Lecture 2 Types of Civil Engineering Contracts
Lecture 2 Types of Civil Engineering Contracts
1
Lecture 2
2
Types of Civil Engineering
Contracts
• Lump Sum Contracts
• Measurement Contracts
• Cost Reimbursement Contracts
• Management Contract
• Design and Build (and Turnkey Contracts)
• Build-Operate-Transfer (BOT)
3
Lump Sum Contracts
• What are lump sum contracts?
• The nature and the extent of the works are normally indicated on
drawings (e.g. plans and workshop drawings) and/or Bills of
Quantities (BQ), and the nature of the materials and workmanship
described in a specification.
4
Lump Sum Contracts
• Lump Sum Without Quantities (Based on Drawings and
Specification)
Photo Source:
http://www.muli.com.au/construction-
industry-software
5
Lump Sum Without Quantities
• In lump sum contacts based on plan and specification, the
contractor undertakes to carry out the work described, or specified,
to completion, for an agreed lump sum.
• The documents required for this contractual arrangement are the
complete working drawings, together with a full specification. No
bills of quantities are supplied to the tenderers who must prepare
their own quantities from the drawings.
• There are substantial risks imposed on the tenderers under this
arrangement. A tenderer is responsible for any errors he makes in
the taking off from the drawings.
• The contractor is required to take up all responsibilities for any costs
incurred due to uncertainties or unforeseen difficulties when
preparing the tender.
6
Lump Sum Without Quantities
• In order to allow for these risks, the tenderers are likely
to include higher cost in their prices.
7
Lump Sum Without Quantities
Advantages
• The time for the preparation of tender documents is reduced, as the
time consuming process of preparing bills of quantities is eliminated.
Disadvantages
• No breakdown of the tender sum is available.
8
Lump Sum With Quantities
• This type of contract, which incorporates a bill of quantities priced by
the contractor, where the quantities of the bulk of the work can be
ascertained with reasonable accuracy before the work is started.
• An item in bills of quantities is as follow:
Description Quantity Unit Rate Total
R.C. Grade 30/20D in 100 m3 $900 $90,000.00
foundation
• The tender sum is derived from the total of the items in the bill of
quantities.
• In lump sum contracts based on bill of quantities, the contractor
undertakes to carry out the work in accordance with the drawings,
specification and as described in the bill of quantities for a lump sum.
9
Lump Sum With Quantities
• This type of contract is suitable for the following
circumstances:-
10
Lump Sum With Quantities
Advantages
• The design team has to finalize the design requirement as much as
practicable before committing into a lump sum contract. As a result,
the employer and the contractor enter the contract with their
commitments clear.
• The employer’s quantities surveyor prepares the bills of quantities
from the drawings, which the competing contractors will price on
the same set of information. It provides a fairer basis for
competition.
• It gives the employer a good indication of the final cost of the work.
• The quantities and the unit rates of the measured items will serve as
the basis for the valuation of variation when there are changes to
the works.
11
Lump Sum With Quantities
Disadvantages
• It takes longer time in the design of the project and preparation of
the bills of quantities before tendering out the works.
12
Measurement Contracts
• This type of contract is sometimes called 're-
measurement' or 'measure and value' contracts.
13
Measurement Contracts
• Measurement Contract based on Bills of
Approximate Quantities
14
Measurement Contract
(based on Bills of Approximate Quantities)
15
Measurement Contract
(based on Bills of Approximate Quantities)
16
Measurement Contract
(based on Bills of Approximate Quantities)
• The unit rates will form part of the contract and work on site may
proceed before the design is completed.
• where the urgent nature of the project does not allow adequate
time for design and firm quantities to proceed tendering.
17
Measurement Contract
(based on Bills of Approximate Quantities)
Advantages:
• Approximate bills permit the overlapping of design and construction
and this will save time before tendering.
• Approximate bills avoid the great expense of preparing firm
quantities, in particular, where there maybe substantial variation
works.
Disadvantages
• The bills of quantities cannot be relied to give realistic total cost at
tender stage as the quantities are approximate (i.e. price certainty)
• Where the bills are too approximate, for example, where the
uncertainty as to the character of the work are too vague, the
usefulness of the bills will be reduced.
18
Measurement Contract
(based on Schedule of Rates)
19
Measurement Contract
(based on Schedule of Rates)
20
Measurement Contract
(based on Schedule of Rates)
Advantages:
• It allows for contract to be signed and work to start on site when
design is in preliminary stage and shorten the pre-contract period.
• The use of standard schedule of rates eliminates the need for lengthy
tendering time.
Disadvantages:
22
Cost Reimbursement Contract
• In cost reimbursement contracts, the price paid is determined on the
basis of the actual cost incurred by the Contractor in carrying out the
work, plus an agreed amount to cover overheads and profit.
• The costs for the works will be the cost of material, cost of labor and cost of plants.
This is normally used where the nature of work is of a urgent nature
23
Cost Reimbursement Contract
This is used in the following circumstances:
• where the requirements are only in general terms because
of the nature of the work, such emergency repair of
damage, and/or of the shortage of time.
24
Cost Plus Percentage
Cost Plus Percentage. The Contractor carries out the work
and is paid all costs, plus a fee which is calculated as a
percentage of whatever the total cost for overheads and
profit.
“Prime Cost + ( % )for Profit & Overhead”
Definition of prime cost: The total of direct material costs,
direct labor costs, and direct expenses.
25
Cost Plus Percentage
Advantages:
• Once the basis of the contract is agreed the work can
commence immediately, thus avoiding the delay which is
necessary if estimates have to be prepared.
• If the contractor is efficient, then the cost to the employer
should represent a fair price for the work undertaken.
Disadvantages:
• It is difficult to predict the final cost at the early stage of
the work.
• Some form of control is necessary in order to ensure that
the correct costs are being charged by the contractor, and
such a control system may be difficult and costly.
26
Cost Plus Fixed Fee
• Cost Plus Fixed Fee. This is used when an accurate
estimate of the maximum total cost can be made and a
fixed fee is agreed on signing of contract.
• The fee for the overheads and profit will be agreed as a
fixed sum unless the scope of work has altered after the
contractor has tendered.
• “Prime Cost + A Fixed Amount for Profit & Overhead”
• The fee will not be adjusted even though there is
difference in actual cost. Since the fee is fixed and will not
be affected by the costs, the Contractor may try to reduce
the time and thus cost of the construction, which will
result in a saving for the Client.
27
Cost Plus Fixed Fee
Advantages:
• The advantage of speed in commencing the work is
undermined, since a fairly detailed scheme of work must
be prepared before a fee can be agreed.
Disadvantages:
• If there are any major variations, which can be difficult to
avoid in this type of work, then the fee must be re-
negotiated to take account of such variation.
28
Target Price
• Target Price. An estimate is prepared for the work and to
be agreed as the target cost of the project.
29
Target Price
• The Contractor is reimbursed in the first place on the basis
of cost plus percentage or fixed fee, and Then comparison
of the actual cost shall be made against the target price. If
there is saving, a bonus will be rewarded to the Contractor.
If the amount of the actual cost is more than the target
price, a penalty shall be imposed on the Contractor.
http://www.webdesigncompany.net
/website-optimization-moving-
target/
30
Target Price
• This method provides an effective incentive for the
contractor. The target price must be fixed accurately, and
the extent of work to be carried out must be well defined.
31
Guaranteed Maximum Price
Contract
• A mixture of fixed or unit price and cost-plus or fixed-fee
model is the guaranteed maximum price contract.
32
Guaranteed Maximum Price
Contract
• When the project scope is well defined, an owner may
choose to ask the contractor to take all the risks, both in
terms of actual project cost and project time.
• Any work change orders from the owner must be
extremely minor if at all, since performance specifications
are provided to the owner at the outset of construction.
• The owner and the contractor agree to a project price
guaranteed by the contractor as maximum.
• There may be or may not be additional provisions to share
any savings if any in the contract. This type of contract is
particularly suitable for turnkey operation.
33
Management Contract
• The management contractor is employed to manage,
coordinate and direct the work of other contractors on
behalf of a employer.
34
Management Contract
• The management contractor’s role is that of providing a
construction management service on a fee basis as part
of the employer’s management team- organizing,
coordinating, supervising and managing the construction
works in cooperation with the employer’s other
professional consultants.
35
Design and Build
• This is a departure from the traditional procedure
whereby the Client and his consultant will provide the
design to the Contractor for his construction.
36
Design and Build
• The procedure is initiated by the employer preparing his
requirements/brief. These are then sent to a selection of
suitable contractors, each of whom prepares his proposals on
design, time and cost.
37
Design and Build
• Such representatives may take the form of an engineer to
ensure the quality of construction work and/ or a
quantity surveyor to advise on and monitor costs.
38
Build-Operate-Transfer
• Globally, this is one of the most popular methods of
privatizing government infrastructure work.
39
Build-Operate-Transfer
• Once the facility is completed, the consortium will
operate the facility for a period of years for example 10 to
30 years as defined by a concession granted by
government.
40
Build-Operate-Transfer
• In Hong Kong, there are many examples of government
infrastructure facilities which have been successfully
completed under the Build-Operate- Transfer scheme. One
such example is the Tate's Cairn vehicular tunnel linking
Shatin to North Kowloon.
41
Build-Operate-Transfer
• Although not as numerous, there are examples of BOT
schemes in Hong Kong which have been successfully
adopted for use in the private sector.
42
Build-Operate-Transfer
• Under the scheme, the Bank
awarded a twenty-five year sublease
of the land, where the existing
headquarters stood, to Nishimatsu
Property (Hong Kong).
• In return for the granting of the
sublease, Nishimatsu were required
to pay a premium as well as
undertake to totally finance the cost
of reconstruction; the Bank chose to
retain its own architect and
consultant team, which Nishimatsu
was required to allow for in its price.
43
Build-Operate-Transfer
• It was further agreed that, upon completion, Standard
Chartered would have the exclusive right to lease back
70% of the floor area, at a fixed rental, up until the expiry
of the twenty-five year sublease when the entire
development would revert to the Bank.
44
Build-Operate-Transfer
• The benefit of this scheme to the Bank was the
opportunity to retain its liquid assets (bankers place
greater value on cash than capital tied up in property),
while Nishimatsu gained by boosting their turnover by
nearly HK$1 billion.
45
Build-Operate-Transfer
• The benefit of this scheme to the Bank was the
opportunity to retain its liquid assets (bankers place
greater value on cash than capital tied up in property),
while Nishimatsu gained by boosting their turnover by
nearly HK$1 billion.
46
Extend Part
47
References
1. Hills, M.J. (1995) Building Contract Procedures in Hong Kong. Hong Kong:
Longman.
48
Bibliography
1. Murdoch, J. and Hughes, W. (2008) Construction Contracts: Law and
Management, 4th edition. London:Taylor & Francis.
49
Contact
• For comments and enquiries, please message to
[email protected]
50
End
51