Lecture 4 Parties To A Construction Contract
Lecture 4 Parties To A Construction Contract
1
Lecture 4
2
Functions, Responsibilities and
Obligations of the Parties
• The Employer/Client
• The Engineer
• The Engineer’s Representative
• The Resident Engineer (RE)
• The Contractor/Main Contractor
• Domestic Sub-Contractor
• Nominated Sub-Contractor (NSC)
• Nominated Supplier (NS)
3
The Employer/Client
The Employer is the Client, who pays the design and
construction costs. The Employer is, therefore, the most
important party to the contract, without him there would
be no contract.
– Once the contract has been signed, the Employer and the
Contractor become equal parties to the contract, each with
duties and obligations one to the other, the most important of
which are set out in the form of agreement (Contract).
4
The Employer/Client
Employers come from one of two sectors:
5
The Engineer
The Consultant Engineer is employed by the
Client :-
• to plan and design the project,
• to draw up the contract (generally including the
preparation of the bill of quantities)
• to obtain tenders
• to let and supervise the work,
• to authorize payments
• to issue certificates.
6
The Engineer
This is a similar role to that of the Architect in
building project:-
7
The Engineer
Engineer As Agent of the Employer
Since the Engineer acts on behalf of the Employer, he is the
agent of the Employer. The Engineer must act honestly and
exercise reasonable skill and care in his capacity as an
Engineer. His rights as the Employer’s agent is as follows:-
• The Engineer shall carry out the duties, and may exercise the
authority, specified in or implied from the contract.
• Where the special approval of the Employer is required before
exercising such authority, he must comply with the requirements set
out in the contract.
• Usually the Engineer has no authority to amend the terms and
conditions of the contract or to relieve the Contractor of any of his
contractual obligations, except as stated in the contract.
8
Engineer’s Representative
The Engineer may employ representative to work on site.
The responsibilities of the Engineer’s Representative are
primarily to assist the Engineer that he must monitor and
supervise the construction and completion of the works.
9
Resident Engineer (RE)
On large projects, beside the project engineer, there may be
another engineer which will be based on site as the Resident
Engineer.
10
Resident Engineer (RE)
The Resident Engineer is responsible for the
following:
• the day-to-day site supervision, ensuring that the work is carried out
in accordance with the conditions, drawings and specification.
• issue of site instructions and variation orders,
• checking interim valuations and recommend amounts for payment,
• provisionally agreement of new and additional rates,
• advising the Engineer on progress, delays and claims.
• keeping all records, registers, drawings, charts and correspondence
that are necessary for the successful completion and historical record
of the contract operations.
11
The Contractor / Main Contractor
The Contractor is the person or persons, firm or
company to whom the contract has been awarded
by the Employer.
12
The Contractor / Main Contractor
The Contractor’s obligations under the conditions of
contract :-
13
The Contractor / Main Contractor
The Contractor’s obligations under the conditions of
contract :-
14
The Contractor / Main Contractor
The Contractor’s obligations under the conditions of
contract :-
15
The Contractor / Main Contractor
The Contractor’s obligations under the conditions of
contract :-
16
Domestic Sub-Contractors
Domestic sub-contractors are employed to undertake the
general portion of work in a project
– for which the Main Contractor has no such trade provision within
his company for example concreting, steelwork, plastering etc.;
– his (MC) own employed labor are busy elsewhere
17
Nominated Sub-Contractor (NSC)
• Nowadays, it is unusual for a single contractor to
undertake all the contract works directly with his own
work force. Even in the event of minor works, the
contractor will need others to assist him for other
specialist trades.
18
Nominated Sub-Contractor (NSC)
• In order to achieve such arrangement, the Employer will
use the system of nomination.
19
Nominated Sub-Contractor (NSC)
Nomination of NSC may arise from the following means:
• expenditure of Prime Cost Sums
• instruction from the Engineer (EI) regarding a variation
(usually for extra works to the contract)
• by agreement between the contractor and the engineer
on behalf of the Employer.
20
Nominated Sub-Contractor (NSC)
Relationship of a Main Contractor with respect to a
Nominated Sub-Contractor in respect of :-
1. Payment
– Normally the contract will require contractor to submit invoices
(payment application) to the Engineer.
– It is the responsibility of the Main Contractor(MC) to include
invoice of the NSC in their application (provided their invoice is
submitted, and complying to the time frame as set out).
– The Employer’s Quantity Surveyor (QS) shall check, evaluate and
assess the payment application and make recommendation to the
Engineer.
– Engineer shall issue the interim payment certificate to the Main
Contractor and it must also state the amount due to the NSC (if
any) .
21
Nominated Sub-Contractor (NSC)
1. Payment (cont’)
22
Nominated Sub-Contractor (NSC)
2. Time
23
Nominated Sub-Contractor (NSC)
3. Disputes
24
Nominated Sub-Contractor (NSC)
4. Facilities
25
Nominated Sub-Contractor (NSC)
5. Indemnity
26
Nominated Suppliers (NS)
Nomination of firms to supply materials may arise in:
– expenditure of Prime Cost Sum( PC sum ) in the contract for the
supply of goods
– Engineer’s Instruction is issued
27
28
29
30
31
Typical Organization structure of
a Large Construction Site
32
Typical Organization structure of
a Large Construction Site
33
End
34