Chapter 7
Chapter 7
Diagrams:
12/02/2024
Normally requires only a block flow diagram.
Prof.Dr. Hale GÜRBÜZ
Class 4: Study (also known as Major Equipment or
Factored) Estimate
Data: List of the major equipment of the process (all
pumps, compressors and turbines, columns and vessels,
fired heaters, and exchangers).
Each piece of equipment is roughly sized and the
approximate cost determined.
The total cost of equipment is then factored to give the
estimated capital cost.
Diagrams: Based on PFD and costs from generalized
charts.
Note: Most individual student designs are in this category.
12/02/2024 Prof.Dr. Hale GÜRBÜZ
Class 3: Preliminary Design (also known as Scope)
Estimate
Data: Requires more accurate sizing of equipment than
used in the study estimate.
In addition, approximate layout of equipment is made
along with estimates of piping, instrumentation, and
electrical requirements. Utilities are estimated.
Diagrams: Based on PFD
Includes vessel sketches for major equipment, preliminary
plot plan, and elevation diagram.
Note: Most large student group designs are in this
category.
12/02/2024 Prof.Dr. Hale GÜRBÜZ
Class 2: Definitive (also known as Project Control)
Estimate
For the detailed estimate, the cost of the estimate is in the range
of 10 to 100 times that of the order-of-magnitude estimate.
For the lowest expected cost range:
Highest Expected Value: ($5.0 × 106)(0.03) = $150,000
Lowest Expected Value: ($5.0 × 106)(0.0015) = $7500
For the highest expected cost range:
Highest Expected Value: ($5.0 × 106)(0.3) = $1,500,000
Lowest Expected Value:
12/02/2024
($5.0 × 106)(0.015) = $75,000
Prof.Dr. Hale GÜRBÜZ
What is the cost of making an estimate?
Determine:
a) The constant K in Equation 7.2
b) The cost of a new heat exchanger with area equal to 180 m2
b) Ca = (661)(180)0.59 = $14,100
Year Marshall and Swift Equipment Cost Index Chemical Engineering Plant Cost Index
1991 931 361
1992 943 358
1993 964 359
1994 993 368
1995 1028 381
1996 1039 382
1997 1057 387
1998 1062 390
1999 1068 391
2000 1089 394
2001 1094 394
2002 1104 396
2003 1124 402
2004 1179 444
2005 1245 468
2006
12/02/2024 1302 Prof.Dr. Hale GÜRBÜZ 500
12/02/2024 Prof.Dr. Hale GÜRBÜZ
https://www.toweringskills.com/financial-analysis/cost-indices/
CEPCI
100 61 % of total
Erection and installation labor 22
Buildings, materials, and labor 7
Engineering and supervision 10
Total 100
12/02/2024 Prof.Dr. Hale GÜRBÜZ
https://www.toweringskills.com/financial-analysis/cost-indices/
a.
Marshal and Swift: Cost = ($25,000)(1302/943) = $34,518
Chemical Engineering: Cost = ($25,000)(500/358) = $34,916
b.
Average Difference: (($34,518 – 34,916)/(($34,518 + 34,916)/2)(100)
= –1.1%
12/02/2024 Prof.Dr. Hale GÜRBÜZ
7.3. Estimating the Total Capital Cost of a Plant
The capital cost for a chemical plant must take into
consideration many costs other than the purchased cost of
the equipment.
As an analogy, consider the costs associated with building a
new home. The purchased cost of all the materials that are
needed to build a home does not represent the cost of the
home.
The final cost reflects:
the cost of property
the cost for delivering materials
the cost of construction
the cost of a driveway
the cost for hooking up utilities, and so on.
12/02/2024 Prof.Dr. Hale GÜRBÜZ
7.3. Estimating the Total Capital Cost of a Plant
The greater the Lang Factor, the less the purchased costs
contribute to the plant costs.
Using data in Table A.3 for shell-and-tube heat exchangers with both
shell and tubes made of carbon steel (Identification Number = 1) and
Figure A.8, FM = 1.
Using Equation A.3 and substituting for P=100 barg and the above
constants,
• It is evident that even the thinnest tube normally used for heat
exchangers is capable of withstanding pressures much greater than
atmospheric. Therefore, the most costly portion of a shell-and-tube
heat exchanger (the cost of the tubes) is relatively insensitive to
pressure.
• The pressure factors for this type of equipment are much smaller
than those for process vessels at the same pressure.
12/02/2024 Prof.Dr. Hale GÜRBÜZ
The purchased cost of the equipment for the heat exchanger in
Example 7.11 would be CP(2006) = ($25,000)(1.383) (500/394)
= $43,880.
If this equipment cost were multiplied by the bare module factor
for the base case, the cost would become CBM = ($43,880)(3.29)
= $144,360. This is 16% greater than the $123,590 calculated in
Example 7.11.
The difference between these two costs results from assuming,
in the latter case, that all costs increase in direct proportion to
the increase in material cost. This is far from the truth. Some
costs, such as insulation, show small changes with the cost of
materials, whereas other costs, such as installation materials,
freight, labor, and so on, are impacted to varying extents.
The method of equipment module costing accounts for these
variations in the bare module factor.
12/02/2024 Prof.Dr. Hale GÜRBÜZ
Materials of Construction (MOCs)
The choice of what MOC to use depends on the chemicals that
will contact the walls of the equipment.
As a guide, Table 7.9, may be used for preliminary MOC
selection.
However, the interaction between process streams and MOCs can
be very complex and the compatibility of the MOC with the
process stream must be investigated fully before the final design
is completed.
Many polymeric compounds are nonreactive in both acidic and
alkaline environments. However, polymers generally lack the
structural strength and resilience of metals.
Nevertheless, for operations at less than about 120°C in corrosive
environments the use of polymers as liners for steel equipment or
incorporated into fiberglass structures (at moderate operating
pressures) often gives the most
12/02/2024 economical
Prof.Dr. Hale GÜRBÜZ solution.
Materials of Construction (MOCs)
These figures are constructed using averaged data from the following
sources: Peters and Timmerhaus [2], Guthrie [9, 10], Ulrich [5],
Navarrete [11], and Perry et al. [3].
The form of this equation is not obvious, and its derivation is based on
the approach used by Ulrich [5]:
2. Find the correct relationship for the bare module factor. For
exchangers, pumps, and vessels, use Equation A.4 and the data in
Table A.4. For other equipment, the form of the equation is given in
Table A.5.
3. For exchangers, pumps, and vessels, find the pressure factor, FP,
Table A.2 and Equation A.2 or A.3, and the material of construction
factor, FM, Table A.3, and Figure A.8. Use Equation A.4 to calculate
the bare module factor, FBM.
4. For other equipment find the bare module factor, FBM, using Table
A.6 and Figure A.9.
6. Update the cost from 2001 (CEPCI – 397) to the present by using
Equation 7.4.
12/02/2024 Prof.Dr. Hale GÜRBÜZ
Example 7.13.
Find the bare module cost (in 2006) of a stainless steel tower 3 m in
diameter and 30 m tall. The tower has 40 stainless steel sieve trays
and operates at 20 barg.
The costs of the tower and trays are calculated separately and then
added together to obtain the total cost.
(20 1)3
0.00315
(2)(944)(0.9) 1.2(20 1)
Fp, vessel 6.47
0.0063
CBM = CpNFBMFq, N=40, Fq=1.0 (since number of trays > 20, Table
A.5)
7.16.
[*] CS = Carbon
12/02/2024 [†] barg
Prof.Dr. Hale
steel; SS = Stainless steel, GÜRBÜZ
= bar gauge, thus 0.0 barg = 1.0 bar
The same algorithm presented above is used to estimate bare module
costs for all equipment.
This information is listed in Table E7.14(b), along with purchased
equipment cost, pressure factors, material factors, and bare module
factors.
Table E7.14(b). Results of Capital Cost Estimate for Example 7.14
C0BM((2001)(
Equipment FP FM FBM C0p(2001)($) CBM(2001)($) $)
E-101 1.0 1.0 3.29 33,000 108,500 108,500
E-102 1.023 1.81 4.70 36,900 177,900 121,300
E-103 1.0 1.0 3.29 3700 12,300 12,300
P-101A/B 1.0 1.55 3.98 (2)(3200) (2)(12,600) (2)(10,300)
T-101 1.681 1.0 5.31 54,700 290,700 222,800
32 trays 1.83 1.83 (32)(2200) 131,200 71,700
V-101 1.513 1.0 3.79 13,500 51,200 40,600
Totals 219,900 797,000 597,800
CEPCI = 397
n
Grassroots cost C GR C TM 0.50 C 0BM,i
i 1