1. Thumb Rule for Concrete Volume
2. Thumb Rule for Steel Quantity for Slab, Beams, Footings & Columns
3. Percentage of Steel in Structural Members
4. Thumb Rules For Shuttering Work
5. Battens Quantity Calculation
6. Thumb Rule for Cement, Sand, Coarse Aggregate Quantity Calculations
7. Thumb Rules For Civil Engineers for Brickwork
8. Thumb Rules For Cement Masonry Quantity
8. Thumb Rules Plastering Quantity
9. Thumb Rules In Building Construction Cost
Thumb rules for construction cost
1000 Sqft House average cost of construction Thumb Rule
FAQs
This PDF document was edited with Icecream PDF Editor.
How do you calculate the steel-by-thumb rule?
Upgrade to PRO to remove watermark.
What is a good rule of thumb?
https://civiconcepts.com/blog/thumb-rules-for-civil-engineering 1/20
9/23/23, 1:07 PM Thumb Rules For Civil Engineering
What is the basic knowledge of civil engineering?
What is the thumb rule to determine beam depth?
Thumb Rules For Civil Site Engineer pdf
Thumb Rules for Civil Engineering
The thumb rule for construction helps you in finding out the solution using a simple mathematical formula and make smart
decisions whenever needed.
But, while using these thumb rules, you must remember that the thumb rule never gives exact or accurate results, you just
have used them for approximate results.
There is a number of Thumb Rule For Civil Engineers that we used in construction work. So, the following are some most
frequently used Thumb rules on the Construction site.
The Thumb rule method is an approximate & comparing method. In thumb rules and the units are not the same when we
compare to get the results. So, ignore units while performing the thumb rule.
Thumb
This PDF document wasRules for
edited with CivilPDF
Icecream Engineering
Editor. In Construction
Upgrade to PRO to remove watermark.
https://civiconcepts.com/blog/thumb-rules-for-civil-engineering 2/20
9/23/23, 1:07 PM Thumb Rules For Civil Engineering
So, for the plan area of 800 Sq. m. the area the total volume of concrete required.
2. Thumb Rule for Steel Quantity for Slab, Beams, Footings & Columns
Following are some important thumb rules for steel calculation for slab, beam, column, and footings.
Steel required in residential buildings = 4.5 Kgs – 4.75 Kgs / sq. Ft.
You can also use BN Datta recommendations for the more accurate result,
The following recommendations Thumb Rules For Civil Engineering are given in B N Datta for the Steel quantity used in
different members of the building.
1) Slab – 1% of the total volume of concrete (Slab steel calculation thumb rule)
2) Beam – 2% of the total volume of concrete
3) Column – 2.5% of total volume of concrete
4) Footings – 0.8% of the total volume of concrete
Example:
How to calculate the steel quantity of slab having the Length, width, and depth of the slab is 5m x 4m x 0.15m
Step 1: Calculate
This PDF document the
was edited Volume
with of Concrete:
Icecream PDF Editor.
Upgrade to PRO to remove watermark.
https://civiconcepts.com/blog/thumb-rules-for-civil-engineering 3/20
9/23/23, 1:07 PM Thumb Rules For Civil Engineering
= 3m3
As per the guidelines given in the BN Dutta reference book the steel quantity of the slab is 1% of the total volume of concrete
utilized.
A thumb rule to estimate the Steel quantity of the above slab = Volume of Concrete x Density of Steel x % of Steel of the
Member
Shuttering costs are taken as 15-18% of the total construction of the building. Shuttering work is done to bring the concrete
into Shape. The Thumb rule to estimate the shuttering required is 6 times the quantity of concrete or 2.4 times the Plinth area.
Components of Shuttering
The Shuttering plate Ply, Battens, and Nails are components of Shuttering.
Suppose, The Shuttering Ply has a length, width & depth of 2.44 x 1.22 x 0.012
If work requires 25 Ply sheets, the total quantity of Battens is 19.82 x 25 = 495 Battens
https://civiconcepts.com/blog/thumb-rules-for-civil-engineering 4/20
9/23/23, 1:07 PM Thumb Rules For Civil Engineering
2
75gms of Binding wire is used for every 1m of Shuttering.
Shuttering oil is applied on the shuttering plate surface used to de-frame or de-assemble from the concrete easily.
(or)
Example :
If, total area of shuttering is 15 m2, then Shuttering oil Consumption = 0.065 x 15 = 0.975.
Thumb rule for Cement required in Brickwork, Cement Masonry & Plastering work in construction
The following are Thumb Rules for civil engineering for brickwork and cement quantity calculations.
Cement Masonry Type & Mix Cement Qty in Bags Cement Qty in Kgs
https://civiconcepts.com/blog/thumb-rules-for-civil-engineering 5/20
9/23/23, 1:07 PM Thumb Rules For Civil Engineering
The thumb rule for house construction cost is a rough estimation of the total cost of construction based on the built-up area of
the house. Typically, thumb rules are quick and easy to use but are not precise and may not take into account specific factors
that affect the actual cost of construction.
As an approximate guide, a common thumb rule for house construction cost is between Rs. 1500 to Rs. 2500 per square foot,
depending on factors such as the quality of materials used, location, design, and labour costs. This would mean that a 1000
square feet house may cost between Rs. 15 lakhs to Rs. 25 lakhs.
Below is a general thumb rule that can be used to estimate the building materials and work required for a given unit area of
construction.
https://civiconcepts.com/blog/thumb-rules-for-civil-engineering 6/20
9/23/23, 1:07 PM Thumb Rules For Civil Engineering
Cement 14.4%
Sand 12.3%
Aggregate 7.4%
Steel 20.6%
Tiles 8%
Bricks 5.4%
Window 3%
Doors 4.4%
Plumbing 7.5%
Electrical 6.8%
Sanitary 4.1%
https://civiconcepts.com/blog/thumb-rules-for-civil-engineering 7/20
9/23/23, 1:07 PM Thumb Rules For Civil Engineering
A common approach to estimating building costs is to use a thumb rule based on the percentage of the total project cost. This
method provides a rough estimate of the building cost and is often used as a starting point for budgeting purposes.
3. DPC 1.2%
5. Roofing 22%
6. Flooring 5%
8. Plastering 9%
9. White Washing 3%
FAQs
How do you calculate the steel-by-thumb rule?
The thumb Rule can be called a guideline, idea, or principle that helps you make quick decisions. “Arrive early” is an efficient
good Thumb Rule for most appointments. It referred to builders who frequently use their thumbs to estimate measurements. It
is a helpful rule even being inexact.
https://civiconcepts.com/blog/thumb-rules-for-civil-engineering 8/20
9/23/23, 1:07 PM Thumb Rules For Civil Engineering
The method for determining the width-depth ratio of reinforced concrete beams is not specifically given in codes. However, a
thumb rule can be used i.e taking depth that is two and a half to three times the beam’s width. For long-span beams, it is
generally economical to use deep and narrow sections.
Thumb Rules For Civil Site Engineer pdf
Thumb Rules For Civil Engineering pdf is essential for any civil engineer, Site engineer, or civil supervisor. They play a crucial
role while taking quick decisions on site. There is some civil engineering basic knowledge that every civil engineer must know.
Thumb rule requirement of standard materials and standard calculation in high raised building,
Steel =3 to 5 kg / sqft.
Cement =0.5bags/ sqft.
RMC =0.05 m3/sqft.
Block =12.5 nos /sqm.
Electrical cast = Rs 133/sqft.
Plumbing cost = Rs 126/sqft.
Fire fighting cost = Rs 40/sqft.
External development = Rs 94.5/sqft.
https://civiconcepts.com/blog/thumb-rules-for-civil-engineering 9/20