JSA-SM-PROJ-0017 General Deck Operations, Work at Height, HFL Unspooling
JSA-SM-PROJ-0017 General Deck Operations, Work at Height, HFL Unspooling
JSA-SM-PROJ-0017 General Deck Operations, Work at Height, HFL Unspooling
: MPF-QHSE-008
Job Safety Analysis /Risk Assessment Form Revision: 03 Rev Date: 21.04.2016
Doc Type: Form Issued Date: 03.05.2016
TASK BEING General Deck Operations, Work at Height, HFL Unspooling PROJECT TITLE :
ASSESSED: (if applicable)
JSA REF NO: JSA-SM-PROJ-0017 JOB SUPERVISOR:
ATTENDEES : ATTENDEES:
SN NAME POSITION COMPANY SIGNATURE SN NAME POSITION COMPANY SIGNATURE
Page 1 of 11
Doc Ref No.: MPF-QHSE-008
Job Safety Analysis /Risk Assessment Form Revision: 03 Rev Date: 21.04.2016
Doc Type: Form Issued Date: 03.05.2016
Permit to work Lift plan in place Inspection of equipment Mechanical isolation /Electrical isolation
Good barrier management Stop work Authority Certified lifting equipment Effective supervision
Effective communication Toolbox talk Correct tools/ PPE Good housekeeping standards
Detailed work procedure/task plan Material Safety Data Sheet(MSDS) Drop object inspection Competent personnel
Suitable environmental conditions Line of Fire awareness Access control Situational Awareness
Page 2 of 11
Doc Ref No.: MPF-QHSE-008
Job Safety Analysis /Risk Assessment Form Revision: 03 Rev Date: 21.04.2016
Doc Type: Form Issued Date: 03.05.2016
ENVIRONMENT
SOURCES/CAUSES OF
S/N TASK HAZARD CONSEQUENCES CONTROLS IN PLACE
RISK RATING
RISK RATING
PROBABILTY
PROBABILTY
HAZARD
SCHEDULE
SEVERITY
SEVERITY
PERSON
ASSET
1 Tools and Cutting Wrong tools and Injury 2 1 1 1 3 2 6 TBT, JSA 3 2 6
Equipment Entanglement equipment selection personnel Ensure personnel are competent
Preparation Shearing Poor task planning Damage to to use tools
Flying particles Poor knowledge of equipment Before using the tool, the worker
tools and equipment shall inspect it to determine that
Damaged tools and it is clean, all moving parts
equipment operate freely
Dedicated storage position
Incorrect PPE
provided for all task tools and
equipment & keep all tools in
good condition with regular
maintenance
Appropriate PPE must be worn at
all time.
All dedicated tools and
equipment to be fully checked
for integrity prior to storage after
use
No modification or adjustment
to any tools or equipment
permitted without consultation
with supervisor
Use the right tool for the job
Operate according to the
Document No: MPF-QHSE-008 Rev 03 Date 21-04-2016
Page 3 of 11
Doc Ref No.: MPF-QHSE-008
Job Safety Analysis /Risk Assessment Form Revision: 03 Rev Date: 21.04.2016
Doc Type: Form Issued Date: 03.05.2016
Slips, trips, & fall’s Congested deck Injury to Toolbox Talk, PTW, Lift plan,
General deck
2 Rigging failure Loads not rigged personnel 3 1 2 1 3 3 9 Walk through talk through of 3 2 6
Operations
Crushing correctly Damage to task.
Page 4 of 11
Doc Ref No.: MPF-QHSE-008
Job Safety Analysis /Risk Assessment Form Revision: 03 Rev Date: 21.04.2016
Doc Type: Form Issued Date: 03.05.2016
Page 5 of 11
Doc Ref No.: MPF-QHSE-008
Job Safety Analysis /Risk Assessment Form Revision: 03 Rev Date: 21.04.2016
Doc Type: Form Issued Date: 03.05.2016
Page 6 of 11
Doc Ref No.: MPF-QHSE-008
Job Safety Analysis /Risk Assessment Form Revision: 03 Rev Date: 21.04.2016
Doc Type: Form Issued Date: 03.05.2016
Page 7 of 11
Doc Ref No.: MPF-QHSE-008
Job Safety Analysis /Risk Assessment Form Revision: 03 Rev Date: 21.04.2016
Doc Type: Form Issued Date: 03.05.2016
Page 8 of 11
Doc Ref No.: MPF-QHSE-008
Job Safety Analysis /Risk Assessment Form Revision: 03 Rev Date: 21.04.2016
Doc Type: Form Issued Date: 03.05.2016
TBT, JSA
Lack of pinch points Pinch points awareness
awareness Correct PPE
Rigging failure Effective hand and body
placement
Equipment failure
Certified rigging
Pinch point Incorrect PPE
Pre-use inspection of rigging
Dropped object Congested deck Barrier off deck area
Uncontrol/swinging Incompetent personnel Essential personnel only
Make up load
Incorrect hand and Competent personnel
connection of first Manual handling body position Good tagline management if
end Cobra head to Slip trip & fall
Ineffective Injury personnel taglines required
HFLDF Collision Communication Good manual handling technique
Damage to
7 Exceeeding Manual lifting 3 1 2 3 3 3 9 Effective communication 2 3 6
Pick up second end equipment
minimum bend Effective housekeeping
Cobra head from Complicated
radius of the HFL Effective co-ordination to be
carousel with crane lift/movement on deck
and connect to Excessive load maintained between crane,
transferred to the Poor housekeeping tensioner and carousel. No load
HFLDF
carousel Vessel motion to be taken by carousel.
Fall from height Ineffective co- WAH PTW
ordination of crane, Safety harnesses to be used
tensioner and carousel Use Safe working platform
operations Personnel awareness of escape
Working at height routes
360 degree awareness
Line of fire awareness
Page 9 of 11
Doc Ref No.: MPF-QHSE-008
Job Safety Analysis /Risk Assessment Form Revision: 03 Rev Date: 21.04.2016
Doc Type: Form Issued Date: 03.05.2016
PROBABILITY
To the best To the best To the best To the best To the best
knowledge of the knowledge of the knowledge of the knowledge of knowledge of the
risk assessment risk assessment risk assessment the risk risk assessment
team the hazard team the hazard team the hazard assessment team the hazard
has not occurred has occurred occurs annually team the is predicted to
within industry & within industry at within the offshore hazard occur at least
Project Schedule (S) circumstances least once but it is industry and/or MPL regularly occurs once during
Description People (P) Environment (E) Asset (A)
when it could not likely that the and the conditions more than once course of the
occur cannot be conditions needed needed for a year within work unless
foreseen for this for recurrence will recurrence may the offshore changes are
task. manifest occur if additional industry and/or made
themselves. factors are present MPL and is
likely to occur
during the task
Page 10 of 11
Doc Ref No.: MPF-QHSE-008
Job Safety Analysis /Risk Assessment Form Revision: 03 Rev Date: 21.04.2016
Doc Type: Form Issued Date: 03.05.2016
1. 1–6 LOW RISKS These are tolerable risks with appropriate control measures in place. The control measures are monitored on routine
basis
2. 8 – 12 MEDIUM RISKS Greater residual risk than Low but remains tolerable with full & effective implementation of control measures. Must
be monitored through with adequate supervision
3. 15 – 25 HIGH RISKS Intolerable if the risks involve hazards to personnel or environment. Must be mitigated further or the work cancelled.
May be tolerable if it only involves hazards to equipment, schedule or facility availability. This must be approved by
the relevant Line Manager and/or Client and documented prior to the work going ahead.
Page 11 of 11