Webinar 5
Webinar 5
Series:
Session 5: Modeling Part 1 – Modeling Requirements, Model Creation, Model Usability
Presentación comercial
1. SOFTWARE P0-E Offers Modeling support for the following programs
Software
• PSCAD
• PSLF
• EMTP-RV
• TSAT-SSAT
• EMTP-ATP
• ANATEM
Presentación comercial
2. GRID CODE EXPERIENCE
• USA
• Australia
• España
• Portugal
• Alemania
• Francia
• UK
• Japón
• Omán
• Jordania
• México
• Brasil
• Uruguay
• Bolivia
• Argentina
• Chile P-E tries to proactively maintain model compliance but
• Egipto
It is challenging to track proposed updates in the US and
• Tailandia
• Vietnam worldwide
Presentación comercial
4. MODEL VALIDATION
Presentación comercial
• P-E provides general purpose models that must be
parametrized for site specific conditions.
• The Power-Electronics Grid Team is based in Valencia, Spain
and can assist with modeling issues and project specific
requirements
• Power-Electronics uses it’s world-wide experience in places like
Chile and Australia to advance the US modeling work
• P-E inverter models are benchmarked again our Hardware-in-
the-Loop
HIL PSCAD
Presentación comercial
¡THANKS!
9 RELIABILITY | RESILIENCE | SECURITY
Facility Model Creation
and Usability
Roadblocks
Billy F. Yancey III
VP Technical Services and Compliance
Preliminary Design Bridging the gaps towards seamless preliminary design to interconnection
Interconnection Request
request.
Balance of Plant Design Steady State Model (PSSE/PSLF) ERCOT Model Quality Test
Voltage control strategy of plant Short Circuit Model (Aspen) PJM Model Testing
Generator models (PSSE, PSLF, Dynamic Model (PSSE/PSLF/TSAT) ISO-NE Model Testing (PP 5-6)
TSAT, PSCAD, Aspen, etc.) Transient Model (PSCAD) HECO Model Testing standards
IEEE P2800 requirements
Facility Model Creation Process
The request for information and review can be a time-consuming process. This is where critical assumptions are
sometimes made that can have significant impacts on projects and could lead to need to restudy during the
interconnection process or even further down the road during commissioning.
RFI Challenges
Request for Information
and Review BOP Design Generator Models
Typically, very preliminary and Depending on requirements
Balance of Plant Design subject to change leading to within a region, dynamic and
Voltage control strategy of plant assumptions transient models may take
Generator Models (PSSE, PSLF, TSAT, Inverter selection is still extended time to provide due
PSCAD, Aspen, etc.) being negotiated and to availability of necessary
finalized controls
Power Plant Controller (PPC)
is most of the time not even
in the discussion at this point
Facility Model Creation Process
Model creation is typically an iterative process. The assumptions made during the request for information gathering
are pre-tested to ensure they meet the necessary requirements and additional equipment/ controls are not needed
before moving to full model testing and benchmarking.
S G Model Creation Steady State Model (PSSE/ PSLF) Short Circuit Model (Aspen)
MPT sizing and OLTC control Utilities requested IBRs to be
Need for additional reactive modeled as current limited
Steady State Model (PSSE/PSLF) devices generators
Short Circuit Model (Aspen) Quantity of IBRs and OEM Moved to Voltage control
Dynamic Model (PSSE/PSLF) selection current source (VCCS)
Transient Model (PSCAD) Recently requested of
converter interface resources
(CIR)
Facility Model Creation Process
Model creation is typically an iterative process. The assumptions made during the request for information gathering
are pre-tested to ensure they meet the necessary requirements and additional equipment/ controls are not needed
before moving to full model testing and benchmarking.
P R E S E N T E D B Y:
Tom Dagenais
Director, System Planning - ATC
• Wisconsin-based company