Method Statement for Testing and Commissioning of Gully, Roof Trench, Snow Melting & Rev 002
Page 2 of 25
Heat Tracing System (Electrical)
Hold
Para. Description of Hold
No.
Page 2 of 25
Abu Dhabi Plaza – Astana, Kazakhstan Document No.
Work Package 4 – Main Works ADP-220533-006
Method Statement for Testing and Commissioning of Gully, Roof Trench, Snow Melting & Rev 002
Page 3 of 25
Heat Tracing System (Electrical)
Item
Comments On Rev.001 Contractor’s Response
No.
1. Comply
Noted
4
Hand writing comment: to insert raws on the commissioning sheet with Comply
5
instruments to be used, calibration certificate, serial number
Page 3 of 25
Abu Dhabi Plaza – Astana, Kazakhstan Document No.
Work Package 4 – Main Works ADP-220533-006
Method Statement for Testing and Commissioning of Gully, Roof Trench, Snow Melting & Rev 002
Page 4 of 25
Heat Tracing System (Electrical)
Table of Contents
1.0 Purpose
3.0 References
4.0 Definitions
5.1 Competency
5.2 Commissioning Engineer
5.3 Foreman
5.4 QC Engineer
5.5 HSE Supervisor
5.6 Supplier Technician
7.1 Preparation
7.2 Procedures for Testing of Gully, Roof Trench, Snow Melting & Heat Tracing System
7.2.1 Pre-commissioning
7.2.2 Commissioning
8.1 Induction
8.2 PPE
8.3 Hazard Identification, Risk Assessment & Control
8.4 Toolbox Talks
8.5 Permit to Work
8.6 Training of Personnel
9.0 Attachments
Page 4 of 25
Abu Dhabi Plaza – Astana, Kazakhstan Document No.
Work Package 4 – Main Works ADP-220533-006
Method Statement for Testing and Commissioning of Gully, Roof Trench, Snow Melting & Rev 002
Page 5 of 25
Heat Tracing System (Electrical)
1.0 PURPOSE
The main purpose of this method statement is to demonstrate procedure Gully, Roof Trench, Snow
Melting & Heat Tracing System (DEVI Heat Tracing System) test & commissioning and to ensure that it
complies with Project Specification Requirements.
This Commissioning Method Statement is applicable for DEVI Heat Tracing Systems installed in all
assets in Abu Dhabi Plaza. The objective is to put in operation, test & commission than record all the
necessary parameters which validates the good functionality of the DEVI Heat Tracing System in Abu
Dhabi Plaza.
3.0 REFERENCES
4.0 DEFINITIONS
The Commissioning Manager will individually assess the manpower requirements required for DEVI Heat
Tracing System Commissioning to meet the schedule. Typically these will include:
Commissioning Engineer
Foreman
QC Engineer
HSE Supervisor
Supplier Technician
Page 5 of 25
Abu Dhabi Plaza – Astana, Kazakhstan Document No.
Work Package 4 – Main Works ADP-220533-006
Method Statement for Testing and Commissioning of Gully, Roof Trench, Snow Melting & Rev 002
Page 6 of 25
Heat Tracing System (Electrical)
5.1 Competency
The competency of all construction personnel shall be controlled in accordance with the
Competent Persons Designation Procedure Ref: ADP-013529-066.
Commissioning Engineer will be in charge of all operations during commissioning of DEVI Heat
Tracing System following HSE requirements and Project Quality Plans.
Maintains work permits with coordination of the HSE Supervisor.
Coordinates with QC Engineer for inspections and raise RFIT if applicable.
Ensures that only trained and competent personnel are involved commissioning process.
Ensures that all plant & equipment are certified, maintained and used correctly.
Ensures that all the required documents and related drawings to execute the Works are up to
date.
Shall prepare open front for his crew and liaise with planning department for progress reporting
and schedule monitoring.
5.3 Foreman
The foreman will carry out his duties by maintaining continuous coordination with the
Commissioning Engineer on daily basis, and ensure proper distribution of the workforce in the
required and planned locations.
To ensure that his assistant foreman/ charge hand are aware of the job requirements and they
have enough information to carry out their duties properly.
To ensure in consultation with the site engineer that the manpower involved in the works are
moving as agreed and planned for the work.
To ensure that the daily work is progressing as planned and advice the Commissioning Engineer
of any requirement for additional resources.
To ensure full coordination with the safety officer to maintain safe working and proper
housekeeping of the site, following the approved safety measures and further ensure that all his
working team are aware of the same to prevent accident and losses.
To inform the Commissioning Engineer and of the areas ready for inspection.
5.4 QC Engineer
Ensure that all inspection and test reports pertaining to everyday work activities are submitted to
the QC inspection.
Prevent the use of equipment that could cause improper functioning of DEVI Heat Tracing
System relative to project Specifications.
Stop any work that is not being done in accordance with the specified requirements and
approvals.
Ensure that commissioning have been done in accordance with approved drawings, approved
method statement , manufacturer recommendation and materials prior to offer for CSC’s & CxA’s
inspection.
Page 6 of 25
Abu Dhabi Plaza – Astana, Kazakhstan Document No.
Work Package 4 – Main Works ADP-220533-006
Method Statement for Testing and Commissioning of Gully, Roof Trench, Snow Melting & Rev 002
Page 7 of 25
Heat Tracing System (Electrical)
The following tools & equipment will be used during the Test & Commissioning of DEVI Heat Tracing
System Commissioning
Electro - Mechanical Complete Hand Tools Box
Thermometer
Clamp Meter / Multimeter
Torch
Movable Step ladders
PPE( Hand Gloves, Safety Goggles)
Safety harness while working in high level in ladders or scaffolding
Note: All tools and equipment’s will be inspected and colour coded before use at site.
7.1 Preparation
Ensure that all approved shop drawings, necessary documents, tools, instruments and other
materials involved are available prior for doing such activities.
Check if work locations / areas are ready for commissioning of DEVI Heat Tracing System
Before starting the work, check that all Safety precautions are in place. Safety Team / Officers
shall be available for monitoring safety measures.
Layout drawing showing the position, ID and other necessary information regarding the unit(s) to
be tested.
Isolation of the areas, Safety Permits, PPE's and warning signs to be displays for carrying out
activities for testing the DEVI Heat Tracing System.
Ensure adequate of manpower, lightings and electrical power supply are provided in the works
areas in order to execute the task activities properly.
The cables will be tested for electrical continuity and insulation integrity before energizing (test
sheets to be included in RFIT)
7.2 Procedures for Testing of Testing of Gully, Roof Trench, Snow Melting & Heat Tracing
System
7.2.1 Pre-commissioning
Installation completed with approved RFIT signed off.
DB Panel serving each Heat Tracing loop to be commissioned with signed RFIC
Area around controllers and thermostats to be free of debris and accessible for testing and further
maintenance
Record equipment data on the commissioning test sheet
Page 7 of 25
Abu Dhabi Plaza – Astana, Kazakhstan Document No.
Work Package 4 – Main Works ADP-220533-006
Method Statement for Testing and Commissioning of Gully, Roof Trench, Snow Melting & Rev 002
Page 8 of 25
Heat Tracing System (Electrical)
7.2.2 Commissioning
8.1 Induction:
Prior to commencing work all personnel shall have attended the HSE induction course conducted by the
JV HSE department. No work shall be undertaken by personnel who have not attended the Project HSE
induction.
Page 8 of 25
Abu Dhabi Plaza – Astana, Kazakhstan Document No.
Work Package 4 – Main Works ADP-220533-006
Method Statement for Testing and Commissioning of Gully, Roof Trench, Snow Melting & Rev 002
Page 9 of 25
Heat Tracing System (Electrical)
All personnel involved in the Testing and Commissioning will comply with the Project requirements for
PPE:
Work Boots with toe protectors
Safety Helmet
Eye Protection with side shields
Gloves (as required)
Dust masks (as required)
Additional PPE identified by the task risk assessment shall also be provided. Personnel shall sign and be
responsible for their own items of PPE issued to them and the Site Engineer shall ensure that his team
is complying with the minimum required PPE and that damaged or defective PPE is replaced or repaired
immediately.
Hazard identification, risk assessment and control are detailed in the appropriate risk assessment and
Job Safety Task Instruction (JSTI) attached herewith. Hazards may vary as the works progress and shall
be re-evaluated. All personnel undertaking DEVI Heat Tracing System commissioning activities shall be
aware of particular location hazards. The Project Risk Assessment Procedure ADP-013529-028 is to be
referred to during the planning stages. Should changes occur during the course of construction which
alters the associated risks then the risk register shall be updated to reflect any additional risk and
mitigation measures.
The attached JSTI is provided to cover the initial work tasks relating to: Gully, Roof Trench, Snow Melting
& Heat Tracing System (DEVI Heat Tracing System) -JSTI (attached). This JSTI is prepared based on
theoretical information interpreted from the project documents. A further assessment will be required at
the actual work site to verify the control measures and address any additional hazards. Reference is to
be made to the relative Health, Safety, Environmental & Security procedures to control the risks
associated with activities where they occur.
Prior to the commencement of site activities the Site Engineer, with support from the HSE Officer, shall
conduct a pre-start toolbox talk with all the crew present. The MEP Supervisor shall explain the DEVI
Heat Tracing System Commissioning activities, focusing on the hazards and risks involved in the activity
and the mitigation measures that shall be taken as detailed in the Risk Assessment.
Regular Toolbox talks shall be conducted in order to prevent complacency within the crew. The Site
Engineer shall conduct a Pre-start toolbox talk for the new person/s prior to starting work.
A Permit to Work shall be obtained, in accordance with the requirements of Permit to Work Procedure
prior to perform the DEVI Heat Tracing System Commissioning.
The supervisor will ensure that all relevant risk assessments, method statements and permit to work
control measures are in place and that all relevant procedures contained within these documents are fully
understood by the operative personnel. Control of substances hazardous to health (COSHH) must be
attached on the work permit for each particular chemicals to be used for the activity, COSHH assessment
must be discuss to the workers pertaining to the proper usage of PPE’s, proper handling of chemicals,
proper disposal and etc. prior to use the chemical.
Page 9 of 25
Abu Dhabi Plaza – Astana, Kazakhstan Document No.
Work Package 4 – Main Works ADP-220533-006
Method Statement for Testing and Commissioning of Gully, Roof Trench, Snow Melting & Rev 002
Page 10 of 25
Heat Tracing System (Electrical)
All personnel involved in DEVI Heat Tracing System commissioning shall be trained in
accordance with the requirements of the Project HSE Program. No personnel shall be assigned
tasks that they have not received appropriate training in or have been assessed for competency.
Further training shall be given as required and when additional training is identified during the
risk assessment process.
All personnel involved in DEVI Heat Tracing System Commissioning activity shall be assessed
for qualifications, competency and if they have the required trade skills and experience, or
trained in accordance with the requirements of the Project standards.
9.0 Attachments:
Page 10 of 25
Abu Dhabi Plaza – Astana, Kazakhstan Document No.
Work Package 4 – Main Works ADP-220533-006
Document Title:
Inspection & Test Plan (ITP) – Gully, Roof Trench, Snow Melting & Heat Tracing System Page 1 of 1 Rev.002
(JV REF. ITP-1122-320 T&C)
Specification 220533
Pre-Commissioning Approved Installation
RFIT All relevant
Checklist for Gully, RFIC & FM-MS-
Review of Documents Approved Drainage document must be
1. Roof Trench, Snow S R R ADP- ADP-
Pre-Commissioning RFIT approved by
Melting & Heat 220533-006-001
Approved Electrical Consultant.
Tracing System RFIC
Approved Drawings
Specification 220533
All relevant
Commissioning Approved Test RFIC & FM-MS-
Measuring the insulation document must be
2. Checklist for Heat Procedure H W W ADP- ADP-
resistance approved by
Tracing Cables Calibration Consultant. 220533-006-002
Certificate
Specification
220533 All relevant RFIC & FM-MS-
Commissioning Checking the functionality
3. Approved Test document must be ADP- ADP-
Checklist for Controller Checking the settings Procedure approved by H W W 220533-006-003
Consultant.
All relevant
Specification document must be RFIC & FM-MS-
Commissioning
Checking the functionality 220533 approved by ADP- ADP-
4. Checklist for H W W
Checking the setting Approved Test Consultant.
Thermostat
Procedure
220533-006-004
Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R – Record Review
ARABTEC CONSOLIDATED CONTRACTORS COMPANY LTD. ABU
DHABI PLAZA – ASTANA, KAZAKHSTAN
4 Drainage serving the Heat Tracing Loop area(s) - RFIT signed off
Remarks:
Supplier Representative
JV Commissioning Engineer
JV QA/QC Engineer
(CSC) AECOM KZ
(CxA) CML
FM-MS-ADP-220533-006-001
ARABTEC CONSOLIDATED CONTRACTORS COMPANY LTD. ABU
DHABI PLAZA – ASTANA, KAZAKHSTAN
Gully, Roof Trench, Snow Melting & Heat Tracing System (Electrical)
DEVI Heat Tracing Cables Commissioning Record Sheet
10
Remarks:
JV Commissioning Engineer
(CSC) AECOM KZ
(CxA) CML
FM-MS-ADP-220533-006-002
ARABTEC CONSOLIDATED CONTRACTORS COMPANY LTD. ABU
DHABI PLAZA – ASTANA, KAZAKHSTAN
Gully, Roof Trench, Snow Melting & Heat Tracing System (Electrical)
Controller Commissioning Record Sheet
Setting
No. Settings Checks Comment
Factory Actual
1 Moisture Level 50
4 Clogged Drain On
JV Commissioning Engineer
(CSC) AECOM KZ
(CxA) CML
FM-MS-ADP-220533-006-003
ARABTEC CONSOLIDATED CONTRACTORS COMPANY LTD. ABU
DHABI PLAZA – ASTANA, KAZAKHSTAN
Gully, Roof Trench, Snow Melting & Heat Tracing System (Electrical)
Thermostat Commissioning Record Sheet
Supplier Representative
JV Commissioning Engineer
(CSC) AECOM KZ
(CxA) CML
FM-MS-ADP-220533-006-004
Astana/Kazakhstan, Abu Dhabi Plaza Project Астана/Казакстан, Проект Абу Даби Плаза
Job Safety Task Instructions Form (JSTI) Форма Оценки Риска по Технике Безопасности
Step 1: Task Planning (task identification and details)/ Шаг 1: Планирование задания (выявление задачи и деталей)
Step 3: Risk Management (list any nearby activities that may impact the work) Шаг 3: Управление Рисками (перечень деятельности которые могут повлиять на работу)
Astana/Kazakhstan, Abu Dhabi Plaza Project Астана/Казакстан, Проект Абу Даби Плаза
Job Safety Task Instructions Form (JSTI) Форма Оценки Риска по Технике Безопасности
Step 4: Job Safety/Hazard Analysis/ Шаг 4: Анализ/Оценки Рисков
Activity
(What must be done? i.e. tools, Hazards Risks
equipment, and material used) (How could an injury occur?) What Can Happen Recommendations
Item
(Can hazards be eliminated or modified?)
Планирование работы. Опасность Риски Меры контроля
Номер (Что надо для работы. Например: (Как может произойти (Что может произойти) (Как опасность может быть устранена)
инструменты, оборудование и травма)
материалы)
Job Safety Task Instructions Form (JSTI) Форма Оценки Риска по Технике Безопасности
Ensure that personnel engaged of working at
Serious injury to personnel height are trained and competent to the given
or even fatality due to fall task.
Fall of material from height. Supervisor must provide full body harness for
Fall from height Injury to personnel due to personnel engaged of working at height.
Working at heights Collapse of scaffold falling debris. Workplace place must be barricaded underneath
3
Cold weather Injury to personnel or even prior to start the work.
fatality due to collapse of A proper work platform should be provided
scaffolds. Monitor the temperature, and wind chill index.
Hypothermia Work rest period implemented.
Wear Winter PPE.
Provide hot beverage for employees.
Job Safety Task Instructions Form (JSTI) Форма Оценки Риска по Технике Безопасности
Job Safety Task Instructions Form (JSTI) Форма Оценки Риска по Технике Безопасности
Wear all required PPE’s.
Slips, trips and fall due to work boots/ rubber boots with toe
Slips scattered materials or protector
Trips rubbish. hard hat
Fall Foot injuries visibility vest / jacket
7 Housekeeping safety glass
Hand injuries
Dust Mask ( as required )
Personnel injury due
Gloves
slippery surface
Supervisor must ensure that used materials
must be stored in designated, to prevent
scattered at work area
Astana/Kazakhstan, Abu Dhabi Plaza Project Астана/Казакстан, Проект Абу Даби Плаза
Job Safety Task Instructions Form (JSTI) Форма Оценки Риска по Технике Безопасности
Step 5: Unplanned Events (if any of the following occurs, stop work and talk to your supervisor)/ Шаг 5: Незапланированные мероприятия: если следующие случаи имеют
место, то остановите работу и известите супервайзера
Nearby work hazards Chemical spills or release
Excessive noise Fires and explosions Unusual odours Heat stress
Опасности на рабочем Утечки химических
Черезмерный шум Пожар и взрывы Странный запах Тепловой удар
месте веществ
Extreme weather/high
winds
Significant near miss Change in the following work conditions:
Evacuation alarm Экстримальные
Существенное, возможное Изменение в процессе работы:
Эвакуация/тревога погодные условия и
происшествия
сильный ветер
Step 6: Unplanned Events (if any of the following occurs, stop work and talk to your supervisor) Шаг 6: Незапланированные мероприятия: если следующие случаи имеют
место, то остановите работу и известите супервайзера
Emergency telephone number: Alarm Code (for commission period)
Телефон экстренной связи: +77015301064 Код сигнализации (при пусконаладке)
Nearest Muster Point/Safety Shelter location: Nearest First Aid Station location:
Ближайший пункт Место Сбора: Ближайший пункт Первой Помощи:
Evacuation Route (Supervisor to explain to workers): Safety shower / eye washer location:
Пути эвакуации(Супервайзер должен объяснить работникам): Пункт промывки глаз:
Astana/Kazakhstan, Abu Dhabi Plaza Project Астана/Казакстан, Проект Абу Даби Плаза
Job Safety Task Instructions Form (JSTI) Форма Оценки Риска по Технике Безопасности
Step 7: Working Crew Details Шаг 7 Список работников (рабочей бригады)
I acknowledge receiving & understanding these instructions, I will fully comply with the assigned job requirements.
Я, подтверждаю что полученную информацию понимаю в полной мере , и я буду полностью соответствовать должностным требованиям.
Sr. Badge No. Signature Sr. Badge No. Signature
Name Ф.И.О Name Ф.И.О
№ № Бейджа Подпись № № Бейджа Подпись
1 26
2 27
3 28
4 29
5 30
6 31
7 32
8 33
9 34
10 35
11 36
12 37
13 38
14 39
15 40
16 41
17 42
18 43
19 44
20 45
21 46
22 47
23 48
24 49
25 50
Astana/Kazakhstan, Abu Dhabi Plaza Project Астана/Казакстан, Проект Абу Даби Плаза
Job Safety Task Instructions Form (JSTI) Форма Оценки Риска по Технике Безопасности
Supervisor Name:
Ф.И.О Супервайзера: ________________________________________ Signature/ Подпись: __________________ Date/Дата: ____________________________ /______/________
This JSTI is prepared based on theoretical information interpreted from the project documents. A further assessment will be required
at the actual work site to verify the control measures and address any additional hazards. Reference is to be made to the relative
Health, Safety, Environmental & Security procedures to control the risks associated with activities where they occur.