Isyaku L Project
Isyaku L Project
Isyaku L Project
1
CHAPTER ONE
1.0 Introduction
This section of the research focuses on the introduction that serves as the background to the
research. The background formed a clear focus of the problem statement. Research questions,
aim and objectives of the research are going to be discussed. The section also discusses scope
Development of economy in every nation is based on construction projects that are undertaken
through several types of contracts. (Gunduz, Nielsen and Ozdemir, 2013). Nowadays, the
delay are increasing. Construction industries are responsible for construction projects but are
suffering from delay phenomenon. This delay phenomenon is a common problem that caused by
various factors, which affects the effort of project performance (Gunduz, Nielsen and Ozdemir,
2013).
Construction delays have negative effects on clients, contractors and consultants in term of
growth in confrontational relationships, distrust, litigation, arbitration, cash flow problems and
general feeling of unease toward one another (mahamud, Bouland and Dmaidi 2012). The timely
delivery of projects within budget and to the require standard of quality specified by the clients,
is often regarded as successful project delivery, failure to complete the project within the
targeted time, budgeted cost and specified standard of quality by the client is referred to as delay
Morakinyo, et al. (2015) stated that delay is a global phenomenon and occur in every
construction project but the degree of its magnitude vary from project to project. Furthermore,
2
Iruobe, et al. (2012) highlighted that effect of delay in construction projects are serious and if not
productivity and increase cost of construction at long run. Commonly, construction projects fall
into cost and time overrun due to issues associated with delays. Delay can cause problem from
prolonging of schedules, additional cost of the project and endangering the quality of the
workmanship (Gonzaley, et al., 2013). These challenges of delays are the problems faced by the
tertiary institution projects Niger State which need urgent solution. These delay in completing
the tertiary institution projects in due time have the negative impacts on the level of assimilation
of knowledge by the student. It also brings about deficit in the facility which will improve the
standard of education in tertiary institution. Therefore, this becomes one of the reasons that
Delay in construction affects the key players in the construction industry including the
contractors, clients and consultants. The Nigerian construction industry has suffered many
setbacks in terms of completing projects on time. Furthermore, most of the construction projects
in Nigeria experienced delay, which lead to the abandonment of the project (Mohammed and
Isah, 2012). In addition to other countries, Malaysian construction industry has been affected by
project delays for many years (Mehdi Riazi, Skitmore and Cheung, 2011). It is significantly
interesting, to study the delay effects in construction industry because research shows that seven
(7) out of ten (10) projects in Nigerian suffered delay in their execution (Ameh and Ogundare,
2013). These increases in project delays in the construction industry is hurting the economy
because it results in wastage of resources, enhance cost of project delivery and frustration among
the key players (Mohammed & Isah, 2012). Yet construction is one of the principal sectors that
3
can revitalize economic growth in Nigeria (Mohammed & Isah, 2012). Investment in
construction projects and related infrastructure and service has multiple direct and indirect
effects on economy of the nation. Unfortunately, delay in tertiary institutions in Niger State
especially buildings, will continue to plague the construction industry in the foreseeable future,
unless mitigation strategies are taken by the industry. The government may lack sufficient
mitigating measures to address the problems of delay. Although much has been done in
identifying the factors that influence projects delay in construction projects in Nigeria and yet the
This is attributed to the fact that there is still lack of information or knowledge for the effective
mitigation strategic measures to address delays. This research therefore, seek to fill the gap that
exist by contribute to these attempts of previous researches in identifying further the causes of
delay in tertiary institutions projects in Niger state with a view of establish mitigation strategic
The problem of delay in the completion period of construction projects in institutional buildings
i. What are the causes of project delay in tertiary institution in Niger state?
ii. What are effects of project delay in tertiary institutions in Niger state.
iii. What measures could be taken to minimize or eradicate delays in tertiary institution
iv. What are the significant relationship between the causes and effects of delay in tertiary
v. How can projects be delivered in tertiary institutions in Niger state without delay
4
1.4 Aim and Objectives of the research
1.4.1 The aim of this research is to appraise the main causes and effects of delay on tertiary
institutional construction projects with a view to minimizing it causes and improve project
delivery.
1.4.2 Objectives
1. To examine the factors responsible for project delay in tertiary institutions in Niger state.
3. To determine the relationship between the factors causes delays identified by the
projects.
Ho: There is no significant relationship between the causes and effects of project delays in
A few selected related articles were presented in this section on causes and effects of delay on
construction works. Yates (2003) studied construction delays, the study developed a decision
support system for construction delay analysis called (DAS). The main categories of delays in
DAS according to the study, includes engineering, equipment, external delays, labour,
Similarly, Mansfield et al,.(1994) studied the causes of delay and cost overrun in construction
project in Nigeria. The result showed that the most important factors are financing and payment
5
for completed works, poor contract management, changes in site conditions, shortage of
Also, Odeh and Battaineh (1999), evaluated the progress reports of 164 building and 28 highway
projects constructed during the period of 1996- 1999 in Jordan. The results indicate that delays
are extensive: the average ratio of actual completion time to the planned contract duration is
160.5% for road projects and 120.3% for building projects. Likewise, AL- Momani (2000),
conducted a quantitative analysis of construction delays by examining the records of 130 public
building projects constructed in Jordan during the period 1990 – 1997. The researcher presented
regression models of the relationship between actual and planned project duration for different
types of building facilities. The analysis also included the reported frequencies of time extension
for the different causes of delays, user changes, weather, site conditions, late deliveries,
Moreover, Mohammed & Isah (2012) conducted a review on project delays in developing
countries during the planning and construction stages. In their study they found that the delay
and cost overrun of construction projects are dependent on the very early stage of the project.
In another related study, Leishman, (1993) presented a paper which discussed different delay
analysiss techniques that are currently used by practitioners in the construction industry, it also
discuss a proposed new delay analysis technique called called the isolated delaytype (IDT).
These techniques were tested against a case example and their strengths and weakness
highlighted.
Empirically based time(physical building time) or contract time ( performance research measure
against the date stipulated in contracts).Bromilaw (1998) developed cost and time model that
could be used to evaluate delay in projects. One outcome of this study was the development of
6
an empirical relationship between total cost of construction and project duration. The equation
period from possession of site to practical completion in days, ‘C’ is the final adjusted project
value, ‘K’ is a constant describing how time performance of cost level. This established the
parameters of cost/ time performance predictability, although the performance of the individual
The relationship was re- tested by Bromilow (1998) in collaboration with the Australian institute
of Quantity surveyors (AIQS) in two follow- up contract time performance studies, in 1976 and
1988. The former study investigated 408 projects built between 1990 and 1996 and found they
despite evidence of greater variation between the time performance of project of similar value,
the relationship between construction duration and project cost uncovered in the 1960s still
holds, the 1988 study investigated 408 projects built between 1976 and 1986. It found that the
average contract time was about 32% for government contracts and 22% for private contracts
concluded that many delays manifest during all projects phases and primarily occur during the
construction phase; however, delay that start in the design phase include inadequate schedule
control by architects, inability of owners to review design in a timely manner, late incorporation
of emerging technologies in to a design, and ineffective coordination and /or inclution of project
user groups. Basu ( 2005) identified factors at the start of project that almost certainly lead to
project delays and provided insight in to the reasons for the delay and their impact on schedule.
Toor and Ogunlana (2008) studied construction delays in Thailand. They found that the
problems faced by the construction industry in developing economies like Thailand could be (a)
7
shortages or inadequacies in industry infrastructure ( mainly supply of resources); (b) caused by
recommended that there should be concerted effort by economy managers and construction
industry associations to provide the necessary infrastructure for efficient project management.
Chan and Kumaraswamy (2008) conducted a survey to determine and evaluate the relative
importance of the significant factors causing delays in Hong kong construction projects. They
analysed and ranked main reasons for delays and classified them in to two groups; (a) the role of
the party in the local construction industry (i.e, whether client, consultants or contractors) and (b)
Result indicated that five major causes of delays were; poor site management and supervision,
unforeseen ground conditions, low speed of decision making involving all project teams, client
initiated variations and necessary variation of works. Odeyinka and yusif (1997) have addressed
the causes of delays in building projects in Nigeria. They classified the causes of delay as
project participants and extraneous factors, client related delays including variations in orders,
slow decision making and cash flow problems. Contractor related delays identified were;
causes of delay identified were; inclement weather, act of nature, labour disputes and strikes.
Similarly, Odeh and Battaineh also conducted a survey aimed at identifying the most important
causes of delays in construction projects with traditional type of contracts from the view point of
construction contractors and consultants. Result of the survey indicated that contractors and
consultants agreed that owner interference, inadequate contractor experience, financing and
payments, labour productivity, slow decision making, improper planning and subcontractors
were among the top ten most important factors. Frimpong et, al., conducted a survey to identified
8
and evaluate the relative importance of significant factors contributing to delay and cost overrun
This research will provide insights that reveal the factors causes delays in tertiary institution
projects in Niger State. It enables project delivery organization or firms to become more
knowledgeable of the causes and effects of project delay, hence looking into ways that can
minimize projects delays. With this both contractors and clients shall maintain productivity and
The research on tertiary institution projects will contribute to the universe of knowledge
regarding the initiation, planning, execution and completion of building projects, since the
The research work will focus on the causes and effects of project delay in tertiary institutions in
Niger state. Data’s will be collected from the Works and Services Department of various
institutions in Niger State. These institutions are Federal University of Technology Minna,
Ibrahim Badamosi Babaginda University Lapai, Federal Polytechnic, Bida, Niger state
polytechnic, Zungeru, Federal college of education Kontagora, Niger State college of education
Minna, College of Agriculture Mokwa, School of Nursing Bida and National Cereal Research
Institute Baddegi.
The targeted group for this research will be professionals like Architects, Quantity Surveyors
2007 & Radosaljevic and Bemert, 2012). that the main project participants in a typical
9
construction project in Nigeria are the client and his/her team of professional advisers
(consultants) on one hand and the main contractor, subcontractors and suppliers on the other
hand.
10
CHAPTER TWO
LITERATURE REVIEW
Construction encompasses all civil engineering works and all types of new building projects as
well as the maintenance and repairs of existing facilities (Salleh, 2009). More so, Radosavljevic
means an act of building or erecting structured products to a prepared shape using appropriate
Zakaria, Ismail and Yusof (2012) identified construction industry as a sector consists of housing,
commercial and infrastructure development. Harrison (2007) defines construction industry as the
subdivision of manufacture and trade based on the building, maintaining, and repairing
of building constructed weather on or off site (CSQ, 2012). The functions that construction has
make it to be big, lively and difficult industry division that plays a vital role in the Nation’s
economy. Building houses, places of works, markets, and places of worships; roads, and
repairing and maintaining nation’s physical infrastructure are part of the functions of
Therefore, construction industry is one of the biggest industries that contributed to the economic
growth of nations. This statement was justified by Mahamid et al. (2012) stated that construction
industry is one of the industry that provides important ingredients for the development of an
economy. Salleh (2009) defines construction industry as a subdivision of the economy that is
11
responsible for the planning, design, construction, maintenance and sometimes demolition of
buildings. The definition further states that it is basically service industry, which obtains its
inputs and outputs from the subdivisions of economy that they are interrelated and inter-linked.
nations, it becomes necessary to study the activities of the industry and also to be very much
vigilant upon all the impediments that will affect the output and quality of the product facilities.
Delay is a term that being referred to as time and cost overrun in construction projects (Memon
et al., 2011). This definition is similar to Hamzah et al. (2012) as delay is time and cost in
construction projects. They stated that delay is time overrun or extension of time for
finishing the project later than agreed in the contract. A delay can also affect to starting or
finishing a specific activity later than planned (Mubarak, 2010). However, the definitions above
captured time and cost but has to be related to the one agreed in the contract or in the inception
stage.
Menesi (2007) defines project delay as the accumulated effect of the delays in the individual
activities. Definition of project delay given here lacks some terms. Budgeted cost and contract
initial period are the most important terms that supposed to be mentioned, because the factors of
delay affect cost and time first before anything else in the construction industry. Amongst the
key players of the industry, contractor normally became the prime victim of delay factors for the
fact that contractor is responsible for all the acts and omissions of the contractor’s employees,
subcontractors, their agents and employees, and any other person performing work under a
12
contract with the contractor (Frank, 2012). Upon all the research conducted, different perceptions
2. Howick et al. 2009 Events that will have an impact on the final
date for completion of the project.
3. Motaleb and Kishk 2010 The time overrun either beyond the
contract date or outside the date that the
parties agreed upon for delivery.
4. Ali, Smith and Pitt 2010 Situation where the project cannot be
completed under the planned time.
8. Marzouk and El-Rasas 2012 Time overrun either beyond the contract
date or beyond the date that the parties
have agreed upon for the delivery of the
project.
13
10. Mehdi Riazi and 2013 Deviation from the originally planned
Lamari period.
Table 2.1 above indicates the definitions of delay from different researchers.
The definitions given mostly consider the inability of the contractor to finished project as
planned. Al-Kharashi and Skitmore (2008) gave the definition as loss of output and revenue in
construction projects. This clearly include cost overrun as the way Memon et al. (2011) and
Hamzah, et al. (2012) defined delay. According to the gathered definitions, delay in construction
project is any situation that can lead to extension of scheduled project period or increase on
initially budgeted cost of the project due to human or natural causes during design and
construction processes.
There are several types of constructions delay due to their causes. They may be caused by the
contractor, client, and client’s representative and from natural source. Aibinu and Jagboro,
(2002) discussed that delays are classified into excusable and non-excusable delays. Excusable
delays are sub divided into excusable with compensation and excusable without compensation
But according to Yates and Epstein (2006), delays can be categorized into four (4) main groups
However, since three decades back, delay was categorized into three (3) groups according to
liability; compensable, excusable and non-excusable delays (Kraiem and Diekmann, 1987).
These three (3) groups of delay were confirmed by Dayi, (2010). Therefore, this research focuses
14
on the four (4) categorization of delay namely; excusable compensable, excusable non-
Excusable delays are delays that the contractor will not be penalized due to their occurrences. It
can be divided into compensable and non-compensable (Tawil et al., 2012). Therefore, excusable
delays simply mean that they are the type of delays which are beyond the control of the
contractor or subcontractors. If it happens, the damages it caused should be on the owner or none
of them responsible for the cause, and in this situation a considerable time be given to the
contractor to complete the project. This situation is known as “time at large” (Hackett et al.,
2007).
Compensable excusable delays are those delays that caused by client (Yates and Epstein, 2006).
It results in time extension and compensation to the contractor. These delays result from various
circumstances as stated by Yates and Epstein (2006). The first is the inability of the owner to
provide work site in time, which causes project delay. Changes which were initiated by the
owner and owner’s delay in delivering order to continue work also subject the project to run in to
delay.
Defective designs, poor coordination of other contractor’s work by the owner and
owner’s inability to supply equipment in time were also types of circumstances that cause
excusable delay with compensation. Misleading of contractor due to the information of the
owner, interference of owner with the performance of the contractor, delay in the approval of
shop drawings are among the situations that lead to excusable delays with compensation. Others
15
are changes in the contract requirements and the encountering of different site condition by the
Excusable delays with compensation at times lead to schedule extension and results to the owner
financial damages to the contractor (Aibinu and Jagboro, 2002). Therefore, this type of delay
will affect the client funding budget because the contractor can claim for damages for all the
Excusable delays without compensation are delays that are not the caused by the owner or the
contractor. They are “Acts of God” or other unforeseeable causes beyond the control of both
parties (Hackett, et al. 2007; Yates and Epstein, 2006). Contracts usually contain a clause called
the force majeure clause, which enumerates the various causes of delays for which neither party
is legitimately responsible.
Non-excusable delays can be attributed to the actions, or inactions, of the contractor. When a
contractor causes delays to the completion of a project, such delays preclude the contractor from
obtaining a time extension and may also trigger delay damages against the contractor. Some of
more common contractor caused delays as mentioned by Muhamad, (2010) include failure of
contractor to mobilize the site and start the work in a timely manner. It includes also delay in the
submission of shop drawings to the owner for approval, inadequate construction equipment and
defective works.
Others examples include deviating from the contract specification, labor, material, and other
16
and subcontractors and failure to execute various portions of the work in a timely manner. More
so, client can claim damages if it had been captured in the contract agreement (Muhamad, 2010).
Therefore, contractor is liable to pay damages to the client in this type of delays. It is important
to note here that contractor is to look at all the possibilities of avoiding the delays for him to
17
2.2.5 Concurrent Delays
On a typical construction project, delays do not constantly fall into one of the three previous
categories discussed but quite often there are multiple factors that cause or contribute to delays
(Yates and Epstein, 2006). Therefore, Ibbs, Nguyen and Simonian (2011) defined concurrent
delays as ordinarily labeled as two or more delays that happen at the same time, either of which
and excusable compensable types of delay. From the above definitions given by the scholars, it is
conformed to the statement of Dayi (2011) which says, it is the type of delays which seems like a
18
2.3 Delay factors in Construction Projects
Delay in construction is associated with three main causes (Hackett et al., 2007). Ren, Atout and
Jones (2008) classified delay into three (3), namely delay caused by contractor, employer or his
representatives and those by events that are out of both the contractor and employers and it is
changes by owner or his agent during construction, partial payments during construction, and
causes of delay in construction projects (Abd El-Razek, Bassioni and Mobarak, 2008).
Ali, et al. (2010) concluded in their research that labor shortage, contractors’ financial
difficulties, construction mistakes and defective works were the most common causes of delay.
Furthermore, the research mentioned the effects of delays on construction industry as cost
overrun, extension of time, late payment, rescheduling, affect company reputation and loss of
productivity and efficiency. The result shows that cost overrun and extension of time have
significant effects on contractor. However, the contractor reputation did not fall in to one of the
common effects on contractor in the research, despite its advantage. Therefore, looking further to
investigate and substantially justify the effects of constructions delays on contractor’s reputation
Saleh (2009) define contactor as the person or organization that is responsible for planning and
execution of construction project. Therefore, contractor related delays are the most important
delays in the construction industry. This statement was justified by Gündüz et al. (2013). They
19
said that contractor-related group of delay factors was the most significant group to cause delays.
1 Alwi and Indone Too much overtime for Lack of trades’ skill.
Hampso sia labour. Slowness in making
n (2003) Inappropriate decisions.
construction methods. Design changes.
Equipment shortage. Delay of material delivery
Poor equipment choice. to site.
Ineffective equipment. Inappropriate construction
Outdated equipment. methods.
Poor site layout.
Poor storage of material.
Misuse of material.
Lack of contractor’s skill.
Lack of trades’ skill.
Poor scheduled delivery.
2 Ren, Dubai Inappropriate Preparing the method
Atout (UAE) organization statement.
and Management. Financing project by the
Jones Lack of technical contractor.
professional in the Organizational chart.
(2008)
organization. Communication externally
Unsmooth external and and internally.
internal communications. Mistake during
Lack coordination with construction.
subcontractors. Unrealistic control
Centralization with top duration.
Management. Many provisional sum and
Delayed mobilization. prime cost.
Incompetent contractor Nomination of
staff. subcontractors and
Poor planning, suppliers.
scheduling or resource Client’s irregular payment
management. to the main contractor.
Poor quality control. Incomplete drawings.
Congested construction Delay in approval of
site. document.
Incomplete contract
document.
Changes in drawings and
20
specifications.
And duration of inspection
procedure.
3 Abd El- Egypt Financing by contractor. Financing by contractor.
Razek, Slow delivery of Delay in contractor’s
Bassioni materials. payment by owner.
and Preparation of drgs and Design changes by owner
sample. or his agent during
Mobara
Lack of data base in construction.
k (2008)
estimating activity Partial payment.
duration and resources. Non-utilization of
Shortage of materials. professional
Controlling SC by MC. construction/contractual
Poor labor productivity. management.
Errors due to Slow delivery of materials.
inexperience. Difficulty of coordination
Shortage in equipment. between various parties
Shortage in labor. (contractor, SC, owner,
Unskilled operators. consultant) working on the
Poor equipment project.
productivity. Slowness of the owner
And accident during decision making process.
construction. The relationship between
different SC schedules.
Preparation of shop
drawings and material
samples.
4. Toor. Thailan Lack of competent Lack of standardization of
and d subcontractor / suppliers. design.
Ogunlan Lack of necessary Lack of contractor’s
a (2008) machinery. experience.
Tools and automation Inadequate experience.
available for project. Lack of competent
Lack of contractor’s subcontractor /suppliers.
experience and control Unrealistic project
over project. schedule.
Poor efficiency of Lack of responsibility.
supervisor or foreman. Contractor’s financial
Using obsolete difficulties.
technology. Poor management.
Contractor’s financial Poor site access.
difficulties. Poor efficiency of
Inappropriate supervisor or foreman.
construction methods. Delay of client payment
Lack good relationship Shortage of funding.
with client/consultant. Errors and omissions in
21
design documents.
Confusing and ambiguous
requirements.
Low constructability of
design.
Lack of timely decision.
Slow responses from the
client organization.
Impractical design.
Unclear lines of
responsibility.
Lack of machinery.
Tools and automation
available for project.
5. Sweis, Jordan Lack of contractor Poor planning and
Sweis, personnel. scheduling of the project by
AbuHam Shortage of professionals. the contractor.
mad, Insufficient coordination Financial difficulties faced
among parties by by the contractor.
and
contractor. Too many change orders
Shboul
Delay in mobilization. from owner.
(2008). Safety rules and Shortage of man power.
regulations practices in the Incompetent technical staff
organization. assigned to the project.
Incompetent technical
staff.
Improper technical study
by the contractor during
the bidding stage.
Poor planning and
scheduling.
Ineffective quality control.
Use of unacceptable
construction techniques.
Financial difficulties.
Delays payments to sub-
contractors.
22
Pakir during construction. Design errors.
(2009) Inadequate of Shortage of supply.
experiences, Slow decision making.
Site accidents. Financial issues.
Negligence. Shortage of materials.
Late deliveries of Cash-flow problems.
materials and equipment. Increase in quantities.
Mismanagement by the Contractor
contractor. mismanagement.
Negotiation during Executive bureaucracy in
construction. the owners’
Mistakes during organization.
construction. Notification of extra
Conflicts in work works.
schedules of Changes in site
subcontractors. condition.
Dispute and shortage of Date of notice to proceed
materials. and financing matters.
Effects
Loss of interest by the
stakeholder.
Blacklist by authorities.
Waste of money and
time.
Declination of
reputation.
7 Motale UAE Late delivery of Causes
b and materials.
Kishk. Slow mobilization of Change orders.
labor. Lack of capability of
(2010)
Shortage of skilled labor. client representative.
Labor productivity. Slow decision making by
Labor supply. client.
Absenteeism and strike. Lack of experience of
Low motivation. client in construction.
Insufficient numbers of Poor site management
equipment. and supervision.
Equipment allocation Incompetent project
problems. team.
Inadequate modern Inflation /price
equipment. fluctuation.
Unreliable sub- Inaccurate time
contractor. estimating.
Inappropriate Late delivery of
construction methods. materials.
Inadequate contractor Improper project
planning/scheduling.
23
experience. Inaccurate cost
Contractor’s financial estimating.
difficulties. High interest rate.
Inaccurate site Client’s financial
investigation. difficulties.
Unreasonable constraint
to client.
Inappropriate onstruction
methods.
Effects
Cost and time overrun.
24
n, Late delivery of delays in design.
Abdur materials. Unrealistic contract
Rahma R/ship between duration and requirements
n. and management and labor. imposed.
Poor site Lack of experience.
Azis
management. Late delivery of
(2011)
Mistakes during materials and equipment.
construction. Relationship
Cash and financial between management and
difficulties. labor.
Poor financial Delay preparation
control on site. and approval of drawings.
Delay in material Inadequate
procurement. planning and scheduling.
Rework. Poor site
Shortage of site management and
workers. supervision.
Incompetent sub- Mistakes during
contractor. construction.
Labor productivity. Changes in
Equipment material specification and
availability and failure. type.
Shortage of skilled
labor.
Waste on site.
No. of construction
going on at the same time.
Lack of
constructability.
Contractual claims.
Unsuitable
construction methods.
Insufficient no. of
equipment.
High cost of
machinery and
maintenance.
Labor absenteeism.
Severe overtime
and delay payment to
supplier and subcontractor.
25
11 Ali, Malaysia Contractor’s financial CAUSES
Smith, difficulties.
and Pitt Material shortage. Labor shortage.
Labor shortage. Contractor’s financial
(2012)
Poor site management. difficulties.
Equipment and tool Construction mistakes
shortage. and defective works.
Construction mistakes Coordination problems.
and defective works. Material shortage.
Coordination problems. Poor site management.
Equipment and tool
shortage.
EFFECTS
26
contractor.
Rework because of
errors during construction.
Delay in
commencement.
Poor qualification
of the contractor’s
technical staff.
Poor resource
management.
Poor site
supervision by contractor.
Improper
construction method.
14 Akogbe, Benin Poor site management Financial
Feng, and supervision. incapability.
and Financial capability. Financial
Zhou Poor subcontractor difficulties of owner.
performance. Poor performance
(2013)
Materials procurement. by SC.
Lack of skilled workers. Materials
Defective work. procurement.
Labour injuries. Changes in
Construction mistakes. drawings.
Inadequate planning. Inadequate
Scheduling, and planning and scheduling.
equipment availability. Slow inspection of
completed works.
Equipment
availability.
Preparation and
approval of drawing.
Accepting
inadequate design.
15 Mahami Palestine Difficulties in Segmentation of
d (2013) financing project by west bank and limited
contractor. movement between areas.
Poor Political situation.
communication by Progress payments
contractor. delay by owner.
Conflict between Lack of equipment
contractor and other efficiency.
parties. Difficulties in
Poor resource financing project by
management. contractor.
Rework due to Personal conflicts
27
errors during construction. among labors.
Ineffective Poor
scheduling of project by communication by
contractor. consultant.
Poor qualification Conflict between
of contractors’ technical contractor and other
staff. parties.
Delay in Award project to
commencement. lowest bid price.
Poor site Unreasonable
supervision by contractor. project time frame by the
Improper owner.
construction method.
The contractor related causes of delay in the construction industry was compiled as in Table 2.2.
The literature available covers one decades of period, ranging from 2008 – 2018. Alwi and
Hampson, (2003) identified twelve (12) contractor related causes of delay in their literature. The
result of their research indicates that lack of trade skills slowness in making decisions, design
changes, and delay in the delivery of materials to site were significantly causes delay in
construction due to contractor lapse. However, the research did not touch the effects of the delay
on the key players in the construction industry, which contractor is one of them.
Another research conducting by Ren, et al.. (2008) stated various factors of delay caused
by the contractor. The findings of the research revealed that preparing method statement,
financing project by contractor, organizational chart, and communications (both internally and
externally) and mistakes during construction caused delay from the contractor side. These most
significant factors in the research most have effects on the contractor. Because the delay that
In addition, Abd El-Razek, et al. (2008) conducted a research in Egypt. The research
identified financing by the contractor, owners delay in payment; changes during construction by
the owner, partial payment and non-utilization of professional contractual management were the
28
most significant factors that caused delay. Out of these factors, financing by the contractor and
resembles Ren, et al. (2008), where it indicates that financing project by the contractor is among
the significant factor that causes delay. In contrast, Toor and Ogunlana (2008) identified lack of
unrealistic project schedule were the most significant factors. The research identified contractor
financial difficulties as less significant. This may be due to geographical locations where the
researches were conducted. However, Sweis, et al. (2008) confirmed that poor planning and
scheduling, financial difficulties by the contractor were the most significant causes of delay that
Improper planning and lack of effective communication were the most significant factors
that caused delay in construction project related to contractor as stated by (Tumi et al., 2009).
But in the case of Motaleb and Kishk (2010), it was stated that late delivery of materials, slow
mobilization of labor, shortage of skilled labor, labor productivity and labor supply were causes
of delay that related to contractor. Others are absenteeism, low motivation, insufficient
equipment and their proper allocation, inadequate standard equipment, unreliable sub-contractors
and inaccurate site investigation were also contractor related causes of delay. However, the
findings of the research revealed that change orders and incapable client’s representative were
the most significant factors that cause delay. These are client and the representative related
causes of delay.
The research conducted by Ayudhya (2011), stated that main contractor financial
29
construction industry, it was stated that lack contractor experience, late delivery of materials and
relationship between labor and management were the significant factors (Memon, et al., 2011).
Ali, et al. (2012), outlined seven contractor related causes of delay in Malaysia as labor shortage,
financial difficulties, mistakes, coordination problem, materials shortage, poor site management
and shortage of equipment. They also outline effects of delay as cost and time overrun, late
payment, rescheduling, affects company reputation, and low productivity and efficiency.
Therefore, looking at all the delay factors and their causes, discussion on the effects of delay is
not adequate. More so, the research conducted, which investigates the effects of delay on
Based on the research conducted by Mehdi Riazi and Lamari (2013), it identifies time frame
extension, increase in cost due the extension of time, government periodic budget and plan
execution, and cost overrun as effects of delays in construction projects. Furthermore, they said
the reputation is always at stake in delay cases and the government risks losing public
confidence, also the depressing condition is subject to litigation and arbitration. Mehdi Riazi et
al. (2011) stated in their research that delays have serious effect on construction organizations,
which results to increase in cost of the project, loss of opportunity cost, damage in reputation,
arbitration, litigation and even to the worse situation of abandonment of the project. However,
scholars concerned on the effects of delays on construction organization in general, but there is
need to look at the effects on the reputation of the organizations since reputation is an intangible
taking on other profit-earning projects with the resources tied down on the delayed project
30
(Ndekugri, Braimah and Gameson, 2008). Table 2.3 summarizes the effects of delay in the
construction industry from various studies. Table 2.3, summaries the effects of construction
delay in construction industry from various researches around the world. This is indicating that
delay has effect on the construction projects. The effects of this delay affect the contractors,
clients and consultants in the projects. This research focuses the contractor and the effects of this
Researchers confirmed various effects of delay in construction industry. Cost overrun, time
overrun, disputes, arbitration, litigation and total abandonment were the effects of delay in
construction industry (Motaleb and Kishk, 2010; Abedi, et al. (2011) and Mehdi Riazi, et al.
(2011). In addition, Mehdi Riazi, et al., (2011) mentioned that, loss of opportunity cost and
Ashnaari et al. (2010) conducted a research and confirmed that increased disputes and costs, loss
of outputs, create social problems, affects social and economic conditions in the project is being
built were effects of delay. Although Alnuaimi, et al. (2010) stated mentioned effects of delay as
time overrun, claims and disputes, cost overruns, affect the performance and moral of labor and
31
Table 2.3: Effects of Delay
No Author Year Location Effects of Delays
32
Abandonment.
8. Ali, Smith 2012 Malaysia Cost overrun.
and Pitt Extension of time.
Late payment.
Rescheduling, affects company
reputation.
Lost productivity and efficiency.
9. Tawil, et al. 2012 Malaysia Increase to disturbance of work.
Loss of productivity.
Late completion of project.
Increase time related cost.
Create third party claims.
Abandonment of contract.
Termination of contract.
Therefore, contractor is one of the stakeholder and key participants in construction project
Consequently, Haseeb, et al. (2011) mentioned over cost and time, disputes, negotiations, law
suits, litigation and abandonment were the effects of delay. Cost overrun, extension of time, late
payment, rescheduling and loss of productivity and efficiency were the effects of delay in
construction industry (Ali, et al. 2012). The research stated that rescheduling as one of the effects
of delay affect company reputation. The last research in Table 2.3 is Tawil, et al. (2012) that
mentioned seven effects of delay. Increase to disturbance of work, loss of productivity and late
completion of project were the effects with highest rank. Others are increase in time related cost,
Effect of delays in the construction industry has gone round all over the developing countries in
the world. Nigeria is not an exception, therefore table2.5 in page highlighted effects of delay in
Nigerian construction industry. This shows that, there is need to identify the effect of
construction delays in the Nigerian construction industry. Therefore, next section is to discuss
33
2.6 The Nigerian Construction Industry
Aibinu and Jagboro (2002) stated that, the Nigerian construction industry remains the position of
occupying a very important place in the nation’s economy. Despite that, the construction
industry suffered severe effects of delays. Oladinrin, Ogunsenmi and Aje (2012) identified that,
the Nigerian construction industry shows an important part in the economy, and the activities of
the industry are also vital to the accomplishment of national socio-economic development goals
activities affect nearly every aspect of the economy and that the industry is vital to the continued
The influence of the construction industry to national economic growth requires improved
efficiency in the industry by means of cost effectiveness and timeliness, and would surely
contribute in savings cost for the country entirely (Ademeso and Windapo, (2005). Construction
industry in Nigeria is like any other construction industry in the world in terms of the economic
growth and also in problems facing. Eshofonie, (2008) justifies that Nigeria is like most
developing countries where construction industry plays a dominant role in the economic
Factors responsible for construction delays varied in to many perspectives and approaches.
Aibinu and Odeyinka (2006) listed 44 causes of delay from their literature review which form
part the questionnaire they distributed. They used concordance analysis to see the prioritization
of these factors. However, they used chi-square to test the prioritized time influencing factor in
construction projects. By relating the Pareto principle to study the distribution pattern of the
delay factors, the work has been able to observe old and frequent problem from a fresh angle. It
34
has also delivered some indication of the input of 44 delay factors to overall project delays. The
result of Pareto analysis established the interdependent nature of building activities and roles.
The research said that, disputes may arise from questions relating to causal factors, contract
interpretation, and quantum of the claims. Therefore, delays represent an area of leakages in the
construction industry. In Nigeria, the problem of delays is more, especially when one considers
According to Mohammed and Isah (2012), delay factors in the Nigerian construction
industry particularly contractor’s related are improper planning, lack of effective communication,
, shortage of supply like steel, financial issues, shortage of material, cash flow problems during
negligence, late deliveries of materials and equipment, liquidated damage and disputes.
Financial difficulties faced by the contractors, failure to pay for completed works, shortages of
resources, escalations of material prices, late delivery of materials, fluctuations in resources cost,
lack of communication, inaccurate site inspection, “lowest bid wins” system, labor disputes and
Akinsulire, 2012).
In another perspective, Sunjka and Jacob (2013) carried a research on the causes of delay in
during construction stage, incompetent site management, wrong choice of bankers, unskilled site
manpower, improper equipment selection and faulty equipment, labor disputes, poor quality
35
materials and material shortages as delay factors related to contractor. Therefore, it is important
to further research on the effects of delay on contractor reputation in the Nigerian construction
industry.
According to Akinsiku and Akinsulire (2012), effects of delay are always unbearable on
construction projects. They also stated that the effects are cost and time overruns, interest
accumulation on capital to finance, wastage and under-utilization of man power resources and
claims. It further stated that under-utilization of equipment, loss of confidence on the contract
(therefore jeopardizing the reputation of contractor in the case of future tendering chances) and
late returns of income are effects of delay. Among the effects also include reduction of
employment opportunities, dispute between parties involved, aids the decrease in the tempo of
economic activities in the nation, additional insurance charges, extra taxes and dues due to delay.
36
Lowering of living standard.
Wastage/underutilization of
resources.
Reduction of employment
opportunities.
Decrease in the tempo of economic
activities.
Decrease in the revenue accruing
to government.
Difficulties in attracting foreign
loans.
3 Akinsiku Questionnaire (quantitative) Finance difficulties by clients and
and contractors.
Akinsulire Analysis The effects are
(2012). Ranking based on the Cost and time overruns interest
accumulation on capital to finance.
(Average Mean Score)
Wastage and under-utilization of
man power resources.
Claims, under-utilization of
equipment.
Loss of confidence on the contract
(therefore jeopardizing the
reputation of contractor in the case
of future tendering chances).
Late returns of income.
Reduction of employment
opportunities.
Dispute between parties involved.
Aids the decrease in the tempo of
economic activities in the nation.
Additional insurance charges.
Extra taxes and dues due to delay.
Insolvency of the contractor,
inability to meet the living
standard.
Arbitration/litigation and total
abandonments.
4 Mohamme Pilot survey and Improper planning.
d and Isah questionnaire Lack of effective communication.
(2012) Design errors.
Analysis Shortage of supply like steel.
Slow decision making.
Financial issues.
Factor Analysis
Shortage of material.
Cash flow problems during
construction.
37
Increase in quantities and
mismanagement by the
contractor.
Effects
Loss of interest by the
stakeholder.
Blacklist by authorities.
Waste of money and time.
Declination of reputation
5 Sunjka and Questionnaire (quantitative) Causes
Jacob Youth unrest.
(2013) Analysis Militancy and communal crises.
Inadequate planning by the
contractors.
Factor analysis, ANOVA and
Delay or non-payment of
t-test
compensation to the communities.
Wrong choice of consultants and
contractors.
Weather condition; poor contract
management by the consultants.
Late identification and resolution
of drawings and specification
errors and omission, lack of
community buy-in.
Poor contract management by the
consultant’s inappropriate design
by the consultants.
Unrealistic contract duration by
the clients.
Poor coordination of
subcontractors by the contractors.
Effects
Time overrun and Budget
overrun.
Disputes and claims.
Others include insolvency of the contractor, inability to meet the living standard,
industry.
Ibironke, et al. (2013) conducted a research titled as “analysis of non-excusable delay factors
influencing contractor’s performance in Lagos state, Nigeria”. The research states that, the
38
Nigerian construction industry has a very poor reputation for coping with delays. Therefore, it is
significantly clear that delay affects the contractors’ performance as well as their reputation in
However, the findings in table 2.4 which were mostly from the southern part of Nigeria listed the
effects of delays in the construction projects. The findings mentioned reputation or declination of
image among the effects of delays, though its effects on the contractor reputation were not
looked into. Reputation is the only effect that is intangible among the effects of delays in the
construction industry. Therefore, it is the main reason that prompts the researcher to look at these
variables most especially on the contractor’s reputation in the northern region of Nigerian.
39
CHAPTER THREE
3.1 Introduction
This research work focused on causes and effects of delay on tertiary institutional construction
projects in Niger State. This chapter outlines the research methodology that will be adopted to
ensure the reliability and proper understanding of this research. These include research design,
research population, sampling frame, and sampling size, sampling techniques, method of data
collection and method of data analysis. The detail explanation of each unit will be given to aid
Research design is defined as the detailed outline of how an investigation will take place a
typical research design will include how data is to be collected, what instrument will be
employed, how the instruments will be used and the intended mean of analyzing data collected
The design of this research is historical in nature using qualitative method. Where by structured
questionnaire will be administered by the respondents. Through the review of the past literature
to identified the major factor that causes delay in tertiary institutional construction projects.
Historical research is defined as integrated notation or description of past events of facts written
in a spirit of critical inquiry for the whole truth. It deals with determination, evaluation and
explanation of the past events essentially it is for the purpose of gaining better and clearer
understanding of the present and making a more reliable prediction of the future.(Alamu and
Olakosi, 2010) Historical research is also defined as a systematic and objective location,
40
evaluation and synthesis of evidence in order to establish facts and draw conclusions about the
past events the major purpose of a historical research is to obtain a better understanding through
the evaluation of the past and intelligent prediction of the future it also aids in avoiding past
a- To have a clear view of the presents situation via the past history (it attempt to understand
b- To arrive at the accurate account of the past to find out the truth about event or subjects
c- To make accurate, reasonable and informed prediction about the future.(Rasaq and
Ajayi,2000).
Population is a collection of elements about which we wish to make an inference this refers to a
set of all possible cases of interest in a given research activity, it is a collection of objects or
individuals whose properties are to be analysed, it could be classified into finite population
(when the element of the population could be physically listed) and infinite population (when the
element of the population could not be physically listed) (Rasaq and Ajayi,2000).
The population of this research will be classified into two types the first being the tertiary
institutional projects awarded from 2007-2019 in Niger state. By either the Federal or State
Governments and the second set of `the population will be the stake holders in the construction
industry which comprises of the clients’ contractors, Quantity Surveyors, Engineers, Project
managers and other professionals that actively participated in the execution of projects over the
41
3.4 Sampling frame
Sampling frame is a list of all items within the population who can be sampled and may include
individuals, house hold or institution. For instance, if we take the house hold as the sampling unit
then a list of house hold heads obtained from the census data can serve as a frame (Rasaq
A theoretical population may include all conceivable elements or members of the population
which in practice, the researcher may not be able to reach. Thus the researcher tries to
differentiate between a working universe and a theoretical universe. The working universe which
he actually uses for the purpose of sampling in the sampling frame which must also be clearly
The sampling frame for this research will be Institutional building projects awarded and executed
in the three senatorial zones of Niger State (A, B and C) within the period of 2007 -2017 in
addition, a list of project monitoring team of the above projects including Engineers, Quantity
surveyors, Project manager, clients and Contractors will be randomly selected to administer
Sampling size is the count of individual sample or observations in any statistical setting such as
The sample size of 60 numbers of institutional building construction projects awarded and
executed in Niger State within the period of 2007 and 2019 Stratified random sampling
techniques will be used for different stake holders that have assisted in the execution of
42
Stratified random sampling is a process in research where by variables are classified into groups
according to desire characteristic of the variables such as sex, location, academic ability, age
group, nationality, religious affiliation, socio – economic group etc. (Rasaq and Ajayi, 2000).
Stratified random sampling may also be defined as a two – stage sampling process which
involves,
ii- Thereafter, using a process of simple random sampling techniques or systematic random
sampling techniques to draw the required sample from each stratum (Rasaq and Ajayi, 2000).
The sample size of this research for the stake holders will be 75 in number which represent the
total number of registered professionals involved in road construction projects in Niger state.
Sampling techniques is a systematic process used to select the required portion of a target
such a way that each element (member) of the population has an equal chance of being selected,
in any research, a representative sample of a population is that sample which has approximately
the characteristics of the population relevant to the research under investigation (Rasaq
andAjayi,2000).
Purposive Sampling of non - probability Sampling techniques will be used to select a required
portion of a target population. It will only consider stakeholders that have assisted in execution
of the project.
selects certain groups as sample because of their relevance to the investigation under
consideration. A major advantage of the purposive sampling techniques is that it ensures the
43
gathering of data from respondents who are difficult to locate but crucial to the study of interest.
(Rasaq andAjayi,2000).
There are two types of data primary data and secondary data. Primary data are the collection of
facts and figures relating to the population in the census for instance, by the user for specific
purpose. The main advantage of obtaining such data is to obtain the exact information needed
terms are carefully defined to avoid misunderstanding, if however, the exact data are later
collected by someone else or group of people for an administrative or research reasons they are
termed as secondary data (Rasaq andAjayi,2000). for the purpose of this research, Primary
To identified factors responsible for delay and effects of delay in tertiary institutional
construction projects an extensive literature review will be required from which a structure
Procedure for data collection will be through the administered of questionnaire to respondents
The study will make use of both descriptive and inferential method of analysis to analyse data
(correlation and regression) while for objective one mean item score and standard deviation will
44
Inferential statistics are mathematical method that employ probability theory for deducing
(inferring) the properties of a population from the analysis of the properties of a data, sample
drawn from it is concerned also with precision and reliability of the inferences it helps to draw
Regression analysis will be used to analysed data for objectives two, three and four
The idea of regression is a step further from merely finding the degree of relationship that exist
between two set of variables, then a line equation can be formulated for the linear equation in
order to predict the value of one variable given the other, finding the equation that gives the
relationship between two variable x and y is known as finding the regression line of x and y
45
Table 3.1 Analytical tools for achieving each objective
46
CHAPTER FOUR
4.1 Introduction
This chapter covers the analysis of the data collected for the study. The analysis was based on the
objectives of the study. The personal data of the respondents were analyzed as well as their
This section primarily described the information or background of respondent in relation to the
firm, years of their working experience, and respondent’s’ academic qualification and
The figure 4.1 shows that 28% of respondents works with construction firms 19% were with
consulting firms while 37% and 16% were from client and project financier organisations.
20
37
15 28
10 19
16
5
0
Contractor Consultant Client Financier
Organasations
47
4.2 Respondents position in the organisation
Figure 4.2 indicates that 11% numbers of respondents sampled for the study were Architects in
their respective organisations, 26% were Quantity Surveyors, while 18% 24% and 21% held
Inferences drawn from this was that the respondents sampled are knowledgeable enough to
25
20
Percentage
15
26
24
10 21
18
5 11
0
ARCHITECT Q/S PROJ. MANAGER CONTRACTOR C/ENGNR.
Positions
Figure 4.3 indicates that 19% of respondents had professional membership of Nigerian Institute
of Builders (NIOB), 28% were holders of Nigerian Institution of Quantity Surveyors while
members with NIA, NSE and NITP were 22%, 17% and 14% respectively. Inferences drawn
from this was that the respondents sampled are certified professional with adequate knowledge
related to the aim of this study to comprehend the contents of the questionnaires, thus providing
suitable responses.
48
Professional bodies of respondents
30
25
20
Pescentage
15
28
22
10 19
17
14
5
0
NIOB NIQS NIA NSE NITP
Professional bodies
49
4.4 Years of experience of respondents in construction
figure 4.40 shows that 10% of respondents sample had working experience of less than 5 years
in the building industry, 19% had between 5- 15 years working experience, while 30% had spent
11 -15 and 41% had 15 years and above working experience in the building industry. This is an
indication that the respondents had spent reasonable time within the industry to have familiarizes
25
20 41
15 30
10 19
5 10
0
<5 Year 5-10 Years 11-15 Years >15 Years
Years
This section covered client related factors, contractor related factors, consultant related factors
and external related factors that caused delay in project delivery. Each factor of delay was
studied using the Statistical Mean Score to examined level of important such as (4.5 to 5.0 VS,
3.5-4.49 Sign, 2.5-3.49 Moderat, 1.5-2.49 fair, 0.0-1.49) of delay factors and group in
construction projects. The ranking of delay factors which were examined by the researcher from
the view point of all respondents were shown in the tables below.
50
Table 4.1 Client related factors
Mean S. Rank
CLIENT RELATED CAUSES scores dev
mean scores revealed that: insufficient funding (4.25), Delay or non-payment for completed
works (3.94), Cash flow problem during construction (3.89), Interference with project
performance (3.86) and Financial issues were top most five factors of delayed of building
project in Niger state thus ranked 1st, 2nd , 3rd, 4th and 5th respectively. This result agrees with
51
In the same way, Increase in quantities, Impractical allocation of resources, slow decision
making, Date of notice to proceed and wrong choice of consultant and contractors were ranked
6th., 7th , 8th, 9th and 10th with statistical mean values of 3.73, 3.65, 3.62, 3.58 and 3.54
respectively. Findings are in agreement with Muhamad, (2010) studied that failure of contractor
to mobilize the site and start the work in a timely manner, delay in the submission of shop
drawings to the owner for approval, inadequate construction equipment and defective works
However, the calculated mean scores were above 3.50 indicated that these factors were highly
Meanwhile, Design alteration and change order, Unrealistic contract duration and Dispute
variation order had statistical mean values of 3.44, 3.27 and 3.14 and were ranked as 11th, 12th
and 13th respectively. Although these factors were having a mean scores between 3.14 and 3.44
and this shows that there were slightly highly responsible for delayed in project delivery. These
results was in line with the findings of Mansfield et al,(1994) studied the causes of delay and
Also, possible prejudice (1.68) and ranked 14th among all the factors responsible for delayed of
project delivery.
52
Table 4.2 Contractor related factors
Mean S. Rank
CONTRACTOR RELATED CAUSES scores dev
53
Change order and mistake 3.42 1.11 23
was revealed from the table that out of twenty eight (28) factors identified by the study, nine (9)
factors which includes: Project management issues, inappropriate construction method, Mistake
like steel, and concrete, Financial matters and Indicative of experience, with the corresponding
mean values of 4.74, 4.70, 4.67, 4.67, 4.64, 4.64, 4.59, 4.59 and 4.53 were ranked 1st, 2nd,
3rd,4th,5th,6th,7th,8th,and 9th respectively. The mean scores related to these factors were
observed greater 4.50 indicating their very highly responsible for project delays. Findings from
Similarly, the table identify that, Conflict in works schedule of subcontractor (3.87), Contractor
regarded contractual relationship (3.86), Experience of project team (3.85), Quality assurance
/control, Poor coordination (3.81), Site accident (3.79), Negligence (3.72), Late delivery of
materials & equipment (3.66), Economic condition (3.65), Liquidated damages (3.61),
Negotiation during construction (3.53) and Inadequate experience (3.49), were ranked 10th, 11th,
13th, 14th, 15th,16th,17th,18th,19th,20th,21st, and 22nd respectively. Inferences drawn from the
analysis indicated that the factors mentioned above were slightly highly responsible for delayed
54
55
Table 4.3 Consultant Related Causes
Mean S. Rank
CONSULTANT RELATED CAUSES scores dev
discovered from the table via statistical mean scores that: Inappropriate design is the most
significant factor of delayed in construction projects with a mean score of (3.93) and ranked 1st,
this was preceded by poor contract management (3.81) and ranked 2nd. While design errors, late
56
strategy, over inspection, long waiting time for inspection & testing, inappropriate coordination
of information, change orders and mistakes and discrepancies in contract documents and quality
assurance/control have mean scores of 3.81, 3.76, 3.73, 3.64, 3.58, 3.55, 3.53 and 3.51
respectively and ranked 3rd , 4th, 5th, 6th, 7th, 8th, 9th and 10th respectively. The mean scores
of these factors were observed to have valued more than average indicating that they were
slightly and highly responsible for delayed in delivery of construction projects in tertiary
institutions in Niger state. However, findings from the study were in agreement with the study of
AL- Momani (2000), that conducted a quantitative analysis of construction delays by examining
the records of 130 public building projects constructed in Jordan during the period 1990 – 1997.
Conversely, the table identified that the factors with lowest mean values were: Long period of
approval of tests and inspections (3.25), experience of project team (3.24), failure of RIBA plan
of work application (3.21) and late identification & resolution of drawings (3.13) and
specification error & omission (3.11) respectively were ranked 11th, 12th, 13th, 14th and 15th
respectively.
Mean S. dev Ra
EXTERNAL RELATED CAUSES scores nk
delayed in projects delivery. Five factors were identified by the study, the factor with highest
57
mean score values is natural disasters (e.g. floods, lightning strikes) having a mean scores of 4.42
and ranked 1st. while weather conditions had a mean score of 4.33 and ranked 2nd, similarly,
Change in government’s leadership & politics (3.70), Interference by political leaders (3.59) and
Religious factors (3.58) were ranked 3rd, 4th, and 5th respectively.
Finding from the study were in (Aibinu and Jagboro, 2002) that delay will affect the client
funding budget because the contractor can claim for damages for all the causes emerged from the
58
Table 4.5: Effects of Construction Delayed
59
Litigation in construction projects 3.40 1.12 22
state. It was established based on the mean scores that: abandonment of building projects was the
most significance effects of project delay with mean score of 4.29 and ranked 1st while
inadequate planning (3.94), variation of project scope (3.93), incompetent project manager
(3.80), delay in progress payment by client (3.77), reduction of employment opportunities (3.74),
faulty design (3.67), wrong estimate (3.64), unrealistic contract duration by the clients (3.64),
shortage of materials (3.59), variation of project scope (3.58) and inadequate cost control (3.57)
were ranked 2nd , 3rd ,4th, 5th, 6th, 7th,8th,9th, 10th 11th, 12th, 13th, 14th and 15th
respectively.
Correlation analysis was employed to determine the relationship between the factor causes
4.6 Table: The relationship between: Client related causes, Contractor related cause and
Eternal factor related
60
Analysis Variables Pearson R2
No Correlation Value P-value Remarks
X Y (R) (%)
The correlation coefficient (r) between Client related factors of delay and contractor related
causes was observed to be positive with value of 0.717. The square of ‘R’ value weight 51.0%
averagely correlated. The P. value stood (0.04) less than 0.05. Similarly, the P-value (0.00)
which was less than critical value at 0.05 indicted that the relationship between the two variables
While the relationship Client related causes and consultant related, were also observed to be
positive and highly correlated with R-values (0.813) and R2 Value% (66%). The P-value was
0.00 greater than 0.005 indicating that the relationship between the two variables was statistical
significant.
While the relationship Client related causes and External related was also observed to be positive
and highly correlated with R.Value (0.792) and R2 (Value %) 62%. The P-value was 0.11
greater than 0.005 indicating that the relationship between the two variables is not statistical
significance.
Inferences drawn from these results were that there is positive relationship between the client
61
Table 4.7 : The relationship between: Contractor related causes and Eternal factors
related, Contractor related cause and Eternal factor related
factors of delay was observed to positive with value “R” value of 0.901. The square of ‘R’ value
(%) weight 81.0% strongly correlated. The P. value stood (0.000) less than 0.05. Hence the P-
value (0.00) which was less than critical value at 0.05 indicted that the relationship between the
two variables was statically significance; hence the null hypothesis was rejected.
Likewise, the correlation coefficient (r) between contractor related factors of delay and external
related factors of delay was observed to be positive with value “R” value of 0.96. The square of
‘R’ value (%) weight 91.0% strongly correlated. The P. value stood (0.32) greater than 0.05.
Hence the P-value (0.32) which was greater than critical value at 0.05 indicted that the
Table 4.8: The relationship between: Consultant related cause and Eternal related factor
62
The correlation coefficient (r) between Consultant related factors of delay and External related
factors of delay were observed to positive with value “R” value of 0.96. The square of ‘R’ value
(%) weight 92.0% strongly correlated. The P. value stood at (0.07) above 0.05. Inferences, drawn
from the analysis indicated that the relationship between the two variables was not statistically
63
4.9 The mitigating measures
Table 4.9: Mitigating Measures
project. It was revealed that the factors identified in the study were very effective n tackling
delays of project delivery in tertiary institutions in Niger State, use of appropriate construction
methods (4.42), systematic control mechanism (4.43), proper emphasis on past experience
(3.93), developing human resources in thes construction industry (3.80), comprehensive contract
64
administration (3.77), use up to date technology utilization (3.74), effective strategic planning
(3.64), frequent coordination between the parties (3.58).were ranked 1st, 2nd, 3rd, 4th, 5th, 6th,
In addition, the factors with least mean scores are; Improving contract award procedure by
giving less weight to prices and more weight to the capacities and past performance of
contractors and frequent progress meeting were ranked 13th and 14th respectively.
Correlations
N 14 14 14 5
N 14 28 14 5
N 14 14 14 5
N 5 5 5 5
65
CHAPTER FIVE
5.1 Conclusion
Based on the findings of this research, the study concludes that, insufficient funding, non
payment of completed works, cash flow problem during construction and interference with
project performance are the major factors that causes delay in tertiary institutions construction
However, contractor related causes of delay in tertiary institution construction projects in Niger
state are, management issues, inappropriate construction method, mistake during construction
stage and improper planning were listed as the major factors. Further more, consultant related
causes of delays are inappropriate design, poor contract management, design error, late
preparation of drawing and other contract document were listed as the major factors. In the
aspect of external related causes natural disaster, weather conditions, change in government
leadership/ politics and interference by political leaders were revealed as the major causes of
delay in relation to the external factors. The research also concludes that the major effects of
construction delay are abandonment of the building projects, inadequate planning, variation of
project scope, incompetent project manager and delay in progress payment by the clients.
The research also concludes that correlation coefficient between client related factors of delay
and client related causes was observed to be positive. The study also concludes that the
relationship between the client related factors and external related factors was also positive.
However, the mitigation measures in their order of importance are use of appropriate
construction method, systematic control mechanism, proper emphasis on past experience and
66
5.2 Recommendation
2. There is need for development of human resource management and proper emphasis on
3. There is need for comprehensive contract administration through the use of up to date
technology
The research highlighted major factors that causes delay in respect to client, contractors and
external related factors were ranked to assist the professional for taking decision in improving
cost performance and proper management of factors that causes delay in tertiary institution
construction projects,
iii. Delay and effects of construction in tertiary institutions of other states in Nigeria.
67
References
Abd El-Razek, M. E., Bassioni, H. A. and Mobarak, A. M. (2008), Causes of Delay in Building
Construction Projects in Egypt: Journal of Construction Engineering and Management,
ASCE, Vol. 134, No. 11, pp. 831-841.
Abedi, M, Fathi, M. S. and Mohammad, M. F. (2011), Effects of Construction Delays on
Construction Project Objectives: Proceeding of the 1st Iranian Student Scientific
Conference in Malaysia, UPM, Malaysia.
Ademeso, O. S. and Windapo, A. O. (2008), Relationship between Material Management
Approach and Scheduled Project Completion Time: Proceeding of Construction and
Building Research of the Royal Institution of Chartered Surveyors Conference, COBRA,
Dublin Institute of Technology.
Afshari, H., Khosravi, S., Ghorbanali, A., Borzabadi, M. and Valipour, M. (2010, December).
Identification of causes of non-excusable delays of construction projects. In International
Conference on E-Business Management and Economics (pp. 42-46).
Aibinu, A. A. and Jagboro, G. O. (2002), The effects of construction delays on project delivery
in Nigerian construction industry: International Journal of Project Management: pp. 593 –
599, Elsevier Science Ltd and IPMA.
Aibinu, A. A. and Odeyinka, H. A. (2006), Construction Delay and their Causative Factors in
Nigeria: Journal of Construction Engineering and Management, ASCE, Vol. 132, No. 7,
pp. 667-677.
Akinsiku, O. E., & Akinsulire, A. (2012). Stakeholders' Perception of the Causes and Effects of
Construction Delays on Project Delivery. Journal of Construction Engineering and
Project Management, 2(4), pp. 25-31.
Akogbe, R. T. M., Feng, X. and Zhou, J. (2013), Importance and ranking evaluation of delay
factors for development construction projects in Benin: KSCE Journal of Civil
Engineering, Vol. 17, No. 6, pp. 1213 – 1222.
Ali, A. S., Smith, A., Pitt, M. and Choon, C. H. (2010), Contractor’s Perception of Factors
Contributing to Project Delay: Case Studies of Commercial Projects in Klang Valley,
Malaysia.
68
Ali, A. S., Smith, A., Pitt, M. and Choon, C. H. (2010), Contractors’ Perception of Factors
Contributing to Project Delay: Case Studies of Commercial Projects in Klang Valley,
Malaysia
Al‐Kharashi, A. and Skitmore, M. (2009). Causes of delays in Saudi Arabian public sector
construction projects. Construction Management and Economics, 27(1), pp. 3-23.
Alnuaimi, A. S., Taha, R. A., Al Mohsin, M. and Al-Harthi, A. S. (2010), Causes, Effects,
Benefits, and Remedies of Change Orders on Public Construction Projects in Oman:
Journal of Construction Engineering and Management, Vol. 136, No. 5, ASCE, ISSN
0733-9364/2010/5, pp. 615–622.
Alwi, S. and Hampson, K. (2003). Identification the Important Causes of Delay in Building
Construction Projects, Proceedings of the Ninth East Asia-Pacific Conference on
Structural Engineering and Construction.
Ameh, O. J. and Ogundare, O. (2013), Impact of Due Process Policy on Construction Projects
Delivery in Nigeria: Journal of Building Performance, ISSN: 2180-2106 Volume 4 Issue
1, pp. 13 – 25.
Ameh, O. J. and Osegbo, E, E. (2011), Study of Relationship between Time Overrun and
Productivity on Construction Sites: International Journal of Construction Supply Chain
Management: Vol. 1, No. 1, pp. 56 – 67.
Asnaashari, E., Knight, A. and Hurst, A. (2010), Delays in the Iranian construction projects:
Stakeholders and economy: Challenges, Opportunities and Solutions in Structural
Engineering and Construction – Ghafoori (ed.) Taylor & Francis Group, London, ISBN
978-0-415-56809-8, pp. 699 – 704.
Ayudhya, B. I. N. (2011), Evaluation of Common Delay Causes of Construction Projects in
Singapore: Journal of Civil Engineering and Architecture, ISSN 1934-7359, Volume 5,
No. 11 (Serial No. 48), pp. 1027-1034, USA.
Behm, M. (2008), Construction Sector: Journal of Safety Research, National Safety Council,
Elsevier Ltd., pp. 175-178.
Chidambaram, R., Narayanan, S. P. and Idrus, A. B. (2012). Construction delays causing risks on
time and cost-a critical review.
Creswell, J. W. (2012), Educational Research: Planning, Conducting, and Evaluating
Quantitative and Qualitative Research: Fourth Edition, PEARSON.
69
Dayi, S. (2010), schedule delay analysis in construction projects: a case study using time impact
analysis method; Middle East Technical University: M. Sc. Thesis.
Eshofonie, F. P. (2008), Factors Affecting Cost of Construction in Nigeria: Univerisity of Lagos
Akoka, Lagos, Nigeria: M.Sc. Thesis.
Frank, G. C. (2012), Construction Quality; Do it right or pay the price: Prentice hall, USA.
Gonzalez, P., Gonzalez, V., Molenaar, K. and Orozco, F. (2013), Analysis of Causes of Delay
and Time Performance in Construction Projects: Journal of Construction Engineering and
Management, ASCE, 04013027 – pp. 1 - 9.
Gündüz, M., Nielsen, Y. and Özdemir, M. (2013), Quantification of Delay Factors Using the
Relative Importance Index Method for Construction Projects in Turkey: Journal of
Management in Engineering, ASCE Vol. 29, No. 2, pp. 133-139.
Hackett, M. and Statham, G. (Eds.). (2007). The Aqua Group guide to procurement, tendering &
contract administration. Blackwell.
Hamzah, N., Khoiry, M. A., Arshad, I., Badaruzzaman, W. H. W. and Tawil, N. M. (2012),
Identification of the Causes of Construction Delay in Malaysia: World Academy of
Science, Engineering and Technology, Vol. 72, pp. 614 – 619.
Harrison, P. (2007), Can Measurement Error Explain the Weakness of Productivity Growth in
the Canadian Construction Industry: CSLS Research Report No. 2007-01.
Hart, K. A. (2006). Generations in the workplace: finding common ground. MLO: medical
laboratory observer, 38(10), pp. 26-27.
Haseeb, M., Lu, X., Bibi, A., Dyian, M. and Rabbani, W. (2011), Problems of Projects and
Effects of Delays in the Construction Industry of Pakistan, Australian Journal of Business
and Management Research Vol.1 No.5, pp. 41-50.
Howick, S., Ackermann, F., Eden, C. and Williams, T. (2009), Understanding the causes and
consequences of disruption and delay in complex projects: how system dynamics can
help: Univeristy of Strathclyde, UK.
Ibbs, W., Nguyen, L. D. and Simonian, L. (2011), Concurrent Delays and Apportionment of
Damages: Journal of Construction Engineering and Management, Vol. 137, No. 2,
ASCE, ISSN 0733-9364/2011/2 pp. 119–126.
70
Ibironke, O. T., Oladinrin, T. O., Adeniyi, O. and Eboreime, I. V. (2013), Analysis of Non-
Excusable Delay Factors Influencing Contractors' Performance in Lagos State, Nigeria:
Journal of Construction in Developing Countries, 18(1), pp. 53–72.
Iruobe, O. J., Ojambati, T. S., Akinpade, J. A. and Iruobe, T. (2012). An investigation into the
impact of total quality management application in the construction industry (a case of
training). Journal of Emerging Trends in Engineering and Applied Sciences, 3(2), pp.
344-348.
Jonathan, I. (2013), Effects of Delay on Building Project Delivery.
Krejcie, R. V. and Morgan, D. W. (1970). Determining sample size for research activities. Educ
Psychol Meas.
Lambropoulos, S. (2007). The use of time and cost utility for construction contract award under
European Union Legislation. Building and environment, 42(1), pp. 452-463.
Leedy, P.D. and Ormrod J. E (2007): Practical Research, Planning and Design, 8th edition.
Pearson: Merrill Prentice Hall.
Le-Hoai, L., Dai Lee, Y. and Lee, J. Y. (2008). Delay and cost overruns in Vietnam large
construction projects: A comparison with other selected countries. KSCE journal of civil
engineering, 12(6), pp. 367-377.
Macdonald, J. R., & Barsoukov, E. (2005). Impedance spectroscopy: theory, experiment, and
applications. History, 1, 8.
Mahamid, I., Bruland, A. and Dmaidi, N. (2012), Causes of Delay in Road Construction
Projects: Journal of Management in Engineering, Vol. 28, No. 3, ASCE, ISSN 0742-
597X/, pp. 300 – 310.
Marzouk, M. M. and El-Rasas, T. I. (2014). Analyzing delay causes in Egyptian constru ction
projects. Journal of Advanced Research, 5(1), pp. 49-55.
Masrom, N. & Asrul, M. (2007). Nature of delay in nominated subcontracting, Universiti
Teknologi Malaysia, Faculty of Built Environment: M Sc. Thesis.
.Memon, A. H., Abdul Rahman, I. and Abdul Azis, A. A. (2011), Preliminary Study on Causitive
Factors Leading to Construction Cost Overrun: International Journal of Sustainable
Construction Engineering and Technology Vol. 2, Issue 1, pp. 57-71.
Menesi, W. (2007). Construction delay analysis under multiple baseline updates: University of
Waterloo, P hD. Thesis.
71
Mohammed, K. A. and Isa, A. D. (2012), Causes of Delay in Nigerian Construction Industry:
Interdisciplinary Journal of Contemporary Research in Business, Institute of
Interdisciplinary Business Research, Vol. 4, No. 2, pp. 785-794.
Moore, P. (2012), Contractors Confront the Growing Cost of Rework: ENR.Com, Engineering
News-Record.
Motaleb, O. and Kishk, M. (2010), An Investigation into Causes and Effects of Construction
Delays in UAE: Association of Researchers in Construction Management, pp. 1149-
1157.
Mubarak, S. A. (2010). Construction project scheduling and control. John Wiley & Sons.
Muhammad, M. M. R. (2010) The Factors and Effect of Delay in Government Construction
Project (Case Study in Kuantan), Universiti Malaysia Pahang: Bachelor Thesis.
Ndekugri, I., Braimah, N. and Gameson, R. (2008), Delay Analysis within Construction
Contracting Organizations: Journal of Construction Engineering and Management, Vol.
134, No. 9, ASCE, ISSN 0733-9364/2008/9, pp. 692–700.
Oladinrin, T. O., Ogunsemi, D. R. and Aje, I. O. (2012), Role of Construction Sector on
Economic Growth Empirical Evidence of Nigeria: FUTY Journal of the Environment,
Vol. 7, No. 1.
Olusegun, A. E. and Michael, A. O. (2011), Abandonment of Construction Projects in Nigeria:
Causes and Effects: Journal of Emerging Trends in Economics and Management
Sciences (JETEMS) 2 (2): ISSN: 2141-7024, pp. 142-145.
Oppenheim, A. N. (2001), Questionnaire Design, Interviewing and Attitude Measurement: New
Edition, Continuum, London.
Pallant, J. (2011) SPSS Survival Manual A step by step guide to data analysis using SPSS 4th ed.
Australia.
Radosavljevic, M. and & Bennett, J. (2012). Construction management strategies: a theory of
construction management. John Wiley & Sons.
Ren, Z., Atout, M., and Jones, J. (2008). Root Causes of Construction Project Delays in Dubai.
In Procs 24th Annual ARCOM Conference, Association of Researchers in Construction
Management pp. 749-757.
Riazi, M., Riazi, S. and Lamari, F. (2013, May). Public sector project delay: the Malaysian
perspective and the way forward. In Proceedings of the 19th CIB World Building
72
Congress, Brisbane 2013: Construction and Society. Queensland University of
Technology.
Riazi, M., Riazi, S., Skitmore, M. and Cheung, Y. K. F. (2011, April). The use of supply chain
management to reduce delays: Malaysian public sector construction projects: In
Proceedings of the 6th Nordic Conference on Construction Economics and Organization
in Society Vol. 2, pp. 403-414, Danish Building Research Institute, Aalborg. University.
Salleh, R. (2009), Critical Success Factors on Project Management for Brunei Construction
Projects: Improving Project Performance: Queensland University of Technology,
Australia: P hD. Thesis.
Sambasivan, M. and Soon, Y. W. (2007). Causes and effects of delays in Malaysian construction
industry. International Journal of project management, 25(5), pp. 517-526.
Sapsford, R. and Jupp, V. (2006), Data Collection and Analysis: 2nd ed. SAGE Publications
Ltd. London.
Singh, Y. K. (2006), Fundamentals of Research methodology and Statistics: New Age
International (P) Limited, Publishers, India.
Sunjka, B. P. and Jacob, U. (2013), Significant Causes and Effects of Project Delays in The
Niger Delta Region, Nigeria: Proceedings of SAIIE25, pp. 641-1-14, Stellenbosch, South
Africa.
Sweis, G., Sweis, R., Abu Hammad, A. and Shboul, A. (2008). Delays in construction projects:
The case of Jordan. International Journal of Project Management, 26(6), pp. 665-674.
Tawil, N. M., Khoiry, M. A., Arshad, I., Hamzah, N., Jasri, M. F. and Badaruzzamam, W. H. W.
(2013), Factors Contribute to Delay Project Construction in Higher Learning Education
Case Study UKM: Research Journal of Applied Sciences, Engineering and Technology,
pp. 3112-3116.
Thomas, R. M. (2003), Blending Qualitative & Quantitative Research Methods in Theses and
Dissertations: CORWIN PRESS. INC., A Sage Publication Company, Thousand Oaks,
California.
Toor, S. U. R. and Ogunlana, S. O. (2008). Problems causing delays in major construction
projects in Thailand. Construction Management and Economics, 26(4), pp. 395-408.
Tumi, S. A., Omran, A. and Pakir, A. K. (2013), Causes of Delay in Construction Industry in
Libya: Proceeding of the International Conference on Economics and Administration:
73
Faculty of Administration and Business, University of Bucharest, Romania, pp. 265 –
275.
Yates, J. K. and Epstein, A. (2006), Avoiding and Minimizing Construction Delay Claim
Disputes in Relational Contracting: Journal of Professional Issues in Engineering
Education and Practice, Vol. 132, No. 2, ISSN 1052-3928/2006/2, pp. 168–179.
Zakaria, Z., Ismail, S. and Yusof, A. M. (2012). Cause and impact of dispute and delay the
closing of final account in Malaysia construction industry. Journal of Southeast Asian
Researc
74