The document describes the manual excavation work method including preparing equipment, surveying the site, excavating using shovels and hoes, and verifying excavation levels with surveys. The excavation will proceed in cycles from corner to corner and between foundations according to the owner's design priority.

Uploaded by

Armawan 99
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
248 views3 pages

Manual Excavation

The document describes the manual excavation work method including preparing equipment, surveying the site, excavating using shovels and hoes, and verifying excavation levels with surveys. The excavation will proceed in cycles from corner to corner and between foundations according to the owner's design priority.

Uploaded by

Armawan 99
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

WORK METHOD DOCUMENT

(MANUAL EXCAVATION)

INTRODUCTION
This method describe manual excavation works in general which is implemented in the project,

SCOPE OF WORK
Scope of work discuss in this method are

 Preparation of equipments and material


 Delivery to the field
 Survey and Marking
 Excavation and Planning Cycle

WORK METHOD
1. Conducting Toolbox Meeting by Supervisor to make sure all workers are informed about
today’s planned work before work started,

Fig. 1 Toolbox Meeting


2. Submitting request for works and method of work to owner’s representative. After work
method approved, preparing equipment for mobilization,
3. Conduct site measurement and put marking to excavation boundary,

Fig. 2 Survey and Marking

4. Using manual excavation equipment such as shovel, hoe and so on to do excavation.


Fig. 3 Manual Excavation
5. After excavation, survey will need to verify level for excavation. After verified by survey,
excavation will consider done.
6. Excavation will start according to owner’s planned design priority and goes on.

Planning from Contractor :

Excavation Planning, description :

1. Excavation will start at corner foundation, and then will go through cycle as seen as in
picture,
2. After complete, pouring lantai kerja’s concrete inside foundation and then carry on to do
another foundation excavation,
3. Proceed excavation on another marked foundation, and partially doing excavation on tie
beam plan,
4. Puoring lantai kerja’s concrete inside tie beam and another foundation.

EQUIPMENT
No Quantit
Equipments Capacity
. y
1 Shovel 3 Unit
2 Hoe 7 Unit
3 Survey Equipment 1 Set

PERSONEL
No
Personalia Quantity
.
1 Engineer 1
2 Supervisor 1
3 ESHS 1
4 Surveyor 1
5 Assistant Surveyor 2
6 Worker 10