Work Plan-3
Work Plan-3
'23 Apr '23 May '23 Jun '23 Jul '23 Aug '23
3/5 3/12 3/19 3/26 4/2 4/9 4/16 4/23 4/30 5/7 5/14 5/21 5/28 6/4 6/11 6/18 6/25 7/2 7/9 7/16 7/23 7/30 8/6
1 146 d Wed 3/15/23 Mon 8/7/23
SUMMARY
2 49 d Wed 3/15/23 Tue 5/2/23
Pre-Construction Actitivities
3 Prepare and submit project schedule and method 7d Wed 3/15/23 Tue 3/21/23
4 Mobilize on Site 3d Wed 3/15/23 Fri 3/17/23 3SS
5 Survey of the sites 3d Sat 3/18/23 Mon 3/20/23 4
6 Submit shop drawings 30 d Tue 3/21/23 Wed 4/19/23 5
7 Submittals for all material 14 d Wed 3/15/23 Tue 3/28/23 3SS
8 Obtain approvals 42 d Wed 3/22/23 Tue 5/2/23 7SS+7 d
9 128 d Wed 3/22/23 Thu 7/27/23
Construction Actitivities
10 Site Works 35 d Wed 3/22/23 Tue 4/25/23
11 MEP -Rehabilitation works 21 d Wed 3/22/23 Tue 4/11/23 8SS
12 Curb stone works 14 d Wed 3/22/23 Tue 4/4/23 11SS
13 Asphalt works 21 d Wed 4/5/23 Tue 4/25/23 12
14 Shelter Works 125 d Sat 3/25/23 Thu 7/27/23
15 Demolition Works 21 d Sat 3/25/23 Fri 4/14/23 5SS+7 d
33 Ceiling & walls Outlets 28 d Fri 5/19/23 Thu 6/15/23 18 5/19 6/15
34 Fixtures & Panel boards installation 28 d Tue 6/20/23 Mon 7/17/23 24 6/20 7/17
35 Commissioning & Testing 7d Tue 7/18/23 Mon 7/24/23 34 7/18 7/24
36 Demobilization 14 d Tue 7/25/23 Mon 8/7/23 35
Page 1
SIMA FOR CONSTRACTION s.a.r.l.