004cost MGMT Procedures
004cost MGMT Procedures
004cost MGMT Procedures
2 0 0 1 E D I T I O N
Cost Management
Procedures
Construction Management
Association of America
7926 Jones Branch Drive, Suite 800
McLean, Virginia 22102-3307 USA
703/356-2622 • FAX: 703/356-6388
www.cmaanet.org
Preface
4.0 Estimating............................................................................................................................................................................ 20
4.1 Selection of Estimating Techniques ..................................................................................................... 20
4.2 Identifying Factors for Conceptual Estimating .................................................................................... 22
4.3 Parameters for Cost Estimating ........................................................................................................... 22
4.4 Concepts of Range Estimating ............................................................................................................. 26
4.5 Quantity Survey-Based Cost Estimate and Procurement Strategies ................................................... 26
4.6 Applications of Quantity Surveys to Cost Estimating .......................................................................... 27
4.7 Summary .............................................................................................................................................. 27
Page 1
CMAA: Cost Management Procedures
Cost control systems and procedures should be consistent with, whenever practical, the
owner’s code of cost accounts. These systems and procedures should also reflect the need of the
owner and the CM to collect cost data in a timely manner and report it in a usable format.
Page 2
CMAA: Cost Management Procedures
2.1 Introduction
Cost management begins at project inception. Virtually as soon as the project owner conceives
of a project concept someone needs to start considering costs. Few project owners ever have
unlimited funds. Most project owners are looking for positive Return on Investment (ROI) and
thus need to constantly monitor project cost to determine whether they will be able to obtain
their desired ROI.
The Standards recommend a preliminary cost investigation. This is discussed as a cost
management plan assembled by the CM early in the pre-design phase which includes all cost
components of the project (e.g., pre-design, design, construction, operation and maintenance,
life cycle costs, etc.). Once developed, this cost management plan should be provided to the
owner and all other members of the team that have been brought aboard the project, for their
review and approval.
Buy-in by all team participants is vital to the success of the cost management plan. From the
outset of the project, all project participants must be working toward project delivery within the
limits of the approved cost management plan and project budget. After each party approves the
cost plan, it becomes the basis and the framework within which the costs of the project are
monitored and controlled throughout the planning, design and construction processes.
Page 3
CMAA: Cost Management Procedures
preliminary estimates, feasibility estimates, order of magnitude estimates, and economic study
methods for performing conceptual estimates:
• Analogous Estimating (Top Down Estimating)—Uses actual costs of similar previously
performed projects as a basis for estimating the cost of this project. When using this form of
estimating, some judgment may have to be applied insofar as project location, project
timing, etc. may cause some adjustments to the cost of the previous project.
• Parametric Modeling—This form of estimating uses known project characteristics
(parameters) in a mathematical equation to arrive at current project costs. Square footage
cost, per bed cost, megawatt cost, etc. may all be used in parametric modeling to arrive at a
conceptual estimate.
• Bottom Up Estimating—The technique involves estimating the cost of individual project
components and then summing the total of the project component estimates. For example,
in a wastewater treatment plant, the estimator may be able to independently estimate the
component costs for primary clarifiers and extended aeration basins on a million gallon per
day basis, and then factor in costs for headworks and screening, yard piping and electrical,
disinfection facilities and discharge piping. Having arrived at a conceptual estimate for each
component of the system, the estimator can sum the component costs to arrive at a
conceptual cost.
• Computerized Estimating —More common today than ever, there are a number of
computer software systems on the market that have national cost databases embedded
within them. The estimator can start by inserting conceptual project information into these
computer models and arrive at a conceptual estimate based on the data contained within
the software.
There are, undoubtedly, other conceptual budgeting techniques available for estimators,
but the above covers those most commonly used.
Page 4
CMAA: Cost Management Procedures
Page 5
CMAA: Cost Management Procedures
Page 6
CMAA: Cost Management Procedures
Page 7
CMAA: Cost Management Procedures
Page 8
CMAA: Cost Management Procedures
2
See Chapter 13, “Cost Engineering”, pages 307 – 331.
Page 9
CMAA: Cost Management Procedures
Project or Funtion
Account Number
Financial Information
Cost Elements
Work by Contractor/Subcontractor/Owner
Work Element Detail Designator
Work Element Detail
Standard Work Element
Subfacility/Subarea Designator
Facility/Area/Major work Division
Project Identifier
If the owner does not have a standard WBS, one should be developed and provided by the CM,
subject to approval by the owner. The WBS system employed on the project should be
consistent with the components of the project and acceptable to all members of the project
team.
The CM should review all budgets for completeness and compatibility with established cost
limitations for the project and attainability. This latter check (attainability) has to do with
managing the owner’s expectations. (Most CMs are familiar with the old story of the owner who
wants a world class cathedral for the cost of a New England clapboard church. This can happen
if project expectations are not managed properly from the outset.) Management of owner
expectations starts with the preliminary construction estimate and the ability to fit the project
into the budget.
The CM should review its findings with the owner and the designer and make necessary
adjustments. It is critical, for cost control purposes, that the assumptions made in preparation
of the project and construction budgets be clearly identified and listed. Equally critical are those
items excluded from the project and construction budgets.
3
Adopted from Barrie and Paulson, page 309.
4
It is beyond the scope of this Procedure Manual to discuss how a WBS system should be formulated. If more information
on development of WBS systems is desired, the reader is referred to PMI’s Practice Standard for Work Breakdown
Structures.
Page 10
CMAA: Cost Management Procedures
2.14 Summary
The criticality of project budgeting cannot be overemphasized. Analysis of project “failures” all
too often leads to the conclusion that an inadequate project budget was established at the outset,
thus dooming the project. If the CM does nothing more than help the owner and the design
team establish a realistic project budget which adequately takes into consideration the owner’s
goals and objectives, a reasonable procurement strategy and known project constraints, then
the CM will have performed an outstanding service. This is a far harder challenge than this
section may have indicated. Unreasonable expectations, unidentified constraints, fuzzy
understanding of procurement requirements can all lead to unrealistic project budgets.
Page 11
CMAA: Cost Management Procedures
Page 12
CMAA: Cost Management Procedures
Page 13
CMAA: Cost Management Procedures
house? To save on equipment costs and project delivery time, is it the owner’s policy to pre-
purchase large equipment items and provide them to the contractor for installation into the
project?
Once the resources needed to deliver the project are identified, the CM needs to estimate the
costs of the necessary resources. Using the previously established WBS system and resource
requirements list, the CM needs to associate costs with each identified resource. The CM can use
known resource rates, historical information, cost databases, etc. to estimate the cost of the
resources leading to a project budget.
The outcome of resource planning and cost estimating is the development of a cost plan for
the project which includes the total project cost for presentation to the owner. The cost plan,
then, is the total anticipated project budget, which includes, as best as can be estimated, all costs
related to the project. Included in the cost plan are the expected cost of planning, design,
construction, land cost, permit fees, financing costs, etc. Upon acceptance by the owner, the cost
plan becomes the budget for the project. Based on this budget, performance of the project will
be continuously monitored and measured.
Page 14
CMAA: Cost Management Procedures
When dealing with publicly funded projects, it is fairly uncommon for the CM to be dealing
with a revenue generating project. Construction of a wastewater or water treatment facility,
police or fire station, school or library is not generally based upon the same sort of calculation as
a commercial project. Typically, a feasibility study for a publicly funded project is trying to
determine the most cost effective manner in which to deliver the project. Publicly funded
projects are generally driven by the needs of the public (e.g., more schools, better highways,
etc.) or by government regulation (e.g., air, water, wastewater, solid waste regulations, etc.). In
cases such as these, the determination to perform the project has already been made and the
role of the CM is to help the public owner deliver the project in the most cost-effective manner.
Sometimes public projects are desirable but not regulatory driven. For example, a performing
arts center may be politically desirable for a municipality, but is hardly forced on a city by
government mandate. If this is the case, then the role of the CM in preparing the early or
conceptual cost estimate is to help the owner determine how much funding is necessary to
deliver this project. In cases such as this, it is not uncommon for the CM to be working with the
municipality’s bond counsel as the results of the conceptual estimates are often used to
determine the amount of bonds to be sold.
Page 15
CMAA: Cost Management Procedures
depending on which cash flow the owner wants the CM to develop) and the conceptual project
schedule. The CM will plot the money spent versus the time to create a classic S curve depicting
anticipated cash flow requirements.
The methodology for preparation of a cash schedule is simple in theory. It starts with
preparation of a basic project schedule. Discrete activities must be defined by the CM, including
scope of work and duration. Once this portion of the exercise is completed, the CM must cost
load each line item or schedule activity. That is, the CM must prepare a cost estimate for each
activity on the schedule. Once activities and costs are plotted on the schedule, the cash flow of
the project can be determined on a weekly or monthly basis, or any other basis the owner wants
to use.
Perhaps the more difficult part of projecting project cash flow lies in the realm of judgement
concerning how the project itself will expend monies. The most simplistic cash flow analysis
assumes a straight-line cash flow. That is, the assumption is that cash will flow equally
throughout the life of the project. Using this assumption, on a $10.0 million, 18-month project,
the assumption is that cash will be used at the rate of $555,556/month, and on some projects
this may actually be correct. The more likely scenario is that cash flow will be considerably less
during the first two or three months of the project, increasing over time to a peak cash flow in
the middle of the project and decreasing toward project’s end. (This is the classic bell-shaped
curve.) The CM should perform this type of analysis when preparing the cash flow schedule.
Two variations of the bell-shaped curve are front-end loaded or back-end loaded cash flow
curves. These types of cash flow schedules develop when there is a good deal of equipment buy
out and installation either very early or very late in the project, thus skewing the project’s cash
flow. Again, the CM must perform this analysis based upon experience and knowledge of the
project.
Page 16
CMAA: Cost Management Procedures
from the contractor only, there is no reason why an identical requirement could not be
levied on the designer. This would allow the CM to monitor design costs.)
• Cost Trending—For each cost element of the project and/or the total project cost itself, the
CM prepares a series of Estimate at Completion (EAC) calculations using the following
model.
EAC = Actual Cost of Work + Remaining Budget
Performed to Date
or
EAC = Actual Cost of Work + (Remaining Budget/Cost Performance Index)
Performed to Date
If the CM performs such calculations on a routine basis, the results can be trended and
reported upon.
• Earned Value Calculations—Earned value has been defined as a method for determining
overall percent complete for a combination of unlike work tasks or an entire project. (See
Skills and Knowledge of Cost Engineering.) Under the earned value concept, a direct
relationship is established between percent complete of an activity and the budget for that
activity.
Earned Value = (Percent complete) x (Budget for that activity)
Percent Complete = (Earned workhours or dollars for all activities)
(Budgeted workhours or dollars for all activities)
Cost and Schedule Performance can then be monitored and reported on using the following
equations.
Budgeted Cost for Work Scheduled (BCWS) = Budgeted workhours or dollars-to-
date represent what is planned to be done.
Budgeted Cost for Work Performed (BCWP) = Earned workhours or dollars-to-date
represent what was actually done.
Actual Cost of Work Performed (ACWP) = Actual workhours or dollars-to-date
represent what was paid for.
Performance against schedule is simply a comparison of what was planned versus what was
done. Performance against budget is measured by comparing what was done to what was paid
for. These relationships are expressed using the following formulas:
Schedule Variance (SV) = (Earned workhours or dollars) – (Budgeted workhours or
dollars) = BCWP - BCWS
Schedule Performance Index (SPI) = (Earned workhours or dollars to date)/
(budgeted workhours or dollars to date) = BCWP/BCWS
Cost Variance (CV) = (Earned workhours or dollars) – (Actual workhours or dollars)
= BCWP – ACWP
Page 17
CMAA: Cost Management Procedures
Page 18
CMAA: Cost Management Procedures
3.11 Summary
The intended purpose of a cost management system is to establish a system and provide tools
that allow the owner and the CM to manage the project budget. It is not sufficient to establish a
realistic budget. Tools are needed to manage the project in such a way as to ensure that the
project is actually delivered within the accepted budget. Tools such as feasibility studies, cash
flow schedules and cost models are all available to help establish and then manage the project
budget. These tools need to be employed throughout the project if the CM is to employ an
effective cost management system
Page 19
CMAA: Cost Management Procedures
4.0 Estimating
4.1 Selection of Estimating Techniques
As Ritz noted in Total Construction Project Management, the basis of the cost management plan
for a project is a reliable project cost estimate, which is the predicted cost of constructing the
project. As such, the cost estimate should be neither optimistic nor pessimistic. The CM should
set forth its assumptions in making the estimate with respect to scope of work, contracting plan,
schedule, labor productivity, construction techniques, estimating methods, etc. Based on this
information, users of the estimate can make their own judgement concerning reliability and
accuracy.
There are different types of estimates used in construction management at various stages of
the project. Ritz identifies four types of estimates while AACEI identifies three, as follows:
Ritz AACEI
Type of Estimate Accuracy Type of Estimate Accuracy
Feasibility Estimates +/- 25 to 30% Order of Magnitude Estimate +50% to -30%
Appropriation Estimates +/- 15 to 25% Budget Estimates +30% to -15%
Capital Cost Estimates +/- 10 to 15%
Definitive Estimates +/- 5% Definitive Estimates +15% to -5%
Depending on which type of estimate is being prepared, the CM has a range of techniques
available. Some examples of estimating techniques which the CM can utilize include the
following:
• In-House Estimating Data Files—CM firms with a history of multiple projects of a
similar type in the past can take past construction cost data and update it for current time
and a specific location.
• Outside Estimating Software Data Files—If the CM does not have much experience with
a particular project type, specific data by project type and location can be purchased from
outside vendors for use in the CM’s computerized estimating system.
• Outside Estimating Services—An alternative is to hire the services of an outside
estimating firm and provide it all known project data. This outside service then produces
the estimate and sends it back to the CM.
• Standard Cost Indexes—Standard cost data can be obtained from a number of sources.
Use of this cost data as modified by the local knowledge and experience of the CM can assist
in producing a reliable cost estimate. Cost indexes available include the following:
General Purpose Cost Indexes—These can be obtained from Engineering News-
Record, the Department of Commerce, the Bureau of Reclamation, R.S. Means
Construction Cost Data, Richardson Estimating Services, Conceptual Cost
Estimating, etc.
Page 20
CMAA: Cost Management Procedures
5
See Lang, “Simplified Approach to Preliminary Cost Estimates”, Chemical Engineering, June 1948.
6
See Hand, “Estimating Capital costs from Process Flow Sheets”, AACEI Cost Engineers Notebook or “From Flow Sheet to
Cost Estimate”, Petroleum Refiner, September 1958.
Page 21
CMAA: Cost Management Procedures
• Parametric Estimates—As the name indicates, this type of estimate is based on certain
parameters that reflect the size or scope of the project. Parametric estimates are most
commonly used in the building construction industry for preparing approximate estimates.
Typically, parametric estimates are used after the preliminary design phase is completed.
• Quantity Take-Off Method—This is the most detailed type of estimate. To perform this
estimate the CM has to have the completed design documents in order to take off or
measure and catalogue the various quantities of work to be performed. To this sum the CM
then adds in labor, labor productivity, equipment, overhead, etc.
There may be other methodologies used in estimating costs. As the amount of project
information available increases, so does the amount of effort necessary to perform an estimate,
as does the accuracy of the estimate itself.
Page 22
CMAA: Cost Management Procedures
Page 23
CMAA: Cost Management Procedures
Labor, including:
Direct wages
Fringe benefits
Labor taxes
Other labor burdens
Labor productivity
Labor supervision
Materials, including:
Quantity take-off amounts
Delivery costs
Taxes
Major equipment
Finalized sizes
Materials
Appurtenances
Equipment, including:
Mobilization
Demobilization
Fuel, oil and gas
Maintenance
Subcontractor bids and quotes, including exceptions
Field general conditions, including:
Bonds
Permits
Insurance
Mobilization
Professional services (i.e., scheduling, structural engineering, etc.)
Safety equipment
Small tools and expendables
Field supervisory staff
Temporary facilities
Travel and lodging
Miscellaneous costs (i.e., clean-up, punchlist, etc.)
Demobilization
Page 24
CMAA: Cost Management Procedures
Page 25
CMAA: Cost Management Procedures
As noted above, different types of projects may call for different cost estimating parameters.
The CM should become aware of these differences when preparing the take-off.
Page 26
CMAA: Cost Management Procedures
This is the classic unit price contract. The bidder has the right of reliance on the quantity
take-off and the units listed and need not perform its own take-off to validate the accuracy of the
take-off provided. In such a system, each unit price must be “fully loaded” (i.e., direct costs,
overhead costs, contingency costs, profit, etc.). Typically, the contract is awarded to the bidder
with the lowest total price based on price extensions and additions of all unit prices quoted.
Based on this system, it can be said that there is no exact contract sum at the time of bidding.
What the owner has are the unit prices provided by the bidder and the estimated units. As the
units increase or decrease, so does the contract cost.
During the life of the contract, the contractor is paid on the basis of units installed into the
project. Units installed are typically calculated by the quantity surveyor based on field surveys of
work in progress. At the end of the job, the final units installed are surveyed and paid for. In
some contracting systems, this requires a “final quantity adjustment change order” to adjust the
contract amount to equal the actual units installed.
4.7 Summary
There are a wide variety of cost estimating techniques available to the CM. They range from
quite simple to very complex and, depending upon when they are applied in the project’s life,
have varying degrees of reliability. The objective of the CM should be to gather all pertinent
information and apply the best technique available at the appropriate stage of the project. This
should be done in order to keep project cost estimates as up-to-date as possible. The CM must
keep refining the project cost estimate in order to keep the owner properly informed concerning
the status of the budget. The various estimating techniques set forth in this section are all
available to accomplish this goal.
Page 27
CMAA: Cost Management Procedures
Page 28
CMAA: Cost Management Procedures
Page 29
CMAA: Cost Management Procedures
Other cost monitoring requirements can be written into the contract documents, provided
that the owner and the CM determine which cost elements are to be monitored prior to the
project bidding.
5.6 Summary
A key role the CM can fulfill on a project is to recommend cost monitoring techniques to the
project owner. CMs are aware of the need to monitor costs in order to ascertain compliance with
the budget. CMs should generally be aware of how to monitor costs on a project. Action needs to
be taken early in a project to determine what costs should be monitored, when they should be
monitored, how they should be reported and what actions should be taken in the event cost
variances arise. The time to establish a cost monitoring system is at the beginning of the project,
not once cost variances have been identified.
Page 30
CMAA: Cost Management Procedures
Page 31
CMAA: Cost Management Procedures
of sources from which estimated cost escalation data can be obtained. All escalation data should
be carefully reviewed.
To verify that the project remains within the construction and project budgets, it is
recommended that (at a minimum) the following estimates be prepared by the CM at the
various stages of the design process:
• Program estimate at planning completion—Upon completion of the planning process,
and prior to initiation of design, the CM should prepare a program estimate. Such an
estimate is intended to assess the probable cost of the approved plan. The purpose of this
estimate is to determine whether the plan can be delivered within approved budgetary
constraints.
• Completion of schematic design—The CM should prepare a schematic design cost
estimate based on measurement of parameter quantities from the designer’s schematic
design stage submittal. It may also be possible to measure approximate quantities for
certain elements of the project at this stage.
• Completion of preliminary design—The CM should prepare a preliminary design cost
estimate based on measurement of approximate or parameter quantities from the
designer’s preliminary design submittal. As the mechanical and electrical designs typically
lag behind the civil, architectural and structural designs, preliminary design estimates often
contain approximate quantities for the architectural, structural and civil works and
parameter quantities for the mechanical and electrical components.
• In-progress final design (this may vary from 60% to 90% complete)—Cost estimates
prepared from working drawings and specifications should be based on quantity estimates
for all major components. Any alternates to be called out in the bidding documents should
also be quantified and estimated, as they become known during the design phase.
• Completion of bidding documents (including any bid addenda issued)—At
completion of the bidding documents, the CM should prepare the definitive estimate for
use by the owner in establishing its project construction budget. This estimate should
include quantities for all portions of the designed project plus an estimate of allowable
contingency during construction. Although bids should be received shortly after this point,
this cost estimate is necessary for many owners in order to advertise for bids. For example,
many states require that a public owner have a formal written estimate of the final design
prior to advertising for bids. Some public owners require such estimates in order for the
county or city council to pass the formal motion authorizing bid advertisement.
Each project must be evaluated based on its unique conditions and characteristics. Design
contingencies should be set for each of these cost verification stages. The design contingency
level should reflect the level of accuracy it is reasonable to expect from cost estimates at the
various stages of the project’s development. The project team should work together to develop
the percentage allowable for design and construction contingencies on an individual project
basis.
Page 32
CMAA: Cost Management Procedures
Page 33
CMAA: Cost Management Procedures
Page 34
CMAA: Cost Management Procedures
6.6 Summary
Cost management must be practiced during the project’s planning and design phases, not
started only after construction commences. The CM needs to manage costs throughout the
entire life of the project. Most of the largest changes to the project are likely to be made during
the preconstruction phase of the project. In order to maintain project budget, the CM must
monitor changes during design and estimate and report on their likely impact to overall
project cost.
Page 35
CMAA: Cost Management Procedures
8
An uncommon but excellent strategy to keep in check unreasonable claims from contractors for delay damages is to add to
the bid form a section requiring the bidder to quantify their damages per day for every day the project is delayed.
Page 36
CMAA: Cost Management Procedures
Schwartzkopf concludes that average cost growth will be in the range of 5% to 10%. It is,
therefore, recommended that a 10% contingency fund be created at the time of contract award
to provide for cost growth. If the project is a remodel of an existing facility, perhaps the
contingency amount should be higher due to the likelihood of unforeseen conditions.
9
See pages 44 – 48.
10
Studied US Army Corps of Engineers and Naval Facilities Engineering Command.
11
Studied 59,155 private projects over 8 year period.
12
Studied 21,934 State and local government projects over same 8 year period, but many were unit priced contracts.
Page 37
CMAA: Cost Management Procedures
Page 38
CMAA: Cost Management Procedures
One way for the CM to exercise control over contingency funds is to establish a specific
contingency account. Once this account is established a formal policy statement should be
issued concerning who can commit the funds and under what circumstances the funds can be
committed. Finally, a formal routine part of the cost reporting system should be a report on the
status of the contingency funds.
13
It should be noted that when a contract is bid on a unit price basis, no separate schedule of values is required, as the
listing of unit prices constitutes the schedule of values.
Page 39
CMAA: Cost Management Procedures
offset bidding, bonding, mobilization and other early job costs which are typically not
reimbursed by the owner as pay items under the contract. Mobilization payments are
sometimes used in order to avoid the issue of front end loading. Finally, the schedule of values
should be detailed enough to allow accurate evaluation of progress payments throughout the life
of the project. Once established, the schedule of values should reduce payment disputes.
14
A practice becoming more commonplace is for the CM to make the determination of the contractor’s progress for each
activity in preparation of the application for payment. The contractor’s responsibility is to accept the CM’s observations
or discuss any differences of opinion.
Page 40
CMAA: Cost Management Procedures
the cost of the project. For example, a clause may be included in the contract documents that no
activity can have a value exceeding 1% of the cost of the project.
The advantage of this system is that the schedule of values is more discrete and can be more
readily used for change order pricing. The disadvantage to this approach is that the schedule of
values will be considerably longer and more complex. In any event, if the CM and the owner
choose to use this system, the requirement must be clearly included in the bidding documents
so that all bidders are aware of the requirement.
The contractor will develop the cost-loaded schedule by allocating the cost details of its bid to
the construction schedule. Such cost loading requires that the contractor allocate its general
conditions cost or field office overhead costs to the activities on the schedule. It must also
allocate markup costs (i.e., home office overhead, contingency and profit) and bond costs to the
activities on the schedule.
Once the baseline schedule and cost loading are approved, the monthly payment application
process will, of necessity, include submittal of an updated schedule showing the status of all pay
items accomplished during the reporting period. The CM will have to review the schedule
update for accuracy with respect to both time and percentage of completion for all activities
worked on during the reporting period.
In the event that a schedule activity is started but not completed within the monthly
reporting period, the contractor will status that activity with the percentage complete status.
The completion percentage times the activity value yields the payment amount owed less
applicable retainage. The CM’s role, in such a situation, is to review and confirm the percentage
completion claimed.
Page 41
CMAA: Cost Management Procedures
• Written notice requirements—The contract documents should have strong, strict and
enforceable written notice requirements. That is, whenever the contractor believes it has
been directed to make a change to the work without receipt of a properly executed change
order, it is required to notify the CM in writing and await the CM’s direction concerning the
changed work. This gives the CM the ability to stop those actions, which may be a change,
but are not warranted, justified, or intended.
• Written change order requirement—Contract language should be included which states
the contractor is not entitled to payment for changed work unless it is in receipt of a
properly executed change order or a written directive to proceed with the changed work.
This is intended to stop “verbal changes” to the work because the contract alerts the
contractor to the fact that it may not be able to recover on a verbal change directive. On the
other hand, the CM and the owner will be required to create a set of change documents and
use them promptly when they want changed work performed.
• Project warrants—One of the more common occurrences in the industry is when the
contractor advises the CM that “your inspector ordered me to make this change, so you owe
me.” The CM often responds with the statement that “inspectors have no authority to issue
changes” and the contractor responds with “how was I supposed to know that?” To avoid
such arguments, each project team member authorized to deal with the contractor should
have a “warrant” (a written document) signed by the owner setting forth their duties and
responsibilities. Some warrants may say, “This individual has no authority to issue or
direct changes to the work”. Other warrants may limit the individual’s authority to changes
not to exceed a certain sum. The concept is to let everyone on the project know who has
authority to direct changes and who does not, a point that is delineated in the project’s
procedures manual.
• Delegation of authority—One of the major problems with changes is the amount of time
to process them through many owners’ organizations. Delay in the decision making process
concerning changes can be very expensive in the long run. To avoid such situations, the CM
and the owner may negotiate a delegation of authority policy. For example, a field project
manager may have authority to issue change orders with a value not to exceed $25,000 on
their own signature. The head of the CM team may be delegated authority up to $50,000,
while all changes over this amount may have to go to the owner’s governing board. The idea
is that if delay in change orders can be reduced, the cost of the changes can also be kept
down.
• Change Control Board—On some megaprojects, Change Order Control Boards are
created for the specific purpose of reviewing and approving the larger, more complex,
design-related changes. Typically these are changes that are beyond the expertise of the CM
and have a potential for design related ramifications. Such boards are often modeled on the
old Configuration Management or Configuration Control Boards initially used by the
Department of Defense in the 1960’s. Such Boards are generally made up of senior staff
involved in project design and operations, along with top management officials from the
owner staff who have ultimate budget authority and responsibility. Those individuals
proposing such major changes must present persuasive arguments concerning the
Page 42
CMAA: Cost Management Procedures
proposed change to the Board, along with appropriate supporting data. The Board will
convene to consider such proposed changes, recognizing that each change before it is large,
complex and will, if approved, change the basis of design. The Board will also understand
that such changes will likely have a significant impact on the project budget. The role of the
CM in situations such as this is most likely to be limited to preparing revised budget and
schedule estimates for the Board prior to its meeting to help it understand the potential
budget and schedule ramifications of each potential change.
• Change Order Policy—Some owners have established a policy that whoever proposes the
change order has to personally appear before the owner’s decision- making body to justify
why the change should be made. The practical effect of such a policy is to put a lot of
pressure on project team members not to make changes unless they are truly needed.
• Budget contingency—All CMs are aware that change is going to happen during
construction. Most owners know this as well. However, some owners fail to establish a
budget contingency at the time of award to handle the cost of changes. The failure to do so
may cause delay in the issuance of changes while appropriate funding is arranged which in
turn, can cause the cost of the changes to increase. The CM should work with the owner
during the time between bid opening and contract award to establish a management
reserve or budget contingency to handle changes to the work. A process also should be in
place to refill the budget contingency if, during the course of the project, the initial
contingency funds are entirely depleted.
There probably are additional change order control mechanisms that can be employed.
During the design period the CM should consider all possibilities, discuss them with the owner,
and reach an understanding on how change will be controlled once the project goes into the
construction phase.
Page 43
CMAA: Cost Management Procedures
crew composition, hours and equipment. Material cost should be listed and substantiated
with written cost quotations and price lists. Markup including overhead, profit and bond
should be added. If this can be accomplished successfully between the owner and the
contractor, “mutual accord and satisfaction” language can be included in the change order.
• Actual Pricing—This is sometimes referred to as force account or time and materials
(T&M) work. The pricing is done while the changed work is being performed and, thus,
represents actual costs based on job cost records of manhours consumed and material and
equipment used. Comprehensive cost records are imperative. On force account or T&M
work, the work should also be documented and verified daily by both the CM and the
contractor.
• Post or Retroactive Pricing—Change order pricing is done after the work has been
completed and no records were maintained nor were job cost records segregated between
base contract and changed work. Cost estimates, similar to forward pricing, are produced
to quantify the scope and cost of the work. This scenario often occurs because the
contractor does not provide timely notice of the change and the work has been performed
before the CM got involved.
In forward pricing of change order work, the CM should consider the following special
factors when evaluating labor production rates:
• Status and condition of the work
• Relative size and capability of the contractor
• Size and complexity of the change
• Climatic conditions
• Mechanization possible
• Labor agreements
• Trade practices
• Learning curve
• Additional supervision required by the change
When evaluating material and equipment costs, the CM should consider the following special
factors:
• Value of salvaged material
• Odd lot sizes that add to cost
• Special delivery costs
• Potential higher price for proprietary items
• Cost escalation since bid opening
• Storage costs that may be necessary
Page 44
CMAA: Cost Management Procedures
Page 45
CMAA: Cost Management Procedures
7.10 Summary
Cost management during project construction is one of the primary responsibilities and most
important roles the CM can fulfill. The CM needs to establish formal cost monitoring and
management procedures for the project; help develop realistic schedules of value; and process
payment applications rapidly. Additionally, the CM should establish an effective system to
control change orders and contain both scope creep and cost growth. Finally, the CM should
implement a system for evaluating the cost of legitimate claims in order to successfully
negotiate resolution of such situations.
Page 46
CMAA: Cost Management Procedures
Page 47
CMAA: Cost Management Procedures
“When changes are issued after the start of a project, it may be possible to measure the
impact of the changes using a measured mile analysis. A measured mile analysis compares an
unimpacted portion of the project with the impacted portion. If a sufficient portion of the
project has been performed prior to the changes and the work quantities are known, then it may
be possible to calculate a productivity baseline by taking the physical units of work installed and
multiplying by the estimated unit rates to determine the earned hours. The earned manhours
are then compared with the actual manhours expended. The manhours expended during the
impact period can then be compared to the manhours earned during the impact period by
taking the units performed during the impact period and extending them by the estimated unit
manhour rates. This ratio can be compared with the baseline ratio. This allows a comparison of
the productivity between the two periods so the productivity impact of change orders can be
quantified. This type of measured mile analysis is termed an earned value analysis.
When unit rate productivity data is available for the same type of work for both periods, a
similar analysis can be done. The measured mile analysis in simplified form is illustrated in the
following formula:
Productivity Change = Unit Productivity Rate During Impacted Period
Unit Productivity Rate During Unimpacted Period
The advantage of this type of analysis is that it factors out all estimating issues because it
focuses only on actual unit costs during an unimpacted period and actual unit costs during an
impacted period. It can be difficult to find unimpacted areas on projects that are complex and
suffer compounding problems.”
Schwartzkopf goes on to point out that when performing such a study, the CM needs to
isolate and attempt to factor out other cost variables which can affect labor productivity but
which are not related to changes in the work. Among the factors listed, Schwartzkopf includes
the following:
• Weather
• Contractor management problems
• Extended overtime
• Acceleration
• Delay
• Crowding of trades
• Type of work being performed
Schwartzkopf concludes his discussion of this type of cost calculation with the statement that
while it can be difficult to find unimpacted work and isolate these other factors, “…actual
measurements of productivity variances are often superior to predicted measures of
productivity loss”.
Page 48
CMAA: Cost Management Procedures
In the event that a measured mile analysis is not possible on a project, the CM may be
required to use alternative analytical techniques such as the national studies referred to above as
modified by the factors Schwartzkopf mentions; comparison studies of this project with other
similar projects; or comparison of this project with historical databases, etc.
15
The owner should include a provision in the bidding documents stating that it has the right to reject all bids and relet the
contract package.
Page 49
CMAA: Cost Management Procedures
alternates) and include them in the bidding documents along with appropriate instructions
in the Instructions to Bidders. At bid opening, the owner can choose these alternates in
order to “make the project fit the budget”. It should be noted that there might be some legal
limitations on the use of bid alternates.16 Owners need to check with legal counsel when
considering the use of bid alternates to ensure a thorough understanding of legal
requirements in their jurisdiction.
• Adjust the project budget to allow award of the contract.
Any and all recommendations made by the CM for contract award should be in writing,
giving the reasons for the decision and include copies of the bids and the bid comparison for the
owner’s use.
16
See, for example, Matter of John C. Grimberg Company, Comp. Gen. No. B-283013 (February 2, 2000).
17
For a more thorough discussion of unbalanced bidding see “Unbalanced Bids and Avoiding disputes Relating to Them”,
Frank A. Manzo and Steven Tell, 1997 Wiley Construction Law Update, Wiley Law Publications, New York.
Page 50
CMAA: Cost Management Procedures
arise if work that is improperly priced in the bid is subject to change; the change order pricing
may be skewed due to bid unbalancing. Problems also arise in negotiating an appropriate
schedule of values if bid unbalancing has occurred in a lump sum bid situation.
To protect themselves against unbalanced bids, owners often insert language in the
Instructions to Bidders to the effect that if the bid is considered unbalanced by the owner then
the owner has the right to declare the bid non-responsive and reject the bid. Notwithstanding
such language in the bidding documents, courts have not uniformly supported the owner’s right
to reject the bid for bid unbalancing.18 It appears that the bid must be “materially unbalanced”
or so substantially unbalanced as to materially harm the owner’s position if the contract is
awarded.
In their article Manzo and Tell offer five potential recommendations to discourage
unbalanced bids.
• Use of a mobilization payment line item in the bid to provide some up-front money and
alleviate, at least in part, the contractor’s need to front-end load the bid.
• Provide the low bidder the opportunity to rebalance the bid, provided that the total bid
amount does not change at all.
• Reject the unbalanced bid and award to the next lowest bidder.
• Use optional bid items to increase risk associated with unbalanced bids thus discouraging
them.
• Reject all bids and rebid the entire project.
In any event, the CM needs to be alert to this problem and guard against it at bid time. If it is
determined that the apparent low bid is unbalanced, this needs to be immediately called to the
attention of the owner and its legal counsel.
18
See, for example, Protest of Severn Companies, GSBCA No. 9353-P 88-3 B.C.A. (CCH) 20,850 (1988).
Page 51
CMAA: Cost Management Procedures
conjunction with the owner and the designer to limit scope creep and cost growth. The CM
must closely monitor owner, designer and contractor actions during construction to limit
cost growth.
The CM must focus on cost, monitor cost, detect cost variances and bring them to the
attention of the owner early enough that cost growth can be controlled and contained. On many
projects, the CM may be the only team member with an understanding of the issues involved
with cost management and cost control. Thus, on many projects, the CM is the only team
member who can fill this key role.
8.6 Summary
The final step in the overall cost management procedure is for the CM to establish and
implement a formal cost control system that encompasses the bidding and construction
process. The CM’s involvement in bid evaluations must include both conformance to bid
requirements as well as to cost control. During construction the CM must be involved in all
project communications in order to monitor the project for cost control purposes.
Page 52
CMAA: Cost Management Procedures
Page 53
CMAA: Cost Management Procedures
19
The definitions herein have been drawn from a draft, unpublished document entitled Glossary of Cost Management
Terms. This document is in the process of being published by the Association for the Advancement of Cost Engineering,
International, Morgantown, West Virginia.
Page 54
CMAA: Cost Management Procedures
Beneficial Occupancy—Use of a project by the owner for its intended purposes (i.e.,
functionally complete) although other contract work, nonessential to the function of the
occupied section, remains to be completed.
Benefit Cost Analysis—An analytical approach to solving problems of choice. It requires (a)
the definition of objectives; (b) identification of alternative ways of achieving each objective;
and (c) the identification for each objective or alternative which yields the required level of
benefits at the lowest cost. It is often referred to as Cost Effectiveness Analysis when the
benefits of the alternatives cannot be quantified in terms of dollars.
Benefit-to-Cost Ratio—Benefits divided by costs, where both are discounted to a present value
or equivalent uniform annual value.
Best Estimate—Usually, but not necessarily, the most likely value (the value that occurs most
frequently in a set of values).
Bid—An offer or a price to perform the work of a contract.
Bidding Documents—The advertisement for bids, instructions for bidders, information
available to bidders, bid form with all attachments, and proposed contract documents
(including all addenda issued prior to receipt of bids).
Boiler Plate—A popular slang term used to describe the standard language of a set of contract
documents (generally including the General Conditions and Requirements, Special Provisions
and Instructions to Bidders).
Bottom-Up Models—Uses a method of estimation that estimates each component of the
project separately and the results are combined (or rolled up) to produce an estimate of the
entire project.
Budget—A planned allocation of resources. The planned cost of needed materials is usually
subdivided into quantities required and unit costs. The planned cost of labor is usually divided
into the workhours required and the wage rates (plus fringe benefits and taxes).
Budget Authorization—An administrative action by management approving an operating
budget for use on the project.
Budget Cost of Work Performed (BCWP)—The sum of the budgets for completed portions of
in-process work, plus the appropriate portion of the budget for level of effort and apportioned
effort for the relevant time period. BCWP is commonly referred to as Earned Value.
Budget Cost of Work Scheduled (BCWS)—The sum of the budgets for work scheduled to be
accomplished (including work in process), plus the appropriate portion of the budget for level
of effort and apportioned effort for the relevant time period.
Budget Estimate—An estimate offered for budgetary and planning purposes only. It does not
constitute a firm commitment that the work can or will be accomplished for this amount.
Budgeting—The process of translating approved or negotiated resource requirements
(manpower, equipment and materials) into a funding profile or time-phased financial targets
and goals.
Page 55
CMAA: Cost Management Procedures
Capital Budgeting—A systematic procedure for classifying, evaluating and ranking proposed
capital expenditures for the purposes of comparison and selection, combined with the analysis
of the financial requirements.
Capital Expenditure—Expenditure made for the acquisition of or addition and betterments to
fixed assets.
Cash Flow—The net flow of dollars into or out of a project. The algebraic sum, in any time
period, of all cash receipts, expenses and investments.
Ceiling Price—The maximum exposure of a customer in any cost sharing relationship.
Change—Alteration or variation to a scope of work and/or the schedule for completing the
work.
Change in Scope—A change in objectives (either in quality or quantity of the specifications
and/or material), work plan, or schedule that results in a material difference from the terms of
an approved budget.
Change in Sequence—A change in the order of work initially specified or planned by the
contractor.
Change Order—A document directing a change in scope.
Claim—A written statement requesting additional time and/or money for acts or omissions
during the performance of the work.
Code of Accounts—A systematic numeric method of identifying various categories of costs
incurred in the progress of a job. The segregation of engineering, procurement, fabrication,
construction and associated project costs into elements for accounting purposes, for example.
Conceptual Schedule—A conceptual schedule is similar to a proposal schedule except that it is
usually time scaled and is developed from the preliminary design of the project.
Configuration—The arrangement of the parts or elements of a project.
Configuration Control or Management—The systematic evaluation, coordination, approval
or disapproval and implementation of all approved changes in the project after formal
establishment of the project configuration.
Consumables—Supplies and materials used up during construction including fuel and
lubricants, utilities, welding supplies, worker’s supplies, medical supplies, etc.
Contingency—An amount added to an estimate or a budget to allow for changes that
experience shows will likely be required.
Contingency Fund—Money set aside to provide for unforeseen expenditures or for anticipated
expenditures of an uncertain amount.
Contract Budget—The cost of the contract plus the actual or estimated cost for authorized
changes, which have not yet been fully priced.
Page 56
CMAA: Cost Management Procedures
Page 57
CMAA: Cost Management Procedures
Design to Cost—A management concept wherein rigorous cost goals are established during
project development and the control of systems costs to these goals is achieved by practical
tradeoffs between operational capability, performance, cost and schedule.
Detailed Estimating—The logical buildup of estimated hours and materials by use of design
documents, or other data whereby each operation is assigned a time value.
Deviation—A departure from established requirements; a nonconformance with contract
requirements; a variance from budgeted cost.
Duration—The time planned to accomplish an activity.
Earned Hours—The time in standard hours credited to a workman or group of workmen as a
result of their completion of a given task or group of tasks.
Earned Value—The periodic consistent measurement of work performed in terms of budget
planned for that work.
Empirical Cost Estimating—The step-by-step creation of a cost estimate based only on the
skills, knowledge, intuition and working files of a proficient cost estimator.
Enhancement—A change which increases the value of something.
Equitable Adjustment—A change in the contract price and/or time to compensate the
contractor for expense or delay incurred due to the actions or lack of action of the owner or the
owner’s representative or other occurrences, or to compensate the owner for contract
reductions.
Escalation—The provision in actual or estimated costs for an increase in the cost of
equipment, material, labor, etc. over that specified in the contract or estimate due to continuing
price level changes over time.
Estimate—To evaluate and calculate the approximate quantity, cost or extent of a given item or
task. Calculation of the total resources required to perform a task and the cost of such resources.
Estimated Cost—The conversion of estimates into dollars by the application of rates and
factors.
Estimated Cost at Completion—The current estimate of what the final cost will be for a
specific task consisting of actual costs-to-date plus the estimated cost of the remaining work to
be accomplished.
Factored Items—Labor or material estimated by the application of a factor to a labor base of
hours or dollars.
Feasibility Study—The study of the applicability or desirability of any management or
procedural system from the standpoint of advantages versus disadvantages in any given case.
Field Labor Overhead—The sum of the cost of payroll burden, temporary construction
facilities, consumables, field supervision and construction tools and equipment.
Field Order—A written order issued to the contractor which orders minor changes in the work
but which does not involve an adjustment in the contract time or price.
Page 58
CMAA: Cost Management Procedures
Forward Pricing—The prospective pricing of overhead and labor rates in advance of specific
contract negotiations.
Fragnet—A portion or fragment of a CPM network usually used to illustrate changes to the
whole network schedule.
General Overhead—The fixed cost in the operation of a business. General overhead is most
often associated with office, plant, equipment, staffing and expenses thereof, maintained by a
contractor for general business operations, which are not specifically applicable to any given job
or project.
Historical Cost Data—An estimating term used to describe a set of data reflecting actual costs
of past projects.
Home Office Cost—Those necessary costs involved in the conduct of everyday business which
can be directly assigned to specific projects or end products, such as engineering, procurement,
expediting, legal fees, audit fees, inspection, estimating, taxes, travel, reproduction,
communications, etc.
Idle Equipment Cost—The cost of equipment that remains on site ready for use but is placed
in a standby basis. Ownership or rental costs (but not operations costs) are still incurred even
while the equipment is idle.
Impact Cost—Added expenses due to the indirect results of a changed condition, delay, or
changes that are a consequence of the initial event. Examples of such costs include premium
time, lost efficiency and extended overhead costs.
Independent Cost Estimate—A cost estimate developed in organizational channels separate
and independent from program channels and having the express purpose of serving as an
analytical tool to validate or crosscheck program-developed estimates.
Interest Cost—The service charge for the use of money or capital, paid at agreed intervals by
the user and commonly expressed as an annual percentage of principal.
Job Cost—The cost arrived at by the method of cost accounting, which collects charges for
material, labor and allocated overhead in the production of a specific project.
Labor Burden—Taxes and insurance the employer is required to pay by law, based on labor
payroll, or on behalf of or for the benefit of labor.
Labor Factor—The ratio between the workhours actually required to perform a task under
project conditions and the workhours required to perform an identical task under standard
conditions.
Labor Productivity—The rate of output of a workman or groups of workers per unit of time,
usually compared to an established standard or expected rate of output.
Labor Variance —The difference between the standard hours priced at the standard rate and
the actual hours priced either at the standard or the actual rate.
Life Cycle—The stages and processes through which a project passes during its development
and full operational use, or the useful life of a project.
Page 59
CMAA: Cost Management Procedures
Life Cycle Cost—The total cost to the owner of the planning, design, construction and
operation of a project over its complete life cycle, including disposal (if appropriate).
Life Cycle Cost Estimate—A cost estimate that covers all costs projected for the project’s life
cycle.
Location Factor—An estimating factor used to convert the cost of an identical project from
one location to another. The factor takes into consideration the impact of climatic conditions,
local infrastructure, local soil conditions, safety and environmental regulations, taxation and
insurance regulations, labor availability and productivity, etc.
Management Control Systems—The systems (e.g., planning, scheduling, budgeting,
estimating, work authorization, cost accumulation, performance measurements, etc.) used by
owners, designers, construction managers and contractor to plan and control the cost and
scheduling of the work of a project.
Management Information System (MIS)—An orderly and disciplined accounting and
reporting methodology which provides for the accurate recording of data and timely
extrapolation and transmission of management information used in the decision making
process.
Management Reserve—A portion of the total allocated budget withheld for management
control purposes rather than designated for the accomplishment of a specific task or set of
tasks.
Mark-Up—As variously used in construction estimating, includes such percentage
applications as general overhead, profit, contingency and other indirect costs. When mark-up
is applied to the bottom of a bid sheet for a particular item, system or other construction price,
any or all of the above items (or more) may be included, depending upon local practice.
Mitigation of Damages—To take all possible measures to avoid damage and delay and, if not
avoidable, to reduce or lessen the extra costs incurred due to the occurrence of an event.
Most Probable Amount—An ambiguous term, which frequently refers to the mean value but
sometimes refers to the mode. In a normal curve, the mean, mode and median are all the same
so that this ambiguity is no problem. In real life, there is a difference and the reader must
ascertain what the author means by “most probable”.
Notice of Award—The written notice of acceptance of the bid by the owner to a bidder stating
that, upon compliance with the conditions precedent enumerated therein, within the time
specified, the owner will sign and deliver the agreement.
Notice to Proceed—A written notice issued by the owner to the contractor authorizing the
contractor to proceed with some or all of the work of the project and establishing the date for
commencement of the contract time.
Overhead—A cost or expense inherent in performing an operation which cannot be charged to
or identified with a part of the work and therefore must be allocated on some arbitrary base
believed to be equitable or handled as a business expense independent of the volume of
production.
Page 60
CMAA: Cost Management Procedures
Page 61
CMAA: Cost Management Procedures
Range Estimating—A risk analysis technology which combines Monte Carlo sampling,
focusing on a few key variables, and heuristics (or rules of thumb) to rank critical risk elements.
The approach is used to establish the range of the total project estimate and define how
contingency should be allocated among the critical elements.
Range of Accuracy—The values between the top and the bottom of the range. For example, if
the outcomes might be from $100 to $1,000, the range is $900 while the range of accuracy is
$100 to $1,000. Usually, the range of accuracy has defined upper and lower limits (such as 10%
confidence and 90% confidence; known as 10.90 range of accuracy).
Reserve—Something saved for future use. An amount of funding set aside for savings,
contingencies or other purposes.
Residual Value—The scrap value of a piece or equipment or some materials at the end of the
economic life of a system.
Resource Histogram—A graphic display of the amount of resource required as a function of
time on a graph. Individual, summary, incremental and cumulative resource curve levels can be
shown.
Resource Leveling—A process whereby resources are sorted out among tasks and activities to
identify and avoid conflicts between scheduling and availability.
Restraint—An externally imposed factor affecting the scheduling of an activity. The external
factor may be a resource, such as labor, cost or equipment or, it can be a physical event that
must be completed prior to the activity being restrained.
Retention—Usually refers to a percent of the contract value (5 or 10 percent) retained by the
owner until work is finished and testing of equipment, etc., is satisfactorily completed.
Return on Investment (ROI)—Usually defined as net income divided by investment amount.
There are three ways of expressing ROI. Return on Assets equals net income divided by total
asset cost and reflects the amount earned from the investment of all financial resources
committed including liabilities and owner’s equity of funds invested in assets. Return on
Owner’s Equity equals net income divided by funds invested by stockholders and reflects the
amount earned on funds invested by shareholders. Return on Invested Capital equals net
income divided by long term liabilities plus stockholders’ equity and focuses on the amount
earned from relatively permanent capital investments.
Risk Uncertainty. The potential hazards or problems inherent in any activity. A measurable
probability of consequence associated with a set of conditions or actions.
Risk Analysis—The second phase of risk management, which includes the quantification of
the effect of all uncertainty (risks) on a project. Usually done by identifying risks and
quantifying each risk’s probability of occurrence and potential severity of impact (typically
expressed as a range of values or probability distribution).
Risk Assessment—The first phase of risk management, which includes the identification of
risks, or uncertainties, which may impact a project.
Page 62
CMAA: Cost Management Procedures
Risk Control—Implementation of the risk management plan. The last phase of risk
management.
Risk Management—All of the steps (phases) associated with managing risks—assessment,
analysis, mitigation, control.
Risk Mitigation—The third phase of risk management, developing a plan to manage the risks
should they arise during the performance of the project.
Rough Order of Magnitude (ROM)—A budgetary or planning figure that is usually a rough
preliminary figure with a generally accepted range of +50% to —30%.
Schedule Variance—In cost terms, the difference between the Budget Cost of Work Performed
(BCWP) and the Budget Cost of Work Scheduled (BCWS). At any point in time it represents the
difference between the dollar value of work actually performed (accomplished) and that
scheduled to be accomplished. In scheduling terms, an ahead-of or behind-schedule condition
or a deviation from the baseline schedule.
Scope Change—A deviation from the project scope agreed to in the contract. A scope change
may consist of an activity either added to or deleted from the original scope. A contractor
change order is needed to alter the project scope.
Shop Drawings (or Submittals)—All drawings, diagrams, illustrations, schedules and other
data which are specifically prepared by or for the contractor to illustrate some portion of the
work and all illustrations, brochures, standard schedules, performance charts, instructions,
diagrams and other information prepared by a supplier and submitted by the contractor to the
designer or construction manager to demonstrate understanding of and compliance with the
provisions of the contract documents.
Should Cost Estimate—An estimate of contract price, which reflects reasonable achievable
economy and efficiency. It is generally accomplished by performing an in-depth analysis of cost
and cost effects. Its purpose is to develop realistic cost objectives.
Solicitation—An official document or notice, seeking prospective contractors to submit bids
or proposals.
Specification, Design (Prescriptive)—A design specification providing a detailed written
and/or graphic presentation of the required properties of a product, materials or piece of
equipment and prescribing the procedure for its fabrication, erection and/or installation.
Specifications, Performance—A statement of required results, verifiable as meeting
stipulated criteria and generally free of instruction as to the method of accomplishment.
Standard Adders—Cost elements which are added to every cost, estimated after the initial
estimate of costs for material and labor, etc. Standard adders may include general and
administrative cost, overhead, profit, etc.
Standard Cost—The normal, expected cost of an operation, process or product including
labor, materials, equipment, and overhead charges, computed on the basis of past performance
costs, estimates or work measurement.
Page 63
CMAA: Cost Management Procedures
Status Report—A report reflecting the situation as of a specified date with respect to
programs, functions, activities, projects or processes.
Subcontract—Any agreement or arrangement between a contractor and any person (in which
the parties do not stand in a relationship of an employer to an employee) and where neither
party is the owner.
Substantial Completion—Work (or a specified part thereof) which has progressed to the
point where, in the opinion of the designer or construction manager, it is sufficiently complete,
in accordance with the contract documents, so that it can be utilized for the purposes for which
it is intended.
Sunk Cost—A cost that has already been incurred and which should not be considered in
making a new investment decision.
Take-Off—Measuring and listing from drawings the quantities of materials required in order
to price their cost of supply and installation in an estimate and to proceed with procurement of
materials.
Target Cost—A cost objective value established by negotiation for incentive type contracts, the
target cost is used as a basis for agreement on target profit and target price, and serves as the
base point for calculating cost sharing incentives or performance awards.
Temporary Construction Cost—Includes costs of erecting, operating and dismantling non-
permanent facilities such as field offices, workshops, staging and storage yards, etc., and
providing associated services such as utilities.
Time and Material Work—A change order or a contract providing for the purchase of
supplies or services on the basis of direct labor hours at specified hourly rates (which include
direct labor, overhead and profit) and materials, at cost.
Time-Phased—The spread of resources (such as labor, funds, materials, etc.) tasks or key
milestones and activities displayed by appropriate time period.
Unexpended Balance—The amount of budget authority previously granted but still unspent
and available for future expenditure. The unexpended balance is equal to the sum of the
obligated and unobligated balances.
Useful Life—The period of time over which an investment is considered to meet its original
objective.
Value Analysis—A systematic and objective evaluation of the function of a project and its
related cost to ensure optimum value. As a pricing tool, value analysis provides insight into the
inherent worth of a project.
Value Engineering—A practice function targeted at the design itself, which has as its objective
the development of design of a facility or item that will yield least life cycle costs or provide
greatest value while satisfying all performance and other criteria established for it.
Variance—In cost control the difference between actual cost and forecast budget cost.
Page 64
CMAA: Cost Management Procedures
Variation in Estimated Quantity—The difference between the quantity estimated in the bid
schedule and the quantity actually required to complete the bid item. Negotiation or adjustment
of price for variations is generally called for when an increase or decrease exceeds a specific
percentage designated in the contract.
Work Authorization—A company instrument, memorandum or document which authorizes
work to be accomplished on a contract, project or program.
Work Breakdown Structure—A management technique for subdividing the total job into its
component elements, which can then be displayed (identified) in a manner to show the
relationship of these elements to each other and the whole project.
Work Directive Change—A written directive to the contractor, issued on or after the date of
the agreement and signed by an authorized individual, ordering an addition, deletion or
revision in the work, or responding to differing or unforeseen physical conditions or
emergencies under which the work is to be performed as provided in the general conditions. A
work change directive may or may not change the contract price or time but is evidence that the
parties expect that the change directed by a work change directive will be incorporated in a
subsequently issued change order following negotiations by the parties as to its effect, if any, on
the contract price or time.
Work Measurement—A technique employed independently, or in conjunction with, cost
accounting for the collection of data on labor hours and production of work units, so that the
relationship between the work performed and labor hours expended can be calculated. The
objective of a work management system is to determine how long it should take an employee to
perform assigned work and to identify opportunities for improvement.
Page 65
CMAA: Cost Management Procedures
11.0 REFERENCES
Association for the Advancement of Cost Engineering. International Skills and Knowledge of Cost Engineering. 3rd
Edition, Revised. Morgantown, West Virginia, AACEI, 1992.
Barrie, Donald S. & Boyd C. Paulson, Jr. Professional Construction Management: Including CM, Design-
Construct and General Contracting. 3rd Edition. New York, McGraw-Hill, 1992.
Construction Management Association of America. Construction Management Standards of Practice.
3rd Edition. McLean, Virginia, CMAA, 1999.
Construction Management Association of America. CMAA Document No. A-3: General Conditions of the
Construction Contract—Owner-Contractor Contract. 1999 Edition. McLean, Virginia, CMAA.
Design-Build Institute of America. Standard Form of General Conditions of Contract Between Owner and Design-
Builder. 1st Edition, October 1998. Design-Build Manual of Practice, Document Number 535, Washington, D.C.,
DBIA.
Hackney, John W. & Kenneth K. Humphreys. Control and Management of Capital Projects. 2nd Edition. New York,
McGraw-Hill, 1992.
Humphreys, Kenneth K. Jelen’s Cost and Optimization Engineering. 3rd Edition. New York, McGraw-Hill, 1991.
Kavanaugh, Thomas C., Frank Muller & James J. O’Brien. Construction Management: A Professional Approach.
New York, McGraw-Hill, 1978.
Kerzner, Harold. Project Management: A Systems Approach to Planning, Scheduling and Controlling. New York,
Van Nostrand Reinhold, 1995.
National Association of Women in Construction. Construction Dictionary. 8th Edition. Phoenix, Greater Phoenix,
Arizona Chapter #98, 1991.
O’Brien, James J. Preconstruction Estimating: Budget Through Bid. New York, McGraw-Hill, 1994.
Project Management Institute. A Guide to the Project Management Body of Knowledge. Upper Darby,
Pennsylvania, PMI Standards Committee, 1996.
Project Management Institute. Practice Standard for Work Breakdown Structures – Exposure Draft Version.
Upper Darby, Pennsylvania, PMI Standards Committee, 2000.
Ritz, George J. Total Construction Project Management. Boston, McGraw-Hill, 1994.
Schwartzkopf, William. Calculating Lost Labor Productivity in Construction Claims. New York, John Wiley &
Sons, Inc., 1995.
Page 66
Cost Management CMAA