - 4
CONNECTION CONDITIONS
4.1 Introduction
4.2 Objective
a) The basic rules for connections are complied with to treat all
agencies in a non-discriminatory manner.
IEGC 24
(c) The ownership and responsibility for all the equipments shall be
clearly specified in a schedule (site responsibility schedule) for
every site, where a connection is made.
4.3 Scope
(a) Prior to a agency being connected to the ISTS all necessary conditions
outlined in the IEGC in addition to other mutually agreed requirements
to be complied with, must be fulfilled by the agency. Any agency
seeking to establish new or modified arrangement of connection to or
for use of ISTS, shall submit an application on standard format to CTU
along with the following details:-
IEGC 25
recommendation/comments. The cost of modification, if any, shall be
borne by the concerned constituent.
(a) General
i) The variation of voltage may not be more than the voltage range
specified in the regulations/standards framed by the Authority.
(c) Protection
IEGC 27
Relay setting coordination shall be done at regional level by RPC. The
RPCs would also identify critical locations where bus bar protection
needs to be provided, if not available.
IEGC 28
4.11 System Recording Instruments
ii) The detailed drawings for the portion of the agency and CTU/
transmission licensee at each Connection Point shall be
prepared individually and copies shall be handed over to other
party.
iii) If any change in the drawing is found necessary, the details will be
furnished to other party as soon as possible.
IEGC 30
ANNEXURE-1
(refer section 4.5)
IEGC 31
CHAPTER-5
(b) Overall operation of the Regional grid shall be supervised from the
Regional Load Despatch Centre (RLDC). The roles of RLDC and
RPC shall be in accordance with the provisions made in Chapter-2
of the IEGC.
(c) All Regional constituents shall comply with this Operating Code, for
deriving maximum benefits from the integrated operation and for
equitable sharing of obligations.
(e) The control rooms of the RLDC, all SLDCs, power plants,
substation of 132 kV and above, and any other control centres of all
regional constituents shall be manned round the clock by qualified
and adequately trained personnel.
(b) No part of the grid shall be deliberately isolated from the rest of the
Regional grid, except (i) under an emergency, and conditions in
which such isolation would prevent a total grid collapse and/or
would enable early restoration of power supply, (ii) when serious
damage to a costly equipment is imminent and such isolation would
prevent it, (iii) when such isolation is specifically instructed by
RLDC. Complete synchronization of grid shall be restored as soon
as the conditions again permit it. The restoration process shall be
supervised by RLDC, as per operating procedures separately
formulated.
IEGC 32
(c) No important element of the Regional grid shall be deliberately
opened or removed from service at any time, except when
specifically instructed by RLDC or with specific and prior clearance
of RLDC. The list of such important grid elements on which the
above stipulations apply shall be prepared by the RLDC in
consultation with the constituents, and be available at
RLDC/SLDCs. In case of opening/removal of any important element
of the grid under an emergency situation, the same shall be
communicated to RLDC at the earliest possible time after the event.
(e) All generating units, which are synchronized with the grid,
irrespective of their ownership, type and size, shall have their
governors in normal operation at all times . If any generating unit of
over fifty (50) MW size (10 MW for North-Eastern Region) is
required to be operated without its governor in normal operation,
the RLDC shall be immediately advised about the reason and
duration of such operation. All governors shall have a droop of
between 3% and 6%.
IEGC 33
maintaining an extra spinning reserve on the other generating units
of the constituent.
(h) The recommended rate for changing the governor setting, i.e.,
supplementary control for increasing or decreasing the output
(generation level) for all generating units, irrespective of their type
and size, would be one (1.0) per cent per minute or as per
manufacturer’s limits. However, if frequency falls below 49.5 Hz, all
partly loaded generating units shall pick up additional load at a
faster rate, according to their capability.
(j) All generating units shall normally have their automatic voltage
regulators (AVRs) in operation, with appropriate settings. In
particular, if a generating unit of over fifty (50) MW (10 MW in case
of North-Eastern region) size is required to be operated without its
AVR in service, the RLDC shall be immediately intimated about the
reason and duration, and its permission obtained. Power System
Stabilizers (PSS) in AVRs of generating units (wherever provided),
shall be got properly tuned by the respective generating unit owner
as per a plan prepared for the purpose by the CTU from time to
time. CTU will be allowed to carry out checking of PSS and further
tuning it, wherever considered necessary.
(l) All Regional constituents shall make all possible efforts to ensure
that the grid frequency always remains within the 49.0 – 50.5 Hz
band, the frequency range within which steam turbines conforming
to the IEC specifications can safely operate continuously.
(r) All regional constituents shall make all possible efforts to ensure
that the grid voltage always remains within the following operating
range.
------------------------------------------------------------------
VOLTAGE – (KV rms)
------------------------------------------------------------------
Nominal Maximum Minimum
5.3.1 Introduction
(c) Each SLDC shall carry out its own demand estimation from the historical
data and weather forecast data from time to time.
5.3.2 Objective
(a) The objective of this procedure is to enable the SLDCs to estimate their
demand over a particular period.
(b) The demand estimates are to enable the SLDC to conduct system studies
for operational planning purposes.
5.3.3 Procedure
5.4.1 Introduction
IEGC 36
5.4.2 Manual Demand Disconnection
(c) Each Regional constituent shall make arrangements that will enable
manual demand disconnection to take place, as instructed by the
RLDC/SLDC, under normal and/or contingent conditions.
(d) The measures taken to reduce the constituents’ drawal from the grid shall
not be withdrawn as long as the frequency/voltage remains at a low level,
unless specifically permitted by the RLDC.
5.5.1 A weekly report shall be issued by RLDC to all constituents of the Region
and RPC Secretariat and shall cover the performance of the Regional grid
for the previous week. Such weekly report shall also be available on the
website of the RLDC concerned for at least 12 weeks.
(a) The RLDC shall prepare a quarterly report which shall bring out the
system constraints, reasons for not meeting the requirements, if any, of
security standards and quality of service, along with details of various
actions taken by different agencies, and the agencies responsible for
causing the constraints.
(b) The RLDC shall also provide information/report which can be called for by
RPC in the interest of smooth operation of ISTS.
IEGC 37
5.6 Operational Liaison
5.6.1 Introduction
(a) This section sets out the requirements for the exchange of
information in relation to Operations and/or Events on the total grid
system which have had or will have an effect on:
• Before any Operation is carried out on Regional grid, the RLDC will inform
each Regional constituent, whose system may, or will, experience an
operational effect, and give details of the operation to be carried out.
IEGC 38
5.7 Outage Planning
5.7.1 Introduction
a) This section sets out the procedure for preparation of outage schedules for
the elements of the Regional grid in a coordinated and optimal manner
keeping in view the Regional system operating conditions and the balance
of generation and demand. (List of elements of grid covered under these
stipulations shall be prepared and be available with RLDC and SLDCs).
c) Annual outage plan shall be prepared in advance for the financial year by
the RPC Secretariat and reviewed during the year on quarterly and
Monthly basis.
5.7.2 Objective
5.7.3 Scope
b) All SEBs/STUs, CTU, ISGS shall provide RPC Secretariat their proposed
outage programmes in writing for the next financial year by 30th November
of each year. These shall contain identification of each generating
IEGC 39
unit/line/ICT, the preferred date for each outage and its duration and
where there is flexibility, the earliest start date and latest finishing date.
c) RPC Secretariat shall then come out with a draft outage programme for
the next financial year by 31st December of each year for the Regional grid
taking into account the available resources in an optimal manner and to
maintain security standards. This will be done after carrying out necessary
system studies and, if necessary, the outage programmes shall be
rescheduled. Adequate balance between generation and load requirement
shall be ensured while finalising outage programmes.
d) The final outage plan shall be intimated to all Regional constituents and
the RLDC for implementation latest by 31st January of each year as
mutually decided in RPC forum.
i) Each Regional constituent shall obtain the final approval from RLDC prior
to availing an outage.
a) Detailed plans and procedures for restoration of the regional grid under
partial/total blackout shall be developed by RLDC in consultation with all
Regional constituents/RPC Secretariat and shall be reviewed / updated
annually.
5.9.1 Introduction
5.9.2 Objective
5.9.3 Scope
5.9.4 Responsibility
b) All Regional constituents and the SLDCs shall be responsible for collection
and reporting of all necessary data to RLDC and RPC Secretariat for
monitoring, reporting and event analysis.
IEGC 41
5.9.5 Reportable Events
IEGC 42
CHAPTER-6
SCHEDULING AND DISPATCH CODE
6.1 Introduction
6.2 Objective
This code deals with the procedures to be adopted for scheduling of the
inter-State generating stations (ISGS) and net drawals of concerned
constituents on a daily basis with the modality of the flow of information
between the ISGS/RLDCs/beneficiaries of the Region. The procedure for
submission of capability declaration by each ISGS and submission of
drawal schedule by each beneficiary is intended to enable RLDCs to
prepare the dispatch schedule for each ISGS and drawal schedule for
each beneficiary. It also provides methodology of issuing real time
dispatch/drawal instructions and rescheduling, if required, to ISGS and
beneficiaries along with the commercial arrangement for the deviations
from schedules, as well as, mechanism for reactive power pricing. The
provisions contained in this chapter are without prejudice to the powers
conferred on RLDC under section 28 and 29 of the Electricity Act, 2003.
6.3 Scope
3. The above flexibility has been proposed in view of the fact that all
States do not have all requisite facilities for minute-to-minute on-line
regulation of the actual net drawal from the regional grid. Deviations from
net drawal schedule are however, to be appropriately priced through the
Unscheduled Interchange (UI) mechanism.
8. Provided that when the frequency is higher than 50.5 Hz, the actual
net injection shall not exceed the scheduled dispatch for that time. Also,
while the frequency is above 50.5 Hz, the ISGS may (at their discretion)
back down without waiting for an advice from RLDC to restrict the
frequency rise. When the frequency falls below 49.5 Hz, the generation at
all ISGS (except those on peaking duty) shall be maximized, at least upto
the level which can be sustained, without waiting for an advise from
RLDC.
10. For all outages of generation and transmission system, which may
have an effect on the regional grid, all constituents shall cooperate with
each other and coordinate their actions through Operational Coordination
Committee (OCC) for outages foreseen sufficiently in advance and
through RLDC (in all other cases), as per procedures finalized separately
by OCC. In particular, outages requiring restriction of ISGS generation
and/or restriction of ISGS share which a beneficiary can receive (and
which may have a commercial implication) shall be planned carefully to
achieve the best optimization.
13. It shall be incumbent upon the ISGS to declare the plant capabilities
faithfully, i.e., according to their best assessment. In case, it is suspected
that they have deliberately over/under declared the plant capability
contemplating to deviate from the schedules given on the basis of their
capability declarations (and thus make money either as undue capacity
charge or as the charge for deviations from schedule), the RLDC may ask
the ISGS to explain the situation with necessary backup data.
14. The CTU shall install special energy meters on all inter connections
between the regional constituents and other identified points for recording
of actual net MWh interchanges and MVArh drawals. The type of meters
to be installed, metering scheme, metering capability, testing and
calibration requirements and the scheme for collection and dissemination
of metered data are detailed in the enclosed Annexure-2. All concerned
entities (in whose premises the special energy meters are installed) shall
fully cooperate with the CTU/RLDC and extend the necessary assistance
by taking weekly meter readings and transmitting them to the RLDC.
15. The RLDC shall be responsible for computation of actual net MWh
injection of each ISGS and actual net drawal of each beneficiary, 15
minute-wise, based on the above meter readings and for preparation of
the Regional Energy Accounts. All computations carried out by RLDC
shall be open to all constituents for checking/verifications for a period of 15
days. In case any mistake/omission is detected, the RLDC shall forthwith
make a complete check and rectify the same.
16. RLDC shall periodically review the actual deviation from the
dispatch and net drawal schedules being issued, to check whether any of
the constituents are indulging in unfair gaming or collusion. In case any
IEGC 46
such practice is detected, the matter shall be reported to the Member
Secretary, RPC for further investigation/action.
5. The SLDCs may also give standing instructions to the RLDC such
that the RLDC itself may decide the drawal schedules for the States.
IEGC 47
6. By 5 PM each day, the RLDC shall convey:
7. While finalizing the above daily dispatch schedules for the ISGS,
RLDC shall ensure that the same are operationally reasonable, particularly
in terms of ramping-up/ramping-down rates and the ratio between
minimum and maximum generation levels. A ramping rate of upto 200 MW
per hour should generally be acceptable for an ISGS and for a regional
constituent (50 MW in NER), except for hydro-electric generating stations
which may be able to ramp up/ramp down at a faster rate.
10. Also, based on the surpluses foreseen for the next day, if any, the
constituents may arrange for bilateral exchanges. The schedules for such
arrangements shall be intimated latest by 10 PM to RLDC, who in turn will
take into account these agreed exchanges while issuing the final
dispatch/drawal schedules at 11 PM provided they would not lead to a
transmission constraint.
11. While finalizing the drawal and dispatch schedules as above, the
RLDC shall also check that the resulting power flows do not give rise to
any transmission constraints. In case any constraints are foreseen, the
RLDC shall moderate the schedules to the required extent, under
intimation to the concerned constituents. Any changes in the scheduled
IEGC 48
quantum of power which are too fast or involve unacceptably large steps,
may be converted into suitable ramps by the RLDC.
12. In case of forced outage of a unit, the RLDC shall revise the
schedules on the basis of revised declared capability. The revised
declared capability and the revised schedules shall become effective from
the 4th time block, counting the time block in which the revision is advised
by the ISGS to be the first one.
16. If, at any point of time, the RLDC observes that there is need for
revision of the schedules in the interest of better system operation, it may
do so on its own, and in such cases, the revised schedules shall become
effective from the 4th time block, counting the time block in which the
revised schedule is issued by the RLDC to be the first one.
IEGC 49
18. After the operating day is over at 2400 hours, the schedule finally
implemented during the day (taking into account all before-the-fact
changes in dispatch schedule of generating stations and drawal schedule
of the States) shall be issued by RLDC. These schedules shall be the
datum for commercial accounting. The average ex-bus capability for each
ISGS shall also be worked out based on all before-the-fact advise to
RLDC.
19. RLDC shall properly document all above information i.e. station-
wise foreseen ex-power plant capabilities advised by the generating
stations, the drawal schedules advised by beneficiaries, all schedules
issued by the RLDC, and all revisions/updating of the above.
20. The procedure for scheduling and the final schedules issued by
RLDC, shall be open to all constituents for any checking/verification, for a
period of 5 days. In case any mistake/omission is detected, the RLDC
shall forthwith make a complete check and rectify the same.
- The Beneficiary pays for VAr drawal when voltage at the metering
point is below 97%
- The Beneficiary gets paid for VAr return when voltage is below 97%
- The Beneficiary gets paid for VAr drawal when voltage is above
103%
IEGC 50
- The Beneficiary pays for VAr return when voltage is above 103%
5. Switching in/out of all 400 kV bus and line Reactors throughout the
grid shall be carried out as per instructions of RLDC. Tap changing on all
400/220 kV ICTs shall also be done as per RLDCs instructions only.
IEGC 51
iii) The two concerned Beneficiaries may mutually agree to adopt a
payment rate/scheme for VAr exchanges between them identical to
or at variance from that specified by CERC for VAr exchanges with
ISTS. If the agreed scheme requires any additional metering, the
same shall be arranged by the concerned Beneficiaries.
iv) The computation and payments for such VAr exchanges shall be
effected as mutually agreed between the two Beneficiaries.
IEGC 52
Annexure-1
(refer section 6.1 (d))
COMPLEMENTARY COMMERCIAL MECHANISMS
2. The sum of the above two charges from all beneficiaries shall fully
reimburse the ISGS for generation according to the given dispatch
schedule. In case of a deviation from the dispatch schedule, the
concerned ISGS shall be additionally paid for excess generation through
the UI mechanism approved by CERC. In case of actual generation being
below the given dispatch schedule, the concerned ISGS shall pay back
through the UI mechanism for the shortfall in generation.
6. The RLDC shall also issue the weekly statement for VAr charges,
to all constituents who have a net drawal/injection of reactive energy under
low/high voltage conditions. These payment shall also have a high priority
and the concerned constituents shall pay the indicated amounts into
regional reactive account operated by the RLDC within 10 (ten) days
of statement issue. The constituents who have to receive the money on
account of VAr charges would then be paid out from the regional reactive
account, within three (3) working days.
10. The RLDC shall table the complete statement of the regional UI
account and the regional Reactive Energy account in the RPC’s
Commercial Committee meeting, on a quarterly basis, for audit by the
latter.
11. All 15-minute energy figures (net scheduled, actually metered and
UI) shall be rounded off to the nearest 0.01 MWh.
IEGC 54
Annexure-2
3. The meters shall have a non-volatile memory in which the following shall
be automatically stored:
vi) Date and time blocks of failure of VT supply on any phase, as a star
(*) mark.
4. The meters shall store all the above listed data in their memories for a
period of ten (10) days. The data older than (10) days shall get erased
automatically. Each meter shall have an optical port on its front for tapping
all data stored in its memory using a hand held data collection device.
IEGC 55
5. The active energy (Wh) measurement shall be carried out on 3-phase, 4-
wire principle, with an accuracy as per class 0.2 S of IEC-687/IEC-62053-
22. In model-A, the energy shall be computed directly in CT and VT
secondary quantities, and indicated in watt-hours. In model-B, the energy
display and recording shall be one fifth of the Wh computed in CT and VT
secondary quantities.
7. The 15-minute Wh shall have a +ve sign when there is a net Wh export
from substation busbars, and a -ve sign when there is a net Wh import.
The integrating (cumulative) registers for Wh and VArh shall move forward
when there is Wh/VArh export from substation busbars, and backward
when there is an import.
8. The meters shall also display (on demand), by turn, the following
parameters:
10. The meters shall be totally sealed and tamper-proof, with no possibility of
any adjustment at site, except for a restricted clock correction. The
harmonics shall preferably be filtered out while measuring Wh, VAr and
VArh, and only fundamental frequency quantities shall be
measured/computed.
IEGC 56
11. All metering equipment shall be of proven quality, fully type-tested,
individually tested and accepted by the CTU before dispatch from
manufacturer’s work.
12. In-situ functional checking and rough testing of accuracy shall be carried
out for all meters once a year by the CTU, with portable test equipment
complying with IEC-60736, for type and acceptance testing of energy
meters of 1.0 class.
13. Full testing for accuracy for every meter shall be carried out by the CTU at
an accredited laboratory, once every five (5) years.
14. The current and voltage transformers to which the above special energy
meters are connected shall have a measurement accuracy class of 0.5 or
better. Main and Standby/check meters shall be connected to different
sets of CTs and VTs, wherever available.
15. Only functional requirements from regulatory perspective are given in this
code. Detailed specifications for the meters, their accessories and testing,
and procedures for collecting their weekly readings shall be finalized by
the CTU.
IEGC 57
Annexure-3
(refer section 6.6.7(iii))
State A State B
State A State B
State A State B
S/S-A S/S-B
Note:
IEGC 59
CHAPTER-7
INTER-REGIONAL EXCHANGES
7.1 INTRODUCTION
1. India was demarcated into five (5) electrical regions in Sixties, for
planning, development and operation of the power system. For over three
decades, the generation and transmission planning continued with
regional self-sufficiency as an objective/criterion, and consequently the
inter-regional links were planned only for marginal exchange of power. Till
2002, the inter-regional links comprised either of 220 kV/132 kV A.C. lines
operating in radial mode, or of HVDC back-to-back links, which allowed
different regions to operate at their own frequency.
1. India has three (3) synchronous power systems today: (a) Northern, (b)
Central (WR-ER-NER), and (c) Southern. The Northern system is
connected to Central mainly through two (2) back to back HVDC links: (a)
2x250 MW Vindhyachal (NR-WR), and (b) 1x500 MW Sasaram (ER-NR).
The Southern system is connected to Central mainly through three (3)
HVDC links: (a) 2x1000 MW Talcher-Kolar (ER-SR), (b) 2x500 MW
Gazuwaka (ER-SR), and (c) 2x500 MW Chandrapur (WR-SR).
1. All ISGS, except Talcher-II STPS, shall be scheduled through the RLDC of
the region in which they are located, even if they have Beneficiaries in
other regions. In other words, an ISGS shall interact with the host RLDC
only. For allocations to Beneficiaries in other regions, the host RLDC shall
interact with the concerned RLDC, as per modalities worked out between
them. The concerned RLDC shall in turn interact with the SLDC of the
respective Beneficiary, and then revert to the host RLDC.
3. Each RLDC shall estimate and apportion transmission losses of its own
region, for the purpose of determining the drawal schedules of the
Beneficiaries and inter-regional schedules with a resolution of 0.1 MW.
3. Talcher-II STPS shall advise the SRLDC (with copies to ERLDC and
Talcher HVDC terminal) the ex-power plant MW and MWh capabilities for
the next day, by 9 AM every day. The SRLDC shall then interact with the
SLDCs of SR, and convey the dispatch schedule of Talcher-II for the next
day to Talcher-II STPS, with copies to ERLDC and Talcher HVDC
terminal, by 5 PM.
5. The base MW level for Talcher-Kolar HVDC link at Talcher end shall be
separately advised by SRLDC to Talcher HVDC terminal. It need not be
equal to the Talcher-II dispatch schedule, since power can flow to SR via
other routes as well, i.e., Gazuwaka HVDC and Chandrapur HVDC. (The
HVDC settings are to be optimized by SRLDC).
8. CEA, ERLDC, SRLDC, NTPC and Powergrid shall jointly work out and
implement the required inter-tripping/runback arrangements between
Talcher-II STPS and Talcher-Kolar HVDC link. In particular, the
arrangements shall aim at keeping within permissible limits the frequency
rise and line overloading in ER and WR in the event of tripping of one or
both poles of the HVDC link.
1. NRLDC shall schedule the interchanges of NR with all other regions, and
also advise the power settings to Vindhyachal and Sasaram HVDC
IEGC 62
stations. The total scheduled import of power from ER/NER into NR may
presently be restricted to 500 MW (the capacity of Sasaram HVDC).
2. The SRLDC shall schedule the interchanges of SR with all other regions,
and also advise the power settings to Talcher, Chandrapur and Gazuwaka
HVDC stations.
4. The settings of HVDC links may not match with the respective inter-
regional schedules. Specifically, unscheduled interchange (UI) may be
allowed from the system with a higher frequency to the system with a
lower frequency, by setting the HVDC links at power levels differing from
the respective inter-regional schedules.
IEGC 63
10. The WRLDC shall schedule the interchange of power of WR with ER and
NER, presently limiting the scheduled import to 1000 MW (thus keeping a
security margin of about 500 MW) on ER-WR links. It shall also monitor
the power flow on ER-WR ties, and in the event of overloading may
request NRLDC/SRLDC to divert some ER-WR power flow through their
respective regions. If the required assistance is not forthcoming or is not
possible, WRLDC shall order any necessary preventive action in its own
region.
11. It is expected that in the normal course, with all major transmission
elements available, there would be no transmission constraints between
NER and ER, and between ER and SR. If any constraints do arise, the
RLDCs shall coordinate between themselves, and with NLDC if
necessary, to remedy the situation.
2. The NR-WR and WR-SR exchanges of UI shall be at the UI rate in WR. All
other UI exchanges shall be at the UI rate in ER. Payments for inter-
regional UI exchanges shall be between the respective regional UI pool
accounts, region-to-region.
IEGC 64
CHAPTER – 8
8.1 The Indian Electricity Grid Code (IEGC) shall be specified by the Central
Electricity Regulatory Commission (CERC) as per section 79 (1) (h) of the
Electricity Act, 2003. Any amendments to IEGC shall also be specified by
CERC only.
8.2 The IEGC and its amendments shall be finalized and notified adopting the
prescribed procedure followed for regulations issued by CERC.
8.3 The requests for amendments to / modifications in the IEGC and for
removal of difficulties shall be addressed to Secretary, CERC, for periodic
consideration, consultation and disposal.
8.5 The State Electricity Regulatory Commissions (SERC) shall specify the
Grid Codes for operation of the respective intra-State system as per
section 86 (1) (h) of Electricity Act, 2003, ensuring that they are consistent
with the IEGC.
IEGC 65
BACKGROUND NOTE
2. The comments and objections received from all parties who responded
were discussed in the hearings held by CERC in July 1999, and after
further interaction between CERC and PGCIL, the first IEGC was issued in
January 2000. There was a review of the IEGC in early 2002 and the first
revision as per CERC’s order dated 22.02.2002 was issued by PGCIL in
March, 2002.
4. As per Section 73(d) of the Act, the “Grid Standards for operation and
maintenance of transmission lines” are to be specified by Central
Electricity Authority (CEA). As and when Grid Standards are specified by
CEA, if required, the IEGC shall be amended.
IEGC 66
5. The present IEGC has a chapter titled “Management of Indian Electricity
Grid Code”, which was relevant in the previous scenario. It provided for
an IEGC Review Panel, with Director (Operation), PGCI as its chairman
and convenor. Any change in IEGC required agreement in the IEGC
Review Panel and approval by CERC. Now that the responsibility for
specifying the Grid code directly vests in CERC, and the Grid Code and its
revisions are to be issued adopting the procedure followed for CERC’s
regulations, the IEGC Review Panel is no longer necessary. The current
exercise of preparing the new draft IEGC is also not being routed through
the present IEGC Review Panel, for the same reasons. The above chapter
has been rewritten, removing all references to the IEGC Review Panel.
6. As per section 28 (3) (c) of the Electricity Act, 2003, the Regional Load
Despatch Centres (RLDC) shall “keep accounts of quantity of electricity
transmitted through the regional grid”. Accordingly, the responsibility of
preparation of Regional Energy Accounts hitherto with the REB
Secretariats, shall stand transferred to the respective RLDCs with effect
from 01.04.2006.
7. The Regional Electricity Boards (REB) have been replaced in the new Act
by Regional Power Committees (RPC). The Central Government vide its
principal resolution dated 25.05.2005 have notified establishment of
RPCs. The IEGC has been revised accordingly.
10. This revised IEGC shall be effective from 1st April 2006.
11. The earlier IEGC was silent regarding the payment for reactive energy
exchanges directly between the States on State-owned transmission lines.
This aspect is now being covered in the revised IEGC under a new section
(6.6.7).
IEGC 68
12. The intra-State scheme for pricing of reactive energy exchanges between
the intra-State entities has to be very carefully deliberated upon by the
concerned SERC/STU, and duly covered in the State Electricity Grid
Code. The requirements of local reactive support may differ from State to
State and the approach may differ from that in this IEGC. For example, the
inter-State generating stations (ISGS) have to generate/absorb reactive
power as per instructions of RLDC, “without sacrificing on the active
generation required at that time”, and “no payment shall be made to the
generating companies for such VAr generation/absorption”. This is
because (1) the ISGS are mostly located away from load-centres, (2) they
generally have a lower variable cost, and (3) they are paid a capacity
charge covering the cost of entire installation, including their reactive
power capability. The situation of intra-State stations may differ in these
respects, and a different approach to their reactive energy output may be
necessary.
13. When the first version of IEGC was drafted in 1999, inter-regional
exchanges were minimal. Many new inter-regional links have since been
commissioned and substantial amounts of energy is now being exchanged
between the regional grids. A new chapter is being added in the IEGC
accordingly, to cover various aspects of scheduling, control and
commercial issues of inter-regional exchanges.
(A.K.SACHAN)
Secretary
IEGC 69